Introductions Meeting Purpose Project Background Scope of Work Staging Concepts Project Schedule Open House
![Page 3: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/3.jpg)
WisDOT Project Development Supervisor Bill Strobel, PE
WisDOT Project Manager Mahesh Shrestha, PE
Design Team Brad Groh, PE – JT Engineering, Inc. Mariah Krueger – WisDOT Greg Payne, PE – WisDOT Sam Bieneman – WisDOT John Kehn – WisDOT
3
![Page 4: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/4.jpg)
Reaffirm project concepts and discuss changes
Outline the anticipated project timeline
Examine draft acquisition limits
Engage real estate staff and answer questions about the acquisition process
4
![Page 5: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/5.jpg)
5
![Page 6: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/6.jpg)
8.2-mile corridor
Major Collector Highway
Mill and overlay completed in 2014
6
![Page 7: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/7.jpg)
Safety Pavement Deterioration Roadway Geometry Traffic
7
![Page 8: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/8.jpg)
8
Crashes 2009-2013
1.7x the state average crash rate for 2-lane rural highway
1.7x the number of fatalities on average Some segments up to 4.6x state average crash rate
4.6x crash rate3.1x crash rate
2.9x crash rate
![Page 9: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/9.jpg)
Emergency Overlay from 2014 improved ride Main problem is with the underlying pavement
9
![Page 10: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/10.jpg)
10
Substandard Intersection layout Shoulder and ditch slope Horizontal curves Objects in clear zone Speed rating
![Page 11: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/11.jpg)
Average Daily Traffic (2010 Count) 3500 – 6000 vehicles per day
2039 Forecast (AADT) 6500 – 8450 vehicles per day
11
![Page 12: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/12.jpg)
Environmental Minimize Section 4f Impacts (Park
Land and Historical Site) Minimize Wetland and River Impacts Avoid Impacts to NRHP Eligible
Archaeological Sites General Avoid Relocations Improve Safety Minimize Project Costs
12
![Page 13: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/13.jpg)
Rehabilitate (Likely Mill & Overlay) from southern project limits to the Gehin Road intersection
Reconstruct from Gehin Road intersection to northern project limits
Improve roadway drainage Establish clear zone Enhance safety throughout the corridor
13
![Page 14: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/14.jpg)
14
Rehabilitation Concept Under Development Rural Reconstruction Proposed Typical Section:
![Page 15: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/15.jpg)
15
![Page 16: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/16.jpg)
16
![Page 17: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/17.jpg)
17
![Page 18: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/18.jpg)
18
![Page 19: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/19.jpg)
19
![Page 20: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/20.jpg)
20
![Page 21: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/21.jpg)
21
![Page 22: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/22.jpg)
22
![Page 23: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/23.jpg)
23
Road Closed to Through Traffic In Work Zone Detour Posted For Non-Local Traffic Staging to Enhance Local Connectivity Stage 1 Work focused on area between Belleville and Paoli County PB intersection remains open Stage 2 Work focused on area between Paoli and northern limits Diane Avenue intersection completed and open
![Page 24: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/24.jpg)
24
Environmental Report Submittal Summer 2017 Transportation Project Plat Approval Summer 2017 Begin Right of Way Acquisition Fall 2017 Agency Scoping/Coordination Ongoing Final Plans May 2019 Construction Summer 2020
![Page 25: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/25.jpg)
25
N
WIS 692020
WIS 692017
CTH PB2018
![Page 26: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/26.jpg)
26
![Page 27: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/27.jpg)
27
![Page 28: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/28.jpg)
28
![Page 29: WIS 69 Reconstruction, County D to Valley Road, …...2017/05/16 · WisDOT Project Development Supervisor Bill Strobel, PE WisDOT Project Manager Mahesh Shrestha, PE Design Team](https://reader034.vdocuments.us/reader034/viewer/2022050307/5f6fcd3ccbb803425d3d896f/html5/thumbnails/29.jpg)
29
Mahesh Shrestha – WisDOT Project ManagerWisDOT – SW Region2101 Wright StreetMadison, WI [email protected]
Project Website: http://wisconsindot.gov/Pages/projects/by-region/sw/wis69/default.aspx