Transcript
Page 1: Webinar - Cost of Losses for Network Investment

LOSS COSTS FOR NETWORK

INVESTMENT ANALYSIS

May 2011

Harry Colebourn

Energeia Pty Ltd

Page 2: Webinar - Cost of Losses for Network Investment

Discussion points

1. Cost of generating energy

2. Cost of transporting energy

3. Loss costs for investment analysis

4. Regulatory positioning

Page 3: Webinar - Cost of Losses for Network Investment

1.1 No-load and load losses

• No-load (shunt) losses occur

all the time and are relatively

constant. They occur due to

unavoidable leakage within

electrical equipment like

transformers, capacitors and

meters

• Load (series) losses occur

due to the delivery of energy

through the network. They

vary approximately with the

square of the loading. Series

losses occur due to the

electrical resistance in

components of the network

like lines and transformers

Load

Series resistance

Shunt resistance

Leakage current

Load current

Generator

Supply network

Page 4: Webinar - Cost of Losses for Network Investment

$1

$10

$100

$1,000

$10,000

Jul-08 Aug-08 Sep-08 Oct-08 Nov-08 Dec-08 Jan-09 Feb-09 Mar-09 Apr-09 May-09 Jun-09

RR

P

Date

R² = 0.46

5,000 7,000 9,000 11,000 13,000 15,000

NSW Demand MW

1.2 Energy market outcomes in 2008-09

• Large variation in regional reference price

• Reasonable correspondence of price with

regional demand using logarithmic fit

Page 5: Webinar - Cost of Losses for Network Investment

1.3 Load and loss profiles

• Load loss (series) is ‘peakier’ than the system load

profile

• No-load (shunt) loss is constant

Cost of energy Shunt loss System load Series loss

2008-09 for NSW 39$ 43$ 47$

Page 6: Webinar - Cost of Losses for Network Investment

1.4 Forecast generation patterns

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Dem

and

, % o

f max

imu

m

Duration, % of hours

Wind & unscheduled

Hydro

OCGT

Coal

CCGT

Generation

type excl. CPRS incl. CPRS

$/MWh $/MWh

Wind & unscheduled 114$ 114$

OCGT 162$ 190$

Coal 60$ 81$

CCGT 60$ 77$

LRMC

LRMC of energy Shunt loss System load Series loss

$/MWh $/MWh $/MWh

Cost incl. CPRS 81$ 91$ 92$

Cost excl. CPRS 60$ 71$ 72$

Generation pattern

assumes generation is

operated to minimise

overall costs

Generation costs

translate to different

costs for loads of

different profiles

Page 7: Webinar - Cost of Losses for Network Investment

1.5 Summary of energy generation

costs

$0 $20 $40 $60 $80 $100

Series loss

System load

Shunt loss

Cost $/MWh

Wholesale price 2008-09

Forecast cost 2020 exc. CPRS

Forecast cost 2020 inc. CPRS

• LRMC of generation is much higher than historical

wholesale price

• The ‘peakier’ load profile of load losses has a

higher cost of generation

Page 8: Webinar - Cost of Losses for Network Investment

Transmission

Subtransmission High Voltage Low Voltage

132 kV 230/400 V 22, 11 kV 66, 33 kV

Distribution Substation

Zone Substation

ST Substation

2.1 Network configuration

• The network comprises several levels with load

supplied from each

• Load or loss supplied by the network:

o generates upstream energy losses in

network equipment; and

o requires upstream network capacity for

its transport

Page 9: Webinar - Cost of Losses for Network Investment

LV load 77.8%

LV loss 2.30%

HV load 6.3%

HV loss 1.8%

ST load 10.7%

ST loss 1.1%

Transmission loss 1.3%

Energy Purchases

from RRN

101.3%

Distribution losses 5.2% of delivery into

distribution network Energy to Distribution

100.0%

2.2 ‘Leaky pipe’ loss diagram

for EnergyAustralia

Subtransmission network

15%

Subtransmission substations

6%

Zone substations 9%

HV Network 26%

Distribution substations

27%

LV network

12%

Meters and load control

4% Shrinkage 1%

Page 10: Webinar - Cost of Losses for Network Investment

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

1 8760

Load

, % o

f pea

k

Duration, hours

Peak load

Base load

Network cost

2.3 Network cost allocation

• Network capacity is required

to meet peak period loads

• The LRMC of network

capacity is around 80% of

average network charges

• Capacity cost allocation is to

the peak 30% of the load

• Capacity cost allocation is

dependent upon the load

profile

Network cost Shunt loss System load Series loss

Proportion of average 75% 80% 131%

Page 11: Webinar - Cost of Losses for Network Investment

3.1 Summary of loss costs

• The cost of losses:

o depends upon the configuration of the network;

o depends upon the level in the network;

o depends upon the load profile; and

o is very substantially higher than the

wholesale cost of energy

$0 $50 $100 $150 $200 $250 $300

Low Voltage

High Voltage

Subtransmission

Transmission

Energy

$0 $50 $100 $150 $200 $250 $300

LRMC energy

TUoS

Transmission losses

DUoS to ST

Losses to ST

DUoS to HV

Losses to HV

DUoS to LV

Losses to LV

Low Voltage

High Voltage

Subtransmission

Transmission

Energy

Low Voltage

High Voltage

Subtransmission

Transmission

Energy

Seri

es lo

ss

Syst

em lo

ad

Metropolitan distributor Regional distributor Sh

un

t lo

ss

Page 12: Webinar - Cost of Losses for Network Investment

4.1 Network investment framework

• Loss costs are settled as part of the Australian

National Energy Market (NEM) trading

arrangements

• With large transmission network investments,

market effects such as losses are considered

under the Regulatory Investment Test for

Transmission (RIT-T)

• There is a strong financial incentive in the

current regulatory arrangements for distributors

to minimise capital and direct operating costs

• There is no explicit requirement for distributors

to consider loss costs in network investments

Page 13: Webinar - Cost of Losses for Network Investment

4.2 Network investment framework (2)

• There is no explicit requirement for distributors

to consider loss costs in network investments

• A loss incentive has been tried and failed in the

late 1990’s, by NSW regulator IPART. The natural

annual variation in losses makes this

problematic

• The least intrusive approach is to impose an

obligation on distributors to use a reasonable

cost for losses in their investment analysis

Page 14: Webinar - Cost of Losses for Network Investment

4.3 Minimum Energy Performance

Standards

• MEPS are established by the Ministerial Council

on Energy’s Equipment Energy Efficiency (E3)

committees, with DEWHA as secretariat

• Distribution transformer MEPS:

o have been in place since October 2004

o Stage 1 Regulatory Impact Statement (RIS) was

based on the 2002 market cost of energy

o review of stage 2 distribution transformer MEPS

commenced in 2007

o Consultation RIS on new MEPS delayed

• Opportunity to influence outcome?

Page 15: Webinar - Cost of Losses for Network Investment

Thank You

Energeia

L20 Tower 2, 201 Sussex Street, Sydney NSW 2000

P +61 2 9006 1550 F +61 2 9420 1634 M +61 412 328 549

E [email protected]

W www.energeia.net.au


Top Related