Wet Weather Consent Decree Implementation Update
Planning Committee
September 10, 2014
![Page 2: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/2.jpg)
Agenda
• Background
• Regional Private Sewer Lateral Ordinance
• Regional Technical Support Program
• Related Discharge Permits
•Next Steps
2
![Page 3: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/3.jpg)
Background Consent Decree Status
• Lodged with federal District court July 28, 2014
• Public Comment Period closed September 2, 2014 (no comments received)
• Consent Decree will become effective immediately upon being entered by the court
3
![Page 4: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/4.jpg)
Background Key EBMUD Requirements
• Construct and operate Urban Runoff Diversion Project by 2017
• Implement capacity improvement along North Interceptor by 2020
• Conduct annual compliance monitoring and modeling
• Continue Regional Private Sewer Lateral (PSL) Ordinance
Develop and implement a Regional Technical Support Program (RTSP)
4
![Page 5: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/5.jpg)
Regional PSL Ordinance Proposed Amendments
• Consent Decree adds new requirement for Public Entities to maintain their sewer laterals (no enforcement requirements for EBMUD)
• Allow Albany and Alameda to join program
– Proposed transition date January 1, 2015
– City of Berkeley will retain its own program
• Clarify ordinance language developed through initial years of implementation
5
![Page 6: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/6.jpg)
Regional Technical Support Program (RTSP) - Overview
• Replaces $2M/yr PSL Incentive requirement under Stipulated Order
• Requires $2M/yr to identify and characterize sources of inflow and rapid infiltration
• Cumulative spend requirement
– i.e. $2M by Year 1, $4M by year 2, etc.
– Provides ability to front-load
• Includes staff time for analysis and investigation
6
![Page 7: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/7.jpg)
RTSP Overview, continued
• EBMUD identifies sources of inflow and rapid infiltration (I/I)
• EBMUD defines which sources are “high priority”
• Satellite communities pursue high priority sources
– Eliminate public sources within 2 years
– Enforce removal of private sources
• Satellite communities consider non-high priority sources in CIP prioritization
7
![Page 8: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/8.jpg)
RTSP Program Significance
• Key element in WWF discharge reduction
– Estimated 15% of excess peak flow originates from inflow (direct sources)
– Model assumes ability to find and remove 75% of inflow
• Critical to meet Consent Decree
– Year 8 “check-in”
– Year 16 “check-in”
– WWF discharge elimination deadlines (2027, 2033, 2035)
8
![Page 9: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/9.jpg)
RTSP Implementation Approach
• Consent Decree requires an RTSP Plan describing first five years of work
– Draft to satellite communities early 2015
– Final to EPA for review/comment/approval Spring 2015
• Initial field work will occur concurrent with RTSP Plan development
– 2014-2015 wet season flow monitoring
– 2015 dry season smoke testing, CCTV, etc.
9
![Page 10: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/10.jpg)
RTSP Work Plan Development
• Define approach to data analysis and field work
• Maintain flexibility to adapt as we learn
• Learn from others
– I/I investigative programs across the country
– Panel of national experts in sewer system management to support RTSP Plan development
10
![Page 11: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/11.jpg)
RTSP Tools and Techniques
• Analysis of data to identify areas of high potential for inflow, for example: – Flow data from EBMUD and satellite communities
– Proximity to creeks and storm drains
– Sewer work records
• Field work to locate and characterize sources – Flow monitoring
– Smoke testing
– CCTV inspection
– Visual inspection 11
![Page 12: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/12.jpg)
Related NPDES Discharge Permits
• Wet Weather Facilities – Scheduled adoption date November 12, 2014
– Reviewing with RWQCB staff
– No significant issues
• Main Wastewater Treatment Plant – Application due October 2014
– Proposed adoption March 2015
– Key issue: Ensure blending requirements dovetail with WWF permit and Consent Decree
12
![Page 13: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/13.jpg)
Next Steps
• Bring proposed Regional PSL Ordinance amendments for Board consideration
• Work with RWQCB on related NPDES permits • Develop initial deliverables for stakeholder
review in early 2015 – RTSP Plan – Flow Model Calibration Plan – PSL Outreach Plan
• Implement initial stages of RTSP data analysis and field work
• Keep Board apprised of key activities 13
![Page 14: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/14.jpg)
Wastewater Service Area and Major Facilities
14
![Page 15: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/15.jpg)
Semi-Annual Regulatory Compliance Update
Planning Committee
September 10, 2014
![Page 16: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/16.jpg)
Agenda
• Enforcement Actions
• Permit for Potable Water Discharges
• Cal OSHA Inspections
• Safety Culture Perception Survey
• Upcoming Activities
2
![Page 17: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/17.jpg)
Enforcement Review
• Strategic Plan KPI = Zero NPDES and Waste Discharge Requirement (WDR) permit Notices of Violation (NOVs) received
– Four NOVs for discharges to water or land
– Two NOVs related to air quality compliance
3
![Page 18: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/18.jpg)
Lafayette WTP NOVs
•May 8, 2012 discharge caused by failure of filter control valve
– Modified controls
•March 27, 2013 discharge to sump going to Lafayette Creek
– Added signage at drains “No Dumping – Drains to Creek”
• $6000 settlement agreement
4
![Page 19: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/19.jpg)
Upcountry NOVs
• Failure to collect data on pH and temperature at Camanche North Shore Water Treatment Plant in June 2014
– Contesting due to lack of discharge
•Missed sample during 2014 Q2 at Clay Station Raw Water Pumping Plant
– Enhanced communication between staff
5
![Page 20: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/20.jpg)
MWWTP NOV Settlement Agreement
NOV for unabated digester gas release on 11/9/13
• 15 minute release through pressure relief valves
• Plugged drain line in flare
• Settlement agreement with $4000 fine
6
![Page 21: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/21.jpg)
MWWTP Air Permit NOV
Digester gas release on 11/22/2013
• Failure of flare igniter
• 830 cu. ft. vented through pressure relief valves
• Requested breakdown relief
•NOV issued 7/28/14
7
![Page 22: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/22.jpg)
General Potable Water Discharge Permit
• Agreement with SF RWQCB & ABAG to fund person to develop permit
• $298,833 estimated total cost
• Agreement with 7 other agencies to share costs
• District share is $50K
![Page 23: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/23.jpg)
SF Regional Permit Progress
• 11/20/13 - admin draft issued for review with water agencies
• 5/8/14 - tentative order issued for public comment
• 5/19/14 - public workshop held
• 7/1/14 – permit postponed pending statewide permit
![Page 24: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/24.jpg)
Statewide Permit
• 6/6/14 – SWRCB issues draft permit
• 8/5/14 – public hearing
• 9/23/14 – permit scheduled for adoption at SWRCB hearing
![Page 25: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/25.jpg)
Cal OSHA Inspections
• 6 inspections initiated based on employee complaint(s)
• 13 facilities examined and scrutinized
• 2 citations
– Fixed ladder exceeds 30 feet without ladder safety system or landing platforms
– Mid-rail is below the halfway point of the guardrail
11
![Page 26: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/26.jpg)
Safety Perception Survey
• 621 of 809 OMD employees surveyed
• Scored in 62nd percentile
• Compared to 750 Companies
•Over 1.5 million responders
12
![Page 27: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/27.jpg)
Survey Action Plans
• Communicating results
• Engage employees
• Identify top issues to address
•Develop specific action-oriented countermeasures
• Retake survey in 2 years
13
![Page 28: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/28.jpg)
Upcoming Activities
•Work with SFRWQCB, ABAG, and Bay Area water utilities to finalize a permit for potable water discharges
•Work with Local Safety Committees to develop action plans based on safety perception survey
• Review fall protection compliance at water distribution reservoirs
![Page 29: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/29.jpg)
Questions?
15
![Page 30: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/30.jpg)
![Page 31: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/31.jpg)
Orinda Water Treatment Plant
Washwater Tank Rehabilitation
Planning Committee Meeting
Orinda Water Treatment Plant
Washwater Tank Rehabilitation
Planning Committee Meeting
September 10, 2014
![Page 32: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/32.jpg)
Orinda WTP Washwater Tank Rehabilitation
• Background
• Site Constraints
• Community Outreach
• Design Mitigations
• Next Steps
![Page 33: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/33.jpg)
Background Orinda WTP circa1938: minimal site constraints
Orinda WTPElevation = 375’
Washwater TankElevation=410’
Source: Google Earth
• 200,000 gallons• At grade• 40 ft. diameter • 22 ft. tall• Bar‐stressed concrete
![Page 34: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/34.jpg)
BackgroundOrinda WTP and washwater tank today
Orinda WTP
Source: Google Earth
Washwater Tank
![Page 35: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/35.jpg)
Site constraints Poor access, trees, no staging area
Tank
Property Line
Slope
![Page 36: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/36.jpg)
Community Outreach
• Approach:
• Notified the community early
• Explained clearly the need for the project
• Provided visual exhibits
• Held community meetings on-site
• Mitigated with design
![Page 37: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/37.jpg)
50’dia
Proposed Tank:
Existing Tank:
Community Outreach
New tank alternative
New tankalternative
Aerial “footprint” vs. Ground-level visualExisting
![Page 38: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/38.jpg)
Community OutreachOn-site meetings clarified neighbor concerns
Mailbox access
Tree removal
Architecture preservation
Curb appeal
![Page 39: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/39.jpg)
Designed Mitigations Adjust retrofit method to site constraints
Manual wrapping minimizes equipment size and tree removal.
Sturdy base anchorages minimizes impact on tank architectural features.
![Page 40: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/40.jpg)
New fence is set back for a “green zone”
Security fence
Low maintenance plantings for screening
Restore cobbles
Add staging area off-site
Minimize tree removal
Retrofit existing tank
Design Mitigated Site planning neighbor concerns
![Page 41: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/41.jpg)
Next Steps
• Maintain communications with neighbors
• Schedule:
– Open Bids Sept 17, 2014
– Recommend Award Oct 14, 2014
– Construction Nov 2014 – Mar 2015
![Page 42: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/42.jpg)
Questions?
![Page 43: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/43.jpg)
Drought Communications with Billpayers
and with Non-billpayers EBMUD Planning Committee
September 2014
![Page 44: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/44.jpg)
2
More than a third of EBMUD customers do not get a bill
387,000 accounts
![Page 45: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/45.jpg)
Non-billpaying residents are ethnically diverse
![Page 46: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/46.jpg)
Non-billpaying residents are younger
![Page 47: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/47.jpg)
Print bill payers get information and news regularly from EBMUD
Direct mail to print bill payers:
• Top of bill message
• Prior-year water use
• Back of bill tips
• Customer Pipeline
• Supplemental inserts
5
![Page 48: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/48.jpg)
Electronic billpayers get links to EBMUD news and information
E-bill with web links:
– Top of bill message
– Prior-year water use
– Back of bill tips
– Customer Pipeline
– Bill FAQs
6
![Page 49: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/49.jpg)
Non-billpayers get most EBMUD news through other sources
Direct mail
• Annual Water Quality Report postcard
Other communication
• Earned media
• Ebmud.com
• Outdoor ads
• Community events
• Presentations 7
![Page 50: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/50.jpg)
Many more non-billpayers say they can’t rate EBMUD
Q10. Thinking specifically about the East Bay Municipal Utility District, using a scale of excellent, good, only fair, or poor, please rate the overall job East Bay Municipal Utility District is doing
![Page 51: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/51.jpg)
92%
79%
90%
83%
80%
68%
79%
71%
76%
66%
75%
67%
71%
57%
Bill Payer
Non-Payer
Bill Payer
Non-Payer
Bill Payer
Non-Payer
Bill Payer
Non-Payer
Bill Payer
Non-Payer
Bill Payer
Non-Payer
Bill Payer
Non-Payer
Total Agree
Non billpayers give EBMUD favorable--but lower--ratings
Provides safe tap water
Provides good tasting tap water
Is an agency I can trust
Cares about the environment
Is a reliable source of information
Operates in communities’ best interests
Is responsive to customer service requests
![Page 52: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/52.jpg)
Conservation rating variance was 13 percent in early 2014
77%
65%
61%
55%
60%
47%
Bill Payer (78%)
Non-paying Renter (22%)
Bill Payer (78%)
Non-paying Renter (22%)
Bill Payer (78%)
Non-paying Renter (22%)
Ensuring the quality of the water we drink
Making sure we have the water supply we need
Encouraging customers to conserve water
![Page 53: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/53.jpg)
TV news is the top source for conservation information
Page 11
7/08 2/08 2007
Television News* 38% 37% 35%
Newspaper 22% 23% 25%
EBMUD Bill insert/newsletter 14% 16% 6%
Radio 5% 12% 9%
Television Commercial 3% -- --
Brochure/Pamphlet 3% 7% 4%
Billboard 2% 4% 4%
EBMUD websites 1% 1% --
Other website 1% 2% --
Other 10% 11% 33%
Don’t Know 1% 5% 3% * In 2/08 and 2007 surveys, “Television” was not split between “News” and “Commercial”
** 2 responses were allowed per respondent in 2/08 and 2007 surveys *** “Other responses include “phone calls” and “letters” from previous EBMUD actions
Where did you see or hear the conservation information?
![Page 54: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/54.jpg)
In 2014, active media relations has been a focus of outreach
•480 unique interviews with reporters
–218 on drought declaration/water supply
–152 on conservation tips, rebates, rules
•370 news reports featured EBMUD
12
![Page 55: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/55.jpg)
Late 2014 proposed outreach intended to reach non-billpayers
• Ongoing
– Earned media, web, presentations, booths, etc.
• October+
– Social media policy
• November
– Updated outdoor media campaign
• December
– Direct mail to non-billpayers
13
![Page 56: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/56.jpg)
![Page 57: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/57.jpg)
Semi-Annual Water Quality Report
Planning Committee September 10, 2014
![Page 58: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/58.jpg)
District’s Water Quality Goals
•Must meet Federal and State Drinking Water Standards
• KPI – Meet 100% of Federal and State Drinking Water Standards
• Strive to meet District’s Water Quality Goals
• KPI – Meet 100% of District’s Water Quality Goals
![Page 59: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/59.jpg)
•Met all Federal and State Drinking Water Standards
•Met 117 of 119 (98%) District’s Water Quality Goals (WQGs)
– Exceeded the WQGs for TTHMs and NDMA
![Page 60: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/60.jpg)
• TTHM – Exceeded WQG in 3 of 32 compliance
calculations
– Project underway to alter chemical injection points at Sobrante Water Treatment Plant
•NDMA – Exceeded WQG in 1 of 10 samples
– WateRF Projects •Natural sources of NDMA precursors
•Alternative polymer evaluation
![Page 61: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/61.jpg)
UCMR 3
• Provide occurrence data to USEPA
• Prelude to potential regulatory action
• 30 unregulated contaminants
• Began monitoring: Fall 2013
• Detected – Chlorate
– Vanadium
– Strontium
– Hexavalent chromium
![Page 62: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/62.jpg)
Hexavalent Chromium (Cr(VI))
• CA established MCL (10 µg/L) on July 1, 2014
•District began UCMR3 monitoring on Fall 2013
• Cr(VI) detected in UCMR3 samples based on USEPA detection limit (0.03 µg/L)
• Based on CA detection limit (1 µg/L) our UCMR3 data would be reported as nondetects.
![Page 63: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/63.jpg)
CalEnviroScreen
•Quantitative assessment of pollution burden
– CalEPA Office of Environmental Health Hazard Assessment (OEHHA)
– Identify areas with high pollution burden
• Version 2.0
– Drinking Water
– Finer resolution
– Draft April 2014
![Page 64: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/64.jpg)
![Page 65: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/65.jpg)
CalEnviroScreen (cont)
• Acknowledge contaminant concentration used may represent untreated water
• Reference to consumer confidence reports
![Page 66: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/66.jpg)
Potential Regulatory Action
• Candidate Contaminant List (CCL) 4
• Unregulated Contaminant Monitoring Rule (UCMR) 4
•Distribution System Reservoirs Rule
– Asked District staff to provide information on District maintenance practices (October 15, 2014)
![Page 67: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/67.jpg)
• Research – District operations continues to experience
nitrification
– Beginning work to gain a better understanding of the underlying causes in an effort to improve operations
• Portland Water Bureau – Lead violation
– Boil Water Notice (TCR violation)
– Nitrification
![Page 68: Wet Weather Consent Decree Implementation Update...Wet Weather Consent Decree Implementation Update Planning Committee September 10, 2014 Agenda •Background •Regional Private Sewer](https://reader033.vdocuments.us/reader033/viewer/2022052800/5f10b1fe7e708231d44a5eb5/html5/thumbnails/68.jpg)
Questions