WORK STUDY
-
7/29/2019 work study by nikhil sharma aec
2/34
WORK STUDY/WORK DESIGN: Work study may be defined as
systematic examination of methods of
carrying on activities (industrialoperations) so as to-
1. Improve the effective use ofmanpower and equipment.
2. Set up standards of performance forthe activities being performed.
-
7/29/2019 work study by nikhil sharma aec
3/34
Work study consists of two complementary
techniques:
A. Method Study
B. Work Measurement (Time Study)
-
7/29/2019 work study by nikhil sharma aec
4/34
Work study :
-
7/29/2019 work study by nikhil sharma aec
5/34
Method study:
It is a systematic recording and criticalexamination of the ways of doing things to
make improvements. It helps to eliminate the unnecessary
movements which results in cutting down theineffective time.
It involves investigation of existing methodsand an approach to improve them.
-
7/29/2019 work study by nikhil sharma aec
6/34
Work Measurement/Time Study :
It is a systematic technique to establishing timestandards for carrying out specific jobs.
It estimates how long a job should take and themanpower and equipments requirements for a givenmethod.
It determines the time for a qualified worker tocomplete a specific job
It defines a level of performance under typicaloperating conditions.
Time standards provide an indication of expectedoutput
Work measurement is used in budgeting, manpowerplanning, scheduling, standard costing, and indesigning worker incentive schemes.
-
7/29/2019 work study by nikhil sharma aec
7/34
Qualified worker:
One who has acquired the skill,knowledge and other attributes to carry
out the work by meeting the standardsof quantity, quality and safety.
-
7/29/2019 work study by nikhil sharma aec
8/34
Qualified Worker:
Achieves smooth and consistentmovements.
Acquires rhythm. Responds more rapidly to signals.
Anticipates difficulties and is more
ready to overcome them. Carries out task without much conscious
attention and seems relaxed.
-
7/29/2019 work study by nikhil sharma aec
9/34
In organizations where no work study is
conducted:
The existence of ineffective time is notrealized/suspected
They may consider ineffective time as a
usual phenomenon They consider it as Build in process and
nothing much can be done about it.
-
7/29/2019 work study by nikhil sharma aec
10/34
The most commonly used methods of
work measurement are:
Time and Motion Study
Work Sampling
Structured Estimating Predetermined Time Standard
(Maynard Operational Study
techniques is one of the widely usedtechniques)
Standard Data
-
7/29/2019 work study by nikhil sharma aec
11/34
The Basic Procedure of Work Measurement:
-
7/29/2019 work study by nikhil sharma aec
12/34
Equipments required:
-
7/29/2019 work study by nikhil sharma aec
13/34
Selecting the Job for Time Study: Points toremember
-
7/29/2019 work study by nikhil sharma aec
14/34
steps required prior to conducting the Time andMotion Study:
A. Precautions:
The purpose and objective of the time study must beclearly explained to everyone. Or else the whole
purpose would be lost. Unless explained, it would be misused/
misrepresented with vested interest by some.
A joint participation of both Union and Managementis required in the process.
The study must be conducted on a qualified worker.
-
7/29/2019 work study by nikhil sharma aec
15/34
Important points:
-
7/29/2019 work study by nikhil sharma aec
16/34
Obtaining and RecordingInformation:
Information about the job is acquired
from two sources:
Direct Observation Photography at the work place ( For minute
details about the machinery)
-
7/29/2019 work study by nikhil sharma aec
17/34
Checking the Method:
Check if any study has been made before andcompare with real situations at present
If compliant has been made, kindly check ifthere is any change in tools ex: worn outtools or improperly sharpened tools, feeding,flow or any additional work has crept in.
In high repetitive short cycle, changes inmethod are very difficult to detect.
-
7/29/2019 work study by nikhil sharma aec
18/34
Breaking the job into elements:
An element is a distinct part of a specified job selected forconvenience of observation.
Why elements are required: To separate the effective time from the ineffective time To be more accurate. One performer may not have the same
pace through out the cycle. Different types of elements can be classified It enables to separate very high fatigued elements so that
fatigue allowances can be decided.
It helps to detect any elimination and additions of elements. Ifwe study the whole cycle it is very difficult to find out additionsor eliminations.
-
7/29/2019 work study by nikhil sharma aec
19/34
Some types of Elements:
A repetitive element: it occurs in every cycle of an operation, Occasional element: It occurs at regular intervals. Constant element:Anelement where time remain constant at
all conditions, example: switching on a mchine,tightening ascrew
Variable Element: an element in which the basic time variesin relation to other characteristics, example: Sawing logs, timevaries with hardness.
Manual element: an element performed by a worker Machine element: an element which is performed
automatically and can not be manually interfered unlessterminated prematurely. Ex: Form Glass Bottles, cuttingelements in machine tools.
Governing Element: element which occupies the majority oftime in a cycle.
Foreign Element (Out side the cycle):An element observedwhich does not form a part of an operation.
-
7/29/2019 work study by nikhil sharma aec
20/34
Timing each Element: Using a Stop Watch
Cumulative timing: The watch runs continuouslyduring the study and all the elements are recorded.At the end of each element, time is recorded. Theindividual element time is recorded by subtractingfrom the total time.
Fly back Timing: The stop watch is immediately putto zero after the time of each element is recorded.
ILO advocates the use of cumulative timing. Because,even if we miss one element, the over all time studywould be recorded. In fly back method slight delay inputting the stop watch into zero would increase thetime of one element.
-
7/29/2019 work study by nikhil sharma aec
21/34
TIME STUDY RATINGS
What is standard rating and standardPerformance?
It is not always possible to engage largenumber of qualified workers. Moreoverpeople do not work consistently from day today or minute to minute. The examiner musthave some means of assessing the rate of theworker whom he is observing. He mustidentify a standard pace of working. Thisprocess of standardization is called as Rating.
-
7/29/2019 work study by nikhil sharma aec
22/34
Rating:
Assessment of the workers rate of working
Relative to observers concept of rate
Standard pace the observer has an image in his mind of a
qualified worker who will naturally work withcommitment and proper relaxation
Rating is generally denoted by a scale of 100
-
7/29/2019 work study by nikhil sharma aec
23/34
Standard Performance:
If a worker maintains a standard pace withappropriate relaxation, the amount of outputachieved by him would be termed asstandard performance over the shift/day.
Out put which qualified worker wouldnaturally achieve
Without over exertion Abides by specific methods
Motivated to their work
-
7/29/2019 work study by nikhil sharma aec
24/34
Grey Areas in standardizing:
Physique
Environment.etc
Discussions
-
7/29/2019 work study by nikhil sharma aec
25/34
Factors without the control of theOperator
Variations in quality of the material being used Variations in the tools or equipments being used Changes in methods and conditions of operation Variation of Mental attention Changes in climate, lighting, temperature The optimum pace at which the worker would work depends on
the physical effort required, constant care and attention,training and experience etc
Greater physical effort, awkward position would slow up thepace. Example: a person pushing a car by the window with onehand in the steering wheel would have lesser speed than a
person pushing it from behind. Similarly a person with a heavy weight will have a faster pace
because he wants to get rid of it. But he would require morerelaxation after the task is done.
-
7/29/2019 work study by nikhil sharma aec
26/34
Factors within the control of the operator:
Variations due to the individualscapability, pace
Variations due to the attitude to work
Variations due to the attitude towardsan organization (If there is a sense of
belongingness)
-
7/29/2019 work study by nikhil sharma aec
27/34
Work content
-
7/29/2019 work study by nikhil sharma aec
28/34
Allowances:
-
7/29/2019 work study by nikhil sharma aec
29/34
The Limitations of Time and Motion Study
Observers are not always competent Those conducting the study are not always proficient in the job
being observed The actions observed are not always reflective of the group as a
whole
Timing by direct observation may lead to inconsistency Rating is a vary disputed area in Time and Motion Study It included individual expertise and judgment in various factors The workers may resent the study if it is being used to
determine the pay scale Workers may change the rate at which they work Pressure may increase mistakes made Workers may alter normal work methods to disrupt the study
-
7/29/2019 work study by nikhil sharma aec
30/34
Predetermined motion time system(PMTS)
Discussions
What are the advantages of predeterminedmotion time system?
Setting standards for a very short motions (very hardto evaluate using other measures)
Standard language of documenting sequences ofelements which define operations
Enable to determine standard times for newoperations for whom we dont have past data
Enable to compare different methods of performing anew task (before applying the preferred method
-
7/29/2019 work study by nikhil sharma aec
31/34
MOST (Maynard Operation SequenceTechnique)
MOST (Maynard Operation SequenceTechnique) is a work measurement
technique Maynard and Company, Inc.in the Unites States.
MOST has been already introduced into
the wide varieties of industries, such asaerospace, automotive, electronics,etc., in EU, US, and Asia.
-
7/29/2019 work study by nikhil sharma aec
32/34
MOST is a work measurement systemwhich can be easily implemented and
practically maintained. MOST is a registered trademark of H. B.
Maynard and Company, Inc.
-
7/29/2019 work study by nikhil sharma aec
33/34
The MOST Systems family:
MOST is designed in multilevel to suitthe various needs of industrial
engineers: Basic MOST
Maxi MOST
Mini MOST
-