Transcript

THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL

by

HERMAN GLENN BALLARD

A thesis submitted to the Faculty of Engineering

of The University of Birmingham

for the degree of

DOCTOR OF PHILOSOPHY

School of Civil EngineeringFaculty of Engineering The University of Birmingham

May 2000

ACKNOWLEDGEMENTS

Many individuals and companies contributed to this research. To name a few:

q David Seymour, my thesis advisor

q Anne Seymour, for giving me a home in Birmingham

q David Hoare and Peter Deasley, thesis examiners

q Greg Howell, business partner and co-thinker

q Lauri Koskela, for his example and inspiration

q Todd Zabelle and the Pacific Contracting team for their willingness to try newideas

q Leo Linbeck III, Ed Beck and Kathy Jones of Linbeck Construction for sharingopportunity and data (3 of the 5 cases were Linbeck projects)

q Norm Barnes and the Barnes Construction team for access to projects

q Iris Tommelein, external thesis advisor and colleague at UC Berkeley

q Jeanne Ballard, my wife, for putting up with me, especially my absences fromhome

ABSTRACT

Project controls have traditionally been focused on after-the-fact detection of variances.

This thesis proposes a control system, the Last Planner system, that causes the

realization of plans, and thus supplements project management's concern for management

of contracts with the management of production.

The Last Planner system has previously been successively applied by firms with direct

responsibility for production management; e.g., speciality contractors. This thesis

extends system application to those coordinating specialists, both in design and

construction, through a series of case studies, one of which also explores the limits on

unilateral implementation by specialists.

In addition to the extended application, two questions drive this research. The first

question is 1) What can be done by way of tools provided and improved implementation

of the Last Planner system of production control to increase plan reliability above the

70% PPC level? Previous research revealed substantial improvement in productivity for

those who improved plan reliability to the 70% level, consequently there is reason to

hope for further improvement, possibly in all performance dimensions, especially with

application across an entire project rather than limited to individual speciality firms. That

question is explored in three case studies, the last of which achieves the 90% target.

The second research question is 2) How/Can Last Planner be successfully applied to

increase plan reliability during design processes1? That question is explored in an

extensive case study, which significantly contributes to understanding the design process

from the perspective of active control, but unfortunately does not fully answer the

question, primarily because the project was aborted prior to start of construction.

However, it is argued that the Last Planner system is especially appropriate for design

production control because of the value-generating nature of design, which renders

ineffective traditional techniques such as detailed front end planning and control through

after-the-fact detection of variances.

1 In this thesis, the term “design” is used to designate both design and engineering

activities, not shaping space to aesthetic criteria.

Issues for future research are proposed, including root cause analysis of plan failures

and quantification of the benefits of increased plan reliability for both design and

construction processes.

TABLE OF CONTENTS

PageTitle Page

Acknowledgements

Abstract

Table of Contents

List of Figures

List of Tables

1.0 Introduction 1-11.1 Conceptual Framework 1-11.2 Assumptions 1-31.3 Contribution to Knowledge 1-5

1.4 The Author's Role in the Research 1-51.5 Structure of the Dissertation 1-8

2.0 Critique of Production Control 2-12.1 What is Production Control? 2-1

2.1.1 The Meaning of “Production” 2-12.1.2 The Meaning of “Control” 2-3

2.2 Project Management 2-52.2.1 The Project Management Body of Knowledge 2-52.2.2 Critique of the Traditional Project Control Model 2-7

2.3 Previous Application of Production Control Concepts to the AEC Industry 2-122.3.1 Melles and Wamelink 2-122.3.2 Koskela 2-14

2.4 Criteria for a Production Control System 2-15

3.0 Description and History of the Last Planner System of Production Control 3-13.1 Hierarchical Structure 3-1

3.2 Should-Can-Will-Did 3-1 3.3 Production Unit Control 3-3 3.4 Work Flow Control 3-5

3.4.1 Constraints Analysis 3-9 3.4.2 Pulling 3-11

3.4.3 Matching Load and Capacity 3-143.4.4 The Last Planner System As a Whole 3-15

3.5 A Brief History of the Last Planner System of Production Control 3-163.6 Previous Applications of the Last Planner System to Design 3-21

3.7 Evaluation of Last Planner against Criteria for Production Control Systems 3-24 3.8 Research Questions: 1) What can be done by way of tools provided and 3-25

improved implementation of the Last Planner system of productioncontrol to increase plan reliability as measured by Percent Plan Complete?2) How/Can Last Planner be successfully applied to increase plan reliabilityduring design processes?

4.0 Research Methodology 4-14.1 Introduction 4-1

4.1.1 Engineering Management as a Field of Study 4-1 4.1.2 Competing Engineering Management Paradigms 4-4

4.2 Research Design 4-6 4.2.1 Research Question 4-6

4.2.2 Research Strategies 4-8 4.3 Research Methods 4-9

4.3.1 Data Collection 4-9 4.3.2 Data Analysis and Evaluation 4-10

4.3.3 Case Studies 4-12

5.0 Case One: CCSR Project 5-15.1 Project Description and Last Planner Implementation 5-1

5.2 PPC and Reasons 5-2 5.3 Observations 5-10 5.4 Learnings 5-11

6.0 Case Two: Next Stage 6-16.1 Project Description and Last Planner Implementation 6-16.2 Data 6-2

6.2.1 PPC and Reasons 6-2 6.2.2 Observations 6-5

6.2.3 Feedback from participants 6-5 6.3 The Nature of the Design Process and Implications for Process Control 6-8

6.4 Evaluation of Last Planner Implementation 6-10 6.5 Learnings 6-12

7.0 Case Three: Pacific Contracting 7-1 7.1 Project Description and Last Planner Implementation 7-1

7.2 PPC and Reasons 7-2 7.3 Observations 7-7

7.4 Learnings 7-8

8.0 Case Four: Old Chemistry Building Renovation 8-18.1 Project Description and Last Planner Implementation 8-1

8.2 PPC and Reasons 8-2 8.3 Observations 8-4 8.4 Learnings 8-5

9.0 Case Five: Zeneca 9-1 9.1 Project Description and Last Planner Implementation 9-1 9.2 PPC and Reasons 9-1 9.3 Constraint Analysis and Make Ready 9-3 9.4 Observations 9-6 9.5 Learnings 9-6

10.0 Conclusions 10-1 10.1 Summary of Case Study Results 10-1 10.2 Research Question: What can be done by way of tools provided and 10-2

improved implementation of the Last Planner system of productioncontrol to increase plan reliability as measured by Percent PlanComplete?

10.3 Research Question: How/Can Last Planner be successfully applied to 10-3increase plan reliability during design processes?

10.4 Directions for Future Research 10-4 10.5 Conclusions 10-9

Glossary of Terms G-1

List of References R-1

Bibliography Biblio-1

Appendix A: Next Stage Kickoff Meeting A-1

Appendix B: Next StageTeleconferences B-1

Appendix C: Next Stage Action Items Log C-1

Appendix D: Next Stage Issues Log D-1

Appendix E: Next Stage Decisions Log E-1

LIST OF FIGURES

Page

3.1 The formation of assignments in the Last Planner System 3-2

3.2 Lookahead Process 3-6

3.3 Make Ready by Screening and Pulling 3-11

3.4 A Traditional (Push) Planning System 3-13

3.5 Last Planner-A Pull System 3-14

3.6 The Last Planner System 3-16

3.7 PPC (Nokia Project) 3-23

3.8 Participant Survey (Nokia Project) 3-23

5.1 CCSR-Weekly PPC 5-5

5.2 CCSR-Reasons for Noncompletion 5-6

5.3 CCSR-PPC without rain 5-6

6.1 Next Stage-PPC 6-4

7.1 Pacific Contracting-PPC 7-2

7.2 Pacific Contracting-Reasons 7-7

8.1 Old Chemistry Building-PPC 8-3

8.2 Old Chemistry Building-Reasons for Noncompletions 8-4

9.1 Zeneca-PPC 9-2

9.2 Zeneca-Reasons 9-2

10.1 Activity Definition Model 10-4

10.2 Reasons Analysis Hierarchy-Directives 10-6

10.3 Reasons Analysis Hierarchy-Prerequisites 10-7

10.4 Reasons Analysis Hierarchy-Resources 10-8

10.5 Reasons Analysis Hierarchy-Process 10-9

LIST OF TABLES

Page

1.1 Conversion/Flow/Value 1-1

3.1 Functions of the Lookahead Process 3-7

3.2 Construction Lookahead Schedule 3-9

3.3 Engineering Lookahead Schedule 3-10

3.4 Constraints Analysis 3-12

5.1 CCSR-Weekly Planning Cycle 5-3

5.2 CCSR-Constraints Analysis Form 5-4

5.3 CCSR-PPC and Reasons Data 5-5

5.4 CCSR-Reasons for Noncompletion (detailed and categorized) 5-7

6.1 Next Stage-Reasons for Noncompletion 6-2

6.2 Next Stage-PPC Data 6-3

6.3 Next Stage-Reasons 6-5

7.1 Pacific Contracting-PPC Data and Reasons 7-3

8.1 Old Chemistry Building-PPC Data 8-3

9.1 Zeneca-Constraint Analysis Form 9-5

Ballard 1-1 Last Planner

CHAPTER ONE: INTRODUCTION

1.0 Conceptual Framework

Production processes can be conceived in at least three different ways: 1) as a process of

converting inputs to outputs, 2) as a flow of materials and information through time and

space, and 3) as a process for generating value for customers. All three conceptions are

appropriate and necessary. However, the conversion model has been dominant in the

AEC (architectural/engineering/construction) industry until very recently (Koskela and

Huovila, 1997).

Table 1.1

Conversion View Flow View Value Generation

Nature ofConstruction

a series ofactivities whichconvert inputs

to outputs.

the flows of information& resources, which

release work: composedof conversion,

inspection, moving andwaiting.

a value creatingprocess which

defines andmeets customer

requirements.

MainPrinciples

Hierarchicaldecomposition of

activities; control andoptimization by

activity.

Decomposition atjoints. Elimination ofwaste (unnecessary

activities), timereduction.

Elimination of valueloss - the gap

between achievedand possible value.

Methods&Practices

Work breakdownstructure, critical path

method. Planningconcerned with timingstart and responsibility

for activities throughcontracting or

assigning.

Team approach, rapidreduction of

uncertainty, shielding,balancing, decoupling.

Planning concernedwith timing, quality and

release of work.

Development and testingof ends against means todetermine requirements.Planning concerned withwork structure, process

and participation.

PracticalContribution

Taking careto do

necessarythings.

Taking care thatthe unnecessaryis done as little

as possible.

Taking care thatcustomer

requirements aremet in the best

possible manner..

Conversion/Flow/Value2

Ballard 1-2 Last Planner

The design and construction of AEC facilities (buildings, process plants, airport

terminals, highways, etc.) poses difficult management problems to which the models and

techniques based on the conversion view have proven inadequate. Tradeoffs between

competing design criteria must be made throughout the design process, often with

incomplete information and under intense budget and schedule pressure. Increasingly,

projects are subject to uncertainty because of the pace of technological change and the

rapid shifting of market opportunities and competitor actions.

Production management concepts and techniques based on the conversion model have

not proven capable of solving these difficult problems. The heart of the conversion model

is the assumption that the work to be done can be divided into parts and managed as if

those parts were independent one from another. Management techniques such as work

breakdown structures and earned value analysis belong to this conversion model. Work

breakdown structures are driven by scoping and budget concerns and have the objectives

of insuring that all the work scope is included in one of the parts, insuring that no work

scopes overlap, and allocating costs to each part such that the rollup yields the total for

the project. This division into parts is necessary in order to allocate responsibility to

internal or external work centers, which can subsequently be controlled against scope,

budget, and schedule commitments.

This is fundamentally a contracting mentality, which facilitates the management of

contracts rather than the management of production or work flow. Production

management is the ‘local’ responsibility of those to whom the various parts are assigned

or contracted. If everyone meets their contractual obligations, the project performs

successfully. Unfortunately, this approach is the opposite of robust. When something

goes wrong, as it very often does, the entire structure is prone to collapse.

Ballard 1-3 Last Planner

If a management philosophy and tools are needed that fully integrate the conversion,

flow, and value models, we might consider the product development processes employed

by firms designing and manufacturing consumer products (automobiles, printers,

toasters, etc.). Such processes have developed potentially useful concepts especially in

the area of value; identification of customer needs and translation into engineering

specifications (Ulrich and Eppinger 1993). Product development processes also are

struggling with other issues relevant to the design of AEC facilities, including design

decomposition, organizational means for integration, etc. (Hayes, et al, 1988; Eppinger,

et al, 1990; Gebala and Eppinger, 1991).

As a contribution to the integration of all three models, this thesis applies the flow

model to managing the design and construction of AEC facilities. Conceptualizing the

design and construction process as a flow of information and materials lends itself to

reducing waste by minimizing time information or materials spend waiting to be used,

time spent inspecting information or materials for conformance to requirements, time

spent reworking information or materials to achieve conformance, and time spent moving

information or materials from one specialist to the next. Further, conceptualizing the

design and construction process as a flow of information and materials allows

coordination of interdependent flows and the integration of design with supply and site

construction.

1.2 Assumptions

Fundamental assumptions underlying this research include the following:

Ballard 1-4 Last Planner

q Current construction industry production management thinking and practice is

dominated by the conversion model, consequently value generation and flow

management concepts and techniques are underdeveloped.

q To be consistent with all three models, conversion, flow, and value, production

management should be conceived as having the purpose of creating customer value

while minimizing waste in time and cost. “Customer value” is understood to include

not only the fitness for use of the facility considered with regard to functionality, but

also with regard to all other criteria to which the customer attaches value, e.g.,

project delivery within a time and for a cost that meets the customer’s market and

financial needs.

q "Production" is understood to include both designing and making. The historical

development of production theory in manufacturing has erroneously suggested that

production is entirely concerned with 'making'.3

q Production management is conceived to consist of criteria determination and work

structuring in the ‘planning’ phase, and to consist of work flow control and

production unit control in the ‘execution’ or ‘control’ phase.

This thesis treats only control functions, not planning functions. It does not treat the very

first and fundamental production management activity; i.e., the determination of

customer needs and their translation into design criteria. Criteria determination belongs

to the value generation view. This thesis treats only the flow view. Similarly, work

structuring activities such as identification, sequencing, and scheduling tasks are also not

3 There may be differences between the U.S. and U.K. in the use of these terms. Hencethe effort to be precise. For the most part, the theory of producing artifacts has emergedfrom efforts to better manage factories. More recently, in some instances, the term"manufacturing" has acquired greater scope than merely factory production.

Ballard 1-5 Last Planner

treated here. The scope of this thesis is the control functions of production unit control

and work flow control.

1.3 Contribution to Knowledge

This dissertation proposes to make the following contributions to knowledge:

q Adapted from manufacturing4, a system for production control, the Last Planner

system, is presented that exemplifies the concept of control as causing events to

conform to plan, as distinct from the traditional conception of project control in

terms of after-the-fact variance detection.

q Appropriate application of the production control system is shown to improve work

flow reliability, which promises substantial benefits in project cost and duration

reduction.

q Improvements to the Last Planner system of production control are developed and

tested in a series of case studies, resulting in new concepts and techniques.

Project controls in the AEC industry have focused on detecting variances from project

objectives for cost and schedule, and have not directly dealt with the management of

production. The Last Planner system of production control has proven an effective tool

for improving the productivity of the production units that implement its procedures and

techniques (Ballard and Howell, 1997). This dissertation shifts the focus from the

productivity of the immediate production unit to the reliability of work flow between

production units, and also extends application of the system to design.

1.4 The Author's Role in the Research

4 I.e., from the models and theories developed in industrial engineering

Ballard 1-6 Last Planner

The Last Planner system has been in development by the author since 1992. Several

papers have previously been published by this author on the subject, the first of them in

1993 (Ballard, 1993) at the founding conference of the International Group for Lean

Construction. Last Planner research began with a focus on improving the quality of

assignments in weekly work plans (Koch Refinery Mid-Plants Project, 1993-45), added a

lookahead process to shape and control work flow (PARC, 19956; DMOS-6, 19967),

and eventually was extended from construction to design (Nokia8 and Hewlett-Packard9,

1996). During that development, the objective shifted from improving productivity to

improving the reliability of work flow. This resulted from a change in conceptual

framework. The initial framework came from the quality management and productivity

improvement initiatives that dominated construction industry performance improvement

efforts in the 1980s. The shift to work flow reliability reflected the author's increasing

awareness of the revolution in manufacturing inspired by the Toyota Production System

and eventually labeled "lean production", and also contact with the thinking of Lauri

Koskela regarding production theory and its application to the construction industry.

A key metric of the Last Planner system is the percentage of assignments completed

(PPC), which is clearly a defect rate and a product of the quality management mentality.

Given the objective of improving productivity, measurements were made of the

relationship between the defect rate of a crew, its PPC, and the productivity of that crew.

Not surprisingly, such measurements revealed a positive correlation10. However, the

5 Ballard and Howell, 19976 Ballard, Howell, and Casten (1996)7 Ballard and Howell, 19978 Koskela, Ballard, and Tanhuanpaa (1997)9 Miles (1998)10 For examples, see the references footnoted previously.

Ballard 1-7 Last Planner

activity focus characteristic of the productivity improvement 'mind' concealed the

importance of that crew's PPC for the productivity of the crews that followed it and built

upon its work product. Even the introduction of a lookahead process was motivated

initially by the observation that simply shielding a crew from poor assignments was

insufficient to optimize crew productivity. To do so required matching load and capacity,

both of which required managing load or work flow. The more powerful and

fundamental opportunity to coordinate action among multiple crews was hidden by the

dominance of what Koskela has called the "conversion model" and its exclusive focus on

the activity as the unit of control rather than work flow.

Prior to the founding of the Lean Construction Institute (LCI) in August of 199711,

the Last Planner system had evolved to roughly its current form, with a clear conceptual

basis in production theory a la Koskela and an explicit and self-conscious objective of

managing work flow. What remained to be done was to learn how to improve work flow

reliability above the 35%-65% range commonly discovered up to that time. One purpose

of this dissertation is to describe what was done to improve work flow reliability,

measured by PPC, and the results achieved. That improving work flow reliability is

beneficial hardly requires argument. However, identifying and quantifying the specific

benefits will be a matter for future research. The second purpose of this research is to

explore applicability of the Last Planner system to design.

11 The Lean Construction Institute was founded in August of 1997 as a partnershipbetween Gregory A. Howell and Glenn Ballard, dedicated to research, training andconsulting in construction industry production management. Subsequently, IrisTommelein and Todd Zabelle have become partners in the enterprise, along with MarkReynolds, Managing Director of Lean Construction International, based in London. Allthe case studies reported in this thesis were undertaken as research projects for LCI, ofwhich this author is Research Director. All case studies were carried out under the

Ballard 1-8 Last Planner

1.4 Structure of the Dissertation

Traditional project control theory and practice is described and critiqued in Chapter

Two. The Last Planner System of Production Control is presented in Chapter Three as

satisfying the requirements revealed by the critique. Chapter Four describes the research

methodology used in the dissertation and is followed by Chapters 5, 6, 7, 8, and 9, each

devoted to a case study. Conclusions from the case studies are reported in Chapter 10,

followed by a glossary of terms, a list of references, a bibliography, and an appendix

consisting of documents from the design case, Next Stage.

direction of this author, who also was the primary participant in project events and theprimary collector of case study data.

Ballard 2-1 Last Planner

CHAPTER TWO: CRITIQUE OF PRODUCTIONCONTROL

2.1 What is Production Control?

The purpose of this chapter is to provide a critique of production control theory and

practice. But first it is necessary to clarify what is meant by “production control”.

2.1.1 The Meaning of “Production”

Production has been an explicit topic of study primarily in industrial engineering, which

has dealt almost entirely with one type of production; namely, manufacturing (in the

sense of 'making'), with only occasional forays into construction, plant maintenance,

building maintenance, agriculture, forestry, mining, fishing, etc. Design and engineering

have infrequently been conceived as production processes; the focus almost entirely

being placed on making things rather than designing them.

Although the meaning of the term at its most universal is synonymous with “making”,

“manufacturing” is most commonly12 used to denote the making of many copies from a

single design, and consequently is primarily focused on products for a mass market, most

of those products being moveable from the place manufactured to the place of use. There

are exceptions to the products being moveable, although still copies from a single design;

e.g., ships and airplanes. Within the world of construction, manufacturing in this sense is

approached mostly closely by 'manufactured housing'.

12 Exceptions occur with thinkers and writings regarding product development, which by

its nature must integrate designing and making, at least in the sense of makingprototypes.

Ballard 2-2 Last Planner

Various types of making have been proposed, among them ‘assembly’, the joining of

parts into a whole, as distinct from ‘fabricating’, the shaping of materials. For example,

construction is often categorized as a type of ‘fixed position manufacturing’ (Schmenner,

1993), along with shipbuilding and airplane assembly. In all these instances of assembly,

the assembled product eventually becomes too large to be moved through assembly

stations, so the stations (work crews) must be moved through them, adding additional

components and subassemblies until the artifact (building, bridge, tunnel, plant, house,

highway, etc) is completed.

Many publications exist on the topic of production management in manufacturing,

the larger part of which adopt the perspective of the industrial or production engineer

(Bertrand et al, 1990; Hopp and Spearman, 1996; Murrill, 1991; Vollman et al, 1992). A

subset of this category concern themselves with the psychological/sociological aspects of

manufacturing management (Scherer, 1998). The development of alternatives to mass

production over the last 40 years has been revolutionary. Early and influential production

management theorists include Jack Burbidge (1983; 1988) and W. Edwards Deming

(1986), to mention but a few from the West. Taiichi Ohno (1988) and Shigeo Shingo

(1988) were the primary architects of the Toyota Production System, the archetype for

lean production, so named in part to counterpose it to "mass" production. Burbidge's

groundbreaking thought began to emerge in the 1960s. Deming was instrumental in the

implementation of quality management and statistical quality control concepts and

techniques in Japan after the 2nd World War. The work of Ohno and Shingo was

concentrated in the period of the late 50's into the 70's. The Machine That Changed the

World (Womack et al., 1990) reported the findings of an international study of the

automotive industry and was followed by Lean Thinking (Womack and Jones, 1996)

Ballard 2-3 Last Planner

which presented the principles and basic concepts behind the new forms of

manufacturing and proposed to extend them to the entire enterprise. Womack and Jones

have popularized and made more easily accessible the concepts and techniques of lean

production.

Defining production as the designing and making of artifacts allows us to understand

how construction is a type of production and also that design is an essential component

in production generally and in construction specifically. Lauri Koskela (Koskela 1992,

1999; Koskela and Huovila 1997; Koskela et al. 1996, 1997) is the foremost production

theorist in construction. His study of the applicability of newly emergent manufacturing

concepts and techniques to the construction industry has driven him back to the

development of a theory of production as such (Koskela, 1999).

2.1.2 THE MEANING OF “CONTROL”

The term “control” has a wide range of meanings. According to the Concise Oxford

Dictionary, its meanings include to dominate, command; to check, verify; to regulate. It

has long been associated with accounting. The Old French contreroller: to keep a roll of

accounts.

Accounting is the essence of project control theory, more fully described in section

2.2.2 below (Diekmann and Thrush, 1986; Project Management Body of Knowledge

(PMBOK), 1996; Riggs, 1986). The essential activity is monitoring actual costs or

schedule performance against target in order to identify negative variances. Corrective

action is obviously necessary in order to correct such negative variances, but the

literature hardly addresses corrective action.

Ballard 2-4 Last Planner

Industrial process control introduces feedback and feedforward mechanisms for

regulating a process (Murrill, 1993). Feedback is initiated by a comparison of actual with

target outputs. Feedforward is initiated by a comparison of actual with target inputs.

The artificial intelligence community contributes the blackboard system of control, in

which coordination of a number of interdependent specialists is managed by rules for

taking turns 'writing on a blackboard'; i.e., for contributing to their collaborative work

(Hayes-Roth, 1985). AI adherents have been in the forefront of empirical study of

design, and despite their technological orientation, have found social and organizational

issues to be of great importance. Finger et al (1995) conclude: “The social process plays

a major role in the articulation and realization of the product design, particularly in large

projects.” (p.89). Bucciarelli (1984) reports that designers spend 85-90% of their time

talking, writing, negotiating, meeting, searching, etc. as opposed to drawing and

calculating.

Production control theorists working in manufacturing distinguish two primary ways

of regulating work flow in manufacturing systems: push and pull. Push systems release

materials or information into a system based on preassigned due dates (from a master

production schedule, for example) for the products of which they are parts. Pull systems

release materials or information into a system based on the state of the system (the

amount of work in process, the quality of available assignments, etc) in addition to due

dates (Hopp and Spearman, 1996). In factory systems, pull may be derivative ultimately

from customer orders. In construction, pull is ultimately derivative from target

completion dates, but specifically applies to the internal customer of each process.

Applicability of these concepts to production control has been explored by this author

(Ballard, 1999).

Ballard 2-5 Last Planner

Some theorists (Kelly, 1994) propose that complex, dynamic systems are regulated

not by anything resembling a central mind, but through the independent action of

distributed decision makers. The following excerpt from Eric Scherer’s introduction to

Shop Floor Control-A Systems Perspective indicates the emergence of a new conceptual

framework,

“To master the challenges of the future, there must be a change inour thinking paradigm. Manufacturing is not deterministic! …theproblem of systems design for shop floor control is no longer theproblem of ‘optimization’. The reductionistic paradigm … needs tobe replaced by a holistic paradigm of agile activity, dynamicbehavior, and evolutionary development.”

2.2 Project Management

2.2.1 THE PROJECT MANAGEMENT BODY OF KNOWLEDGE

The construction industry is organized in projects and current production theory and

practice are heavily influenced by the concepts and techniques of project management.

According to PMI’s A Guide to the Project Management Body of Knowledge, “a project

is a temporary endeavor undertaken to produce a unique product or service.” The

making (i.e., manufacturing) of multiple copies of a product does not occur through

projects so understood. This focus on product uniqueness and the project form of

organization has dominated thinking about production of the built environment so far as

to discourage learning from non-project industries such as product manufacturing

(Koskela, 1992).

Again according to PMI (1996), project management includes the management of

integration, scope, time, cost, quality, human resources, communications, risk, and

procurement. Any or all of these could conceivably concern the actual production

process itself, but perhaps most of all time and cost.

Ballard 2-6 Last Planner

Time management is said to consist of activity definition, activity sequencing, activity

duration estimating, schedule development, and schedule control. The focus is entirely on

delivering project objectives; in Koskela’s terms, on the transformation or conversion

processes (activities) and not on flow or value generation processes. Activities are to be

defined so as to facilitate a division of labor and subsequent tracking (accounting) of

conformance to requirements. There is no mention of structuring work for flow or of

defining activities so that they facilitate the actual performance of the work. Activity

sequencing assumes that handoffs from one set of specialists to the next occur only once;

that there is no repetition or cycling to be managed (“conditional diagramming methods”

are mentioned-see page 63-but not developed). Schedule control is concerned with

managing changes to the schedule rather than with execution of scheduled work; with

the exception of expediting as a type of time management corrective action (see page

72). Cost management is treated very much in the same way as time management. The

question for project management thus remains: ‘Who manages production and how?’

PMI differentiates between project processes and product-oriented processes (page

27), the former being characteristic of all types of projects and the latter specific to the

various types of production with which projects may be involved. What is missing in this

distinction is the concept of the project itself as a temporary production system linked to

other temporary and permanent production systems for materials, equipment, labor, etc.

Projects as such have no necessary connection with production. For example, a project

may be to solve a problem of getting voters to register. In this broad sense of the term,

‘project’ becomes virtually synonymous with a single instantiation of the problem solving

process, and project management consists of the tools and techniques for managing

problem solving processes in groups. On projects that do have production objectives,

Ballard 2-7 Last Planner

production itself takes place alongside project management, but is not directly the

business of project management. Consequently, project control consists of monitoring

progress toward project objectives and taking corrective action when the ship appears to

be off course.

This concept of project control is very different from production control, which is

dedicated to causing events to conform to plan and to replanning when events cannot be

conformed. Production control conceives production as a flow of materials and

information among cooperating specialists, dedicated to the generation of value for

customer and stakeholders.

2.2.2 CRITIQUE OF THE TRADITIONAL PROJECT CONTROL MODEL

Project control has been hitherto conceived and carried out consistently with the

conversion or transformation view of projects (Koskela and Huovila, 1997). The

received wisdom regarding AEC project control systems is founded on a widely shared

conception of their purpose. “This (project control) system must provide the information

needed for the project team and project participants to identify and correct problem areas

and, ultimately, to keep project costs and schedule ‘under control’.” (Diekmann and

Thrush, 1986). The objective is to detect negative variances from target, so corrective

action can be taken. This is quite different from the active concept of control dominant in

manufacturing production control systems, especially those employing a pull strategy, in

which the purpose of control is to cause events to conform to plan. In the following, we

further examine traditional project controls and their difference from the concept of

control in the Last Planner system, which is to be introduced in Chapter 3.

In traditional project control, the objects of control are time and resources.

Resources (labor hours, material, equipment, indirects) are planned and controlled

Ballard 2-8 Last Planner

through cost control systems, the objective of which is productivity, i.e., efficient use of

resources. A budget is prepared for each resource, the use of resources is monitored

against their budgets, and periodic forecasts are made of resource requirements based on

the current state of the project.

Controlling time involves planning, scheduling, and monitoring. Planning decides

what is to be accomplished and in what sequence. Scheduling determines task duration

and timing. Monitoring checks progress of tasks against the schedule and forecasts when

work will be completed. The objective of time control is production or progress, not

productivity.

Decisions made regarding budget and schedule, productivity and production must

recognize their interdependence. Productivity and production are formally related in

earned value systems, which propose a solution to the problem that progress and

expenditure of resources need not coincide. Rates of resource consumption are

established for the various kinds of work to be performed on a project; e.g., 9.32

engineering labour-hours per piping isometric drawing or 12.4 labour-hours per purchase

order. Completing an individual piping isometric drawing earns 9.32 labour-hours

regardless of the actual number of hours consumed in its production. Progress toward

project completion is tracked by accumulating the earned hours and comparing that to

the total hours to be earned for the entire project. For example, suppose the project

schedule calls for production of 10 piping isometric drawings at time t, but only 9

drawings have been produced. Only 83.88 (9 x 9.32) hours have been earned of the 93.2

scheduled, so that portion of the project is 10% behind schedule (83.88/93.2=.90). That

is a measure of production against schedule.

Ballard 2-9 Last Planner

Productivity can be quite a different story. Suppose it has taken only 80 hours to

produce the 9 piping isometric drawings. Since 83.88 hours were earned, the

performance factor is .95 and the piping group is operating at 95% of its budget for

isometric drawings. In this case, the project is behind schedule, but under budget.

Production is poor and productivity is good.

Earned value analysis is a means for controlling projects through productivity and

progress. By itself, it would have the design manager believe that a project is performing

well if it is earning labor hours at the budget unit rate and also earning sufficient hours to

maintain a scheduled earnings plan expressed as percentages of earned hours to total

hours to be earned. The obvious weakness in this control mechanism is that projects may

exhibit budget productivity and be on the earnings plan, but not be doing the right work

in the right way at the right time. Although things appear to be on track, the train is

destined to eventually run off the rails because work is being produced that does not

conform to product quality requirements or to process quality requirements (e.g., out of

sequence). Consequently, quality control is invoked as a separate control mechanism,

although rarely if ever controlling against the objective of expressing customer needs in

engineering specifications, but rather controlling against the objectives of avoiding

calculational and dimensional errors. As for the issue of the timing of work, it has proven

necessary to establish schedule milestones to enforce adherence to a work sequence.

These rear guard actions are frequently ineffective against the dominant progress and

productivity controls, which consequently cause managers to throw the lever in the

wrong direction because they misevaluate actual project performance (Howell and

Ballard, 1996).

Ballard 2-10 Last Planner

Work Breakdown Structure (WBS) is a key element in traditional project controls.

“A WBS provides a framework for integrated schedule and cost planning and allows for

monitoring and control by management by establishing the manner in which estimates are

assigned and costs are accumulated and summarized.” (p. 21, Diekmann and Thrush,

1986). The objective is to divide the work to be done in the project into parts so they can

be monitored and controlled. No mention is made of the production process as such.

[NB: Inclusion of the flow view adds new criteria to the decomposition process. Roughly

speaking, we want to break the whole into parts so we can more easily put the parts back

together again. Structure work for flow and assembly, not only for budgeting and

monitoring.]

Further decomposition in the traditional process eventually defines work packages as

the smallest unit. Work packages often correspond to contract packages or to pay items

within a single contract. The dominance of the conversion view is perhaps best revealed

in the following quotes: “A work package is a cost center.” (p. 73, Neil, James M.

Construction Cost Estimating for Project Control, 1982). “The WBS provides the

framework for defining the project from the top all the way down to its smallest

components and for accumulating the costs associated with each piece. In so doing, the

WBS provides a data base from which problem areas can be identified, forecasts made,

and corrective action can be taken.” (p. 21, Diekmann and Thrush, 1986). It appears to

be assumed that costs arise within that part of the project in which they are detected.

Further, control is essentially control of behaviour, given the default assumption that

tasks/work packages/contracts can be carried out. The flow view, with its

interdependence of parts (both as regards the 'product' and the process of making that

product), is neglected in this perspective. Equally neglected is consideration of capability.

Ballard 2-11 Last Planner

We are clearly dealing here with a type of push system and the controls appropriate to a

push system.

Despite the focus on cost and schedule ‘accounting’, theorists recognize the primacy

of the control act itself. “Without corrective actions a project control system becomes

merely a cost/schedule reporting system.” (p. 29, Diekmann and Thrush, 1986).

However, the traditional view is that control consists of correcting deviations from plan.

Deviations are expected, but that expectation is not rooted in the idea that variation is

natural, but rather that sin is inevitable. Diekmann and Thrush devote less than two pages

of a 108 page paper to corrective action and provide no more advice than to inform

managers and supervisors at every level in the project about deviations so they can

“…correct those trouble spots.” (p. 28). They appear to assume that causes of deviation

will be apparent and the appropriate corrective action obvious. “These problems can be

easily traced to their source allowing early detection of unfavorable trends.” (p. 33,

Diekmann and Thrush, 1986). If the standard corrective actions are indeed ‘Try harder!’

and ‘Add more men!’, that would be consistent with the traditional view.

Advocates of system dynamics have proposed to supplement traditional network

analyses and models, adding to the “…growing evidence that network analysis on its

own is not sufficient to model and manage the behaviour of projects.” (Williams et al.,

1995, p. 154). They propose to provide additional information to project managers so

they avoid misevaluating the state of the project and consequently making decisions that

cause things to get worse rather than better (See p. 125 of Rodrigues, 1994). Ballard and

Howell (1996) suggest that it is impossible to make good decisions about causes or

corrections of deviations, relying only on productivity and progress data, without

understanding work flow. One can hardly avoid concluding that the traditional control

Ballard 2-12 Last Planner

system is indeed based almost exclusively on the conversion or activity view of the

production system.

2.3 Previous Applications of Production Control Concepts to the AECIndustry

A survey of the literature reveals several primary contributors to the theory and practice

of production (as opposed to project) control in the construction industry. Ballard and

Howell’s contributions are described in Chapter Three. Melles and Wamelink (1993)

developed a very similar line of thinking independently, culminating in their joint PhD

thesis at Delft University, The Netherlands. Lauri Koskela, Senior Researcher at

Finland’s building research institute, VTT, is the leading theorist in production

management in construction. The University of Reading has been active in the field of

production management for a number of years. John Bennett’s Construction

Management from 1985 is an excellent example of their work. Addis’ 1990 book,

Structural engineering: the nature and theory of design, is also a highly relevant work

for this research. Alexander Laufer’s work on project planning takes a production

control orientation by virtue of its focus on uncertainty and variability and their

management. Given the relative obscurity of Melles and Wamelink’s, only their work is

presented in detail. The work of Koskela is described only to the extent needed to remind

the reader of his vital contributions. That should in no way be taken as an indication of

relative importance of the various contributions.

2.3.1 MELLES AND WAMELINK

Introducing their discussion of the theory of production control, Melles and Wamelink

(1993) explain, “Contrary to what is customary in the construction industry we shall not

Ballard 2-13 Last Planner

assume, beforehand, the theories in the field of project management. …Production

control in construction companies has traditionally been aimed at the control of

projects.” For Melles and Wamelink, production control consists of “…the activities

relating to the adjustment of all aspects of the production process, so that the

preconditions in which the production process is to be executed, are met.” Drawing on

manufacturing production control, they emphasize: 1) Thinking in terms of hierarchical

levels of decision; i.e., control at company level, factory level, and production unit level,

and 2) Thinking in terms of decision functions within the hierarchical levels; i.e.,

aggregate production control, material coordination, workload control, workorder

release, workload acceptance, detailed workorder scheduling, capacity allocation, and

shop floor control. The manufacturing model on which they rely is that of Bertrand et al.,

1990.

Melles and Wamelink propose a ‘translation’ of the manufacturing model into

decision functions appropriate to various types of construction, identifying at the

‘factory’ level project coordination (achieved in part by network schedules), mobilisation

planning (by means of “six weeks scheme”), and allocation planning (by means of “task

scheme”).

In addition to the primary contribution of directing attention to manufacturing theory

and practice, Melles and Wamelink’s work identifies functionalities AEC industry

production control systems should possess. Their specific objective was to assist in the

design of information systems. Consequently, they did not explicitly apply their model to

evaluation of current management systems and practice. However, the overwhelmingly

negative results of so doing are implicit in their critique of project management software.

For example, speaking of project coordination, they comment, “…it can immediately be

Ballard 2-14 Last Planner

deduced that the project management software available on the market is indeed about a

certain aspect (within the framework, the decision function project coordination). The

other decision functions (resource planning, mobilization planning, etc.) are, generally

speaking, not recognizable.” (p. 35). This critique is made more explicitly in Wamelink et

al., 1993.

2.3.2 KOSKELA

Lauri Koskela (1999) proposes the following design criteria or principles for a

production control system. In fact, he claims they are true for the Last Planner system,

which is to be presented in Chapter Three:

"The first principle is that the assignments should be sound regarding their

prerequisites. This principle has also been called the Complete Kit by Ronen

(Ronen 1992). The Complete Kit suggests that work should not start until all the

items required for completion of a job are available. Thus, this principle strives to

minimize work in suboptimal conditions.

"The second principle is that the realization of assignments is measured and

monitored. The related metrics, Percent Plan Complete (PPC), is the number of

planned activities completed, divided by the total number of planned activities, and

expressed as a percentage. This focus on plan realization diminishes the risk of

variability propagation to downstream flows and tasks.

"Thirdly, causes for non-realization are investigated and those causes are removed.

Thus, in fact, continuous, in-process improvement is realized.

"The fourth principle suggests maintaining a buffer of tasks which are sound for each

crew. Thus, if the assigned task turns out to be impossible to carry out, the crew

can switch to another task. This principle is instrumental in avoiding lost

Ballard 2-15 Last Planner

production (due to starving) or reduced productivity (due to suboptimal

conditions).

"The fifth priciple suggests that in lookahead planning (with time horizon of 3-4

weeks), the prerequisites of upcoming assignments are actively made ready. This,

in fact, is a pull system that is instrumental in ensuring that all the prerequisites are

available for the assignments. On the other hand, it ensures that too great material

buffers do not emerge on site.”

2.4 Criteria for a Design Production Control System

The preceding review and critique of the literature suggests the following guidelines and

criteria for an effective design production control system:

q Variability must be mitigated and remaining variability managed. Variability is virtually

disregarded in current control systems. But the construction industry certainly has its share of

variability: variability in quality, variability in processing times, variability in deliveries, etc.

Neglect of variability causes greater variability, and there is always an associated penalty.

According to Hopp and Spearman (1996), variability results in some or all of the following:

§ buffering of flows, which increases lead times and work-in-process

§ lower resource utilization

§ lost throughput

q Assignments are sound regarding their prerequisites.

q The realization of assignments is measured and monitored.

q Causes for failing to complete planned work are investigated and those causes are removed.

q A buffer of sound assignments is maintained for each crew or production unit.

q The prerequisites of upcoming assignments are actively made ready.

q The traditional schedule-push system is supplemented with pull techniques. Not only do pull

systems usually perform better than push systems (Hopp and Spearman, 1996), but pull systems are

Ballard 2-16 Last Planner

especially needed in conditions of variability.

q Production control facilitates work flow and value generation. Production thinking and practice in

all areas has focused primarily on the task goals of production and neglected flow and value

(Huovila and Koskela, 1997). The object of traditional project control has been behavior. What

needs to be controlled is work flow.

q The project is conceived as a temporary production system. The model for corrective action in

traditional project control is course correction, drawn by analogy from the path of a vehicle bound

for a specific destination with a target arrival time and a specified spending budget or otherwise

limited resources. If the project is to be conceived rather as a temporary production system, the

course correction model is radically oversimplified and inappropriate. The flow of materials and

information is what is to be controlled. They flow through very complex networks of temporary and

permanent production systems. Corrective action must be taken within an understanding of these

networks and of the impact of changes in sequence, processing methodologies, buffer location and

sizing, local control strategies (e.g., pull or push), etc.

q Decision making is distributed in production control systems. Traditional project control assumes

the necessity and possibility of central control. The underlying image is that of a single mind and

many hands. Arguably, dynamic production systems cannot be controlled centrally, but rather are

adaptive creatures driven by decision making at their periphery.

q Production control resists the tendency [of designers and engineers] toward local suboptimization

(Green, 1992). Green's comment was specifically directed to the tendency of designers and

engineers toward local suboptimization, but that is a general tendency of any system in which there

is a division of labor.

In Chapter Three, the Last Planner system of production control is described and

evaluated against these criteria.

Ballard Last Planner `3-1

CHAPTER THREE: DESCRIPTION AND HISTORY OFTHE LAST PLANNER SYSTEM OF PRODUCTION

CONTROL

3.1 Hierarchical Structure

Aside from the simplest and smallest jobs, design and construction require planning and

control done by different people, at different places within the organization, and at

different times during the life of a project. Planning high in the organization tends to

focus on global objectives and constraints, governing the entire project. These objectives

drive lower level planning processes that specify means for achieving those ends.

Ultimately, someone (individual or group) decides what physical, specific work will be

done tomorrow. That type of plans has been called "assignments". They are unique

because they drive direct work rather than the production of other plans. The person or

group that produces assignments is called the "Last Planner" (Ballard and Howell 1994).

3.2 Should-Can-Will-Did

The term "assignments" stresses the communication of requirements from Last Planner

to design squad or construction crew. But these products of planning at the production

unit level are also commitments to the rest of the organization. They say what WILL be

done, and (hopefully) are the result of a planning process that best matches WILL with

SHOULD within the constraints of CAN.

Ballard Last Planner `3-2

Figure 3.1

SHOULD

CAN WILLLAST PLANNER

PLANNING PROCESS

The formation of assignments in the Last Planner planning process.

Unfortunately, last planner performance is sometimes evaluated as if there could be no

possible difference between SHOULD and CAN. "What will we do next week?”

“Whatever is on the schedule," or “Whatever is generating the most heat.” Supervisors

consider it their job to keep pressure on subordinates to produce despite obstacles.

Granted that it is necessary to overcome obstacles, that does not excuse creating them or

leaving them in place. Erratic delivery of resources such as input information and

unpredictable completion of prerequisite work invalidates the presumed equation of

WILL with SHOULD, and quickly results in the abandonment of planning that directs

actual production.

Failure to proactively control at the production unit level increases uncertainty and

deprives workers of planning as a tool for shaping the future. What is needed is to shift

the focus of control from the workers to the flow of work that links them together. The

Last Planner production control system is a philosophy, rules and procedures, and a set

of tools that facilitiate the implementation of those procedures. Regarding the

procedures, the system has two components: production unit control and work flow

Ballard Last Planner `3-3

control. The job of the first is to make progressively better assignments to direct workers

through continuous learning and corrective action. The function of work flow control is

perhaps evident in its name—to proactively cause work to flow across production units

in the best achieveable sequence and rate.

3.3 Production Unit Control

The key performance dimension of a planning system at the production unit level is its

output quality; i.e. the quality of plans produced by the Last Planner. The following are

some of the critical quality characteristics of an assignment:

q The assignment is well defined.q The right sequence of work is selected.q The right amount of work is selected.q The work selected is practical or sound; i.e., can be done.

“Well defined” means described sufficiently that it can be made ready and completion can

be unambiguously determined. The "right sequence" is that sequence consistent with the

internal logic of the work itself, project commitments and goals, and execution strategies.

The "right amount" is that amount the planners judge their production units capable of

completing after review of budget unit rates and after examining the specific work to be

done. "Practical" means that all prerequisite work is in place and all resources are

available.

The quality of a front line supervisor's assignments may be reviewed by a superior

prior to issue, but such in-process inspection does not routinely produce measurement

data, even when corrections are necessary. Planning system performance is more easily

measured indirectly, through the results of plan execution.

Percent Plan Complete (PPC) is the number of planned activities completed divided

Ballard Last Planner `3-4

by the total number of planned activities, expressed as a percentage. PPC becomes the

standard against which control is exercised at the production unit level, being derivative

from an extremely complex set of directives: project schedules, execution strategies,

budget unit rates, etc. Given quality plans, higher PPC corresponds to doing more of the

right work with given resources, i.e. to higher productivity and progress.

Percent Plan Complete measures the extent to which the front line supervisor's

commitment (WILL) was realized. Analysis of nonconformances can then lead back to

root causes, so improvement can be made in future performance. Measuring

performance at the Last Planner level does not mean you only make changes at that

level. Root causes of poor plan quality or failure to execute planned work may be found

at any organizational level, process or function. PPC analysis can become a powerful

focal point for breakthrough initiatives.

The first thing needed is identification of reasons why planned work was not done,

preferably by front line supervisors or the engineers or craftsmen directly responsible for

plan execution. Reasons could include:

q Faulty directives or information provided to the Last Planner; e.g. the informationsystem incorrectly indicated that information was available or that prerequisitework was complete.

q Failure to apply quality criteria to assignments; e.g. too much work was planned.q Failure in coordination of shared resources; e.g. lack of a computer or plotter.q Change in priority; e.g. workers reassigned temporarily to a "hot" task.q Design error or vendor error discovered in the attempt to carry out a planned

activity. This provides the initial data needed for analysis and improvement of PPC, andconsequently for improving project performance.

3.4 Work Flow Control Here we turn to the topic of work flow control; i.e., causing work to move between

Ballard Last Planner `3-5

production units in a desired sequence and rate. Production Unit Control coordinates the

execution of work within production units such as construction crews and design squads.

Work Flow Control coordinates the flow of design, supply, and installation through

production units.

In the hierarchy of plans and schedules, the lookahead process has the job of work

flow control. Lookahead schedules are common in current industry practice, but typically

perform only the function of highlighting what SHOULD be done in the near term. In

contrast, the lookahead process within the Last Planner system serves multiple functions,

as listed in Table 3.1. These functions are accomplished through various specific

processes, including activity definition, constraints analysis, pulling work from upstream

production units, and matching load and capacity, each of which will be discussed in the

following pages.

Ballard Last Planner `3-6

Figure 3.2

5

Selecting, sequencing, &

sizing work we think can be done

Master Schedule

Make work ready by screening & pulling

Information

Selecting, sequencing, & sizing work

we know can be done

Current status & forecasts

Lookahead

Workable Backlog Weekly

Work Plans

ProductionResources

Completed Work

Chart PPC & Reasons

Action topreventrepetitiveerrors

PLANNING SYSTEM

Last Planner System with Lookahead Process highlighted

The vehicle for the lookahead process is a schedule of potential assignments for the next3 to 12 weeks. The number of weeks over which a lookahead process extends is decidedbased on project characteristics, the reliability of the planning system, and the lead timesfor acquiring information, materials, labor, and equipment. Tables 3.2 and 3.3 areexamples of construction and engineering lookahead schedules, respectively. Thelookahead schedule is not a simple drop out from the master schedule. Indeed, it is oftenbeneficial to have the team that is to do the work in the next phase of a projectcollectively produce a phase schedule that serves to coordinate actions that extendbeyond the lookahead window (the period of time we choose to look ahead).

Ballard Last Planner `3-7

Table 3.1

Functions of the Lookahead Process

• Shape work flow sequence and rate• Match work flow and capacity• Decompose master schedule activities

into work packages and operations• Develop detailed methods for executing

work• Maintain a backlog of ready work• Update and revise higher level schedules

as needed.

Functions of the Lookahead Process Prior to entry into the lookahead window, master schedule or phase schedule activities

are exploded into a level of detail appropriate for assignment on weekly work plans,

which typically yields multiple assignments for each activity. Then each assignment is

subjected to constraints analysis to determine what must be done in order to make it

ready to be executed. The general rule is to allow into the lookahead window, or allow

to advance from one week to the next within the lookahead window, only activities that

can be made ready for completion on schedule. If the planner is not confident that the

constraints can be removed, the potential assignments are retarded to a later date.

Figure 3.3 is a schematic of the lookahead process, showing work flowing through

time from right to left. Potential assignments enter the lookahead window 6 weeks ahead

of scheduled execution, then move forward a week each week until they are allowed to

enter into workable backlog, indicating that all constraints have been removed and that

they are in the proper sequence for execution. If the planner were to discover a

Ballard Last Planner `3-8

constraint (perhaps a design change or acquisition of a soils report) that could not be

removed in time, the assignment would not be allowed to move forward. The objective is

to maintain a backlog of sound work, ready to be performed, with assurance that

everything in workable backlog is indeed workable.13 Weekly work plans are then

formed from workable backlog, thus improving the productivity of those who receive the

assignments and increasing the reliability of work flow to the next production unit.

Table 3.2

PROJECT: Pilo t 5 WK LOOKAHEAD

ACTIVITY 3 / 9 # # # NEEDSM T W T F S M T W T F S M T W T F S M T W T F S

Scot t 's crew

"CUP" AHUs-1 0 CHW, 2 HW X X X X X X X X X X X X X X X CHW d elivers 1 -8 -9 7 t hru

1-13 .HW de live rs 1 -2 0.Punch, lab e l, & t ag AHUs x x x Mat er ials on sit e

Ro n's crew

DI St eam to Humid ifier x x x Mat er ials on sit e

DI St eam Blowd own x x Check ma te rial

DI St eam Co nd. t o x x x x x x x x x x x x x Mat er ial on s it eco olers (1 3 )

Charles ' crew

2 00 deg HW 1 -"H" x x x Mat l de live ry 1 -8 -9 7

20 0 deg HW 1 -"B" x x x x x x x x x x Re lease mat l for 1 -1 5 -9 7& 1 -"D"1 st flr 2 0 0 d eg HW x x x x x x x x x x Mat er ial on s it e . Need Westguides & ancho rs Wing flr co ve red.Richard's c rew

2 -"A" HW & CHW x x x x x Co nt rol va lve s for added VAV co ils

CHW in C-E-G tunnels x x x x x x x x x x x x x x x Need tunne ls paint ed & re lease ma te rials

Misc FCUs & co nd. drains x x x x x x x x x x Ta ke off & o rde r ma te rialsin "I" , " J", & "K" 1 st flr

Punch, lab e l & t ag x x x x x x x x x x Mat er ial on s it e

1 / 1 3/ 97 1 / 20 / 9 7 1 / 2 7/ 97 2 / 3 / 9 7

Construction Lookahead Schedule14

13 Deliberately building inventories, inventories of ready work in this case, may seem

contradictory to the goals of just-in-time. To clarify, inventories of all sort are to beminimized, but as long as there is variability in the flow of materials and information,buffers will be needed to absorb that variability. Reducing variability allows reductionof buffer inventories.

14 The "5 Week Lookahead Schedule" excludes the week covered by the Weekly WorkPlan, so shows only 4 weeks.

Ballard Last Planner `3-9

3.4.1 CONSTRAINTS ANALYSIS

Once assignments are identified, they are subjected to constraints analysis. Different

types of assignments have different constraints. The construction example in Table 3.4

lists contract, design, submittals, materials, prerequisite work, space, equipment, and

labor; plus an open-ended category for all other constraints. Other constraints might

include permits, inspections, approvals, and so on. Design constraints can virtually be

read from the Activity Definition Model: clarity of directives (level of accuracy required,

intended use of the output, applicable section of code), prerequisite work (data,

evaluations, models), labor and technical resources. We previously met these constraints

in the discussion of Production Unit Control; then as reasons for failing to complete

assignments on weekly work plans.

Table 3.3

Project:Discipline:Process

Planner: sChecked By; x

Prep. Dt: 3/14/02 Week Ending: Week Ending: Week Ending: Week Ending:

Activity 3/28/02 4/4/02 4/11/02 4/18/02 OUTSTANDING NEEDSM T W T F M T W T F M T W T F M T W T F

Provide const support (Q & A)

x x x x x x x x x x x x x x x x x x Need questions from subs.

Review submittal(s) x x Need submittals from sub.Aid with tool install dsgn effort.

x x x x x x x x x x x x x x x x x x x Frozen layout, pkg 1 dwgs.

Design drains from tools to tunnel tie-ins.

x x x Frozen layout, input from tool install on installation preferences

Help layout people complete a layout that will work well with tool install routing and drains into the tunnel.

x x Correct tool list.

Complete Pkg 2 specifications

x x x x x Final eqpt and mtl usage from mech & tool install.

Create work plans x x x xSend package to QA/QC reviewer for drain design review

x x Final design dwgs for drains; plot time

Start/complete QA/QC review

x x Set of Package 2 review docs, dwgs

Engineering Lookahead Schedule

Engineering Lookahead Schedule

Ballard Last Planner `3-10

Constraints analysis requires suppliers of goods and services to actively manage their

production and delivery, and provides the coordinator with early warning of problems,

hopefully with sufficient lead time to plan around them. In the absence of constraints

analysis, the tendency is to assume a throw-it-over-the-wall mentality; to become

reactive to what happens to show up in your in-box or laydown yard.

Figure 3.3

6

Screen assignments & make ready each week enough work to maintain 2 week

workable backlog

Notify coordinator

of constraints

status

Explode scheduled activities into work packages on entry tothe lookahead window

1 2 3 4 5

Assign-ments

Workable Backlog

Master schedule activities entering 6th week

Reasons why planned work not completed

The Lookahead Process: Make Ready byScreening & Pulling

Make Ready by Screening and Pulling

3.4.2 PULLING

Pulling is a method of introducing materials or information into a production process.

The alternative method is to push inputs into a process based on target delivery or

completion dates. Construction schedules have traditionally been push mechanisms,

Ballard Last Planner `3-11

seeking to cause intersections in the future of interdependent actions.

Table 3.4

ID A c t i v i t y S t a r t C o n t r a c t D e s i g n S u b m i t t a l s M a t e r i a l s P r e - R e q u i s i t e S p a c e E q u i p m e n t L a b o r O t h e r

2 6 0

S m a l l In t e r i o r W a l l F o r m

s L in e s 4 - M . 8 , 3 - M , 3 -

K , 4 - K . 8 , 3 - H

2 / 9 / 9 8

O K R F I 6 8 O K O K r e b a r O K O K O K N o n e

3 1 0L a r g e In t e r io r W a l l

L i n e L F o r m2 / 9 / 9 8

7 0 0In t e r io r S m a l l W a l l s 3 F a

n d 3 D F o r m s2 / 9 / 9 8

1 1 4 2S m a l l In t e r i o r W a l l F o r m

s L in e s 5 - M . 8 , a n d 5 - K . 82 / 9 / 9 8

1 7 0E a s t W a l l B e t w e e n L i n e

s 2 a n d 6 L in e D o u b le U p2 / 1 3 / 9 8

7 2 0In t e r io r S m a l l W a l l s 3 F a

n d 3 D D o u b le - u p2 / 1 3 / 9 8

1 1 4 6

S m a l l In t e r i o r W a l l s L i n

e s 5 - M . 8 , a n d 5 -

K . 8 D o u b l e - u p

2 / 1 3 / 9 8

3 2 2L a r g e In t e r io r W a l l

L i n e L D o u b l e u p2 / 1 6 / 9 8

2 9 0

S m a l l In t e r i o r W a l l s L i n

e s 4 - M . 8 , 3 - M , 3 - K , 4 -

K . 8 , 3 - H D o u b l e - u p

2 / 1 7 / 9 8

7 3 5In t e r io r S m a l l W a l l s 3 F a

n d 3 D S t r i p2 / 1 8 / 9 8

Screening Assignments: StatusingConstraints

Constraints Analysis

By contrast, pulling allows materials or information into a production process only if the

process is capable of doing that work. In our Last Planner system, conformance of

assignments to quality criteria constitute such a check on capability. Further, making

assignments ready in the lookahead process is explicitly an application of pull techniques.

Consequently, Last Planner is a type of pull system.

Ballard Last Planner `3-12

Figure 3.4

A Traditional (Push) Planning System

PLANNING THE WORKINFORMATION

PROJECT OBJECTIVES

SHOULD

EXECUTING THE PLANRESOURCES DID

A Traditional (Push) Planning System

Certain things have long been pulled as opposed to pushed; e.g., concrete. With its short

shelf life, concrete cannot be ordered too far in advance of need. Fortunately, the lead

time15 for concrete is short, so it is usually possible to wait until you know when it will

be needed before ordering it.

Generally, a window of reliability greater than supplier lead time is needed in order

for pulling to be most effective. Otherwise, the pulled items may not match up with the

work to which they are to be applied. In the industry now, supplier lead times are for the

most part much greater than our accurate foresight regarding work completion, hence

perhaps a reason for the infrequent use of pulling mechanisms.

15 Lead time is the time in advance of delivery one must place an order. It is often

referred to as “supplier lead time”.

Ballard Last Planner `3-13

Figure 3.5

Last Planner: A Pull System

SHOULD

CAN WILLLAST PLANNER

PLANNING PROCESS

Last Planner: A Pull System

3.4.3 MATCHING LOAD AND CAPACITY

Matching load to capacity within a production system is critical for productivity of the

production units through which work flows in the system, and is also critical for system

cycle time, the time required for something to go from one end to the other.

Along with its other functions, the lookahead process is supposed to maintain a backlog

of workable assignments for each production unit (PU). To do so requires estimating the

load various chunks of work will place on PUs and the capacities of PUs to process

those chunks of work. Current estimating unit rates, such as the labor hours required to

erect a ton of steel, are at best averages based on historical data, which are themselves

laden with the tremendous amounts of waste imbedded in conventional practice. When

Ballard Last Planner `3-14

load and capacity are estimated, are we assuming 30% resource utilization or 60%?

What assumptions are being made about variation around averages? Can we expect

actual unit rates to fall short of the average half the time? Clearly we need much more

accurate data than is typically available.

Whatever the accuracy of load and capacity estimates, the planner must still make

some adjustments. Either load can be changed to match capacity, capacity can be

changed to match load, or, more commonly, a combination of the two. Given the

advantages of maintaining a stable work force and avoiding frequent changes, the

preference is often for adjusting load. However, that will not be the case when there are

pressures to meet scheduled milestones or end dates.

Load can be changed to match capacity by retarding or accelerating work flow.

Capacity can be changed to match load by reducing or increasing resources. Pulling helps

balance load to capacity because the PU can request what it needs and in the needed

amounts.

3.4.4 THE LAST PLANNER SYSTEM AS A WHOLE

Last Planner adds a production control component to the traditional project management

system. As shown in Figure 3.6, Last Planner can be understood as a mechanism for

transforming what SHOULD be done into what CAN be done, thus forming an inventory

of ready work, from which Weekly Work Plans can be formed. Including assignments on

Weekly Work Plans is a commitment by the Last Planners (foremen, squad bosses) to

what they actually WILL do.

Ballard Last Planner `3-15

Figure 3.6

ProjectObjective

Information SHOULDPlanning theWork

Last PlannerProcess

CAN WILL

ProductionResources DID

The Last Planner System

3.5 A Brief History of the Last Planner System of Production Control

The functions of production management systems are planning and control. Planning

establishes goals and a desired sequence of events for achieving goals. Control causes

events to approximate the desired sequence, initiates replanning when the established

sequence is either no longer feasible or no longer desirable, and initiates learning when

events fail to conform to plan (Ballard, 1998). When environments are dynamic and the

production system is uncertain and variable, reliable planning cannot be performed in

detail much before the events being planned. Consequently, deciding what and how much

Ballard Last Planner `3-16

work is to be done next by a design squad or a construction crew is rarely a matter of

simply following a master schedule established at the beginning of the project. How are

such decisions made and can they be made better? These questions were the drivers of

initial research in the area of production unit level planning and control under the title of

the “Last Planner System”, a summary report of which is included in Ballard and Howell

(1997).

A key early finding was that only about half of the assignments made to construction

crews at the beginning of a week were completed when planned. Experiments were

performed to test the hypothesis that failures were in large part a result of lack of

adequate work selection rules (these might also be called work release rules). Quality

criteria were proposed for assignments regarding definition, sequence, soundness, and

size. In addition, the percentage of assignments completed was tracked (PPC: percent

plan complete) and reasons for noncompletion were identified, which amounted to a

requirement that learning be incorporated in the control process.

Definition: Are assignments specific enough that the right type and amount ofmaterials can be collected, work can be coordinated with other trades, andit is possible to tell at the end of the week if the assignment was completed?

Soundness: Are all assignments sound, that is: Are all materials on hand? Isdesign complete? Is prerequisite work complete? Note: During the planweek, the foreman will have additional tasks to perform in order to makeassignments ready to be executed, e.g., coordination with trades working inthe same area, movement of materials to the point of installation, etc.However, the intent is to do whatever can be done to get the work readybefore the week in which it is to be done.

Sequence: Are assignments selected from those that are sound in theconstructability order needed by the production unit itself and in the orderneeded by customer processes? Are additional, lower priority assignmentsidentified as workable backlog, i.e., additional quality tasks available in caseassignments fail or productivity exceeds expectations?

Size: Are assignments sized to the productive capability of each crew orsubcrew, while still being achievable within the plan period? Does the

Ballard Last Planner `3-17

assignment produce work for the next production unit in the size andformat required?

Learning: Are assignments that are not completed within the week tracked andreasons identified?

As a result of applying these criteria, plan reliability (the percentage of assignments

completed) increased, and with it, crew productivity also increased (Ballard and Howell,

1997)16.

The use of explicit work selection rules and quality criteria for assignments was

termed “shielding production from upstream uncertainty and variation.” (Ballard and

Howell 1994) Such shielding assures to a large degree that productive capacity is not

wasted waiting for or looking for materials and such. However, because of its short term

nature, shielding cannot avoid underloading resources when work flow is out of

sequence or insufficient in quantity. Further, reasons for failing to complete planned

assignments were dominated in most cases by materials-related problems. Consequently,

a second element of the Last Planner System was created upstream of weekly work

planning to control work flow and to make assignments ready by proactively acquiring

the materials and design information needed, and by expediting and monitoring the

completion of prerequisite work (Ballard, 1997).

The tool for work flow control was lookahead schedules. The construction industry

commonly uses lookahead schedules to focus supervisors’ attention on what work is

supposed to be done in the near future. Experiments in work flow control were

performed using lookahead schedules in a very different way than had been traditional. A

16 On the whole, improvements tended to be from PPC levels around 50% to the 65-70% level, with a

corresponding increase of 30% in productivity. Productivity improvement has ranged from 10% to40%+. It is hypothesized that these differences result from different initial resource utilizationlevels. For example, if initial utilization is 50%, corresponding to a PPC of 50%, then increasingPPC to 70% is matched with an increase in utilization to 65%, which amounts to a 30%improvement in productivity.

Ballard Last Planner `3-18

set of rules was proposed for allowing scheduled activities to remain or enter into each

of the three primary hierarchical levels of the scheduling system:

q Rule 1: Allow scheduled activities to remain in the master schedule unless positive knowledgeexists that the activity should not or cannot be executed when scheduled.

q Rule 2: Allow scheduled activities to remain in the lookahead window only if the planner isconfident that the activity can be made ready for execution when scheduled.

q Rule 3: Allow scheduled activities to be released for selection into weekly work plans only if allconstraints have been removed; i.e., only if the activity has in fact been made ready.

In addition, a set of objectives was proposed for the lookahead process:

q Shape work flow sequence and rateq Match work flow and capacityq Decompose master schedule activities into work packages and operationsq Develop detailed methods for executing workq Maintain a backlog of ready work

Lookahead windows are structured such that week 1 is next week, the week for which a

weekly work plan is being produced. Week 2 is two weeks in the future. Week 3 is three

weeks in the future, and so on. Early data indicated that plans as close to scheduled

execution as Week 2 only contained about half the assignments that later appeared on the

weekly work plans for that week. Week 3’s percentage was only 40% (Ballard, 1997).

Failures to anticipate assignments appear to result in large part from lack of detailed

operations design and consequently could be remedied by incorporating detailed

operations design into the lookahead process (see First Run Studies in the Glossary of

Terms)..

While some operations design can be performed once the type of operation and its

general conditions are known, detailed design (certainly of construction operations)

cannot be done until certain additional information is available; i.e., information

regarding material staging areas, adjacent trades, competing claims on shared resources,

which individuals will be assigned to the work, etc. Consequently, detailed operations

Ballard Last Planner `3-19

design should be performed within the lookahead window, close in time to the scheduled

start of the operation. It is provisionally assumed that this timing requirement applies also

to design activities, but this will be subject to research findings.

3.6 Previous Applications of the Last Planner System to Design

Previous to the research reported in this dissertation, the Last Planner System had not

been applied in full to design production control. However, elements of the Last Planner

System have previously been applied to the management of production during the design

phase of projects. Koskela et al (1997) report that the traditional method of design

management on their test project was incapable of producing quality assignments, and

described the traditional method as follows:

“A drawing due date schedule, and a summary drawing circulation list form the

basis of design management. There are design meetings every two weeks or so,

where a contractor representative (site manager) acts as the chairman. The

contractor may also organize meetings to address specific problems between design

disciplines.

Thus, the primary control set is to reach the drawing due dates. Instead the order or

timing of individual design tasks is not scheduled, but are left for self-management

by the design team. In practice, the design tasks to be executed or input information

needed are discussed in the weekly design meetings. However, this procedure is not

perfect. There is no effective follow-up of decided action, and only a part of output

due is often available. It seems that often parties come unprepared to the meeting.

Design decisions are often made in improvized style, and decisions taken are not

always remembered in next meetings.” (p. 9)

Among the improvement actions taken was progressive detailing of the schedule (in onemonth chunks), documentation of input information needs reported in design meetings,explicit commitment of design supervisors to tasks in the next few weeks, monitoring of

Ballard Last Planner `3-20

assignments completed, and identification of reasons for noncompletion. As a result,PPC soon rose to the 70% level. (The negative dip in design meetings [SK] 10-12resulted from a major design change.) The design time for the building was 30% underthe standard time for the type of building and participants rated the method favorably, asshown in Figure 3.7.

Miles (1998) reports a more complete and extensive implementation of the Last

Planner System, which included the lookahead process. Overall PPC averaged around

75%, design was completed approximately 10% earlier than anticipated, and design costs

were reduced by 7%. The research also replicated in design earlier findings in

construction (Howell, 1996) regarding the prevalence of plan quality failures. They

found that failures to complete assignments were divided in a ratio of 2 to 1 between

internal impacts they potentially could control and external impacts over which they had

little or no control.

Figure 3.7

0 %

10 %

20 %

30 %

40 %

50 %

60 %

70 %

80 %

90 %

100 %

SK3

SK4

SK5

SK6

SK7

SK8

SK9

SK10

SK11

SK12

SK13

SK14

SK15

SK16

0

10

20

30

40

50

60

70

80

Num

ber

of ta

sks

PPC

Number of tasks

REALIZATION % OF ASSIGNED DESIGN TASKS

VTT Building Technology 1997, VPT

PPC (Koskela et al, 1997)

Figure 3.8

Ballard Last Planner `3-21

The average replies, on ascale of -2 to 2, to thequestions :1. Was the availability ofinput data improved?2. Was the decisionmaking in design processimproved?3. Did the method yieldbenefits?4. Was it laborious towork according to themethod?5. Should the method beused in the next project?

-2,00

-1,50

-1,00

-0,50

0,00

0,50

1,00

1,50

2,00

2

question 1

question 2

question 5question 3

question 4

VTT Building Technology 1997, VPT

Participant Survey (Koskela et al, 1997)

3.7 Evaluation of Last Planner against Criteria for Production ControlSystems

The criteria proposed in the previous chapter were:

q Variability is mitigated and remaining variability managed.q Assignments are sound regarding their prerequisites.q The realization of assignments is measured and monitored.q Causes for failing to complete planned work are investigated and those causes are removed.q A buffer of sound assignments is maintained for each crew or production unit.q The prerequisites of upcoming assignments are actively made ready.q The traditional schedule-push system is supplemented with pull techniques.q Design production control facilitates work flow and value generation.q The project is conceived as a temporary production system.q Decision making is distributed in design production control systems.q Design production contro resists the tendency toward local suboptimization.

That the Last Planner system of production control conforms to these criteria and

principles should be apparent. It is explicitly dedicated to the reduction and management

of variability. One of the quality criteria for assignments is soundness. PPC measurement

is central. Reasons for plan failure are tracked and analyzed. The lookahead process has

the explicit purpose of maintaining a buffer of sound tasks and also actively makes

Ballard Last Planner `3-22

scheduled tasks sound and facilitates work flow and value generation. Pulling is evident

both in the assignment quality criteria and in the make ready function within the

lookahead process. The framework for Last Planner is the conception of projects as

temporary production systems. Distributed decision making is evident in the requirement

that only quality assignments be accepted and also in the work flow control decisions to

be made within the lookahead process. And, finally, Last Planner resists the tendency

toward local suboptimization in its application of the criterion 'sequencing', applied both

in lookahead planning and to weekly work plan assignments.

3.8 Research Questions

This new production planning and management method has been in development since

1992 (Ballard & Howell 1997). It has been successfully used in a series of projects

ranging from oil refineries to commercial building construction. Hitherto it has been

used primarily in site construction, rather than in design and engineering and its

implementation has generally resulted in an improvement of work flow reliability, as

measured by percent plan complete, to 65-70% PPC. The questions driving this research

are: 1) What can be done by way of tools provided and improved implementation of the

Last Planner system of production control to increase plan reliability above the 70%

PPC level? 2) How/Can Last Planner be successfully applied to increase plan

reliability during design processes ?

It is intuitively obvious that making work flow more reliable (predictable) can reduce

the cost or duration of the total project. When the numerous specialists can rely on

delivery of calculations, drawings, materials, and prerequisite work from other

Ballard Last Planner `3-23

specialists, both within and outside the project team, they are better able to plan their

own work, and better planning yields better performance. All else being equal, with

greater flow reliability should come more efficient production, less wasted effort and

rework, and better matching of resources to tasks. Even partial and limited

improvements in work flow reliability have demonstrated schedule and cost

improvements (Koskela et al., 1997 and Miles, 1998).

It is also apparent that construction benefits from greater reliability in the flow to the

construction site of information and materials. The impact of more reliable flow of design

information on project cost and duration is much greater in the construction phase of

projects than in design. When constructors can take action in advance of receiving design

information that coordinates the flow of labor and equipment, material deliveries, and

completion of prerequisite work, the project runs more smoothly and efficiently. We

have numerous instances from construction processes showing the benefits of increasing

material and information flow reliability even within the job site itself (Ballard, et al,

1996; Ballard and Howell, 1997).

Consequently, it is appropriate to focus the research question on improving work flow

reliability, with confidence that improving reliability is beneficial to project performance.

Subsequent research may seek to refine and quantify these causal relationships, but the

current research needed is to establish more effective methods for production control in

general and to extend production control techniques to design.

Ballard 4-1 Last Planner

CHAPTER FOUR: RESEARCH METHODOLOGY

4.1 Introduction

This thesis is about engineering management, not about epistemology. However, some

epistemological assumptions lie behind any attempt to add to knowledge, in whatever

field. Making those assumptions explicit allows the reader to better understand and

assess claims and inferences. The purpose of this introduction is to clarify

epistemological assumptions. Three issues will be addressed: 1) To what field of

knowledge is this thesis proposing to contribute? 2) Difficulties associated with

competing paradigms in the field. 3) The research strategy and methods used in this

thesis.

4.1.1 ENGINEERING MANAGEMENT AS A FIELD OF STUDY

The topic of this thesis is engineering management, which is assumed to belong to the

general field of technology rather than science. Roozenburg and Eeckels propose that

technology and science pursue different goals through different processes or

methodologies (Roozenburg and Eeckels, 1995, pp. 32-35). Science pursues knowledge

acquisition, while “technology-the design, making, and using of artifacts-is a

systematized form of action.” Both can be pursued methodically. For both, certain rules

have been developed, the observance of which is supposed to “…contribute to efficient

performance of the activity involved.” Both processes involve reasoning. Which

conditions should these two different reasoning processes meet, so they can claim

reliability, meaning that the conclusions to which they lead are correct or true? The

criterion for reliability of scientific reasoning is the truth of the resulting statements. The

criterion for reliability of technological reasoning is the effectiveness of the action

Ballard 4-2 Last Planner

process, based on that reasoning. Of course we may pose a ‘scientific question’ about a

technological claim: ‘Is it indeed true that the proposed action will be effective?’ That is

precisely the type of question posed in this thesis. ‘Is it true that implementing a specific

set of policies and techniques collectively called “the Last Planner system of production

control” improves the reliability of work flow?’

Given this ‘scientific’ question about a technological matter, what methodological

rules are appropriate? What kind of data is needed to answer the question and what kind

of inferences can we expect to make from such data? Many engineering management

theses pose claims about some aspect of engineering management action, use surveys to

collect data regarding same, then apply statistical analyses to test the adequacy of their

claim. This methodology works from a sample of a population to claims about the

population itself by statistical generalization. ‘If 79% of a 151 member sample report that

they include safety records in their prequalification of contractors, what generalization

can I make regarding all members of the population that prequalifies contractors?’ Rules

of statistical generalization exist for answering such questions.

However, statistical generalization from sample to population is an appropriate

methodology in the field of engineering management only if one is interested in testing

claims about current behavior. If the objective is to introduce new policies and behaviors

with the intent of improving engineering management practice, a different type of

methodology is needed. The world of engineering management practice may well be void

of practitioners following the proposed new policies and techniques, so there is no

sample to take. The question is not ‘How many people employ the Last Planner system

Ballard 4-3 Last Planner

and with what effect?’ What’s needed is a type of experiment rather than a survey17. The

relevant question has the form ‘Will the desired consequences result from taking the

proposed action?’

What type of ‘experiment’ is needed to pursue the research questions: 1) What can

be done by way of tools provided and improved implementation of the Last Planner

system of production control to increase plan reliability as measured by Percent Plan

Complete? 2) How/Can Last Planner be successfully applied to increase plan reliability

during design processes? As is said in the States, “experiment” is a loaded term.

Scholars differentiate between so-called ‘true’ experiments and quasi-experiments

(Campbell and Stanley, 1966). Some propose that case studies be conceived as a type of

experiment, having similar methodological rules (Yin, 1994). No position is taken here

regarding these matters except that some type of experiment is the appropriate

methodology for the type of research question posed as distinct from a survey of current

practice. ‘Experiment’ is conceived in practical terms to mean acting in the world with an

intended effect. As with all experiments, the researcher must be open to learning more or

different things than expected. As with all experiments, generalization from findings is

problematic.

Experiments don’t prove conclusions in the sense of logical deduction even in the

field of natural science. Experimental reasoning is a type of reductive reasoning from

particular to general quite unlike either formal logical reasoning or statistical

generalization. Everything depends on the specifics of given situations. What are the

17 Surveys may be used in conjunction with an experiment or a case study devoted to

implementation of a policy. For example, one could survey participants for opinionsregarding the effectiveness of the policy. The point here is that survey cannot be theprincipal or primary research strategy for conducting policy evaluation.

Ballard 4-4 Last Planner

relevant variables and to what extent can they be controlled? Some experiments in

natural science can approximately isolate one (set of) variable(s) from others and so

argue more persuasively that ‘things don’t burn in the absence of oxygen.’ However,

even that extreme type of argument depends essentially on the cohesion and consistency

of theories. As long as the phlogiston theory held sway, oxygen was invisible to the

mind’s eye (Kuhn, 1962). Generalization from experiments is fundamentally a matter of

telling a good story; i.e., having a good theory.

4.1.2 COMPETING ENGINEERING MANAGEMENT PARADIGMS

According to Thomas Kuhn, in his The Structure of Scientific Revolutions (1962),

theories emerge from paradigms, which are fundamental propositions and assumptions

about the subject matter that tend to remain implicit except in periods when paradigms

change. It could be argued that engineering management is currently in just such a period

of paradigm shift. In such periods, communication becomes even more perilous than

normal because the community of researchers and practitioners no longer share a

common language and presuppositions. The research question posed in this thesis

belongs to an emerging engineering management paradigm, in conflict with the prevailing

paradigm. Consequently, care must be taken lest the change in language and

presuppositions hinder the reader. That can best be done by making changes in language

and presuppositions explicit. Recognizing that paradigm shifts are periods of intellectual

conflict, it is not expected that all readers will accept the proposed changes.

In the midst of a paradigm shift, it is difficult and perhaps impossible to clearly

delineate the boundaries of the opposed camps. The conflict is itself producing that

delineation, at the conclusion of which the vanguished disappears into the sands of time

Ballard 4-5 Last Planner

and the victor rides forward toward its own inevitable yet incomprehensible future

defeat. Nonetheless, an effort is required to clarify ‘where all this is coming from.’

The conflict in engineering management was presented in Chapter Two as an

opposition between those who adopt the view of production (the design and making of

physical artifacts) as transforming or converting inputs into outputs and those who add

the flow and value views. At first glance, this hardly appears to belong in the same league

as the shift from a geocentric to a heliocentric cosmology—perhaps the most famous

example of a paradigm shift. Nonetheless, the shift from the conversion to the flow and

value views is enormously important. A prime example is variability, which is itself

virtually invisible from the conversion-only view. Manufacturing has taken the lead in the

development of production theory, yet according to manufacturing theorists,

“…variability is not well understood in manufacturing….” (Hopp and Spearman, 1996,

p. 311) One can only assume that variability is even less well understood in the AEC

industry, where it would seem to be even more an issue. From a pure conversion view,

variability is managed primarily through the provision of schedule and cost contingencies

at the global level of projects, but is neglected in the structuring of work flows and

operations. Once contracts are let, variability ‘officially’ appears only in the form of

failure to meet contractual obligations.

Closely related to the conversion/flow distinction is that between project and

production management. Project management concepts and techniques are oriented to

the determination of project objectives and the means for achieving them (planning), then

to monitoring progress toward those objectives (control). This is a highly abstract

perspective, appropriate to any endeavour that is goal-driven and time-limited; i.e., to

projects. Unfortunately, project management concepts and techniques are employed in

Ballard 4-6 Last Planner

attempts to manage production processes that take on project form without regard to the

specific nature of the projects and production to be managed. This is the more

unfortunate as many projects involve production; i.e., designing and making things.

Management of production projects requires the use of production management concepts

and techniques, which in turn are derivative from the conversion/flow/value views.

Is variability in processing times, arrival rates, errors, and breakdowns visible to

those comfortable with the project management/conversion paradigm? Such matters

might be considered to belong to ‘mere’ production; to be in the province of the

engineering or construction crafts rather than a matter for management. For such

readers, the research questions posed in this thesis may well appear either trivial or

irrelevant.

4.2 Research Design

4.2.1 RESEARCH QUESTION

Prior to selecting a research strategy, it is necessary to determine the research topic,

question, and purpose. The topic of this research is engineering management; more

specifically, improving control of design and construction processes on

architectural/engineering/construction projects. The questions driving this research are:

1) 1) What can be done by way of tools provided and improved implementation of the

Last Planner system of production control to increase plan reliability above the 70%

PPC level? 2) How/Can Last Planner be successfully applied to increase plan

Ballard 4-7 Last Planner

reliability during design processes18? The purpose of the research is to evaluate and

improve the effectiveness of this managerial policy and practice.

Evaluation is a type of applied or action research (McNeill, 1989), concerned with

technology in the broad sense; i.e., goal-oriented action. Evaluations typically pursue

improvement of the subject policy or practice in addition to rating effectiveness against

objectives. Simple rating is often made more difficult because of changes made mid-

stream in the policy or practice being evaluated. Opportunity for improvement seldom

waits on the desire for an unambiguous definition of what is to be evaluated. Indeed,

evaluation and improvement often blur together, especially when the researcher is

involved in the creation and implementation of the policies and practices being

implemented and evaluated, as is the case with this researcher and research. Some might

worry about an involved researcher’s objectivity. On the other hand, it may simply be

that technological research demands another concept and procedure than that of

traditional, fact finding research.

Evaluation does not fit neatly within the classification of traditional purposes of

enquiry; i.e., exploratory, descriptive, explanatory. The conceptual model for

technological research appears to have been drawn from the natural sciences, for which

the (immediate) goal is rather to understand than to change the world. Policy evaluation

involves exploration, description, and explanation, but subordinates those purposes to

the overriding purpose of improving practice. Nonetheless, improving practice requires

understanding what works and does not work, and to as great an extent as possible,

understanding why what works and what does not. Consequently, the purpose of this

18 In this thesis, the term “design” is used to designate both design and engineering

activities; not shaping space to aesthetic criteria.

Ballard 4-8 Last Planner

research includes determining the extent to which the Last Planner system is effective

and why it is or is not effective.

4.2.2 RESEARCH STRATEGIES

The three traditional research strategies are experiment, survey, and case study (Robson,

1993, p.40). It has previously been argued in this chapter that a survey strategy is

inappropriate for the question posed by this research. The research strategies that could

possibly lend themselves to investigation of this research question include true

experiments, quasi-experiments, and case studies.

True experiments require establishing a control group that differs in no relevant way

from the experimental group. A true experiment was not appropriate because of the

difficulty of establishing a control group and lack of control over extraneous variables.

At first glance, it would seem to be possible to use a pre-test, post-test, single group

design, measuring flow reliability of the same group before and after implementation of

the Last Planner system. This approach has several difficulties: 1) Work flow reliability is

not an explicit, measured objective of traditional production control systems, so pre-test

quantitative data is not available, and 2) our ability to generalize from the experimental

results is limited by the possibility that those who choose to try the Last Planner method

are somehow different from those who do not so choose. The second difficulty could be

managed by conditioning and qualifying the inferences drawn from the experiment. The

first difficulty, the lack of quantitative data on flow reliability for the pre-test, could be

handled by substituting subjective data, in the form of interview results. However, this is

clearly an inferior solution, and so pushes the researcher to find a more effective research

strategy.

Ballard 4-9 Last Planner

Quasi-experiments are “…experiments without random assignment to treatment and

comparison groups.” (Campbell and Stanley, 1966, cited in Robson, 1993, p. 98) They

admittedly sacrifice some of the rigor of true experiments, but are nonetheless

appropriate for a large range of inquiry, where true experiments are impossible or

inappropriate. The key issue regarding quasi-experiments is what inferences can be

drawn. It is proposed that inferences be justified in terms of study design, the context in

which the study occurs, and the pattern of results obtained (Cook and Campbell, 1979).

While this strategy responds to the difficulty of generalizability posed above, it still

leaves us without pre-test quantitative data on flow reliability in design, and

consequently, is not by itself an adequate strategy for pursuing this research.

Case study is “…a strategy for doing research through empirical investigation of a

contemporary phenomenon within its real life context using multiple sources of

evidence” (Robson, p. 52). Case studies are an appropriate research strategy when there

is little known about the topic of interest, in this case, for example, how production is

managed in design; and a change in theory or practice (production control) is proposed

(Robson, p.169). Multiple case studies allow the researcher to pursue a progressive

strategy, from exploration of a question to more focused examination of trials. Given the

policy nature of the research question being posed, a multiple case study strategy seems

appropriate.

4.3 Research Methods

4.3.1 DATA COLLECTION

Executing a research strategy requires methods for data collection and analysis. What

research methods are available, especially for case studies, the research strategy to be

Ballard 4-10 Last Planner

pursued in this thesis? Of those available, which fit best with conditions such as

accessibility to people and documents, involvement of the researcher in managerial

decision making, time available, etc?

Methods for data collection include direct observation, interviews and questionnaires,

and documentary analysis. A variant of direct observation is participant observation; i.e.,

observational reporting by a researcher who is part of the group being observed.

All these methods of data collection are used in this research. In all cases, the

researcher served as a consultant to the project team, and consequently was in the role of

participant observer rather than a neutral observer. Specific observational data was

collected from participation in project coordination meetings and other events devoted to

planning and controlling design and construction processes. Interviews or questionnaires

were used in all cases to collect team member assessments, both during the course of

each project and at the conclusion of each. Interviews were also used to collect other

participants’ observations of meetings and events relevant to project control at which the

researcher was not present. Records collected included meeting minutes and memos,

various forms of schedules, and action item logs. In all cases, measurements were made

and recorded of short-term assignments, their due dates, actual completion dates, and

reasons for failure to complete assignments on their due dates.

4.3.2 DATA ANALYSIS AND EVALUATION

McNeill (1989) suggests three key concepts: reliability, validity, and representativeness.

Reliability concerns the extent to which research can be repeated by others with the same

results. “Validity refers to the problem of whether the data collected is a true picture of

what is being studied.” Representativeness concerns whether the objects of study are

typical of others, and consequently, the extent to which we can generalize.

Ballard 4-11 Last Planner

Reliability in action research is inevitably questionable because of the active role

played by the researcher in generating the phenomena being studied. Validity of findings

is especially difficult in survey research because of the potential difference between what

people say and what they do. It is less a problem for action research because of its public

nature and the availability of measurement data such as PPC (Percent Plan Complete).

Generalizability from the cases is a question that cannot be completely answered, no

more than it can for a limited number of laboratory experiments. However, unlike

laboratory experiments, policy implementations are made in the messy reality of

organizations and social relations. Few if any variables can be completely controlled. In

the case of this research, attempts are made to control key variables of implementation

and execution of the system. However, it is recognized that control is partial and

incomplete. Nonetheless, having demonstrated even on a single project that plan

reliability can be improved is sufficient to establish system effectiveness. Future work

may be devoted to better understanding the conditions necessary for such success.

Another difficulty is that plan reliability is measured by PPC ('percent plan complete';

i.e., percentage of assignments completed), but PPC does not directly measure plan

quality. First of all, success or failure in assignment completion may be a consequence

either of the quality of the assignment or of its execution. Since the Last Planner system

primarily attempts to improve plan quality, execution failures and therefore PPC may not

vary with its effectiveness. In addition, apart from unsound assignments, it is often

difficult to differentiate between an execution and a quality failure. Was the assignment

poorly defined or was the problem with the lack of effort or skill on the part of the

designers or builders?

Ballard 4-12 Last Planner

Yet a further difficulty is the ambiguity of assignment ‘completion’ when assignments

have not been well defined. An assignment to “Produce as many piping drawings as you

can by the end of the week” might be marked as completed. The researcher can partially

guard against this problem by reviewing assignments for adequate definition. However, it

is virtually impossible for the researcher to prevent someone marking assignments

completed in order to ‘make the worse appear better’. The best defense might be to

convince those doing the marking that PPC is not a measure of individual but of system

performance. Unfortunately, that is not quite true. Individuals can be better or worse at

defining, sizing, sequencing, and assessing the soundness of assignments. PPC records of

individual front line supervisors can be revealing of those capabilities.

For these various reasons, evaluating the impact of the Last Planner system on plan

reliability is no straightforward matter. Similar difficulties beset improving the system,

which occurs through understanding and preventing plan quality failures. It is often

difficult to accurately determine reasons for failure. Unsoundness of assignments is the

easiest to determine because something is lacking that is needed to do the assignment

properly; e.g., a soils report, a stress calculation, a decision between alternative designs,

etc. Failures from sizing or sequencing are more difficult to identify. The later case

studies incorporate efforts to improve plan failure analysis based on experiences in the

previous cases.

4.3.3 CASE STUDIES

The research was done through a series of case studies. The first case, the CCSR project,

was an exploratory extension of the Last Planner system to the coordination of multiple

trades on a construction project. The primary improvement from that case was the

addition of the constraints analysis process. The second case, the Next Stage project, is

Ballard 4-13 Last Planner

an exploratory case study on the extension of the Last Planner system to design

production control. Case Three shows the efforts of a speciality contractor, Pacific

Contracting, to improve its work flow reliability. It may well reveal the limits on a

speciality contractor implementing the Last Planner system unilaterally. Case Four, the

Old Chemistry Building Renovation project, shows the potential for improvement in

work flow reliability from a more thorough and deliberate education and training of the

project team. Case Five is the Zeneca Project, one of several implementations of the Last

Planner system undertaken by Barnes Construction with significant education and

coaching provided to the participants, and application of the latest thinking and

techniques in the Last Planner system.

Ballard Last Planner5-1

CHAPTER FIVE: CASE ONE-CCSR PROJECT

5.1 Project Description and Last Planner Implementation

The CCSR Project was a laboratory building for Stanford University for which the

general contractor was Linbeck Construction. CCSR stood for Center for Clinical

Services Research. Prior to CCSR, the Last Planner system of production control had

been implemented primarily by contractors doing direct production work. There was

some question about how to apply Last Planner to subcontracted projects and how

effective that application might be. CCSR was selected as a pilot project to explore

feasibility and develop techniques. The specific research question was: How/Can plan

reliability be improved during site construction on largely subcontracted projects?

The research plan was to introduce the techniques listed below during weekly

subcontractor coordination meetings, then measure PPC and track reasons for

noncompletion of weekly assignments.19 In addition to the Last Planner procedures and

techniques previously developed, the intent was to do the following:

1. Detailed scheduling by phase20.

2. Intensive subcontractor involvement in phase scheduling.

3. Collection of status input from subs before the scheduling meeting.

4. Trying to select only tasks each week that are free of constraints.

19 The author introduced the system to the project and visited periodically during the

course of the subsequent three month pilot. Under the author's direction, AbrahamKatz, a Stanford graduate student, assisted the project superintendent withscheduling and documentation as part of an independent study performed forProfessor Martin Fischer. The author is a consulting professor at Stanford and also atthe University of California at Berkeley.

Ballard Last Planner5-2

5. Measuring PPC, identifying and acting on reasons.

A weekly planning cycle (Table 5.1) was established that specified who was to do what

during each week as regards planning and control. For example, subcontractors were to

status their tasks scheduled for the next 3 weeks by noon Monday, so the general

contractor (GC) could revise the short interval schedule, which in their case covered a 6

week lookahead period.

Status reporting consisted of completing a constraints analysis form, shown in Table

5.2, which shows selected scheduled tasks for three of the subcontractors on the project.

Common constraints on the readiness of scheduled tasks for assignment and execution

were included on the form; i.e., contract, design, submittals, materials, prerequisite work,

space, equipment, and labor. An open-ended, "other" category was also provided to

capture less common constraints. The intention was to focus attention and action on

making scheduled tasks ready by removing their constraints.

5.2 PPC and Reasons

Several kinds of data were collected: PPC and reasons, auxiliary documents such as

phase and master schedules, and the observations of the

researcher. PPC and reasons data was collected each week from

12/24/97 through 3/3/98, during the wettest season in the San

Francisco area in recorded history. Although the project had taken

weatherizing precautions to minimize weather-related delays, such

as type of fill material and drainage systems, nonetheless rain was

20 A phase was conceived in terms of a relatively independent facility system. For

example, the first phase-during which this research was conducted-was from

Ballard Last Planner5-3

by far the most frequently cited reason for failing to completed

assignments on weekly work plans

Table 5.1

I.

CCSR-Weekly Planning Cycle

Table 5.2

CCSR Weekly Planning Cycle

excavation to slab-on-grade.

GCproduces apreliminary

short intervalschedule &

gives to subsand A/E

Friday Noon

A/E andsubs statustasks in next3 weeks andgive back to

GC

GC revisesshort

intervalschedule

GC and subs meetto: 1) status this

week's plan,identify reasons forfailing to completeplanned tasks, andagree on actions toprevent repetition,and 2) finalize the

lookaheadschedule

GC producesand

distributesplan reliability

charts andfinal shortinterval

schedule

All perform workon the current

weekly work planand expediteremoval of

constraints onfuture weeks' work

plans

Wed-TuTu P.M.Tu A.M.Mon P.M.Mon A.M.

GC collectsinformationneeded to

produce the shortinterval schedule;e.g. progress oncurrent week'splan, updated

delivery schedules(rebar, responses

to RFIs, etc),changes in

objectives ordesign

Friday A.M.

* The short interval schedulecovers the construction tasks

required to achieve a schedulemilestone (e.g. slab-on-grade

by 2/28/97) and the designand supplier tasks providing

needed information andmaterials. The team developsa detailed schedule for each

phase of the job at least 4weeks before starting that

phase. The phase schedulethen becomes the controlschedule for short interval

scheduling each week.

* Subs status tasks forthese constraints:contract, design,submittals, matls,prerequisite work,

tools & eqpt, space,labor, other. A/Estatuses tasks by

specifying theinformation or decision

needed.*Both subs and A/Eare answering the

questions: 1) Ifconstraints are in your

control, are youconfident they will beremoved in time? 2) Ifconstraints are not in

your control, what helpdo you need from

others?

Guidelines: 1)Schedule for nextweek (Wed thru

Tu) only tasks thathave no

constraints or haveonly constraintsyou know can be

removed in time. 2)Schedule in the

2nd and 3rd weeksonly tasks you areconfident can bemade ready in

time. The goal is100% plan

reliability for thenext three weeks.

* The planreliability chartsmeasure how

well the team isachieving its

goal ofschedulingthree weeksahead only

tasks that canbe completed,and completing

all tasksscheduled upto three weeks

ahead. Theidea is that

productivity willbe higher whenschedules are

reliable.

* GC reviews thephase schedule

and masterschedule for

neededadjustment.

Ballard Last Planner5-4

Table 5.2

Wills

II. ID

Activity Start Contract Design Submitta

ls

Material

Pre-Requisite

Space Equipment

Labor Other

950 Tunnel Lobby -Walls Rebar

3/4/98

1040 Footings 6 & 7Dowels

3/4/98

1220 Footings 6 & 7Between A andH Dowels, andFootings E & GDowelsBetween 4.5and 8

3/4/98

630 Line 4 Walland Line CWall Rebar

3/6/98

344 Large InteriorWall Line Jand H.8 Rebar

3/9/98

1154 Small InteriorWall RebarLines 6-K, and6-M, 6-P

3/9/98

CupertinoElectric

ID Activity Start Contract Design Submitta

ls

Material

Pre-Requisite

Space Equipment

Labor Other

402 Inspection 3/4/98UndergroundElectrical N-WS-W Quadrant

3/5/98

CCSR-Constraints Analysis Form

PPC was measured as shown in Figure 5.1, ranging from an initial measurement of 56%

during the week of 12/24/97 to 70% in the week of 3/3/98. Rain

was cited as the reason for 18 plan failures (see Figure 5.2) and

was a contributing reason to even more. Other

Ballard Last Planner5-5

frequently cited reasons were lack of prerequisite work (14), availability or quality of

design information (8), and submittals (6).

Removing rain as a reason, weekly PPC would have been as shown in Figure 5.3, with a

mean PPC for the research period of 71% (149 of 211

assignments completed), which compared favorably to work flow

reliability achieved through previous application of the Last

Planner system to projects which were not subcontracted.21

Figure 5.1

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

12/24/97 12/31/97 1/6/98 1/14/98 1/18/98 1/25/98 2/3/98 2/10/98 2/17/98 2/24/98 3/3/98

Week

% C

om

ple

ted

CCSR-Weekly PPC

21 Ballard et al., 1996; Ballard and Howell, 1997

Ballard Last Planner5-6

Table 5.3

Week 12/24/97 12/31/97 1/6/98 1/14/98 1/18/98 1/25/98 2/3/98 2/10/98 2/17/98 2/24/98 3/3/98

PPC 56% 86% 57% 67% 73% 75% 50% 53% 74% 44% 70%

TasksCompleted

5 6 8 10 11 18 7 10 23 19 14

TasksPlanned

9 7 14 15 15 24 14 19 31 43 20

Rain 1 1 3 6 2 2 1 2 18

Pre-Requisite 2 2 1 7 2 14

Design 1 1 4 2 8

Submittal 2 2 2 6

Other 1 1 1 1 4

Space 1 2 3

Equipment 2 2

Labor 1 1 2

Materials 1 1

Contract 0

CCSR-PPC and Reasons Data

Figure 5.2

0

5

10

15

20

25

Rain Pre-Requisite Design Submittal Other Space Equipment Labor Materials Contract

Reason

Nu

mb

er O

f O

curr

ence

s

CCSR-Reasons for Noncompletion

Ballard Last Planner5-7

Figure 5.3

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

12/2

4/97

12/3

1/97

1/6/

98

1/14

/98

1/18

/98

1/25

/98

2/3/

98

2/10

/98

2/17

/98

2/24

/98

3/3/

98

Weekly PPC

Mean PPC

CCSR-PPC without rain

As shown in Table 5.4, reasons for plan failure were categorized as either an Execution

Failure or a Plan Failure22. Of the 57 total failures23, 28 were determined to have resulted

from some defect in planning, while 29 were attributed to some defect in execution. The

18 failures caused by rain were categorized as execution failures. Disregarding rain, Plan

Failures would have amounted to 28 of 38, or 74%, further evidence that to a substantial

degree, our fate is in our own hands as regards planning and work flow. In even extreme

weather conditions, fully half of noncompletions resulted from poor planning.

22 This distinction was introduced into the Last Planner system in Ballard (1994).23 Note the absence of detailed information for failures in the week of 12/24/97. Their

inclusion would add 4 noncompletions to the total.

Ballard Last Planner5-8

Table 5.4

Week 12/31Activity Reason Type Of Failure

item 6 - Sump Pit LidForm

Other: Low Priority Plan

Week 1/6Activity Reason Type Of Failure

item 3 - UndergroundPlumbing

Rain Execution

Item 13 - East WallForms

Design: RFI Execution

Item 32 - Elevator WallForms

Pre-Requisite: NotIdentified

Plan

Item 43 - 2&3 LineExcavation

Equipment: Backhoe Execution

Item 44 - A,C & 4 LineExcavation

Equipment: Backhoe Execution

Item 45 - 2&3 Line Rebar No Excavation Plan

Week 1/14Activity Reason Type Of Failure

item 26 - Elevator 1&2SOG Pour

Floor Drain Submittals Plan

Item 44 - Elevator PourUp to Tunnel Level

Shop Drawings Plan

Item 43 - Form SouthEast Quadrant

Waiting RebarFabrication

Plan

Item 29 - Rebar J Line Waiting On Excavation PlanItem 7 - Access Panel Submittal Plan

Week 1/18Activity Reason Type Of Failure

210 - Design ChangeRebar Submittals

Not Back Plan

270 - Interior Wall RebarSubmittals

Not Back Plan

A,C, & 4 Line Excavation Productivity/Rain ExecutionA,C, & 4 Line Rebar No Excavation Plan

Week 1/25Activity Reason Type Of Failure

Ballard Last Planner5-9

Excavate Line F and 7(MidWest)

Rain Execution

Interior Wall Forms Rain ExecutionN,Q,L Lines RebarInstallation

Rain Execution

Reveals Location Waiting On Architect PlanRFI Line 7 (Cupertino) Answer Incomplete PlanTunnel Piping Submittal Approval Plan

Week 2/3

Activity Reason Type Of FailureExcavate F Line Rain ExecutionBackfill Sump pit Rain ExecutionTemplate Footings A and4 Line

Rain Execution

Electrical ConduitElevator 5

Rain Execution

Small and Large WallsSingle Form

Rain Execution

Wall Double up @Tunnel Lobby

Waiting For Inspection Plan

Backfill N-E/S-E Quad. Rain Execution

Week 2/10

Activity Reason Type Of FailurePlumbing between lines J& M

Rain Execution

Plumbing Line 6.5 Rain ExecutionSmall Interior Walls Form Eleveator Jack Drilling /

RainExecution

Small Interior WallsDouble Up

Eleveator Jack Drilling /Rain

Execution

Large Interior Walls Form Eleveator Jack Drilling /Rain

Execution

Large Interior WallsDouble Up

Eleveator Jack Drilling /Rain

Execution

Small Wall Rebar Eleveator Jack Drilling /Rain

Execution

Line L wall Rebar Eleveator Jack Drilling /Rain

Execution

E & G Line Rebar from 2to 5

Eleveator Jack Drilling /Rain

Execution

Ballard Last Planner5-10

Week 2/17

Activity Reason Type Of FailureElevator Wal Backfill Rain ExecutionLine J Excavation Backfill

Plumbing/Rain/MudExecution

Line 6.5 Excavation After 6 & 7 Line Concrete PlanSmall Interior Wall Forms Design Change PlanSmall Walls Double Up Design Change PlanSmall Walls Rebar Design Change PlanPerimeter Wall Line 2Rebar

Design Change Plan

Footings 6 & 7 Rebar Rain Execution

Week 2/24

Activity Reason Type Of FailurePlanter Excavation Space PlanInterior Small Walls Rebar Change/Permit PlanTunnel lobby SOG Sequence Change PlanLine L Wall Rebar Change/Permit PlanLine J Footing Rain ExecutionWall Line 2 From A-D Man Power Plan

Week 3/3Activity Reason Type Of Failure

Footings E&G Excavation Space For Crane PlanLine J Concrete Rain ExecutionFootings 6&7 Concrete Rain ExecutionCourt Yard Planter Crane Reach PlanSmall Interior Walls Man Power PlanPipe Ties In @ Tunne Waiting On Stanford Info Plan

CCSR-Reasons for Noncompletion (detailed and categorized)

5.3 Observations

Subcontractors were not selected based on their understanding or willingness to

participate in the Last Planner production control system. They were selected based on

traditional criteria such as financial soundness and bid price. Subcontractor personnel

first learned about the system and the expectations regarding their roles and

Ballard Last Planner5-11

responsibilities within it after coming to the site. Not surprisingly, some were more

capable and enthusiastic about participating than others. Even so, the project

superintendent continued to use the Last Planner system and reported that eventually all

foremen were participating and that they began to hold each other accountable for

keeping their weekly work plan commitments. Nonetheless, it would have been

preferable both to incorporate participation in the production control system in the

selection criteria and subcontracts, and also to have devoted more time and effort to

education and training.

Shortly after introducing the system, it became apparent that more active

involvement of others besides the site foremen was needed. Subcontractor project

managers were invited to attend the weekly meetings and were better able to understand

what was going on, and specifically better able to provide status information regarding

constraints such as submittals, design issues, fabrication, and deliveries. There was also

efforts made to involve the architect and design engineers on the project. Unfortunately,

those efforts failed, in part because of the stage of design completion and the fact that the

production architect/engineer was on a lump sum contract and concerned lest they run

out of money before they ran out of work.

Analysis of constraints was a key element introduced into the Last Planner system on

CCSR. Efforts to collect constraints information from subcontractors prior to the

coordination meeting were mostly unsuccessful, perhaps in large part because there is no

tradition in our industry for such activities. Consequently, much of meeting time was

dedicated to data collection rather than planning and problem solving.

Ballard Last Planner5-12

5.4 Learnings

Learnings for future projects included:

q Incorporate production control requirements into subcontracts.

q Select subcontractors for their ability and willingness to participate in the production

control system.

q Involve owner, architect, and engineers in the production control process; preferably

from the beginning of design.

q Send to subcontractor project managers by email or fax each week constraint reports

with the next 5-6 weeks scheduled activities listed and ask them to status their

activities and report back. Make sure this happens so meeting time can be used for

planning and problem solving as opposed to data collection.

q Use team planning techniques to produce schedules for each phase of work, with

participation by foremen, superintendents, and designers.

q Incorporate reasons identification, analysis, and corrective action into weekly

coordinating meetings. Otherwise, there is a danger that incompletions become

accepted as unavoidable.

Ballard Last Planner6-1

CHAPTER SIX: CASE 2-NEXT STAGE PROJECT

6.1 Description of the Project and Last Planner Implementation

Next Stage Development was created to design, build, and operate a series of 7,000 seat

enclosed amphitheaters in various U.S. cities, accommodating Broadway shows and

musical entertainment with amplified sound. Its first project was the Texas Showplace,

located in Dallas, Texas. Architect, design consultants, engineering firms, fabricators,

and construction contractors were selected based on qualifications and willingness to

participate in the project. The intent was to create an All-Star team by selecting the very

best.

The general contractor and equity participant in Next Stage Development is Linbeck

Construction, a founding member of the Lean Construction Institute, which was

cofounded by the author and Greg Howell in August, 1997. Next Stage’s management

chose to implement elements of “lean thinking” in the design and construction of its

facilities, specifically including the Last Planner method of production control. A Kickoff

Meeting was held for the production team May 19-21, 1998 in Houston, Texas and co-

facilitated by the author. Key outcomes of the meeting were 1) forming the fifty plus

individuals and multiple companies into a team, and 2) collectively producing a “value

stream” (Womack and Jones’ [1996] term for the flow diagram of a production process

that produces value for the stakeholders in the process). This author's report on the

Kickoff Meeting is included in Appendix A.

In the Kickoff Meeting, the participants were divided into a number of different

teams, corresponding roughly to the facility systems: Site/Civil, Structural, Enclosure/

Architectural, Mechanical/Electrical/Plumbing/Fire Protection, Theatrical/Interiors, and

Ballard Last Planner6-2

Project Support. These teams remained intact as the administrative units for production

of the design.

After the Kickoff Meeting, the design process continued, initially with a target

completion date of 11/15/99. However, after roughly the middle of August, 1998, delays

in arranging equity financing and performance commitments caused the construction

start and end date to slip ever further out, until the project was finally suspended..

The design process was managed primarily through biweekly teleconference

(Appendix B). Tasks needing completion within the next two week period were logged

as Action Items (Appendix C) , with responsibility and due date assigned. Tasks needing

completion beyond the next two week period were logged as Issues (Appendix D).

Design decisions were recorded in a Design Decisions Log (Appendix E). When action

items were not completed as scheduled, reasons were assigned from a standard list

(Table 6.1) and a new due date was provided.

Table 6.1

1. Lack of decision2. Lack of prerequisites3. Lack of resources4. Priority change5. Insufficient time6. Late start7. Conflicting demands8. Acts of God or the Devil9. Project changes10. OtherNext Stage-Reasons for Noncompletion

6.2 Data

6.2.1 PPC AND REASONS

The percentage of action items completed was tracked and published biweekly.

Ballard Last Planner6-3

Table 6.24 week movingave.

57% 60% 63% 64% 58% 57% 55%

PPC - NextStage™ Texas ShowPlace Planning Percent Complete for Preconstruction Meetings

Week 7/1/98 7/15/98 7/29/98 8/12/98 8/26/98 9/9/98 9/23/98 10/7/98 10/21/98 11/4/98

PPC 46% 50% 63% 71% 57% 61% 68% 47% 54% 54%TasksCompleted

28 33 48 37 29 36 26 20 26 20

TasksPlanned

61 66 76 52 51 59 38 43 48 37

Next Stage-PPC Data

The number of tasks or action items completed was divided by the number planned each

two week period and a percentage calculated. For example, In the two week period

beginning 11/4/98, 37 action items were assigned, of which 20 were completed, which

amounts to 54%. In addition, a four week moving average was calculated in order to

smooth the data and hopefully reveal trends. Through 11/4/98, the four week moving

average was 55%, calculated by averaging the previous four weeks data.

The columns in Figure 6.1 represent the aggregate average completion percentage

for all teams for each two week planning periods. PPC rose from an initial measurement

of 46% to above 70% in the 4th two week planning period. Subsequently, perhaps

connected with the end date slipping out, PPC rose and fell in a generally downward

trend, winding up around 55%.

Ballard Last Planner6-4

Figure 6.1

Next Stage PPC Data

There was considerable variation between teams. Through 9/9/98, PPC of the various

teams was as follows:

Site/Civil 78%

Structural 35%

Enclosure/Architectural 62%

Mechanical/Electrical/Plumbing/Fire Protection 55%

Theatrical/Interiors 52%

Project Support 85%

Table 6.3 exhibits the reasons categories used on the project and the frequency of reason

by category each week of the data collection period. It is apparent that three categories

dominate; i.e., lack of prerequisite work, insufficient time, and conflicting demands, in

that order. Unfortunately, such categories reveal little about root causes, so do not

facilitate corrective action.

Percent of Plan Completed

0%

10%

20%

30%

40%

50%

60%

70%

80%

7/1/98 7/15/98 7/29/98 8/12/98 8/26/98 9/9/98 9/23/98 10/7/98 10/21/98 11/4/98

Week

% C

om

ple

ted

Ballard Last Planner6-5

Table 6.3

Reasons/Date

7/1/98

7/15/98

7/29/98 8/12/98 8/26/98 9/9/98 9/23/98 10/7/98

10/21/98

11/4/98

12/2/98

AllWee

ksDecision 1 1 3 1 1 1 3 3 3 17Prerequisites

7 16 8 2 7 10 3 5 6 4 68

Resources 1 2 0 3PriorityChange

3 4 6 1 1 15

InsufficientTime

5 6 1 6 6 10 8 10 6 4 62

Late start 4 1 1 1 1 8ConflictingDemands

7 7 3 1 7 2 4 6 5 42

Acts of God 3 0 3ProjectChanges

0 1 1

Other 2 1 3Next Stage-Reasons

6.2.2 OBSERVATIONS (See Appendices A and B for a report on the Kickoff meeting andthe author’s notes on project teleconferences.)

6.2.3 FEEDBACK FROM PARTICIPANTS

In October, 1998, the Site/Civil team agreed to select five plan failures and analyze them

to root causes by asking "Why?" up to five times in succession. Review of Site/Civil’s

analyses revealed that failure to understand criteria for successful completion of

assignments was the most common cause. Generally, failures were caused by not

understanding something critically important; City requirements for traffic analysis,

applicable codes for drainage, actual soil conditions, who had responsibility for what.

Presenting reasons were often quite distant from root causes and frequently the failing

party did not control the root cause. This sample also raised significant questions about

adherence to quality requirements for assignments. For example, why did Site/Civil

accept #1 (were they sure they had the capacity to take on this additional task?) or #2

Ballard Last Planner6-6

(why did they think Mechanical would give them the information they needed in time for

Civil to do its work?)?

Failure #1: Failed to transmit site plan package to the

general contractor as promised. Reason provided: conflicting

demands—“I was overwhelmed during this period.” 5 why’s

revealed that the required time was underestimated for collecting

the information needed because the City’s requirements for traffic

analysis were different and greater than had been assumed.

Failure #2: Failed to revise and submit site drainage for

revised commissary roof drainage. Reason provided: prerequisite

work. The mechanical contractor originally provided drainage

data on pipe sizes, inverts, etc., then discovered that City codes

required additional collection points. Civil is waiting on

Mechanical to provide data on these additional collection points.

Failure #3: Failed to complete Road “D” plan to support

easement and operating items. Reason provided: prerequisite

work. The root cause was the same as for #1; i.e., failure to

understand City requirements for traffic analysis.

Failure #4: Failed to make an engineering determination

from 3 alternative pavement designs provided. Reason provided:

prerequisite work and insufficient time. “This item was not

anticipated. Why was it not anticipated? The City refused to

accept our pavement design. Why did they refuse to accept our

Ballard Last Planner6-7

pavement design? Soil conditions were different from past

projects. The lack of prerequisite design work referred to the soil

borings in the borrow site. We also are investigating other sources

for dirt. Why was time insufficient? We neglected to plan for the

time required to mobilize soils testing.” The root cause was

assuming soil conditions would be the same. A process flow

diagram might have revealed the significance of that assumption.

Failure #5: Failed to determine/coordinate location of

easements after final design by Texas Utilities. Reason provided:

prerequisite work. “Prerequisite design work involved the

determination of routing and service options. There was confusion

over who was responsible. There were delays on the part of TU

Electric due to the absence of key people.” Failure to specify who

was to do what prevented requesting a specific commitment from

TU Electric. If TU Electric refused to make that commitment,

Civil could have refused to accept its action item until receipt of

their input. If TU Electric had committed, Civil might have been

informed when key people were absent.

Low PPC was attributed by some members of the management team to the lack of a

construction start date, and the consequent use by suppliers of resources on more urgent

projects. The high percentage of plan failures due to conflicting demands appears to be

supportive of this claim. However, this reasons analysis exercise and observation of

teleconferences suggests that contributing causes were failure to apply quality criteria to

Ballard Last Planner6-8

assignments and failure to learn from plan failures through analysis and action on

reasons.

6.3 The Nature of the Design Process and Implications for ProcessControl

'Making' has the job of conforming to requirements. Design produces those

requirements. If there were complete predictability of design's output, design would

generate no value. Consequently, variability plays a different role in design as opposed to

construction (Reinertsen, 1997). This raises the question of the type of control

appropriate to generative processes like design.

Let us first consider more closely the nature of the design process. Consider the task

of producing a piping isometric drawing versus the task of doing a piping layout for a

given area. In order to do the layout, the designer must know where other objects are

located in the space. She must know locations, dimensions, material compositions, and

operating characteristics of end-points. Some of these constraints and conditions of her

problem will not change. Some may well change in response to her difficulty achieving a

satisfactory solution. Consequently, the final piping layout will emerge from a process of

negotiation and adjustment, which cannot be determined in advance.

An example from the Next Stage case illustrates the point. The design team was

faced with selecting the theater seats, which might appear at first glance to be a fairly

simple problem of applying criteria derivative from the general level of 'quality' desired in

the facility balanced against the purchase price of the seats. In fact, the criteria are far

from straightforward or simple. Seats can either be mounted on the floor or riser-

Ballard Last Planner6-9

mounted, the choice between them being interdependent with the structural pads for the

seats, which in turn constrains choices regarding the return air plenum, which can either

go through the floor or risers. That choice in turn impacts cleaning time and cost: how

quickly can they set up for the next show? As it happens, chairs come with different

types of upholstery, which can change the amount and type of smoke to be removed.

Components such as chairs may not be offered in all varieties; e.g., although we

might prefer a riser-mounted chair, such chairs only come with a certain type of

upholstery that would overload current plans for smoke removal. Everything's connected

to everything. We are designing one whole, so parts have the logic of part to whole,

potentially conflicting properties, etc. Product design decisions can impact the entire

range of 'ilties': buildability, operability, maintainability, etc., etc. In this case, delay in

selecting chairs delayed final determination of structural geometry, which in turn delayed

completion of the 3D model of the structure.

Overly 'rationalistic' models of problem solving processes are inappropriate for the

design process, which rather oscillates between criteria and alternatives, as in a good

conversation from which everyone learns (See Conklin and Weil's "Wicked Problems"

for another presentation of this idea.). In their Soft Systems Methodology, Checkland and

Scholes offer the same critique of 'hard' systems thinking as applied to action research;

i.e., such thinking failed because it assumed that objectives were defined and the task was

simply to determine how to achieve those objectives. Rather than conceiving the project

process to consist of determining design criteria then applying those criteria in the

production of the design, design should be conceived as a value generating process

dedicated to the progressive determination of both ends and means.

Ballard Last Planner6-10

Specialization is essential for successful design. No one can understand in detail all

the different types of criteria, constraints, and alternatives that might be considered.

However, specialists tend toward suboptimization because they become advocates for

what they understand to be important, often without sufficient understanding of what

else is important24. Specialists are often advocates for the priority of specific criteria!

Given this value generating nature of design, controls based on the model of after-

the-fact detection of negative variances inevitably focus entirely on controlling time and

cost, leaving design quality as the dependent variable (p.199, Reinertsen, 1997). What is

needed is a production control system that explodes tasks near in time to their

performance, one that counteracts the tendency to suboptimization by explicitly focusing

common attention on design criteria, one that facilitates value generation and information

flow among specialists; i.e., the Last Planner system.

6.4 Evaluation of Last Planner Implementation

Four Next Stage project managers evaluated implementation and effectiveness of the

Last Planner system in response to a short survey produced by the author. The four rated

Last Planner effectiveness relative to traditional forms of project control 5, 5, 6, and 7 on

a scale of 1 to 7, which is equivalent to saying that Last Planner was 44% more effective

than traditional practice. However, examination of actual practice on the project suggests

tremendous opportunity for further improvement.

Plus: -attempted to select only assignments needed to release other work

-measured and communicated PPC and reasons

24 See Lloyd, et al., 1997 for the tendency to see one's task in terms of one's 'product'

rather than in terms of participating in an iterative, interactive, evolving process.

Ballard Last Planner6-11

Minus: -minimal preparation of participants

-no work flow control and make ready process

-poor definition of assignments

-no action on reasons

Each action item was determined completed or incomplete, and reasons were selected

from the list of categories. However, no analysis of reasons was done, either during or

between teleconferences. There was also no apparent attempt to act on the reasons that

were identified. Work selection was tested against the ‘pull’ requirement by asking why

it was needed to be done now, but rarely were assignments rejected for unsoundness or

size. Frequently, it appeared that assignments were accepted with the implicit

commitment to do one’s best rather than an explicit commitment to complete based on

knowledge of the execution process, understanding of relevant criteria, identification of

needed informational inputs, and allocation of necessary resources. Assignments were

not systematically exploded into an operations level of detail and, consequently, the

interdependence of assignments was often not understood.

In summary, Next Stage did not fully change its production control system from the

traditional, and either did not implement or did not implement completely the elements of

the Last Planner system; i.e., work flow control, production unit control, and a learning

process. Nonetheless, the Next Stage experience was valuable for its contributions to

learning and further development of the Last Planner System. Much has been learned

and developed since the Next Stage case. Opportunities and needs for the future are well

summarized by Ed Beck, Linbeck project manager, in the following response to the

author's survey question: What improvements in LPS (Last Planner System) objectives,

procedures, or implementation do you suggest for future projects?

Ballard Last Planner6-12

q Client buy-in at the user level

q Complete orientation of all participants

q A simpler value stream

q A more systematic format

q A better list of reasons to categorize planning failures

q Utilization of the 5 why's

q Utilization of the 6 week lookahead

q A more expeditious way to meet and create a weekly plan

q Periodic revisiting of the value stream

q Publishing graphs and reasons and answers to questions to all

q A tune-up meeting at strategic times along the course of the project

q Periodic assessment comparing what is happening versus what normally happens.

6.5 Learnings

The Next Stage case study reinforced the need to improve plan reliability in design

processes and also suggested improvements to the production control system required to

achieve better plan reliability.

-make sure project management understands the production control system and

its objectives

-provide additional training to participants

-include ‘puller’ on action item log

-explode scheduled activities using the Activity Definition Model; i.e., specify the

process to be used to complete an assignment, the directives or criteria to which

Ballard Last Planner6-13

it must conform, the prerequisite work needed from others, and the resources

necessary to do the work.

-establish a lookahead window with screening criteria for advancement

-track the status of assignments as they move through the lookahead window

-adopt a sizing criterion for assignments that consistently demands less output

from production units than their estimated capacity to accommodate variability in

capacity. (This seems especially important for design. Other studies suggest that

routinely 20% of capacity is used to do needed but previously undefined work

each week.)

-improve the categorization of reasons and reasons analysis to facilitate

implementation of the learning process, which consists of: analyze reasons to

actionable causes, assign or take corrective action, and record results.

Ballard Last Planner7-1

CHAPTER SEVEN: CASE THREE-PACIFICCONTRACTING

7.1 Project Description and Last Planner Implementation

Pacific Contracting is a speciality contractor primarily involved in design and installation

of building envelopes; i.e., cladding and roofing systems. The author began working with

the company in 1995 as a consultant. Subsequently, Pacific Contracting became a charter

member of the Lean Construction Institute and its President, Todd Zabelle, became an

LCI partner.

Implementation of the Last Planner system by a speciality contractor is important for

several reasons. First of all, specialists work for many general contractors, not all of

whom may endorse the Last Planner principles and objectives. Secondly, the specialist

has a different role in the production system than does a general contractor or

construction manager. The latter's role is primarily to coordinate production, but the

production itself is done by specialists, even if they are directly employed by the general

contractor. Drawing on a manufacturing analogy, the speciality contractor is like a job

shop, while the coordinator is like an assembler. Many of the functions of the Last

Planner system, such as matching load to capacity, fall more particularly on the specialist,

whether design or construction, than on the coordinator of design or construction

processes.

Ballard Last Planner7-2

7.2 PPC and Reasons

Pacific Contracting, using the latest tools and techniques developed by the author,

participated in the effort to discover how to improve PPC to and above the 90% level, an

LCI research project. The data collection period extended for 41 weeks, ending in mid-

October, 199925. As can be seen from Figure 7.1, there appears to have been a period of

improvement through Week 19, then a decline followed by another upward trend

through Week 28, followed by a brief period of decline, with finally another upward

trend through the period of data collection.

Figure 7.1

0%10%20%30%40%50%60%70%80%90%

100%

Wee

k 4

Wee

k 6

Wee

k 8

Wee

k 10

Wee

k 12

Wee

k 14

Wee

k 16

Wee

k 18

Wee

k 20

Wee

k 22

Wee

k 24

Wee

k 26

Wee

k 28

Wee

k 30

Wee

k 32

Wee

k 34

Wee

k 36

Wee

k 38

Wee

k 40

Percent Plan Complete 90% 43% 67% 4 Week Moving Average

Pacific Contracting-PPC

25 The LCI research on improving PPC continued beyond the data collection period

reported in this dissertation.

Ballard Last Planner7-3

A possible explanation for the decline is that a very small number of assignments were

actually made ready in time to be placed on weekly work plans, so that a single

noncompletion registered as a relatively large percentage of failures. As shown in Table

7.1, from Week 17 through Week 23, no more than 4 tasks were assigned on weekly

work plans. From Week 19 through 23, at least one weekly assignment was not

completed, limiting PPC to a maximum of 75%. This likely impact of lookahead planning

on PPC adds impetus to the need for future development of metrics specifically for the

lookahead process and its improvement.

Table 7.1

Week 1 2 3 4 5 6 7 8Percent Plan Complete 90% 43% 67% 50% 67% 100% 69% 100%4 Week Moving Average 0% 0% 0% 65% 58% 70% 71% 79%Activities Scheduled 10 7 9 8 12 8 13 5Activities Complete 9 3 6 4 8 8 9 5Total Incompletions 1 4 3 4 4 0 4 0Activities Scheduled 10 7 9 8 12 8 13 5Client 0 0 0 0 0 0 0 0Engineering 0 0 0 0 1 0 0 0Materials 0 0 0 1 0 0 1 0Equipment 0 0 0 0 0 0 0 0Craft 0 0 0 0 0 0 0 0Pre-Requisite 0 1 1 0 0 0 0 0Subcontractor 0 2 1 0 0 0 2 0Plan 1 1 1 3 3 0 1 0Weather 0 0 0 0 0 0 0 0

Ballard Last Planner7-4

Week 9 10 11 12 13 14 15 16Percent Plan Complete 80% 88% 100% 63% 83% 83% 100% 83%4 Week Moving Average 83% 81% 88% 79% 80% 78% 82% 88%Activities Scheduled 10 8 3 8 6 6 8 6Activities Complete 8 7 3 5 5 5 8 5Total Incompletions 2 1 0 3 1 1 0 1Activities Scheduled 0 0 0 0 0 0 8 6Client 0 0 0 0 0 0 0 0Engineering 0 0 0 1 0 0 0 0Materials 0 0 0 0 0 0 0 0Equipment 0 0 0 0 1 0 0 0Craft 0 0 0 0 0 1 0 0Pre-Requisite 0 0 0 0 0 0 0 0Subcontractor 1 0 0 1 0 0 0 0Plan 1 1 0 1 0 0 0 0Weather 1 1 0 1 0 0 0 1

Week 17 18 19 20 21 22 23 24Percent Plan Complete 100% 100% 25% 50% 50% 67% 75% 70%4 Week Moving Average 90% 94% 69% 55% 50% 47% 60% 67%Activities Scheduled 1 2 4 4 4 3 4 10Activities Complete 1 2 1 2 2 2 3 7Total Incompletions 0 0 3 2 2 1 1 3Activities Scheduled 1 2 4 4 4 3 4 10Client 0 0 0 0 0 0 1 1Engineering 0 0 1 0 0 0 0 0Materials 0 0 0 0 0 0 0 0Equipment 0 0 0 0 0 0 0 0Craft 0 0 0 0 2 0 0 0Pre-Requisite 0 0 2 0 0 0 0 0Subcontractor 0 0 0 1 0 0 0 2Plan 0 0 0 1 0 1 0 0Weather 0 0 0 0 0 0 0 0

Week 25 26 27 28 29 30 31 32Percent Plan Complete 40% 67% 89% 100% 33% 57% 75% 50%4 Week Moving Average 64% 64% 70% 77% 80% 75% 68% 56%Activities Scheduled 5 3 9 5 3 7 4 4Activities Complete 2 2 8 5 1 4 3 2Total Incompletions 3 1 1 0 2 3 1 2Activities Scheduled 5 3 9 5 3 7 4 4Client 1 0 0 0 0 1 1 0Engineering 2 0 0 0 0 0 0 1Materials 0 0 0 0 1 1 0 0Equipment 0 0 0 0 0 0 0 0Craft 0 0 0 0 0 0 0 0Pre-Requisite 0 0 0 0 0 0 0 1Subcontractor 0 0 0 0 1 0 0 0Plan 0 1 1 0 0 1 0 0Weather 0 0 0 0 0 0 0 0

Ballard Last Planner7-5

Week 33 34 35 36 37 38 39 40 41Percent Plan Complete80% 100% 86% 90% 100% 71% 79% 82% 92%4 Week Moving Average65% 73% 78% 88% 91% 86% 83% 81% 82%Activities Scheduled 5 2 7 10 4 7 14 11 12Activities Complete 4 2 6 9 4 5 11 9 11Total Incompletions 1 0 1 1 0 2 3 2 1Activities Scheduled 5 2 7 10 4 7 14 11 12Client 0 0 0 1 0 0 0 0 0Engineering 0 0 0 0 0 0 0 0 0Materials 0 0 0 0 0 0 0 0 0Equipment 0 0 0 0 0 0 0 0 0Craft 0 0 1 0 0 2 2 0 0Pre-Requisite 0 0 0 0 0 0 0 0 1Subcontractor 0 0 0 0 0 0 0 0 0Plan 1 0 0 0 0 0 1 2 0Weather 0 0 0 0 0 0 0 0 0

Pacific Contracting-PPC Data and Reasons

Pacific Contracting categorized reasons for noncompletion of weekly assignments in

terms of Client, Engineering, Materials, Equipment, Craft, Prerequisite Work,

Subcontractor, Plan, or Weather. Bret Zabelle, Operations Manager for Pacific

Contracting, provided the following comments regarding their reasons categories:

"As I started to write our definition of engineering as a reason, I had a moment of

clarity. Engineering cannot be a reason. You either have the engineering for a

task complete or you don't. If you don't have the engineering complete, the task

should not be scheduled on a work plan. The only instances I can think of for

engineering is miscalculation of quantities, structural collapse or failure.

"Craft:When all the resources are available to perform a task on the WWP

(weekly work plan) and the craft workers do something different. Also refers to

craft absenteeism.

Ballard Last Planner7-6

"Subcontractor: This is similar to engineering as a reason. If we have

a subcontractor who did not complete prerequisite work in front of us, we should

not put our activity on the WWP until it is available. Also refers to fabricators.

They promise components will be fabricated by a certain date and fail.

"Plan: Planning failures occur when we do stupid things like schedule

activities if the engineering is not complete, materials, tools and workers are not

available, our own subcontractors or other contractors have not completed

prerequisite activities. Sometimes we schedule tasks that are more complex than

we thought."

Considering reasons for failures to complete weekly assignments, as shown in Table 7.1

and also graphically in Figure 7.2, much the most common reason was "Plan", Pacific

Contracting's own disregard of assignment quality criteria or inability to understand how

the planned work was to be done, and to anticipate all the steps and resources necessary.

The next most frequent reason was errors of some sort in execution of assignments by

Pacific Contracting's craft supervisors and workers.

Altogether, the vast majority of weekly work plan failures were well within the

control of Pacific Contracting. However, it should be remembered that matters might be

just the opposite as regards the lookahead process which makes ready assignments for

selection in weekly work plans. Again, we are reminded of the importance of measuring

and analyzing lookahead process performance.

Ballard Last Planner7-7

Figure 7.2

Pacific Contracting-Reasons

7.3 Observations

During the period of data collection, Pacific Contracting did not work with a single

general contractor that embraced the Last Planner system. Specialists appear to have

tremendous difficulty achieving high levels of PPC when not working on 'last planner'

projects. The consequent lack of resource utilization is a waste the recovery of which

could contribute to faster or more projects. On the other side of the matter, speciality

contractor efforts to avoid that waste seem inevitably to decrease both plan reliability and

progress of projects as seen from the perspective of project coordinators.

Once work is available to speciality contractors, they appear-based on this one

instance-to be able to achieve a relatively high level of plan reliability, limited mostly by

their own ability to plan and execute.

Client

Engineering

Materials

Equipment

Craft

Pre-Requisite Subcontractor

Plan

Weather

Ballard Last Planner7-8

7.4 Learnings

For speciality contractors to increase plan reliability to the 90% level and above requires

that the coordinators of the projects on which they work embrace the Last Planner

system's objectives and especially the lookahead process, which is dedicated to making

tasks ready for assignment and to balancing load and capacity. For their part, speciality

contractors must adhere to the discipline of Last Planner rules and perhaps also use the

technique of first run studies26 more consistently and well.

26 First run studies are extensive planning of upcoming operations by a cross functional

team including representatives of those who are to do the first operation, followedby methodical study, redesign of the operation, and retrial until a standard isestablished to meet or beat for execution of that operation. First run studies followthe Shewhart Plan-Do-Check-Act cycle, made popular by W. Edwards Deming.

Ballard Last Planner8-1

CHAPTER EIGHT: CASE FOUR-OLD CHEMISTRYBUILDING RENOVATION PROJECT

8.1 Project Description and Last Planner Implementation

Linbeck Construction, a founding member of the Lean Construction Institute, was the

general contractor for Rice University's Old Chemistry Building Renovation Project in

Houston, Texas. Linbeck brought John Pasch, Rice's facilities manager, to the Neenan

Company's annual winter conference in 1998. At that conference, James Womack spoke

on the need and opportunity to extend lean production (manufacturing) concepts and

techniques to the construction industry and Greg Howell27 shared the Lean Construction

Institute's vision of that application. John was sufficiently impressed that he allowed

Linbeck to negotiate with its primary subcontractors rather than competitively bid them

as had been the University's practice. At this point, a substantial building program stood

in the offing and Linbeck was one of three contractors competing for the lion's share.

Kathy Jones, Linbeck's project manager, had the author conduct several educational

and training sessions with project personnel, including the architect. Unfortunately, the

architect refused to participate in the Last Planner system. However, the subcontractors

became totally committed and enthusiastic about the planning process during the course

of the job, as did Rice University's personnel. The project was completed to a very

aggressive schedule to the satisfaction of users and within the budget. Rice University

was so well pleased with the performance that Linbeck won its Fondren Library Project,

and is well situated to do roughly half a billion dollars worth of work in the Rice

Program over the next several years.

Ballard Last Planner8-2

8.2 PPC and Reasons

The author facilitated team scheduling exercises that produced an overall project

schedule, then a more detailed schedule for the initial phase of work and the design

development needed to support it. That phase schedule became the driver for weekly

work planning, the results of which are shown in Figure 8.1.

Over a period of approximately eleven weeks, PPC rose to a level of 85% or so, then

stabilized at that level for the duration of the project. This was an unprecedented

accomplishment at the time, and resulted from the dedication of the owner, general

contractor, and subcontractor personnel to the Last Planner System and its goal of plan

reliability. Kathy Jones reinforced the Last Planner principles by fining those who used

the expression 'I hope' or 'hopefully' in connection with a commitment to do work. (The

fine was a six pack of beer to be collected at the project-ending celebration.) The project

manager for one subcontractor volunteered at an LCI research workshop that "It's fun to

go to work now!"

27 Co-founder with the author of the Lean Construction Institute in August, 1997.

Ballard Last Planner8-3

Figure 8.1

0.0%

10.0%

20.0%

30.0%

40.0%

50.0%

60.0%

70.0%

80.0%

90.0%

100.0%

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

PPC

4 Wk Mvg Ave.

Old Chemistry Building-PPC

Table 8.1Date 1/25/99 2/1/99 2/8/99 2/15/99 2/22/99 2/29/99 3/8/99 3/15/99 3/22/99 3/29/99 4/5/99 4/12/99 4/19/99 4/26/99

TasksCompleted

20 38 40 48 49 44 46 46 56 57 71 66 66 66

TasksAssigned

39 55 49 57 61 60 57 57 66 66 77 76 75 82

Date 5/3/99 5/10/99 5/17/99 5/24/99 6/1/99 6/7/99 6/14/99 6/21/99 6/28/99 7/6/99 7/12/99 7/19/99 7/26/99

TasksCompleted

60 53 65 64 50 55 65 69 62 62 66 63 73

TasksAssigned

64 62 72 69 56 64 72 80 67 83 76 71 80

Date 8/2/99 8/9/99Tasks Completed 59 53Tasks Assigned 67 65

Old Chemistry Building-PPC Data

Ballard Last Planner8-4

Of the relatively few failures to complete weekly assignments, most were caused by lack

of manpower or failure to complete prerequisite work ("make ready"). As this occurred

during a building boom in the Houston area, the low frequency of manpower problems is

a testament to the subcontractors' dedication to the project.

The remaining reasons categories were Schedule Accuracy (the assignment shouldn't

have been made), Material Deliveries, Design Coordination, Equipment (part of the

building, not construction equipment), Rework, Weather, and Overcrowding.

Figure 8.2

0%

5%

10%

15%

20%

25%

30%

35%

Man

power

Mak

e Rea

dy

Sched

. Acc

urac

y

Mat

'l Del.

Des. C

oord

.

Eqpt.

Del

Rewor

k

Wea

ther

Overc

rowdin

g

Old Chemistry Building-Reasons for Noncompletions

8.3 Observations

Lack of participation by the architect was a serious deficiency on the project, perhaps

concealed by the high PPC and low incidence of design coordination as a reason for

failing to complete weekly work plan assignments. Design problems did impact the job,

but that impact would only be evident in schedule changes and in the lookahead process.

Ballard Last Planner8-5

Unfortunately, the lookahead process was not fully and formally developed on this

project, in part because it was still being defined and its techniques created at the time

Old Chemistry was initiated.

Linbeck intends to extend the Last Planner System to the design phase of the

Fondren Library Project, and has Rice University's agreement to keep the same

subcontractors in place for that project. This commercial alliance among Linbeck and its

'preferred' suppliers is a critical component in the recipe for success.

8.4 Learnings

On the positive side, the Old Chemistry Building Renovation Project demonstrated that

PPC could be maintained consistently at a level of 85% through development and

nurturing of teamwork and the subsequent team enforcement of norms and rules. The

commercial success of the general contractor and its subcontractors indicates the power

and impact of increasing plan reliability. Specific techniques that were trialed successfully

on this project included team scheduling, specifically team production of detailed phase

schedules, resulting from intense negotiation among the speciality contractors

themselves, within a schedule framework established by the general contractor.

As for things that might be done better on future projects, implementation of Last

Planner in design and involvement of design professionals is certainly number one. Lesser

issues, but still important, include the need for a more transparent lookahead process and

the need for more explicit learning from analysis and action on reasons for failures.

Ballard Last Planner9-1

CHAPTER NINE: CASE FIVE-ZENECA PROJECT

9.1 PROJECT DESCRIPTION AND LAST PLANNER IMPLEMENTATION

Barnes Construction is a member of the Lean Construction Institute and is embarked on

transforming itself into a lean organization. Part of that transformation is to be achieved

by implementation and perfection of the Last Planner system of production control.

Implementation of the Last Planner system began with classroom training, followed by

site visits and coaching, all provided by the author.

Zeneca is a biotechnology company located in Richmond, California near San

Francisco. The Zeneca Project reported here is one of a series of seismic retrofits of

laboratory and office buildings being performed by Barnes. Of all the cases included in

this dissertation, the Barnes case incorporates most of all previous learnings and the

latest developments in technique and implementation. One of the critical improvements

to be seen is in the methodical analysis and removal of constraints from scheduled tasks.

9.2 PPC AND REASONS

As shown in Figure 9.1, the period of data collection extended from the week of 6/26/99

through the week of 10/11/99. It appears that PPC gradually improved throughout that

period until culminating in four consecutive weeks in which PPC measured 100%.

Ballard Last Planner9-2

Figure 9.1

0%

20%

40%

60%

80%

100%

120%

6/28/99 7/6/99 7/12/99 7/19/99 7/26/99 8/2/99 8/9/99 8/16/99 8/23/99 8/30/99 9/7/99 9/13/99 9/20/99 9/27/99 10/4/99 10/11/99 10/18/99 10/25/99 11/1/99

PPC 4 Wk Mvg Ave

Zeneca-PPC

With such a high percentage of weekly assignments completed, there were relatively few

Figure 9.2

Decided to hold off6% Pulled from wrong week

6%

Space conflict11%

Theft of Bobcat wheel6%

Design11%

Prerequisite Work32%

Not Defined16%

Installation Error6%

Sub Manpower6%

Zeneca-Reasons

Ballard Last Planner9-3

noncompletions, and so few occasions for identifying reasons for noncompletions. Such

as were identified are shown in Figure 9.2.

9.3 CONSTRAINT ANALYSIS AND MAKE READY

The technique of constraints analysis, pioneered on the CCSR Project, became a key tool

in Zeneca's success. As originally envisioned, status information regarding constraints

was collected each week on all tasks scheduled to start within the next 6 weeks. Notes

and action items were added to the constraint analysis form to serve as a reminder to

various parties regarding the actions they needed to take to make tasks ready in time to

be performed. The primary rule applied to this lookahead process was to only allow tasks

to retain their scheduled starts if the planners were confident they could be made ready in

time. Otherwise, they were to appeal for help to higher levels of their organizations, then,

if make ready actions indeed could not be taken in time, defer the task until it could be

made ready.

Following is a statement, by this writer, of the directives governing the Last Planner

system installation and execution at Barnes:

Barnes Production Control Requirements

1. Hold weekly subcontractor coordination meetings on each project. Insistsubcontractors give input into weekly work plans and lookahead schedules.

2. Select weekly work plan assignments from those that meet quality criteria ofdefinition, soundness, sequence, and size. Issue weekly work plans and expectevery superintendent and foreman to have them in their pocket. Use the weeklywork plan form and be sure to complete all sections, including make ready needsand workable backlog. When assigned tasks extend beyond one week, specifywhat work is to be completed within the week.

3. Each week, calculate the percent plan complete (PPC) for the previous week andidentify reasons for each assignment that was not completed. Try to get to root

Ballard Last Planner9-4

or actionable causes. Don't beat people up for plan failure, but insist that theylearn from their experience.

4. Maintain a 5 week lookahead schedule at a level of detail needed to identify makeready needs. Add 1 week each week.

5. Do constraints analysis on each activity on the 5 week lookahead schedule, usingthe constraints analysis form. Remember to mark an activity as unconstrainedonly if you have positive knowledge that the constraint does not exist or has beenremoved ('guilty until proven innocent').

6. Each week, email or fax the constraints analysis form to each subcontractor thathas activities scheduled on the lookahead and ask them to provide statusinformation.

7. Assign make ready actions as appropriate; e.g., the technical engineer will resolveRFIs, the project sponsor will expedite outstanding payments, the projectcontrols manager will deal with contract and change order issues, etc. Obviously,subcontractors will also have make ready tasks such as generating submittals,expediting fabrication and deliveries, acquiring necessary equipment and tools,reserving labor, etc.

8. Maintain a statused and current master project schedule.9. Involve subcontractors in producing master and phase schedules. Phase schedules

are detailed plans for completing a specific phase of project work; e.g., sitepreparation, foundations, superstructure, skin, etc. Use the team schedulingtechnique in which participants describe activities on sheets that they stick on awall, then negotiate details, sequencing, etc.

Project Checklist

1. Does the project hold weekly subcontractor coordinating meetings?2. Are weekly work plan forms completed each week, including make ready needs

and workable backlog?3. Are weekly assignments adequately defined; e.g., is the work to be completed

during the week specified?4. Are weekly work plans used in the field; e.g., does every foreman and

superintendent carry it with them?5. Are weekly work plans reviewed in the coordinating meetings, PPC calculated,

and reasons identified?6. Is a 5 week lookahead schedule maintained, with one week added each week?7. Are subcontractors requested each week to provide status information regarding

constraints on the activities listed on the project lookahead schedule?8. Which subcontractors provide information each week for constraints analysis?

Which subcontractors don't?9. Are make ready actions assigned each week?10. What people carry out their make ready assignments? Who doesn't?11. Is the rule followed that activities keep their scheduled dates only if the planner is

confident they can be made ready in time?12. Of those activities scheduled to start within the next 3 weeks, what percentage

are not made ready?

Ballard Last Planner9-5

13. Is the rule followed to only allow activities onto weekly work plans that have hadall constraints removed that could be removed before the start of the plan week?

14. What is the project's PPC? Is it rising, falling, or staying the same?15. What are the dominant reasons for failing to complete assignments on weekly

work plans?16. Is a master project schedule and phase schedule maintained current and updated

once a week?17. Are subcontractors involved in producing master and phase schedules using team

scheduling?

Table 9.1

Activity Planned StartResponsibleContract / Materials LaborEquipment Prereq Weather

ID Date PartyChange OrdersAE CompleteSubmittalsRFI's Work

E-20 First Floor

Install dowel template 12-Aug NLB X X X X X X X Above X

Pour mat slab @E-10 17-Aug NLB X X X X Concrete X X Above X

Move tower shoring to E-1423-Aug Safway X X X X X X Crane Above X

Hard demo (Beams) 30-Aug Cal-WreckingX X X X X X X Above X

One side walls 13-Sep Peck & HillerX X X X X X X Collectors X

Install wall rebar 16-Sep McGrathX X X X X X X Above X

Epoxy dowels 22-Sep NLB X X X X X X X Above X

Pull Test 23-Sep ICI X X X X X X X Above X

Close forms 24-Sep Peck & HillerX X X X X X X Above XE-10 FirE-10 First Floor

Install tower shoring 23-Aug Safway X X X X X X Crane Cure X

Excavate footing 13-Sep Cal-WreckingX X X Possible footing resizeX X Collectors X

Chip footings if necessary16-Sep Cal-WreckingX X XIf necessary X X X X X

Drill and epoxy dowels @mat16-Sep NLB X X X X X X X X X

Install rebar @mat 17-Sep McGrathX X X X X X X Above X

Rebar template 24-Sep NLB X X X X X X X Above X

Activity Description Design

Zeneca-Constraint Analysis Form

Ballard Last Planner9-6

9.4 OBSERVATIONS

The extremely high level of plan reliability achieved on Zeneca may have resulted in part

from its being relatively simple, not technically but rather operationally. A relatively few

subcontractors were involved28, and few were required to work in close proximity, either

temporally or spatially. On the other hand, the production control processes and

techniques employed appear also to have made a contribution. Apart from the Old

Chemistry Building Renovation Project, in no other case were subcontractors more

intimately involved in the lookahead process or in weekly work planning. Further, the

contractor's execution of the lookahead process, particularly constraints analysis and

assignment of action items to remove constraints, was much more rigorous than on

previous projects.

9.5 LEARNINGS

It is possible to achieve PPC levels above 90% over an extended period of time through

consistent implementation of Last Planner system techniques. Especially important in

28 Once the rebar installation was well underway, rarely were more than 5 subcontractors

scheduled to work on the project in any week. Safway-shoring, McGrath-rebarinstallation, ICI-rebar inspection, Peck & Hiller-formwork, Cal-Wrecking-demolition, National-concrete coring. By contrast, on an interiors project underwayat the same time, an average of 10 subcontractors were given assignments eachweek.

Ballard Last Planner9-7

this regard are constraint analysis and subcontractor participation in planning and

control.

Ballard Last Planner10-1

CHAPTER TEN: CONCLUSIONS

10.1 Summary of Case Study Results

Data collection for the five case studies was concluded in the following order and dates,

all within the period in which this dissertation was in progress:

q Case One-CCSR Project Jan-Mar '98

q Case Two-Next Stage July-Nov '98

q Case Three-Pacific Contracting Jan-Oct '99

q Case Four-Old Chemistry Building Renovation Feb-Aug '99

q Case Five-Zeneca June-Oct '99

CCSR addressed the question how to apply the Last Planner system to subcontracted

projects as distinct from the direct hire production to which for the most part it had

previously been applied. The application was successful and piloted constraints analysis

as a tool for evaluating the readiness of potential assignments and for identifying the

actions needed to make them ready.

Next Stage was an exploratory case study on the application of Last Planner to

design. Interruption of the project prevents drawing firm conclusions, however

participants considered the Last Planner system successful and superior to traditional

methods of project control. Numerous learnings were drawn from the case, perhaps the

most important being the need to explode design tasks into operational detail near in time

to their execution, in order to accommodate the self-generating characteristic of the

design process. The Activity Definition Model was created for that purpose and has

subsequently been applied extensively for the purpose of task explosion.

Ballard Last Planner10-2

The Pacific Contracting case explored the limitations faced by a speciality contractor

trying to unilaterally apply the Last Planner system. Diligent adherence to system rules

allowed the contractor to achieve an average 76% PPC level. However, several periods

of precipitously lower performance appear to have been correlated with failure of their

customer projects to make work ready when scheduled, reducing the amount of work

available to Pacific Contracting and consequently making them vulnerable to low PPC

should they experience any plan failures at all. Another interesting finding was that plan

failures within their control tended to be primarily from lack of detailed, advance

operations design. Pacific Contracting has rededicated themselves to the routine use of

First Run Studies in response to this finding.

The Old Chemistry Building Renovation case revealed a sustained PPC of 85%. With

the opportunity to benefit from previous cases, the project team also added a very

successful education and team building component to achieve this breakthrough result.

The fifth and last case study, Barnes Construction's Zeneca Project, sustained a PPC

near 100%, apparently settling the question whether or not that level of plan reliability

can be achieved. It is not suggested that every project will be able to achieve the same

results even should they imitate Zeneca's rigorous application of Last Planner rules and

techniques. The relatively few subcontractors involved during the measurement period

may have simplified the coordination problem beyond the norm. However, the extensive

involvement of subcontractors in planning and constraints analysis is a model to be

imitated by all.

10.2 Research Question: What can be done by way of tools provided andimproved implementation of the Last Planner system of productioncontrol to increase plan reliability above the 70% PPC level?

Ballard Last Planner10-3

Review of the case studies suggests that plan reliability improves with adherence to the

Last Planner system rules, with extensive education and involvement of participants, and

with use of techniques such as task explosion, constraints analysis, make ready actions,

shielding production from uncertainty through selection of quality assignments, and

identification and action on reasons for failing to complete assigned tasks. The PPC

levels recorded were significantly better than previous measurements. Previously,

measured PPC above 70% was very rare (Ballard and Howell, 1997). In the latter three

case studies, all achieved PPC levels of 76% or higher, with Zeneca consistently above

90%.

10.3 Research Question: How/Can Last Planner be successfully appliedto increase plan reliability during design processes?

Evidence for settling this question is not so decisive. The exploratory case suggested but

did not confirm that Last Planner can effectively be applied to design production control.

However, the Last Planner system as now developed appears to be precisely matched to

the nature of the design process. Unlike making, which covers a wide range of tasks,

including making multiple copies of a single design, design itself is essentially generative.

As such, a process control system is required that does not assume a simple matching of

criteria and design alternatives, but rather facilitates a progressive, dialectical

development of both.

Perhaps the most valuable contribution of the case was its clarification of the nature

of the design process and consequently of the obstacles to management control. The

primary response to those obstacles has been the development and implementation of the

Activity Definition Model as a technique for exploding design tasks as they enter the

Ballard Last Planner10-4

lookahead process. Ideas and suggestions for further research on this question are

described below.

10.4 Directions for Future Research

The case studies suggest the need for further modifications to the Last Planner System,

some specifically intended to make it better fit design applications and others for general

improvement. The prevalence of confusion over directives as a reason for plan failure in

the Next Stage case study indicates a need for more explicit specification of the

directives governing design tasks. A tool for making that specification is the Activity

Definition Model29 shown in Figure 10.1.

Figure 10.1

Activity Definition Model

Process

Directives

Output

Resources

Prerequisite Work

MeetsCriteria?

ReleaseYes

Redo

No

Activity Definition Model

ACTIVITY DEFINITION

OUTPUT represents the result or deliverable produced by performing the scheduled

activity. In the case of complex deliverables, a process flow diagram is created and each

of its deliverables is decomposed using the same activity definition model.

Ballard Last Planner10-5

What are the DIRECTIVES governing my output, process, and inputs? To what

criteria must my output conform in order to serve the needs of our customer production

units? What PREREQUISITES do I need from others? What RESOURCES do I need to

allocate to this assignment?

Before releasing the output to the PUs that need it, it is to be evaluated against the

criteria and , if nonconforming, either the criteria are revised based on new insights into

customer or stakeholder needs, or the output is revised to better meet the criteria30.

JOINT SUPPLIER/CUSTOMER ASSIGNMENTS

A critical element for success is explicit agreement between ‘customer’ and ‘supplier’

regarding those criteria. The PU producing the output should understand how it is to be

used by the customer PUs before production. Subsequently, inspection can be either by

the producer or jointly by producer and customer.

Self-inspection and joint supplier/customer inspection are key concepts in the method

of in-process inspection, which reduces defects through empowerment of the workers

themselves, as opposed to exclusive reliance on external inspectors. This quality

assurance prior to releasing work between PUs has been extended by some lean

contractors to the progressing of work. Only products and installations that have passed

quality control inspection can be counted as completed work, and then only if they are in

the work packages (batches) needed by the customer PUs.

29 Although developed independently by this author in the mid-1980s, the Activity

Definition Model is similar to IDEF, although arguably the concept of "directives" isdifferent from the IDEF concept of "constraints".

30 Conformance of outputs to design criteria is not a matter of matching. It is rather theexception than the rule that any design alternative maximally satisfies all the multiplecriteria. The question is rather at what level of value must tradeoffs be made among

Ballard Last Planner10-6

Recognizing the critical need for the supplier process and the customer process to

agree on directives, and the objective of selecting and executing only those assignments

that release work to others, it is proposed to make the supplier and customer jointly

responsible for successful completion of assignments. The supplier should make sure

he/she understands what the customer needs. The customer equally should make sure the

supplier understands what he/she needs. Aside from assignments generated by push

scheduling, in the absence of an explicit pull signal from the customer, the supplier can

assume that the task does not need to be performed at this time.

REASONS CATEGORIZATION AND ANALYSIS

The reasons categories used on the Next Stage Project did not promote identification of

root causes. Consequently, it is proposed to use the elements of the Activity Definition

Model as the primary categories and also to provide a guide for reasons analysis that will

facilitate identification of actionable causes.

those competing criteria. Exploration of such issues is part of the future researchagenda beyond the scope of this thesis.

Ballard Last Planner10-7

Figure 10.2

Reasons Analysis Hierarchy-DirectivesThe primary categories are directives, prerequisites, resources, and process. Once placed

within one of these categories, a plan failure can be analyzed in accordance with the

guidelines expressed in Figures 10.2-10.5.

A-1: I didn'tunderstand the real

criteria for mydeliverable.

A.1.1: Didn'tunderstand what the

requestor needed andwhy she wanted it.

A.1.2: Didn'tunderstand the

applicablerequirements.

A.1.3: Redefinition ofcriteria occurred

during the plan week.

Why didcriteriachange

during theweek?What

could bedone to

avoid theneed for

change orto find outabout thechange

andinclude in

yourweekly

planning?

Why didn'tyou

understandwhat the

requestorneeded or

theapplicablerequiremen

ts? Whatwould

preventrepetition?

A-2: The directiveswere incorrect.

A.2.1: Incorrectspecification ofprerequisites.

A.2.2: Incorrectspecification of

resources.

A.2.3: Incorrectspecification of

processes.A.2.4: Incorrectspecification of

output.

Whatchanges

indirectives

areneeded?Who canmake thechanges?

Directives-related PlanFailures

Ballard Last Planner10-8

Figure 10.3

Reasons Analysis Hierarchy-Prerequisites

B.1: Didn't requestneeded

prerequisites.

B.2:Incomplete

request.

B.3: Promise notkept by provider of

prerequisite.

B.1a: Didn't know itwas needed.

B.1.b: Knew it wasneeded, but didn'tmake the request.

B.2.b: Failed toidentify the provider.

B.2.c: Failed tospecify content.

B.2.d: Failed tospecify delivery time.

Prerequisites-related Plan Failures

B.4: Can't make anagreement with

supplier

B.2.e: Failed toprovide sufficient

lead timeWhy didn't you knowthat prerequisite wasneeded or why didn't

you make the request.What would prevent

repetitions?

Regarding each of theabove, ask what caused

the failure and what couldprevent it reoccurring.

Analyze B.3 cases bystarting over again,

selecting A, B, C, or D,and carrying out the

analysis. But this time,the failure being

analyzed is that of theprerequisite providerwho failed to keep hispromise rather than

the Last Planner whofailed to complete anassignment becausethat provider failed to

keep his promise.

Why can'tyou make

anagreement

with thesupplier?

Ballard Last Planner10-9

Figure 10.4

Reasons Analysis Hierarchy-Resource

C.1: Lack ofequipment or

tools

C.2: Insufficient laboror time

C.1.a:Breakdown(Ask what

could be doneto prevent

breakdowns.)

C.1.b:Overloaded

(Ask why loadswere not

integrated.)

C.2.a: Didn'trequest

enough laboror time

C.2.a.1: Didn'tunderstand

load.

C.2.a.b: Didn'tunderstand

capacity.

C.2.b: Labor was requestedand allocated but not

available when needed.

C.2.b.1: Gotbumped by

higher priority(Ask why

priority wasnot known in

advance.)

C.2.b.2:Absenteeism (Askwhy absence was

not known inadvance; if absence

was avoidable.)

Ask why the priority changed,what could be done to avoidthe need for change, or what

could be done to includeknowledge of the change in

weekly planning.

Resources-relatedPlan Failures

Ballard Last Planner10-10

Figure 10.5

Reasons Analysis Hierarchy-Process

10.5 Conclusion

The Last Planner system of production control, improved through the case studies

included in this thesis, has been shown to be effective in achieving and maintaining plan

reliability above the 90% level in site installation. Applicability and effectiveness of the

Last Planner system to design remains to be definitively determined, however the

generative nature of the design process suggests that a control system such as Last

Planner is needed, as opposed to approaches that rely on push scheduling and early

d.1 Error in processingproduced defective output

d.2 Acts of God orthe Devil produced

defective output

d.1.a Processing error wascaused by lack of skill

d.1.b Processing error wascaused by inadequate

processd.1.c Processing error wascaused by inadequate tools

or equipment

d.1.d Processing error wascaused by a change in the

working environment

What wentwrong? Why

wasn't itanticipated?

Ask for thecause of eachcause; e.g.,

why was skillinadequate?...why was

processinadequate?

Process-relatedPlan Failures

Ballard Last Planner10-11

selection from alternatives. Further development of the Last Planner system is suggested

regarding activity definition, joint supplier/customer assignments, and reasons analysis.

In addition, research is needed to quantify and understand the benefits of greater plan

reliability for safety, quality, time, and cost.

Ballard G-12 Last Planner

GLOSSARY OF TERMS31

activity definition model An input-process-output representation of design tasks,supplemented by specification of criteria (entering the process rectanglefrom above) and of resources (entering the process rectangle from below)and an inspection process resulting either in redo or release to the customerprocess. The model is used as a guide to exploding design tasks into a levelof detail at which their readiness for execution can be assessed andadvanced.

assignment a directive or order given to a worker or workers directly producing orcontributing to the production of design or construction. Example: Scott,you and Julie are to make the changes in wall locations detailed in memo#123 by the end of the week. Anne, you find out what the buildingauthorities will require for a structural permit.

capacity the amount of work a production unit, whether individual or group, canaccomplish in a given amount of time. Example: Jim the engineer canperform 10 piping stress analyses per day on average, but the analyses to bedone this week are particularly difficult. He will only be able to do 7. Jim’saverage capacity is 10, but his capacity for the specific work to be done thisweek is 7.

commitment planning Planning that results in commitments to deliver on which others inthe production system can rely because they follow the rule that only sound

31 This glossary was produced specifically for this thesis. An expanded version, with

some modifications in definitions, is available at <www.leanconstruction.org>. It wasproduced by this author and Iris Tommelein, LCI principal and Associate Professorat the University of California at Berkeley.

Process

Criteria

Output

Resources

Input

MeetsCriteria?

ReleaseYes

Redo

No

Ballard G-13 Last Planner

assignments are to be accepted or made. Example: On my work plan fornext week, I have included providing Cheryl the soils data she needs toevaluate alternative substructure systems for the building. All knownconstraints have been removed from my task, I understand what’s requiredand how the information will be used, and I have reserved needed labor andequipment.

constraints something that stands in the way of a task being executable or sound.Typical constraints on design tasks are inputs from others, clarity of criteriafor what is to be produced or provided, approvals or releases, and labor orequipment resources. Screening tasks for readiness is assessing the status oftheir constraints. Removing constraints is making a task ready to beassigned.

control to cause events to conform to plan, or to initiate replanning and learning.Example: Exploding master schedule activities into greater detail, screeningthe resultant tasks against constraints, and acting to remove thoseconstraints are all control actions intended to cause events to conform toplan, or to identify as early as practical the need for replanning. Learning isinitiated through analysis of reasons for failing to cause events to conform toplan.

customer the user of one’s output. Example: John needs the results of our acousticaltests in order to select the best location for his mechanical equipment. Johnis our customer because he will use what we produce.

design Design is a type of goal-directed, reductive reasoning. There are alwaysmany possible designs. Product design reasons from function to form.Process design reasons from ends to means.

design criteria the characteristics required for acceptance of product or process design.Example: The structural engineer needs both geometric and load inputs fromthe architect, mechanical engineer, and electrical engineer. Loads need onlybe accurate within 20%. Example: The cladding design must be consistentwith the architectural standards of the local historical society. In addition, itmust be within the 2 million pound budget and installable within a 6 weekwindow concluding no later than 6th April, 2000.

exploding expressing a task in greater detail, typically by producing a flow diagram ofthe process of which the output is the task being exploded, then determiningthe sub-tasks needed to make the task ready for assignment and executionwhen scheduled. Sub-tasks are categorized in terms of the activity definitionmodel, resulting in actions to clarify or specify criteria, requests for inputsfrom suppliers, and reservation of needed resources.

first run studies extensive planning of upcoming operations by a cross functional teamincluding representatives of those who are to do the first operation, followed

Ballard G-14 Last Planner

by methodical study, redesign of the operation, and retrial until a standard isestablished to meet or beat for execution of that operation. First run studiesfollow the Shewhart Plan-Do-Check-Act cycle, made popular by W.Edwards Deming.

last planner the person or group that makes assignments to direct workers. ‘Squadboss’ and ‘discipline lead’ are common names for last planners in designprocesses.

load the amount of output expected from a production unit or individual workerwithin a given time. Within a weekly work plan, what is to be accomplishedby a design squad or individual designer, engineer, draftsperson, etc. Aquality assignment ‘loads’ a resource within its capacity.

lookahead planning The middle level in the planning system hierarchy, below front endplanning and above commitment-level planning, dedicated to controlling theflow of work through the production system.

lookahead schedule the output of lookahead planning, resulting from exploding masterschedule activities by means of the activity definition model, screening theresultant tasks before allowing entry into the lookahead window oradvancement within the window, and execution of actions needed to maketasks ready for assignment when scheduled. Lookahead schedules may bepresented in list form or bar charts.

lookahead window how far ahead of scheduled start activities in the master schedule aresubjected to explosion, screening, or make ready. Typically design processeshave lookahead windows extending from 3 to 12 weeks into the future.

make ready take actions needed to remove constraints from assignments to make themsound.

planning defining criteria for success and producing strategies for achievingobjectives.

plan reliability the extent to which a plan is an accurate forecast of future events,measured by PPC. For example, if your weekly work plans have a 60% PPC,they accurately predict completion/release of 60% of the weekly assignments.

PPC percent plan complete; i.e., the number of planned completions divided intothe number of actual completions.

prerequisite work work done by others on materials or information that serves as aninput or substrate for your work. Example: You need to know the surfacearea of glass, provided by the architect, in order to size cooling equipment.

Ballard G-15 Last Planner

production unit(PU) a group of direct production workers that do or shareresponsibility for similar work, drawing on the same skills and techniques.Example: a team of electrical designers and engineers responsible for aspecific area or functions of a building.

productivity the ratio of the amount of work produced to the resources used in itsproduction. Example: x drawings per labour hour.

PU See production unit.

pulling initiating the delivery of materials or information based on the readiness of theprocess into which they will enter for conversion into outputs. Example:Request delivery of prerequisite information at or before the time you will beready to process that information. Note: what’s different here is that thereadiness of the process is known rather than wished. Either the process isready prior to requesting delivery or plan reliability is sufficiently high thatwork plans can be used to predict readiness.

reasons…for failing to complete weekly assignments; e.g., lack of prerequisites,insufficient time, unclear requirements. Reasons can also be sought for failingto advance scheduled tasks from master schedule to lookahead schedule orfrom one week to the next within the lookahead schedule.

resources labour or instruments of labour. Resources have production capacities as wellas costs. Consequently, materials and information are not resources, but ratherwhat resources act on or process.

screening determining the status of tasks in the lookahead window relative to theirconstraints, and choosing to advance or retard tasks based on their constraintstatus and the probability of removing constraints.

shielding..production units from uncertainty and variation by making only qualityassignments.

should-can-will-did to be effective, production management systems must tell us whatwe should do and what we can do, so that we can decide what we will do,then compare with what we did to improve our planning.

sizing…...assignments to the capacity of the production unit to do the work. Example:Ruben and James should be able to collect that data and analyze it byThursday. But, I forgot, it’s Ruben and Tim. Tim’s not as experienced. I’dbetter give them an extra day.

sound assignments that have had all constraints possible removed. Example: Wenever make assignments that are not sound. We always check if we have orcan get necessary information from others, if the requirements are clear, etc.

Ballard G-16 Last Planner

supplier the provider of needed inputs; prerequisite work, materials, information,resources, directives, etc.

supplier lead time the time from sending a request for delivery to the delivery.

underloading making assignments to a production unit or resource within a productionunit that absorbs less than 100% of its capacity. Underloading is necessary toaccommodate variation in processing time or production rate, in order toassure plan reliability. Underloading is also done to release time for workers totake part in training or learning, or for equipment to be maintained.

utilization the percentage of a resource’s capacity that is actually used. Example:Because of time lost waiting for materials, our labour utilization last week wasonly 40%.

weekly work plan a list of assignments to be completed within the specified week;typically produced as near as possible to the beginning of the week.

window of reliability how far in advance future work completions can be accuratelyforecast. Example: If you can accurately forecast only 1 day in advance whenwork will be completed, then your window of reliability is 1 day.

workable backlog assignments that have met all quality criteria, except that some mustyet satisfy the sequence criterion by prior execution of prerequisite workalready scheduled. Other backlog assignments may be performed within arange of time without interfering with other tasks. Example: Completing thosespare parts lists doesn’t have to be completed for 3 months, but it won’t harmanything if they are produced earlier, so use them as fallback or fill-in workwhen needed.

work flow the movement of information and materials through a network of productionunits, each of which processes them before releasing to those downstream.

work flow control causing information or materials to move through a network ofproduction units in a desired sequence and rate.

Ballard R-17 Last Planner

LIST OF REFERENCES

Addis, William (1990), Structural engineering: the nature and theory of design, Ellis Horwood,London.

Alarcón, L., ed. (1997) Lean Construction. Balkema Publishers, Rotterdam, The Netherlands.

Ballard, Glenn (1993). "Improving EPC Performance." Proceedings of the 1st Annual Conference of theInternational Group for Lean Production, Espoo, Finland, August, 1993. Available in Alarcon, 1997.

Ballard, Glenn (1994). "The Last Planner". Spring Conference of the Northern California ConstructionInstitute, Monterey, CA, April 22-24, 1994.

Ballard, Glenn and Gregory Howell (1994). “Stabilizing Work Flow.” Proceedings of the 2nd AnnualConference of the International Group for Lean Construction, Santiago, Chile, October, 1994. Availablein Alarcón, 1997, 101-110.

Ballard, Glenn, Howell, Gregory, and Casten, Mike (1996). “PARC: A Case Study”. Proceedings of the4th annual conference of the International Group for Lean Construction, University of Birmingham,U.K.

Ballard, Glenn (1997). “Lookahead Planning: The Missing Link in Production Control”. Proceedings ofthe 5th annual conference of the International Group for Lean Construction, Griffith University, GoldCoast, Australia.

Ballard, Glenn and Howell, Gregory (1997). “Shielding Production: An Essential Step in ProductionControl.” Journal of Construction Engineering and Management, Vol. 124 No. 1, American Society ofCivil Engineers, New York, NY, 11-17.

Ballard, Glenn (1998). “Front End Planning”. Unpublished. Workshop on Front End Planning, LeanConstruction Institute, Houston, TX, 11/99.

Ballard, Glenn (1999). “Improving Work Flow Reliability”. Proceedings of the 7th Annual Conferenceof the International Group for Lean Construction, University of California, Berkeley, CA. p. 275-286

Bennett, J. (1985), Construction Project Management, Butterworths, London. 220 p.

Bertrand, J.W.M., J.C. Wortmann, and J. Wijngaard (1990). Production Control: A Structural andDesign Oriented Approach. Elsevier, Amsterdam.

Bucciarelli, L.L. (1984), “Reflective practice in engineering design”, Design Studies 5(3), 185-190.

Burbidge, J.L. (1983). “Five golden rules to avoid bankruptcy”. Production Engineer, Vol 62, No. 10,13-4.

Burbidge, J.L. (1989). Production Flow Analysis. Oxford University Press, Oxford.Campbell, D.T. and Stanley, J. (1966) Experimental and quasi-experimental designs for research.Chicago: Rand McNally.

Checkland, P. & Scholes, J. (1990), Soft systems methodology in action, John Wiley & Sons.Cook, T.D. and Campbell, D.T. (1979). Quasi-Experimentation: design and analysis issues for fieldsettings. Rand McNally, Chicago.

Ballard R-18 Last Planner

Conklin, E. Jeffrey and Weil, William (1998). "Wicked problems: Naming the pain in organizations."Reading Room Research Center; http://www.3mco.fi/meetingnetwork/readingroom/gdss_wicked.html

Deming, W. Edwards (1986). Out Of The Crisis, 2nd ed. Cambridge, Mass.: MIT Center for AdvancedEngineering Study.

Diekmann, James E. and K. Bryan Thrush (1986). Project Control in Design Engineering. ConstructionIndustry Institute, University of Texas at Austin.

Eppinger, S.D., Whitney, D.E., Smith, R.P., and Gebala, D.A. (1990). “Organizing the Tasks inComplex Design Projects.” ASME Design Theory and Methodology Conference, Chicago.

Finger, Susan, Konda, Suresh, and Subrahmanian, Eswaran (1995), “Concurrent design happens at theinterfaces”, Artificial Intelligence for Engineering Design, Analysis and Manufacturing, 9, CambridgeUniversity Press, pp 89-99.

Gebala, David A. and Eppinger, Steven D. (1991). “Methods for analyzing design procedures”. DE-Vol.31, Design Theory and Methodology, ASME, 227-233.

Green, Marc, editor (1992). Knowledge Aided Design. Academic Press Limited, London.

Hayes, Robert H., Wheelwright, Steven C., and Clark, Kim B. (1988). Dynamic Manufacturing:Creating the Learning Organization. Free Press, New York, 429 p.

Hayes-Roth, Barbara (1985). “A Blackboard Architecture for Control”. Artificial Intelligence, ElsevierScience Publishers B.V., Amsterdam, The Netherlands, 252-321.

Hopp, Wallace J. and Spearman, Mark L. (1996). Factory Physics: Foundations of ManufacturingManagement. Irwin/McGraw-Hill, Boston, Massachusetts.

Howell, G. (1996). Plan Reliability of Electrical Contractors. A research report prepared for theElectrical Contracting Foundation, National Electrical Contractors Association, Washington, D.C.

Howell, Gregory and Glenn Ballard (1996). “Can Project Controls Do Its Job?” Proceedings of the 4thAnnual Conference on Lean Construction, Birmingham, England. (Available athttp://web.bham.ac.uk/d.j.crook/lean/)

Kelly, Kevin (1994). Out of Control. Addison-Wesley, Reading, Massachusetts.

Koskela, L. (1992). Application of the new production philosophy to construction. Tech. Rept. 72,Center for Integrated Facility Engineering, Stanford Univ., Stanford, CA, Sept., 75 pp.

Koskela, L., P. Lahdenperaa and V-P. Tanhuanperaa. 1996. Sounding the potential of lean construction:A case study. Paper presented at the Fourth International Conference on Lean Construction, School ofCivil Engineering, University of Birmingham, Birmingham, UK, August 25 - 28, 1996. 11 p.

Koskela, L., Ballard, G., and Tanhuanpaa, Veli-Pekka (1997). “Towards Lean Design Management”.Proceedings of the 5th annual conference of the International Group for Lean Construction, Gold Coast,Australia.

Koskela, L. & Huovila, P. (1997). “On Foundations of Concurrent Engineering” in Anumba, C. andEvbuomwan, N. (eds.). Concurrent Engineering in Construction CEC97. London 3-4 July. TheInstitution of Structural Engineers, London, 22-32.

Ballard R-19 Last Planner

Koskela, L. (1999). “Management of Production in Construction: A Theoretical View”. Proceedings ofthe 7th Annual Conference of the International Group for Lean Construction, University of California,Berkeley, CA. p. 241-252

Kuhn, Thomas S. (1962). The structure of scientific revolutions. University of Chicago Press, Chicago.

Laufer, Alexander (1987). “Essentials of Project Planning: Owner’s Perspective”. Journal ofManagement in Engineering, 6(2), 162-176.

Laufer, A. and Tucker, R. (1987). "Is Construction Project Planning Really Doing Its Job?" ASCEJournal of Construction Engineering and Management, 5, pp 243-266.

Laufer, A., Tucker, R, Shapira, A., Shenhar, A. (1994) “The multiplicity concept in construction projectplanning”. Journal of Construction Engineering and Management, American Society of CivilEngineering, New York, NY

Laufer, Alexander, Denker, Gordon R., and Shenhar, Aaron J. (1996). “Simultaneous management: thekey to excellence in capital projects.” International Journal of Project Management, 14(4), ElsevierScience Ltd., Great Britain. 189-199.

Laufer, Alexander (1997), Simultaneous Management, AMACOM, New York, NY. 313 pp.

Lloyd, Peter, Deasley, Peter, Seymour, David, Rooke, John, and Crook, Darryl (1997). “EthnographicBenchmarking in the Aerospace and Construction Sectors: a Method for Inducing Cultural Change”.[Unpublished IMI Case for Support. Private communication.]

McNeill, Patrick (1989). Research Methods, 2nd edition . Routledge, London.

Melles, Bert and Wamelink, J.W.F. (1993). Production Control in Construction. Delft University Press,Delft, The Netherlands.

Miles, Robert (1998). “Alliance Lean Design/Construct on a Small High Tech Project”. Proceedings ofthe 6th Annual International Conference for Lean Construction. Sao Paolo, Brazil.

Murrill, Paul W. (1991). Fundamentals of process control theory. Instrument Society of America,Research Triangle Park, North Carolina.

Neil, James M. (1982) Construction Cost Estimating for Project Control. Morrison-Knudsen.

Ohno, Taiichi (1988). Toyota Production System: Beyond Large-Scale Production. Productivity Press,Cambridge, Massachusetts. (Translation not credited.)

Project Management Institute, Standards Committee (1996). A Guide to the Project Management Bodyof Knowledge. Project Management Institute, Upper Darby, PA

Reinertsen, Donald (1997). Managing the Design Factory. The Free Press, New York.

Riggs, Leland S. (1986). Cost and Schedule Control in Industrial Construction. Construction IndustryInstitute, University of Texas at Austin.

Rittel, Horst W. J. and Webber, Melvin W. (1973). "Dilemmas in a General Theory of Planning." PolicySciences 4 (1973), 155-169.

Robson, Colin 1993. Real World Research: A Resource for Social Scientists and Practitioner-Reseachers. Blackwell Publishers Ltd., Oxford, U.K.

Ballard R-20 Last Planner

Rodrigues, A. (1994). “The role of system dynamics in project management: A comparative analysiswith traditional models”. Proceedings of the 1994 International System Dynamics Society, Lincoln,MA, USA, 214-225.

Ronen, B. (1992). “The complete kit concept.” International Journal of Production Research, 30(10),2457-2466.

Roozenburg, N.F.M. and Eekels, J. 1995. Product Design: Fundamentals and Methods. John Wiley &Sons, Chichester, U.K.

Scherer, E. (editor) 1998. Shop Floor Control-A Systems Perspective. Springer-Verlag, New York.

Schmenner, Roger W. (1993). Production/Operations Management: From the Inside Out-5th edition.Prentice Hall, Englewood Cliffs, New Jersey. 825 p.

Shingo, Shigeo (1988). Non-Stock Production: The Shingo System for Continuous Production.Productivity Press, Cambridge, Massachusetts.

Ulrich, Karl T. and Eppinger, Steven D. (1995). Product Design and Development. McGraw-Hill, NY,NY. HD31 U47 1995

Vollman et al, Manufacturing Planning and Control Systems, 3rd edition. Irwin Professional Publishing,Chicago, 1992.

Wamelink, J.W.F., Melles, B., and Blaauwendraad, J. (1993). Comparison of Control Concepts andInformation Systems in Different Parts of the Dutch Construction Industry. Delft University ofTechnology, Delft, The Netherlands.

Williams, Terry, Eden, Colin, Ackermann, Fran, and Tait, Andrew (1995). “Vicious circles ofparallelism”. International Journal of Project Management, Vol. 13 No. 3, Elsevier Science Ltd, 151-155.

Womack, James P., Jones, Daniel T., and Roos, D. (1990). The Machine That Changed the World.Harper Perennial, NY, NY.

Womack, James P. and Jones, Daniel T. (1996). Lean Thinking: Banish Waste and Create Wealth inyour Corporation. Simon and Schuster, NY, NY.

Yin, Robert (1994). Case Study Research: Design and Methods. Sage Publications, Thousand Oaks, CA

Ballard Biblio-21 Last Planner

BIBLIOGRAPHY

AASHTO (1991). AASHTO Guidelines for Preconstruction Engineering Management, AmericanAssociation of State Highway and Transportation Officials, Washington, DC, September, 1991.

AASHTO Task Force on Preconstruction Engineering Management (1996). Guide for Contracting,Selecting, and Managing Consultants, American Association of State Highway and TransportationOfficials, Washington, DC.

Addis, William (1994). The Art of the structural engineer. Artemis, London.

Adler, P., Mandelbaum, A., Nguyen, V., and Schwerer, E. (1996) “Getting the Most out of Your ProductDevelopment Process”. Harvard Business Review, March-April, 1996, pp 4-15.

Akao, Y (1990). Quality Function Deployment: Integrating Customer Requirements Into Product Design.Productivity Press, Cambridge, 1990.

Allen, Chris (1996). “Value Judgment”. New Civil Engineer, 7th November, pp 18-19.

Allinson, Kenneth. The Wild Card of Design: A Perspective on Architecture in a Project ManagementEnvironment. Butterworth Architecture, 1993.

American Society of Civil Engineers (1981), Proceedings of the Speciality Conference on EffectiveManagement of Engineering Design.

ASQC Construction Technical Committee (1987). Quality Management In The Constructed Project.Milwaukee, Wisconsin: ASQC Quality Press.

Andersson, Niclas and Johansson, Patrik (1996). “Re-engineering of the Project Planning Process” inTurk, 1996. 45-53.

Anumba, C. and Evbuomwan, N. (eds.). Concurrent Engineering in Construction CEC97. London 3-4July. The Institution of Structural Engineers, London.

Applebaum, H. (1982) “Construction Management: Tradition versus Bureaucratic Methods”.Anthropological Quarterly, 10/82, 55(4).

Archibald, Russell D. (1992). Managing High-Technology Programs and Projects, 2nd edition. JohnWiley & Sons, Inc., New York, NY.

Argyris, Chris, Putnam, Robert, and Smith, Diana McLain (1985). Action Science. Jossey-BassPublishers, San Francisco.

Argyris, Chris and Schön, Donald A. (1978). Organizational learning: A Theory of action perspective.Addison Wesley, Reading, MA.

Austin, S., Baldwin, A., & Newton, A., (1994), “Manipulating the flow of design information toimprove the programming of building design”, Construction Management and Economics, 12:445-455.

Austin, S., Baldwin A. and Newton, A. (1996). “A Data Flow Model to Plan and Manage the BuildingDesign Process”. Journal of Engineering Design, 7(1), 3-25.

Ballard Biblio-22 Last Planner

Austin, Simon, Baldwin, Andrew, Li, Baizhan, and Waskett, Paul (1998), Development of the ADePTMethodology: An Interim Report on the Link IDAC 100 Project, Department of Civil and BuildingEngineering, Loughborough University.

Austin, Simon, Baldwin, Andrew, Hammond, Jamie, and Waskett, Paul (1999). “Application of theAnalytical Design Planning Technique in the Project Process”. Proceedings of the Conference onConcurrent Engineering in Construction, Helsinki, August 25-27, 1999. 10p.

Bacon, Matthew (1998). “Information Management in the Briefing Process”. Product and ProcessModelling in the Building Industry, Amor (ed.), Building Research Establishment Ltd., Watford, U.K.

Ballard, Glenn and Koskela, Lauri (1998). “On the Agenda for Design Management Research.”Proceedings of the 6th Annual Conference of the International Group for Lean Construction, GuarujaBeach, Brazil, August, 1998.

Bardram, Jakob E. (1997). “Plans as Situated Action: An Activity Theory Approach to WorkflowSystems” in Hughes et al, 1997.

Barlow, K. (1981) “Effective Management of Engineering Design”. Proceedings of the SpecialityConference on Effective Management of Engineering Design, American Society of Civil Engineers,New York, NY, pp 1-15.

Bennett, John and Ferry, Douglas (1990). “Specialist contractors: A review of issues raised by their newrole in building”. Construction Management and Economics, 8(3), 259-283.

Bennett, J., Flanagan, R., Lansley, P., Gray, C. and Atkin, B. (1988), Building Britain 2001, Centre forstrategic studies in construction, Reading.

Betts, M. & Lansley, P., (1993), “Construction Management and Economics: A review of the first tenyears”, Construction Management and Economics, 11:221-245.

Betts, M. & Wood-Harper, T. (1994), “Re-engineering construction: a new management researchagenda”, Construction Management and Economics, 12:551-556.

Blanchard, B.S. (1991). System engineering management. John Wiley and Sons, Inc., New York, NY.

Brailsford Associates, Inc. (1995). Groton School Athletic Facilities Program, Phase I: PreliminaryAssessment Report. Brailsford Associates, Inc., Washington, D.C. DESIGN CRITERIA

Bucciarelli, L.L. (1994). Designing Engineers, MIT Press, Cambridge, MA.

Bulow, I. von (1989). “The bounding of a problem situation and the concept of a system’s boundary insoft systems methodology”. Journal of Applied Systems Analysis, 16, 35-41.

Button, Graham and Sharrock, Wes (1997). “The Production of Order and the Order of Production” inHughes et al, 1997.

Checkland, P.B. (1981). Systems Thinking, Systems Practice. John Wiley & Sons, Chichester.

Choo, Hyun Jeong, Tommelein, Iris D., and Ballard, Glenn (1997). “Constraint-Based Database forWork Package Scheduling.” Submitted for review to the ASCE Computing Congress ’98.

Christiansen, T.R. (1993). Modeling efficiency and effectiveness of coordination in engineering designteams : VDT - the Virtual Design Team. Ph.D. Dissertation, Dept. of Civil Engineering, StanfordUniversity, 260 pp.

Ballard Biblio-23 Last Planner

CIB (1996). Towards a 30% productivity improvement in construction. Construction Industry Board,Working Group 11. Thomas Telford, London.

CIB (1997). Briefing the Team. Construction Industry Board Ltd., Working Group 1. Thomas Telford,London.

CIDA (1994). Project Definition Guide. Construction Industry Development Agency, Sydney, Australia.

CII (1995). Pre-Project Planning Handbook. Special Publication 39-2, Construction Industry Institute,University of Texas at Austin.

CIOB (1995). Time for Real Improvement: Learning from Best Practice in Japanese Construction R&D.Report of DTI Overseas Science and Technology Expert Mission to Japan, The Chartered Institute ofBuilding, 1995.

CIRIA (1996). Design Management for Productivity. Construction Productivity Network Report WR21,Construction Industry Research and Information Association, January 1996.

CIRIA (1996). How Others Manage the Design Process. Construction Productivity Network ReportWR20, Construction Industry Research and Information Association, January 1996.

Clark, Kim B. & Fujimoto, T. (1991). Product Development Performance, Harvard Business Press,Cambridge, MA.

Cleland, D.I. and King, W.R. (eds) (1988). The Project Management Handbook, 2nd edition, VanNostrand Reinhold, USA.

Clough, Richard and Sears, Glenn (1979). Construction Project Management, 2nd edition. John Wiley &Sons, New York.

Cole, A.J. and Boardman, J.T. (1995). “Modelling Product Development Processes Using a Soft SystemsMethodology” in Integrated Design and Process Technology, Texas.

Coles, Edward J. 1990. Design Management: A study of practice in the building industry. TheChartered Institute of Building, Occasional Paper No. 40. 32 pp.

COMIC, 1993. Informing CSCW System Requirements. The COMIC Project, Esprit Basic ResearchProject 6225. Document ID D2.1. 270 pp.

Concurrent Technologies 1995. Proceedings of the 1995 Concurrent Engineering Conference.Concurrent Technologies.

Conklin, E. Jeffrey and Weil, William (1998). Wicked Problems: Naming the Pain in Organizations.http://www.3mco.fi/meetingnetwork/readingroom/gdss_wicked.html

Construction Task Force (1998). Rethinking Construction. Report of the Construction Task Force to theDept. of the Environment, Transport and the Regions, United Kingdom.

Cooper, K.G. (1993). “The rework cycle: benchmarks for the project manager”. Project ManagementJournal, 1993 24(1).

Cowan, H.J., Gero, J.S., Ding, G.D., and Muncey, R.W. (1968). Models in Architecture, Elsevier,London.

Ballard Biblio-24 Last Planner

Cowan, H.J. (1977a). An Historical Outline of Architectural Science, 2nd edition. Applied Science,London.

Cowan, H.J. (1977b). The Masterbuilders. John Wiley, New York.

Cowan, H.J. (1977c). Science and Building. John Wiley, New York.

Cowan, H.J. (1980). “Quantitative and Qualitative Understanding of Engineering Phenomena”.Proceedings Ingenieurpädagogik ’80, Wien.

Cowan, H.J. (1981). “Design Education Based on an Expressed Statement of the Design Process”. Proc.Instn. Civ. Engrs, 70, 743-753.

Coyne, Richard D. (1988). Logic models of design. Pitman, London. 1988. 317 p.

Coyne, Richard D., Michael A. Rosenman, Antony D. Radford, Bala M. Balachandran, and John S.Gero (1990). Knowledge-Based Design Systems. Addison-Wesley, Reading, Massachusetts. 567 p.

Crook, Darryl, Rooke, John, and Seymour, David (1996) “Research Techniques in ConstructionInformation Technology” in Turk, 1996. Pp 133-144.

Crook, D., Rooke, J., and Seymour, D. (1997) “Preserving methodological consistency: a reply toRaftery, McGeorge, and Walters”. Construction Management and Economics, 1997 (15), pp 491-494.

Cross, Nigel (1993), “Science and Design Methodology: A Review”, Research in Engineering Design,5:63-69.

Curtis, B. (1992), “Insights from empirical studies of the software design process”, Future GenerationComputing Systems, 7(2-3), 139-149.

Curtis, B., Kellner, M. & Over, J. 1992. “Process modeling”. Communications ofthe ACM, vol. 35, no. 9, 75-90.

Dasu, Sriram and Eastman, Charles (1994). Management of Design: Engineering and ManagementPerspectives. Kluwer Academic Publishers, Boston, MA.

Deasley, Peter (1995). “Pragmatic Models of Concurrent Product/Process Development”, EPSRC GrantRef GR/K39417.

Dell’Isola, M. (1981) “Methods for establishing design budgets and schedules”. Proceedings of theSpeciality Conference on Effective Management of Engineering Design, American Society of CivilEngineers, New York, NY, pp 99-120.

Dobberstein, M. 1998. “Control on the Verge of Chaos-Analysis of Dynamic Production Structures”.Shop Floor Control-A Systems Perspective. Springer-Verlag, New York.

Dorf, Richard C. and Kusiak, Andrew, editors (1994). Handbook of design, manufacturing, andautomation. Wiley, New York. 1042 p.

Economist, The (1999). “Innovation in Industry”. The Economist, February 20, 1999.

El-Bibany, H. and Abulhassan, H. (1997) “Constraint-based collaborative knowledge integration systemsfor the AEC industry”. Proceedings of the Conference on Concurrent Engineering in Construction,Institute of Structural Engineers, London, U.K., pp 216-226.

Ballard Biblio-25 Last Planner

Eppinger, S.D. (1991). “Model-Based Approaches to Managing Concurrent Engineering”. InternationalConference on Engineering Design, Zurich.

Evans, S. (1996). “Implementing Step Change in Supplier Co-Development Capability: TheManagement Challenge of Design Across the Extended Enterprise”, IMI Grant (Ref: GR/K 78533).

Finger, Susan, Fox, M.S., Prinz, F.B., & Rinderle, J.R. (1992). “Concurrent design”, Applied ArtificialIntelligence, 6, 257-283.

Finger, S., Gardner, E., & Subrahmanian, E. (1993). “Design support systems for concurrentengineering: A case study in large power transformer design”, Proceedings of the InternationalConference on Engineering Design, ICED ’93, The Hauge.

Fleig, J. and R. Schneider 1998. “The Link to the ‘Real World’: Information, Knowledge andExperience for Decision Making”. Shop Floor Control-A Systems Perspective. Springer-Verlag, NewYork.

Galbraith, J.R. (1974). “Organization Design: An Information Processing View”. Interfaces 4 (1974),28-36.

Gebala, David A. and Eppinger, Steven D. (1991). “Methods for analyzing design procedures”. DE-Vol.31, Design Theory and Methodology, ASME, 227-233.

Gibson, G.E., Jr. Tortora, A.L., and Wilson, C.T. (1994). Perceptions of project representativesconcerning project success and pre-project planning effort. Source Document 102, ConstructionIndustry Institute, University of Texas at Austin.

Gibson, G.E., Jr. and Hamilton, M.R. (1994). Analysis of pre-project planning effort and successvariables for capital facility projects. Source Document 105, Construction Industry Institute, Universityof Texas at Austin.

Gibson, G.E., Jr., Kacczmarowski, J.H., and Lore, H.E., Jr. (1995). “Pre-Project Planning Process forCapital Facilities”. ASCE Journal of Construction Engineering and Management, 121(3), 312-318.

Glesne, Corrine and Peshkin, Alan (1991), Becoming Qualitative Researchers: An Introduction,Longman, White Plains, NY.

Gray, Colin, Hughes, Will and Bennett, John (1994). The Successful Management of Design: AHandbook of Building Design Management. Centre for Strategic Studies in Construction, University ofReading, Reading, U.K., 100 pp.

Green, Stuart (1994) “Beyond value engineering: SMART value management for building projects”.International Journal of Project Management, 1994, 49-56.

Green, S. D. (1996). “A metaphorical analysis of client organizations and the briefing process”.Construction Management and Economics, 14, 155-164.

Green, S. (1998). “The technocratic totalitarianism of construction process improvement: a criticalperspective”. Engineering, Construction and Architectural Management, 1998 5(4), 376-388.

Green, S. (1999). “The missing arguments of lean construction”. Construction Management andEconomics, 17(2), 133-137.

Groak, Steven (1992). The Idea of Building: Thought and Action in the Design and Production of Buildings. E &FN Spon, London.

Ballard Biblio-26 Last Planner

Guba, Egon G. (editor, 1990). The Paradigm Dialog. Sage Publications, London. 424 p.

Harmon, Roy L. and Peterson, Leroy D. (1990). Reinventing The Factory: Productivity Breakthroughs InManufacturing Today. The Free Press, New York.

Harmon, Roy L. and Peterson, Leroy D. (1992). Reinventing The Factory II: Managing The World ClassFactory. The Free Press, New York.

Haviland, David (1984). Managing Architectural Projects: The Project Management Manual. AmericanInstitute of Architects, Washington, D.C.

Higgin, Gurth and Neil Jessop (1965). Communications in the Building Industry. TavistockPublications, London, U.K.

Hoefler, Brian G. and Mar, Brian W. (1992). “Systems-Engineering Methodology for EngineeringPlanning Applications”, Journal of Professional Issues in Engineering Education and Practice, Vol.118, No. 2, April, 1992. American Society of Civil Engineers, New York, NY.

Holt, Gary (1998). A guide to successful dissertation study for students of the built environment, 2nd

edition. The Built Environment Research Unit, School of Engineering and the Built Environment,University of Wolverhampton, U.K.

Hounshell, David A. (1984). From the American System to Mass Production, 1800-1932. The JohnsHopkins University Press, Baltimore, MD.Hounshell, David A. (1988). “The Same Old Principles in the New Manufacturing”. Harvard BusinessReview, Nov-Dec 1988, 54-61.Howell, G.A. and Ballard, G. (1995). Managing Uncertainty in the Piping Function. Report to theConstruction Industry Institute, The University of Texas at Austin, TX, Nov., 103 pp.

Howell, G., Laufer, A., and Ballard, G. (1993a). “Uncertainty and Project Objectives” in ProjectAppraisal, 8, 37-43. Guildford, England.

Howell, G., Laufer, A., and Ballard, G. (1993b). "Interaction between sub-cycles: one key to improvedmethods." ASCE, J. of Constr. Engrg. and Mgmt., 119(4), 714-728.

Hughes, J., Somerville, I., Bentley, R., et al. (1993). “Designing with Ethnography: Making WorkVisible”, Interacting with Computers 5:239-253.

Hughes, John; Prinz, Wolfgang; and Schmidt, Kjeld (editors) 1997. Proceedings of the Fifth EuropeanConference on Computer Supported Cooperative Work. Kluwer Academic Publishers, Dordrecht, TheNetherlands.

Hull, Frank M., Collins, Paul D., and Liker, Jeffrey K. (1996). “Composite Forms of Organization as aStrategy for Concurrent Engineering Effectiveness.” IEEE Transactions on Engineering Management,43(2), 133-142.

Hult, M. and Lennung, S. (1980). “Towards a definition of action research: a note and a bibliography”.Journal of Management Studies, 17(2), 241-250.

IDC (1985). Design Deliverables Lists: High –Tech Greenfield Facility. Industrial Design Corporation,Portland, Oregon.

Johnson, H. Thomas, and Kaplan, Robert S. (1987). Relevance Lost: The Rise And Fall Of ManagementAccounting. Harvard Business School Press, Boston.

Ballard Biblio-27 Last Planner

Josephson, Per-Erik & Hammarlund, Yngve. 1996. Costs of quality defects in the 90’s. Report 49.Building Economics and Construction Management, Chalmers University of Technology. 125 p. (InSwedish)

Juran, Joseph, and Gryna, Frank M., Jr. (1986). Quality Planning and Analysis. McGraw-Hill, NewYork.

Knott, Terry (1996) No Business As Usual. British Petroleum Company, London, U.K.

Kolodner, Janet 1993). Case-Based Reasoning (. Morgan Kaufmann Publishers, San Mateo, CA.

Kusiak, Andrew, editor (1993). Concurrent Engineering: automation, tools, and techniques. Wiley,New York. 589 p.

Lafford, Geoff, Penny, Charles, O’Hana, Simon, Scott, Neil, Tulett, Mike, and Buttfield, Anne (1998).Managing the design process in civil engineering design and build – a guide for clients, designers andcontractors. Funders Report /CP/59, Construction Institute for Research and Information Association,February, 1998.

Latham, Michael (1994). Constructing the Team, HSMO, London. TH425 L3 1994 Engr

Laufer, A. (1998). Implementable Research: A Prerequisite for Implementation of Research Results.Self-published, Haifa, Israel

Lawson, Bryan (1980). How Designers Think. The Architectural Press Ltd, London, U.K.

Levitt, R.E., Cohen, G.P., Kunz, J.C., Nass, C.I., Christiansen, T., and Jin, Y. (1994). “The ‘VirtualDesign Team’: Simulating How Organization Structure and Information Processing Tools Affect TeamPerformance.” in Carley, K.M. and Prietula, M.J. (eds.), Computational Organization Theory.LawrenceErlbaum Assoc. Pubs., Hillsdale, N.J.

Lewin, Kurt (1964). Field theory in social science: selected theoretical papers. Edited by DorwinCartwright, 1951. Greenwood Press, Westport, Connecticutt. 346 p.

Liker, Jeffrey K. and Fleischer, Mitchell (1992). “Organizational Context Barriers to DFM,” inManaging Design for Manufacturability, ed. G.I. Susman, Oxford University Press.

Liker, Jeffrey K., Fleischer, Mitchell, and Arnsdorf, David (1992). “Fulfilling the Promises of CAD”.Sloan Management Review, Spring 1992, 74-86.

Liker, Jeffrey K., Sobek II, Durward K., Ward, Allen C., and Cristiano, John J. (1996). “InvolvingSuppliers in Product Development in the United States and Japan: Evidence for Set-Based ConcurrentEngineering”. IEEE Transactions on Engineering Management, 43(2), 165-178.

*Lloyd, Peter and Deasley, Peter (1997). “What’s the Story? Text Based Analysis of EngineeringDesign” in International Conference of Engineering Design (ICED) University of Tampere, Tampere,Finland, pp 2/371-376.

Lock, Dennis (1993). Handbook of Engineering Management. 2nd edition, Butterworth-Heinemann,Oxford.

London, Kerry A. and Kenley, R. (199Q). “Client’s Role in Construction Supply Chain NetworkManagement: A Theoretical Model”.

Ballard Biblio-28 Last Planner

Lottaz, Claudio, Clément, Denis E., Faltings, Boi V., and Smith, Ian F. C. (1999). “Constraint-BasedSupport for Collaboration in Design and Construction”. Journal of Computing in Civil Engineering,American Society of Civil Engineers, New York, 23-35.

MacPherson, S.J., Kelly, J.R., and Webb, R.S. (1993). “How designs develop: Insights from case studiesin building engineering services”, Construction Management and Economics, 11, 475-485.

Manicas, P.T. and Secord, P.J. (1983) “Implications for Psychology of the New Philosophy of Science”.American Psychologist, 38, 399-413.

McGeorge, D., Raftery, J., and Walters, W. (1997) “Breaking up methodological monopolies: a multi-paradigm approach to construction management research”. Construction Management and Economics,1997 (15), pp 291-297

Moldaschl, M. 1998. “Rationality, Culture and Politics of Production”. Shop Floor Control-A SystemsPerspective. Springer-Verlag, New York.

Moldaschl, M. and Weber, W.G. (1997). “The ‘Three Waves’ of industrial group work – Historicalreflections on current research in group work.” in The use of social science for social reconstruction,Human Relations, special issue to the 50th Anniversary of the Tavistock Institute, London.

Morris, P.W.G. and Hough, G.H. (1987). The Anatomy of Major Projects: A Study of the Reality ofProject Management. John Wiley and Sons, UK.

Morris, P.G.W. (1994). The Management of Projects. Thomas Telford, London. 358 p.

Murphy, R. (1981) “Developing Work Packages for Project Control”. Proceedings of the SpecialityConference on Effective Management of Engineering Design, American Society of Civil Engineers,1981, p 50-79

National Research Council (1991). Improving Engineering Design. National Academy Press,Washington, D.C.

O’Brien, W., Fischer, M., and Jucker, J. (1995) “An economic view of project coordination”.Construction Management and Economics, 13 (3), pp 393-400.

Ohno, Taiichi (1988). Toyota Production System: Beyond Large-Scale Production. Productivity Press,Cambridge, Massachusetts. (Translation not credited.)

Perrow, Charles (1984). Normal Accidents: Living With High-Risk Technologies. Basic Books, NewYork.

Perrow, Charles (1986). Complex organizations: A Critical Essay, 3rd edition. McGraw-Hill, New York.

Pietroforte, R. (1997) “Communication and governance in the building process”. ConstructionManagement and Economics, 15, pp 71-82.

Plossl, George W. (1991). Managing in the New World of Manufacturing: How Companies can ImproveOperations to Compete Globally. Prentice Hall, Englewood Cliffs, New Jersey.

Raz, Tevi and Globerson, Shlomo (1998). “Effective Sizing and Content Definition of Work Packages”.Project Management Journal, December, 1998, 17-23.

Reinertsen, Donald (1997). Managing the Design Factory. The Free Press, New York.

Ballard Biblio-29 Last Planner

Rodrigues, Alexandre and Bowers, John (1996). “The role of system dynamics in project management”,International Journal of Project Management, Vol. 14, No. 4, pp. 213-220.

Runeson, G. (1997) “The role of theory in construction management research: comment”. ConstructionManagement and Economics, 1997, pp 299-302.

Scherer, E. 1998. “Understanding Shop Floor Control-A Close Look at Reality.” Shop Floor Control-ASystems Perspective. Springer-Verlag, New York.

Schön, Donald A. (1983). The Reflective Practitioner: How Professionals Think in Action. TempleSmith, London.

Schön, Donald A. (1995). “The New Scholarship Requires a New Epistemology”. Change, Vol. 27, No.6, November/December, 1995, Washington, DC. pp. 26-34.

Schüpbach, H. 1998. “From Central Planning and Control to Self-Regulation on the Shop Floor”. ShopFloor Control-A Systems Perspective. Springer-Verlag, New York.

Senge, Peter M. (1990). The Fifth Discipline: The Art and Practise of the Learning Organization.Doubleday Currency, USA.

Senge, Peter M. (1994). The Fifth Discipline Fieldbook. Doubleday, New York.

Seymour, D. and Rooke, J. (1995) “The culture of industry and the culture of research”. ConstructionManagement and Economics, 13(4), pp 511-523

Seymour, D., Crook, D., and Rooke, J. (1995) “The role of theory in construction management”.Construction Management and Economics.

Seymour, David 1998. Project Phoenix-Evaluation: First Draft of Final Report. The University ofBirmingham, U.K.

Seymour, David, Rooke, John, and Adams, Kim (1998). “The Organizational Context of Benchmarkingand Metrics”. Submitted for publication.

Seymour, D.E. and Rooke, J. (1998). “Construction Management Research and the Attempt to Build aSocial Science”. Journal of Construction Procurement, Vol 4, No 1, 59-73.

Shammas-Tomas, M., Seymour, D., and Clark, L. (1996) “The effectiveness of form qualitymanagement systems in achieving the required cover in reinforced concrete”. Construction Managementand Economics, 14(3).

Shingo, Shigeo (1981). Study of Toyota Production System. Japan Management Association, Tokyo.

Shingo, Shigeo (1988). Non-Stock Production: The Shingo System for Continuous Production.Productivity Press, Cambridge, Massachusetts.

Simon, Herbert A. (1970). The Sciences of the Artificial. MIT Press, Cambridge, Massachusetts.

Stuber, F. 1998. “Approaches to Shop Floor Scheduling-A Critical Review”. Shop Floor Control-ASystems Perspective. Springer-Verlag, New York.

Stuber, F. 1998. “Guidelines for System Design for Operational Production Management.” Shop FloorControl-A Systems Perspective. Springer-Verlag, New York.

Ballard Biblio-30 Last Planner

*Susman, Gerald and Evered, R.D. (1978). “An assessment of the scientific merits of action research”.Administrative Science Quarterly, 23 (December), 582-603.

Sverlinger, P.O. (1996). “Productivity in Construction-A Survey of Disturbances Affecting Productivityin the Design Phase.” 2nd International Congress on Construction: Productivity in Construction-International Experiences, November 5-6, 1996, Singapore.

Tatum, C.B. (1985). “Evaluating Construction Progress.” Project Management Journal, SpecialSummer Issue, 1985, 52-57.

Tavistock Institute (1966). Interdependence and Uncertainty. Tavistock Publications, London, U.K.

Taylor, Frederick W. (1985 [1911]). The Principles of Scientific Management. Hive Publishing, Easton,Pennsylvania.

The Business Roundtable (1997). The Business Stake in Effective Project Systems. Construction CostEffectiveness Task Force.

Tommelein, Iris D. (??). “Constructing Site Layouts using Blackboard Reasoning with LayeredKnowledge.” Chapter 10 in Knowledge Representation.

Tommelein, Iris D. (1997a) “Discrete-event Simulation of Lean Construction Processes”. Proceedings ofthe Fifth Conference of the International Group for Lean Construction, Griffith University, Gold Coast,Australia

Tommelein, Iris D., editor (1997b). Expert Systems for Civil Engineers: Integration Issues. AmericanSociety of Civil Engineers, Reston, VA.

Tommelein, Iris D. and Ballard, Glenn (1997a). “Look-Ahead Planning: Screening and Pulling.”Technical Report No. 97-9, Construction Engineering and Management Program, Dept. ofEnvironmental and Civil Engineering, University of California. Berkeley, CA. Proceedings of theSecond International Seminar on Lean Construction (Seminario Internacional a Construcao semPerdas), 20-21 October 1997, Sao Paulo, Brazil.

Tommelein, Iris D. and Ballard, Glenn (1997b). “Coordinating Specialists.” Technical Report No. 97-8,Construction Engineering and Management Program, Dept. of Environmental and Civil Engineering,University of California, Berkeley, CA. Proceedings of the Second International Seminar on LeanConstruction (Seminario Internacional a Construcao sem Perdas), 20-21 October 1997, Sao Paulo,Brazil.

Tookey, J.E. and Betts, J. (1999). “Concurrent Engineering Issues in the Aerospace Industry-Lessons tobe Learned for Construction?” Proceedings of the Conference on Concurrent Engineering inConstruction, Helsinki, August 25-27, 1999. 11p.

Vollman et al, Manufacturing Planning and Control Systems, 3rd edition. Irwin Professional Publishing,Chicago, 1992.

Ward, Allen, Jeffrey K. Liker, John J. Cristiano, and Durward K. Sobek II (1995). “The Second ToyotaParadox: How Delaying Decisions Can Make Better Cars Faster”. Sloan Management Review, Spring1995, pp. 43-61.

Ballard A-31 Last Planner

APPENDIX A: NEXT STAGE PRODUCTION TEAMKICKOFF MEETING

MTG NOTES: MAPPING SESSION, 4/98

-how do they establish need dates and estimate durations?-how decide who should be involved in what discussions?-Case: seat selection

(floor-mounted or riser-mounted) is interdependent with (structural padsfor seats), which in turn constrains the (return air plenum), which can go either(through the floor or risers), which has an impact on (cleaning time and cost: howquickly can they setup for the next show?). As it happens, chairs come withdifferent types of upholstery, which can change the amount and type of smoke tobe removed. Points: -components such as chairs may not be offered in allvarieties; e.g., although we might prefer a riser-mounted chair, such chairs onlycome with a certain type of upholstery that would overload current plans forsmoke removal. –everything’s connected to everything/designing one whole, soparts have the logic of part to whole, potentially conflicting properties, etc.-Important to include directives in conversion maps?-Discovered in an earlier mapping session with the structural team that could startstructural engineering six weeks later and have steel delivered six weeks earlierthan initially estimated. Result of having members of the steel supply chaintogether in the discussion: structural engineer, fabricator, and erector.Consolidated construction drawings, fabrication drawings, and shop (fielderection) drawings into a single set.-The production team and I are starting after ‘schematic design’. What happenedthen?-Design production consists of making calculations, producing drawings,sourcing, etc. These provide info. for further decision making, which is the bigissue.-Might use some product development techniques, e.g. functionalities, et al.

NOTES ON NEXT STAGE KICKOFF MTG 5/19-21/98

§ Design completed prior to meeting: Size and function of theater (enclosed“amphitheater”, 7000 seats-by Auerbach Associates, theater consultants),look and size and most materials of exterior (by ELS Architects, who wereselected with theater consultant’s help) and type of structure (steel frame)-they could make a model. This approximates conceptual design and perhapssome elements traditionally included in design development.

§ Ed Beck assembled some members of the building teams prior to the meetingand mapped their value streams, using block flow diagramming, but switchedto MS Project when he merged the maps. Lots of negative reaction to theCPM-too small and detailed, hard to read and follow.

Ballard A-32 Last Planner

§ Teams were mgmt/support, theatrical/interiors, MEP/FP, buildingenclosure/architectural, and civil/structural. About half the team members hadparticipated in the initial process mapping with Ed.

§ One purpose of the meeting was to test the feasibility of completing theproject by an 11/15 move-in date and, if feasible, to create a schedule fordoing so. The other primary purpose was to create a team willing and able towork together.

§ The first half day was devoted to introductions (very effective exercise thatgot people loosened up and surfaced expectations), clarification of thebusiness objectives of NextStages, and the design history. The second halfday was devoted to a brief intro. to the concepts and history of lean thinkingand to the airplane game. The second day started with teams reviewing theirprocess maps for completeness, then transitioned after some confusion intosubgroups working on problems and a central group creating a milestone-level CPM for the construction phase, working backwards from the 11/15move-in. The first half of the third day (plus some) was spent first reviewingand refining the inputs requested of each team by others, then by extendingthe milestone schedule through design to the present. Burning issues wererecorded. Teams created more detailed internal schedules that fit within themilestone schedule. Many obstacles were identified and removed in sidecaucuses-“kill the snake now”.

§ Participants seemed to like it. Architects and engineers said they liked gettinginput from fabricators and installers. Everyone liked getting decisions madeon the spot rather than going through multiple loops of submission, review,rejection, rework, submission, etc.

PROBLEMS SOLVED/DECISIONS MADE

♦ Integrated base frame for ‘suspended’ scaffolding into ceiling grid of House.♦ GO on wind test.♦ Agreed to decide on audio proposal asap.♦ Included cladding attachments in 3D model so can fabricate in shop.♦ Agreed to start keeping a design decision log (tho’ inexplicit assignment

of responsibility and inexplicit process)♦ Decoupled front window and sunscreen.♦ Eliminated one roof elevation.♦ Substituted PVC membrane for BUR.♦ ????? Need to collect these for the record

EXPERIMENTAL ELEMENTS

♦ Selection by qualifications not price♦ Shared business and design information♦ Open book accounting

Ballard A-33 Last Planner

♦ Group planning♦ Pull planning (backward pass)♦ Cross functional team including owner, architect, engineers, fabricators,

and erectors/installers♦ Initial attempt to integrate product and process design (needs to be

highlighted and done self-consciously, with prior specification of designcriteria for each)

♦ Production control extended to design as well as construction (future)♦ Consolidation of drawings: design development, contract documents

(construction doc’s), and shop drawings. (Joint production of same byengineer, fabricator, and installer?)

WHAT MIGHT HAVE BEEN DONE BETTER

§ Mapping with the teams in advance was probably valuable, but would have beenmore so if all team members were present.

§ Timing: Many said this should have been done earlier, but that may have beenwith reference to the end date rather than to the stage of design development.Should it be done earlier in design development?

§ The collaborative process is historically based on the ConstructionManagement/Guaranteed Maximum Price (CM/GMP) approach. Subcontractorsand fabricators have not previously been included in the collaboration, which wasrestricted to the owner, contractor, and architect, with the contractor serving asthe owner’s watchdog over cost during the design process. Management of thedesign has not been part of the process. Residue of that approach are still presentin NextStages, which seems to have thought of the architect and theaterconsultant as having the closest relationship to the owner, then engineers, thenfabricators and installers. The general contractor still will contract with thesubcontractors, who will (typically) deal directly with suppliers and fabricators.Better to have installers be in the first tier around the table, then have them bringin fabricators and engineers? Should the architect be integrated with theenclosure team, since their concern is with shaping space?

§ Better to have the teams use the same format for mapping so they could be morevisible and more easily integrated into a whole? Better to use workmappinggraphic terminology than block flow diagramming?

§ Explicit attempt to integrate product and process design, with prior specificationof design criteria for each.

§ Explicit commitment to joint production of drawings by engineer, fabricator, andinstaller and sub-group planning of that process.

§ WHAT’S DIFFERENT AT ICE HOUSE?

§ Installers in first tier§ Workmapping

Ballard A-34 Last Planner

§ Installers (and fabricators?) involved in schematic/conceptual design§ Explicit identification of criteria for design of product and process§ Different commercial arrangements?

NOTES TO FILE

§ Design decision log: there was no record of the design brief or basis for makingdesign and planning decisions. (What’s the relationship between production planningand design? They are essentially the same kind of processes, both are designprocesses, but one is of the product and the other of process for designing orbuilding the product. Ed initially resisted mixing design decision making in withscheduling, but they forced themselves together, which seems quite natural andinevitable given that they are both design processes.)

§ Need to create new names for the phases of the design/construction process in orderto break the grip of the conventional schematic/design development/contractdocuments/shop drawings model?

§ I strongly suspect that many design decisions are now made with a mind toprotecting what the decision maker knows is important, but without understandingwhat else is important.

§ Everyone seemed released by the prospect of working for the good of the job as awhole, but also many said that it was just a matter of having costs reimbursable. Sosimple if true, but I believe that form needs to be filled with production managementcontent a la lean thinking.

§ How measure the impact of consolidating DDs, CDs, and SDs into a single set ofdrawings?

§ How measure the impact of integrated, team design of product and process?§ How measure the impact of production control over the entire design-procure-install

process?§ Need a better process for identifying and developing client values.§ Ditto for translating those values into design criteria.§ Need a way to publicize decisions that change the product or process design criteria-

transparency.

WHAT TO RESEARCH AND WHAT/HOW TO MEASURE?

The cross functional team approach to integrated design of product and process.Also how values are identified, how they are translated into design criteria, and howthose criteria are actually applied in the design process. Keep documents (maps,schedules, meeting minutes), collect participant evaluations, seek hard measurements ofimprovement in product design, cost, or delivery time.

Application of shielding to control of design production. Describe process,collect data (PPC, reasons, actions), collect participant evaluations, seek hardmeasurements of improvement; eg. productivity, durations, costs.

Ballard B-35 Last Planner

APPENDIX B: NEXT STAGE PROJECTTELECONFERENCES

Coordination on the Next Stage project was done largely by means of biweekly

teleconferences, in which each design team 'met' in succession throughout one long day,

with the management team present throughout. The notes below are those of this author

made prior to or during the teleconferences of 7/29/98, 8/26/98, 9/9/98, 9/23/98,

10/7/98, and 12/16/98.

PREP FOR 7/29/98 TELECONFERENCE, 7/28/98

-The big issue was lack of pipe inverts (elevations?) at building drainagecollection points.-Should PPC measure at milestone, submilestone, action item level, or all three?-Are “dates required” actually that or date it's thought the task will be done?-Consider deferring decisions to accommodate uncertainty.-How much is driven by permitting and approvals?-Making assignments at systems team level-action items. Too detailed?-Opaque what planning is done from which assignments are accepted; e.g., howdo specialists know loads and capacities?-Ditto what planning is done after plan period assignments are accepted; e.g., doteams or specialists create a detailed schedule for the plan period, or incorporatethese assignments in their schedule along with others?-Goal: eliminate plan quality failures. Then absorb execution failures intoplanning.-Need to prioritize action items? NB: difficult to size.-How to identify when one action item depends on another in the same planperiod?-Need to clarify purpose of the teleconference? Is it a planning meeting toidentify tasks, or a meeting to status the plan and learn how to plan better?-Need to make the planning system explicit: levels and corresponding processes.-What experiments at Next Stage?

-Pull scheduling; pull as work selection criterion-Group scheduling-Organization in system teams-How to control design?-How to plan design?-How to achieve concurrency?-How to develop a supply chain?-How to best use 3D(+) modeling?

-How might Last Planner benefit design?

Ballard B-36 Last Planner

-If the designer knows what work is upcoming, he/she (or others) canprepare for it: better understand the task, make ready: pull prerequisites,resolve conflicting directives, collect information. Also, design mgmt canbetter match capacity to load, reducing idle resource time andoverproduction. Avoid having too many or too few specific skill sets todo the available work.-If more assigned tasks are sound (ready), less designer time is spentswitching between assignments. Also, assignments can be more oftencompleted when scheduled, better advancing the design project.

TELECONFERENCE, 7/29/98

-See AA07.01.8.03 “Resolve building storm/sanitary site collection points andpipe inverts.” [my comment: need elev. of storm drains and above from ME] Thiswas assigned as a group task to the mechanical engineer, civil engineer, projectmanager, and the plumber due 7/10 and subsequently rescheduled to 7/28. Seealso AA07.15.98.09 “Complete site drainage design criteria” [my comment: needpipe inverts at bldg collection points]-Poor definition of assignment in AA07.15.98.16 “Meet with Lone Star Park todiscuss terms and conditions for purchasing their borrow material.” Markedcompleted, but output unclear.-NB: importance of really understanding the action: -what’s it mean? –what’sprerequisite? –how long to perform once sound?-AB07.01.8.08 wasn’t pulled, so due date was deferred to 8.12.98.-Perhaps an example of lack of definition: AC07.15.98.02 “Resolve insulationrequirements for shell of the building.” Failed for lack of info from ME on heatloads. Didn’t ask them specifically although they were included under “Actionby”.-Completion of 3D model impacted by multiple minor changes. Driver isintention to use model to produce fabrication drawings. Loading info. is neededlater, but need roughout loads up front. Geometry is needed first—was delayedby changes in seating platforms.-“value stream had no cushion.” Need to redo value stream to capture thatlearning?-Interesting example of the complexity of actions lurking beneath a seeminglysimple assignment: AD07.15.98.07 “Coordinate location of proscenium delugesystem with other systems.” Questions that arose in discussion: ‘Does the curtainhave a membrane that will require wetting both sides? How to control the delugesystem? Possibly applicable code requires heat sensors on stage-not yet provided.Code not explicit about sensor locations, etc.’-IB07.15.98.03 “Schedule for steel fabrication may be too tight.” Concernedabout tolerances in design and construction, especially regarding the seatingplatforms.-Apparent problem: ‘Committing’ to an action that has predescessors, perhaps ina chain, some of which do not have identified prerequisites. A constraint: difficultto know very far in advance what that logic is because it is developed as eachstep is taken?

Ballard B-37 Last Planner

-NB: Important to note when a design criterion is being produced? Also…totrack decisions re design criteria?-Make ‘issues’ deliberately include next 1-2 plan periods and use to developdefinition of the actions needed?-Are most/many failures from lack of definition? If so, need a make ready periodin which….-Clearly the actual planning/replanning rhythmn is faster than biweekly.-Biweekly: *Adjust milestone (and submilestone?) schedule *Each team statuses& categorizes the previous plan period. *Each team develops a work plan for thenext plan period. *Teams “meet” to merge work plans. *Hold this meeting, thenfinalize team workplan and coordinate by phone-“Can you…?”

-

*Does this structure work for design? Are strong commitments possible?*Design tasks are often closely coupled in time, so lots of ‘deliveries’ areneeded within the plan period.

-What statusing and categorizing can be done by individual players? Is ateleconference the best way to do this?-Why didn’t Jerry ask Gary for the piping inverts?- Milestone Schedule

Sub-Milestone Schedule

Work Plan

*Each player is responsible for pulling what they need from others?

-Perhaps the key virtue in design is rapid replanning rather thanplan reliability.

-A key is understanding each other’s needs and the value stream.-Levels of Schedule

Should

AdjustedShould

Make Ready Backlog CommitmentPlanning

Will

LookaheadPlanning

Project

Team A Team B

Player A-1 Player A-2 PlayerB-1

Player B-2

Ballard B-38 Last Planner

♦ Milestone Schedule/Value Stream♦ Submilestone (work release between teams)-PPC measured♦ Work Plans (actions by players within teams)-PPC measured for use

by player; reported to project as indicator of reliability.♦ Action Item List♦ Decision List♦ Issues List♦ Player schedules

-

-Whoever needs something from someone else is responsible for preciselydefining the need and should pull it from them.-How to confirm pull? Must someone else give you an order or should eachplayer work independently toward the milestones unless he receives an order?Share work plans so others know what you’re doing.-It’s really hard to know the design criteria for specific design products.-Many action items result from needs for input info.-loads (structural, heat,energy, etc.), dimensions, etc. Fits with problem solving model?-Might help if they had a limited glossary of action types: 1) determinedesign/decision criteria, 2) understand the design task and process, 3) collectinput info., 4) generate alternatives 5) evaluate alternatives, 6) select fromalternatives/decide, 7) approve…[activity definition model].

Each player statuses their work plans,schedules, calculates PPC, identifies & initiatesaction on reasons for plan failure

All players attend team meeting tocomplete status and corrective action,and to identify/communicate needs andcommit to action items. And to lookahead 1-2 plan periods and refinedefinition of future actions.

Support Team revisesvalue stream and planningprocess visible/available toall

Each player develops workplan, incorporating inputfrom Support Team,visible/available to all.

Execution

Measure, Chart,& Publicizestatus vsMilestones

Ballard B-39 Last Planner

-

-

-Still need to decide who does what design (detailing?)-engineering consultantsor speciality contractors?-These don’t all look like commitments to me.-Definition of action items is a problem. Don’t fully understand what’s beingpulled (what’s needed), design/decision criteria, prerequisites.-‘Make ready’-applied to design-starts with understanding the design task,process & dependencies, & criteria. Should be done prior to work entering theplan period.-Are all players developing work plans that include both action items and workneeded to support value stream unless modified by pulls? Urge them to track

Players status work plans & develop preliminarywork plans for next period. (Ask for what youneed. Record what’s been requested that youcan do. Email PPC & Reasons to teamcoordinator.)

Team Meetings to communicateneeds (& to make lookahead itemsready; understand them?)

I need todefine theobjectives &agenda forthesemeetings.

Revise valuestream

Players develop final work plans &share with other players

Execution

Measure &Learn

BiweeklyTeam Meeting

Revise ValueStream

Publish Charts& CorrectiveActions

Status

Players develop &share work plansweekly

Execution

OffWeeks

Ballard B-40 Last Planner

their own PPC and act on Reasons. Urge them to come to meetings with actionitems statused & categorized and perhaps with something to share aboutcorrective action.-Need to update value stream each 2 weeks.-Make system transparent.

TELECONFERENCE 8/26/98

-AA08.12.98.01 “Revise and submit site drainage…” is a follow-on from theearlier added collection points issue. Civil engineer still waiting on roof drainsinfo from mechanical engineer. AA08.26.98.10 “Second set of overflow drainsconnect to main system….” Discovered apparent code requirement for aseparate downspout for overflow drain until it turns underground; previouslymisunderstood. Project mgmt believes the city will accept an alternative design ifwell argued. Some concern expressed that the requirement may have goodreason; i.e., redundant protection of roof from overloading and collapse.Learning: important (always?) to understand the basis for the directive. NB:Decision point when ‘negotiating’ directives: ‘fight or flee’.-Seems like good discipline in action item identification etc.-When step back and look at the master schedule?-Example of criteria clarification and importance: AA08.26.98.08 “ContactTAS/Barrier Free Texas to initiate early review and resolve the filing andapproval process.” CE discovered that they wanted minimum travel fromhandicap parking to front entrance, hence a new action item to conform design tothis criterion. Previously assumed less stringent requirement.-Not identifying or analyzing reasons. How to best do so?-AB08.26.98.04 Computer memory had to be added to run the model. (Str. Eng.hasn’t done 3D model before, or smaller?) Str Eng is producing drawings as theybuild the model. Need to complete model in order to determine member sizes.-Need order mill steel 1 month before breaking ground—decision confirmed.-Would be neat if could easily and quickly see the consequences of choosingweek n or week n+1 for completion of an action. If could, then could choosesometimes to expedite, add resources, etc. in order to do earlier, if desirable.-Example of interdependencies: AC07.15.98.02 “Resolving insulationrequirements for shell of the building.” Sound/power ratings of cooling towerswill drive amount of insulation or double sheet rock.-Good example of detailed info needed by one specialist (cladding contractor)from another (architect): AC08.26.8.02 “Clearly identify on the concept drawingsthe location of each color, and determine quantity of the vertical, horizontal andsmooth panels so the cost for custom colors for each type can be assessed.”-Ongoing saga of the fire protection curtain: AD08.26.98.03 “Follow up onproscenium deluge system meeting….” NB: poor definition—“follow up”. Reallya life safety issue that belongs in Theatrical. Opaque curtain is allowed by codebut is not customary.

Ballard B-41 Last Planner

-Waiting on food service consultant added late to team-Creative Industries.Didn’t expedite getting equipment layout from them. Supposed pull was fromME, but he didn’t realize that.

TELECONFERENCE 9/9/98

-How well do participants think this management process is working? Useful totrack PPC and reasons? Any actions taken on reasons? How much time is spentand wasted (respent) re clarity of directives?

-Design output(s) Criteria Authority Advisors Basisparking lot layout provide handicap city? Texas Access

w/ min travel tobldg entrance

roof overflow separate downspout city - ind.prot.drains from overflow drain

systemsuntil it turns underground

Pull request Reason needed Requestor Requestee

-Critical to find the ‘hard’ points of the design space. If cost limit is exceeded,may have to sacrifice functionality, capacity, or ‘quality’.-Must be discouraging that construction keeps slipping. How to use the added

time? When/how to stop?-NB: Different issues and tools may be useful for different disciplines. E.g., civil

seems to depend heavily on permitting requirements. Try to list design outputsand applicable requirements, and criteria (must have/nice to have) for eachdiscipline and system team.-There was a mention that ELS would make their next milestone, indicating

some attention is being paid to the milestone schedule.-A different kind of problem—agree on criteria, but disagree on what satisfies

them. Or, designed to one set of criteria, but a specialist designs to a new set(e.g., acoustical insulation). Specialists are advocates for specific criteria!-How often do we not fully understand the design decision to be made? E.g.,

select and locate mechanical equipment to suit requirements for loads at leastcost, then factor in acoustical criteria and discover a cost of $200K in insulation,wall type, etc.-Interim assessment of Last Planner?-Reasons analysis and action-how to?-Record criteria?…in decisions log?/or activity definition ‘explosion’-redraw design value stream, incorporating learnings-record pull in action items log so they can expedite and clarify?

Ballard B-42 Last Planner

-Team tackle increase in acoustical-related costs: architect (visual, space layout),acoustical consultant (calculates mitigation techniques), mechanical engineer(point sources). Acoustical consultant calculates need for 50 foot masonry wallto provide desired acoustical insulation from mechanical equipment noise.Alternative is to select quieter equipment, relocate equipment, or shieldequipment locally.-Issue: Bass Performing Arts Center had a target NB=18, but actual turned out

to be=13. How to ensure not overspending?-NB: teams are driven by specific milestones; e.g., “complete 3D model” now

appears to be the guiding star for the structural team. What’s driving each teamin each phase? Equipment selection must be a big issue for mechanical andelectrical. Also equipment locations, which includes ducting, etc.-Need a schedule for completing the design. Calculate from a supposed 11/15

construction start date?-Seems like if we better understand the interdependence of decisions, we could

better manage the design process.-NB: highly specialized consultants are expert in: 1) the real requirements;

wiggle room-what can be negotiated; alternatives (wind tunnel tests to determine‘actual’ wind loads), 2) ways of meeting the real requirements plus desiredcriteria, 3) sometimes expertise or technological means for calculating orassessing alternatives; e.g., a testing lab. or special software.-AA08.12.98.01 Continuing saga of site drainage—CE didn’t receive info.

needed. Apparently no pull. Wasn’t needed in plan period. Still don’t know ifthere is an unavoidable code requirement for multiple leaders, but city isconfident they can allow us ‘what we want’.-Example of one period action item requiring prerequisites from another

scheduled for same period: AA09.09.98.08 and …09. 8 was to get test data onpossible borrow material. 9 was to make a rec from 3 alt pavement designs. Whydid we think we could do this in the period? May have assumed local materialcould be used. Obviously expected to get test results sooner than today, whenCE actually received them.-Handicap parking saga: Must reconfigure; put more handicap spots in front of

bldg.-CE didn’t complete many action items during the plan period. What hours were

spent and what was accomplished?-Considering change in seating. No change to building structure expected. How

big a deal? Decided to defer 3D model transfer until a decision on seating ismade.-Metal color samples saga: AC08.26.98.01. Manufacturer waiting on receipt of

third of three color samples from paint company.-Confusion re criteria: AD09.09.98.07. EE thought theatrical didn’t want

transformer in dimmer room, but actually didn’t want it in amplifier room. Evenso, unclear what transformer location is best.-Deluge curtain saga: Determined applicable code—NFPA (Nat’l. Fire

Protection Ass’n.) 13.-Rough categorization of decisions in Decision Log: design itself, problem

definition, process, needs definition.

Ballard B-43 Last Planner

-No review of PPC or reasons within the meeting.

TELECONFERENCE 9/23/98

-What can be done to improve sequencing, make ready (soundness), and sizing?-Revisit the design value stream to make sure we understand the best

sequence.-Explode master schedule activities as they enter the lookahead window.

Use activity definition model to make sure we understand the scope of

activities.-Identify who/what is pulling each assignment in the lookahead.-Have pullers pull.-Issue minutes by Friday after Wednesday meetings.-Have assignees apply assignment quality criteria; empower them to say

‘no’.-Learn how long tasks actually take and adjust future estimates. Also, be

con- servative.-Understand the consequences of failing to complete assignments, so cantake better risks.-Be more precise in the statement of assignments. Avoid “review”,“follow up”, etc.-Analyze reasons to actionable causes. Use 5 Whys.-I’m uncomfortable with the idea that these meetings produceassignments. Often need additional definition before can apply qualitycriteria. Why not allow changes negotiated between ‘suppliers’ and‘customers’, with notice to all? In other words, make planning continuousrather than periodic?

-Clear need to issue ‘minutes’ immediately after each meeting. Players not usingaction item log.-Decided to ‘target’ completion of wall/acoustic design (AB09.09.98.0?)although not sure will complete. Should understand implications of failure.-Dangerous to complete design without knowing the users of the facility?-It’s not bad to do more than what’s on the action item log. It is bad to not dowhat’s on the log. E.g., the architect chose to spend available time to completeglass and stair design package, and let slip detailing external wall mockup. Couldhave tagged latter as a workable backlog item.-Communication ‘preferences’: some people are not comfortable with multiplechannels: phone, email, fax, etc.-Not being colocated is a problem. Personal connections, ease of communication,getting the right people together, lack of unplanned meetings (water cooler,corridor).-Is there a list of equipment with vendor, price, weight, energy requirements, heatgenerated, etc?-Is/Should there be a statement of design criteria for each system, subsystem,component? Is the Decisions Log sufficient? Per architects, some theatricalconsultants produce room documents/books.

Ballard B-44 Last Planner

-My actions:-Analyze reasons with architect.-Understand how individual planning systems hinge to centralizedplanning system. When/how do players match load to capacity? Do theycheck that match before accepting assignments? Each player has work todo that does not appear on the master schedule and may not be pulledexternally.-Identify action items that involve clarifying or generating design criteria.-Develop examples of activity definition models

-Could do for seat layout, cladding, roofing, etc.-First screen in evaluating/generating alternative designs is—does it meetdesign criteria? 2nd concern: is one preferable in re nonbinding criteriasuch as constructability, ease of acquiring materials, cost, time, etc?

-Need a category “Not pulled”?-Pull what you need: ‘customer’ processes not consistently expediting what theyneed from ‘suppliers’.-Collectively define the task up front; who leads?-Item No. Item Desc. Action by Pulled by Revised Date Date Completed NeedThis Plan Period?-I would like to see how each player identifies and tracks their work and howthey use the planning system. Are players able to make good commitments;balance load and capacity?---One weakness appears to be lack of commonunderstanding of action items at close of meetings.-Type as we go and email instant for review of wording.-Design work can reveal more definition of a design activity. E.g., handicapparking: developed a layout before fully understanding the design criteria.

Int wall designin acousticallysensitive areas

Process FlowDiagram or singleActivity

Db25/Firerating/Etc

Inputs

Resources

Ballard B-45 Last Planner

Investigation revealed that change to conform to actual criteria may require morefill material.-Discussion: Civil has had high PPC. Because of external deadlines? Is there anissue of commitment? On the contrary view, I suggest we find out:

-Are those accepting action items applying quality criteria?-Are players able to accurately match load and capacity?-Are players able to accurately predict ‘deliveries’? Do they expedite

deliveries?-Are players able to sequence activities to best meet project objectives?

-Analysis of reasons: 89/125 (71%)=40 (prerequisites)+24(insufficienttime)+25(conflicting demands). Regarding prerequisites, we’re apparently notvery good at predicting or causing delivery of needed inputs. Regardinginsufficient time, we apparently are not very good at estimating the time neededto accomplish specific tasks. Regarding conflicting demands, may needclarification. Does this mean unexpected demands or failure to accuratelyquantify multiple demands? If the former, there’s a problem with identifyingpriorities even 2 weeks ahead of time. If the latter, same problem as withinsufficient time. (NB: some “prerequisite”-based failures are ripple effects;failure of prerequisites within same plan period.)

1.Sequence: identify priorities 2 weeks ahead-demands on time andrelative priority of demands. Do we understand the design process? Canwe identify what needs to be done in what order? Do we understandwhat’s involved in doing each of these activities?2.Soundness: predict deliveries; expedite deliveries3.Size: quantify time needed to accomplish tasks

TELECONFERENCE 10/7/98

-Blueline/Online coming up. Will post minutes thereon this time.-Added administrative assistant to speed production of minutes.-Target start date now 12/1/98, but February is most likely.

Civil

-CE confused re pull for first item. Thought it wasn’t pulled, but is given targetdate. In any case, still lacks storm drain info.-Easement requested. Added to final plat. Includes electrical yard. CE will copyFisk Elec and Texas Utilities. Curt asks if it goes through landscaping-obviouslythe architect has not been involved-requested copy. Still need Texas Utilitiesacceptance of our elec yard layout. –Have agreement to tie overflow drains intoceiling verticals. Making proposal to city.-For action item 05 we need the mechanical engineer. Civil has to conform hisplans for additional drains. (This issue just refuses to die!)-Grand Prairie school district has 30,000 CY of fill material about 4 miles fromour site. Sandy clay. Pi of 21 & 25. Suitable for cement stabilization. Asking forproposals. Est. cost of handling $5/CY. Est. cost of material $1? Our budget is$5 total for select material. This is not select material. Would be $1 over budget.

Ballard B-46 Last Planner

May be able to mix with cheaper material from other sources. Not ready to selectpavement design.[NB: Estimates become controls; e.g., $5/CY for selectmaterial.]-(11) General Electric Service scope of work—need Fisk Electric.-55 foot light pole is agreed.-(4) Revised handicapped parking plan and posted 9/25.[Is an issue showing interdependence of action items?]-Issues:

-Life Safety pkg.: ELS has issued a draft and is collecting comments.Asked to receive by 9th. Life Safety consultant back next week. Targetissue date is the 16th.-Timmel to ask TU what they propose to give us.-Lone Star borrow material not yet pulled.-Lone Star easement—Halff has sent note requesting.-No new issues from review of site value stream.-Statusing site value stream

-Erosion control plan filed? Yes.-Final plat complete? Yes. Sent to Kaminsky’s attorney for

review.-Grading permit. Not applied, but should be automatic when

needed.-Down to closing on land and filing for permits.-Land trade with District-need to happen 10/14.

-4 Week Moving Average PPC=61%. How to improve?Proposed to analyze in depth a sample of failures from each team,selecting only from top 3 reasons. Could a team representative perform 5Whys on 3 failures of each of the 3 types and report to Ballard?

-Seating configuration: curve schema GO pending cost estimate by Bruce Perry.Bruce: No difference in cost for stud framing (Merrick Brothers) betweensegmented and curved. Estimate: $10k for layout. NB: Bruce careful to state hisassumptions re the design./Need return air openings—to be worked out. Betterto form in concrete or steel?/ELS will detail each type of riser mount heights—3types./Acoustical issues? ELS thinks not, but will check withconsultant./Decision: Change platform design. Agree will cost <$200K. 5 weeksto price in detail. Need to work out framing requirements. Merrick says 8 feet.HW says 20 feet. Same type framing? [Watch this one. How well did we identifythe ripple effect of this design change?]

Structural:

-Riser issue: height of riser, material, attachment method; Merrick, Haynes-Whaley, Irwin, ELS.-3D model on hold for revisions to seating platform. Need to complete beforefinal estimate.-NB: Robert is clearly pulling duration estimates from his nether region. Oftenrequests for info. have the flavor of demands for commitment—or just plainwishful thinking.]

Ballard B-47 Last Planner

-Prefab stairs. Can use for fire stairs but lobby stairs must be detailed bystructural engineer.-Structural and foundation permit date will be pushed back by 2 weeks to 11/24.[Need to do more process mapping! Harder to do at a distance.]-Update from Haynes-Whaley, Str. Eng: Good meeting with ELS last week.Finalizing fly tower. Need input from Jaffe re concrete pads for mechanical eqpt.on low roof. Offline discussions to be held on interior wall design. Steve of CCwants Peterson to install tall house wall-discuss with HW. Peterson to install allpurlins.-[NB: The traditional method seems to be for each discipline to push forwardindependently, then adjust as as inputs are acquired from others. To what extentdo they proceed on assumptions or pull/wait for what they need?]

Skin:

-NB: Joel asks each team/person if they need anything they don’t have.-Metal samples and price are in hand. Price not an issue.-Wall mockup pkg. from ELS: each c. 10’x20’ high; to show 3 conditions; e.g.,vertical panels and soffits. Locate offsite on adjacent property-Kaminsky’s. Alsoapplies to construction trailers? Can defer grading until last minute? Cost: ELS toprovide simplified drawings. [Why not do a computer model?]-Need some concrete under rooftop units on low roofs, but no masonry wall. Notsure re no. of layers of gyp. board in stud wall. Only possible exception is unitserving dressing room. [Why has this been so hard/taken so long to resolve?]-ELS to give CC the change point from X to Y at back of house.-Material for low canopy roof will be visible from lobby. Need different material?

MEPF:

-How many items of kitchen eqpt. do we now have? No. of supply and exhaustfans have increased from 6 to 24. Why? Amy couldn’t say. To handle offline.-Impact of smoking area on exhaust.-8400 feet of 2 inch slots in seat framing.-Biggest issue to resolve is concessions.-Acoustic shielding of mechanical units: when deal with duct noise? When willduct layout be done? 10/12: main duct runs laid out and sized.[Collecting status info., clarifying current state of design: “Are there anymechanical units on the other side of the building?”]-NB: NC25 not maximum in lobbies and cheap seats.-Fire pump: What available water pressure? Need a pump? Yes-125hp. Should beserved off emergency generator? Fisk to examine.-Locations/sources of cable, telephone, etc? Need to meet with phone co.-How many phone outlets will be required? No. of incoming lines? Need to showon floor plan-phone, data, closed circuit TV. Bill Cambra.-[Civil engineer seems to handle all ins and outs from property.]-Requirements for cable TV? Comes into telephone data room. Satellite dish onsite? On roof backstage?

Ballard B-48 Last Planner

-Before addition of loading dock, first floor plans showed gas meter locationwhich now doesn’t work. Where is gas meter now? Where to bring gas to?-U.G. plumbing at perimeter: lower priority-work to 5 week schedule. [The issueseems to be what’s needed in order to design the underground plumbing.]-Duct designer needs seat redesign backgrounds. Need to evaluate but add 2weeks for design change (10/26).-Lighting heat loads complete. Emergency power loads need to be updated-now230 hp, but kitchen eqpt not settled. Also normal loads.-Mtg on structural issues at ELS last week got chunks of work done. [colocationissue!]-[watch for interdependencies/gnarly issues: kitchen, seating, acoustics]

Pricing:

-Cost of project has clearly risen, but need definitive estimate. Becoming the hotitem.-Estimating is based on drawing takeoffs. Want reproducibles.-Electronic transfer hasn’t worked. Don’t transmit error free.

TELECONFERENCE 12/16/98

-Current categorization of reasons does not reveal actionable causes.-Has pricing diverted attention from scheduling?-Why is the estimate so important? Amount of $ needed; financing. Fix GMPs foreach player.-Don’t always understand the decision chain; e.g., color selections would seem tobe needed late, but may be needed earlier to match exterior and interior colors.-ELS considering board vs stone wall to lower cost. But not much such matl.Would violate City’s architectural review? Considering using inside to replacesomething else. May be more labor than stone. NB: Functionalities are revealedby technology and component selections. E.g. need 10 by 10 area for scissor liftto be used to relamp lights in high lobby ceiling. Could have chosen lights thatcould be lowered for relamping.-The longer the plan period, the more difficult it is to defer commitments untilreceipt of prerequisites, rather than betting on the come. The shorter the planperiod, the less lead time is available for planning future periods.-Missing water and electricity in parking lot.-Overflow drain issue: now 2 separate systems are required (issue that won’tdie!).-NB: local differences—CHPA didn’t know gas meter size beforehand.-scheduled new item: begin fire protection drawings by 1/15. 6-8 week designperiod. Need for permit. Focus on distribution system rather than sprinklers.

Ballard C-1 Last Planner

APPENDIX C: NEXT STAGE ACTION ITEMS LOG

The following log was the primary coordinating device used on the Next Stage project.

Each teleconference was given a sequence number, beginning with AA07.01.98,

indicating the design team (AA indicated Site/Civil, BB indicated Structural, etc.) date of

the teleconference. Action items that were identified within each teleconference were

given a sequence number such as AA07.01.98.01. Assignment of action items was made

to the various companies participating on the project by use of their initials, e.g., ELS

stood for the architectural firm. The date required was specified. If an action item failed

to be completed by the required date, a reason number was (usually) indicated in the

column labeled RNC, and a new required date listed in the column Date Required. Once

completed, a date completed was provided and the rows devoted to the action item were

darkened.

1. Lack of decision2. Lack of prerequisites3. Lack of resources4. Priority change5. Insufficient time6. Late start7. Conflicting demands8. Acts of God or the Devil9. Project changes10. Other

Action items are grouped by design team, sequenced in the order Site/Civil (AA),

Structural (AB), Enclosure/Architectural (AC), Mechanical/Electrical/Plumbing/Fire

Protection (AD), Theatrical/Interiors (AE), and Project Support (AF).

Ballard C-2 Last Planner

Linbeck Next Stage DevelopmentThe Texas Showplace

ActionItems

Log

As of December 2, 1998 Project Progress Meeting Revised: 12.14.98

Date Originated-Item No.

Item Description ActionBy

RNC

DateRequired

DateCompleted

A.Site/Civil

Texas Accessibility Standards:AA07.01.98.01 • Provide TAS requirements to ELS HA 07.07.98 07.07.98AA07.01.98.02 • Identify preliminary and final TAS review

process.ELS 07.14.98 07.14.98

AA07.01.98.03 Resolve building storm/sanitary site collectionpoints and pipe inverts; still lacking inverts.Coordinate profiles with water linesurrounding building to be deeded to City.

CHPA/HA/

LCC/TSPH

2 07.10.9807.31.98

08.02.98

AA07.01.98.04 Develop site and parking lighting compatiblewith Lone Star Race Park for site plansubmission for Planning and Zoning approval(Control Road "B").

TEE/FE/HA

6 07.14.9808.12.98

08.12.98

AA07.01.98.05 Provide color rendering for submission forPlanning and Zoning review/approval; resolvelandscape issues (IA07.01.98.05).

ELS 7 07.14.9807.27.98

07.27.98

AA07.01.98.06 Transmit Site Plan package (2 sets) to LCC. HA 7 07.14.9807.17.98

07.17.98

AA07.01.98.07 Review/Revise value stream diagram. HA 07.14.98 07.14.98AA07.01.98.08 Provide/confirm building electrical load for

site utility plan.TEE/HA/

FE7 07.14.98

07.17.9807.28.98

AA07.01.98.09 Provide invert elevation for storm water pipeat loading area.

HA 07.14.98 07.14.98

AA07.15.98.01 Provide recommendation for AccessibilitySpecialist to ELS

HA 07.17.98 07.15.98

AA07.15.98.02 Contact power company for projectinformation.

TEE 07.20.98 07.20.98

AA07.15.98.03 Have traffic impact analysis completed. HA 07.20.98 07.20.98AA07.15.98.04 Send copy of traffic plans and traffic impact

analysis to Lone Star Park.HA 07.20.98 07.20.98

AA07.15.98.05 Complete conceptual point grading planaround building.

ELS 6 07.20.9808.12.98

08.11.98

Ballard C-3 Last Planner

AA07.15.98.06 Resolve grading at diagonal wall withlandscape architect.

ELS 6 07.20.9808.12.98

08.11.98

AA07.15.98.07 Obtain Accessibility Specialist list from TexasDept. of Licensing.

ELS 07.22.98 07.22.98

AA07.15.98.08 Select an Accessibility Specialist HA/ELS 07.28.98 07.28.98AA07.15.98.09 Complete site drainage design criteria HA 2 07.24.98

08.12.9808.12.98

AA07.15.98.10 Complete off-site civil design of City requireditems of work (IA07.01.98.04). Submittedcomments, not required for City Council, butfor Plat Approval (Approved at Planning andZoning meeting).

HA 07.24.9809.09.98

09.09.98

AA07.15.98.11 Complete Road "D" plan to support easementand operating items negotiations with LoneStar Park (Received conceptual designapproval 07.24.98).

HA 2 07.24.9808.12.98

08.12.98

AA07.15.98.12 Resolve and provide presentation materials toCity Planning for internal staff review.

HA 07.24.98 07.24.98

AA07.15.98.13 Planning Department internal staff briefing(IA07.01.98.02).

NS/HA 07.27.98 07.27.98

AA07.15.98.14 Confirm city mailings/posting on-site noticeannouncing zoning revision hearing(IA07.01.98.03).

NS/HA 07.27.98 07.27.98

AA07.15.98.15 Determine amount of project requirement forborrow material.

HA 07.28.98 07.27.98

AA07.15.98.16 Meet with Lone Star Park to discuss terms andconditions for purchasing their borrowmaterial.

NS/LCC 07.28.98 07.27.98

AA07.29.98.01 Resolve date of City Council hearing;coordinate date with Economic Developmentassistance package hearing/approval.

NS 07.31.98 08.12.98

AA07.29.98.02 Dialog with Lone Star Race Park managerregarding lighting fixtures.

TEE 08.03.98 08.12.98

AA07.29.98.03 File original drawings/graphics for Planning &Zoning meeting (IA0701.98.07).

HA 08.03.98 08.12.98

AA07.29.98.04 Meet with Grand Prairie building officials todetermine multiple permit packages anddocument requirements (IF07.15,98.05).

ELS/HA/NS 08.06.98 08.06.98

AA07.29.98.05 Planning and Zoning hearing/approval(IA07.15.98.01).

NS/HA 08.10.9808.24.98

08.24.98

AA07.29.98.06 Decision regarding rescheduling 08.18.98 CityCouncil hearing

NS/ELSHA 08.12.98 08.12.98

AA07.29.98.07 Complete water line/easement design aroundbuilding.

HA 08.12.98 08.12.98

AA07.29.98.08 Resolve construction start date(IA08.26.98.01).

NS Issues Log 08.26.98

AA07.29.98.09 Resolve electric power supply options,permanent and temporary. M. Dickman metR. Cox of Texas Utilities (IA08.26.98.02)

TEE/HA/LCC

Issues Log 08.26.98

Ballard C-4 Last Planner

AA07.29.98.10 Advance terms and conditions for purchasingborrow material from Lone Star Park(IA07.01.98.09/IA07.15.98.06). Evaluatematerial. Pull is the GMP. Est. 50,000 ydsselect material.

NS/HA 08.12.9809.09.98

09.09.98

AA07.29.98.11 Prepare revised Site/Civil estimate. HA 08.12.98 08.26.98AA08.12.98.01 Revise and submit site drainage (added

collection points) for revised commissary roofdrainage (in Pricing Documents) and sanitary(not changed) Received commissary plan.Storm drain info to HA by 09.16.98 forcompletion by 09.23.98 (10.07.98).

CHPA/HA

272

08.19.9809.23.9810.07.98

10.21.98

AA08.12.98.02 Update site estimate. HA 08.26.98 08.26.98AA08.12.98.03 Revise and submit site plan to reflect

commissary, and its impact on site - truckentry, loading area, trash containers, etc.

HA/ELS/CHPA/NS

08.19.98 08.26.98

AA08.12.98.04 Design lighting operation/wiring for Road D(IA08..26.98.03). Sketch within one month byTEE. Needs current site plan.

NS/HA/TEE Issues Log 08.26.98

AA08.12.98.05 Traffic operational plan to be sent to HA. NS 08.14.98 08.26.98AA08.12.98.06 Resolve traffic/road design issues with Lone

Star Park (IA07.01.98.01).NS/HA 08.12.98

AA08.12.98.07 Complete right-of-way abandonment(IA07.01.98.10).

NS/HA 08.18.9809.01.98

08.12.98

AA08.12.98.08 Complete district land trade (IA07.01.98.11). NS/HA 09.01.98 08.12.98AA08.12.98.09 Review of documents/Final Plat for

improvement dedication to City.(IA07.15.98.04)

NS/HA 08.12.98

AA08.12.98.10 Rethink overflow drain vs. scuppers for roofdrainage. (Related item AD08.12.98.01)

ELS/CHPA 08.26.98 08.26.98

AA08.12.98.11 Resolve traffic analysis outstanding items, i.e.access route to new commissary prior toplanning and zoning hearing. Prepare relatedexplanatory drawing. Director of planningconfirmed that there was no need to revise &resubmit.

HA 08.14.98 08.26.98

AA08.12.98.12 Present revised site plan at Planning & Zoninghearing.

NS/HA 08.19.98 08.26.98

AA08.26.98.01 Provide LCC with a full set of documents HAused to prepare estimate.

HA 08.26.98

AA08.26.98.02 Decision on sign size and location metes andbounds to support easement documents.

NS/HA/ELS

1 08.26.9809.23.98

09.23.98

AA08.26.98.03 Decision on date for City Councilmeeting/approval, 09.02.98 (IA07.01.98.08).

NS 08.28.98

AA08.26.98.04 Contact R.Cox,Texas Utilities aboutcoordinating base CAD file.

HA 08.31.98

AA08.26.98.05 Contact R.Cox, Texas Utilties about serviceprovisions and Texas Utilities participation.

NS 08.31.98

AA08.26.98.06 Resolve pavement thickness design prior to theCity Council hearing.

HA 09.01.98

Ballard C-5 Last Planner

AA08.26.98.07 Prepare an exploration plan for borrowmaterial evaluation and comparison.

HA 09.09.98

AA08.26.98.08 Contact TAS/Barrier Free Texas to initiateearly review and resolve the filing andapproval process (BFT completerd earlyreview with comments. Filing can be in 2 ormore packages).

ELS 09.09.98

AA08.26.98.09 Cost-Benefit analysis both light poles andvarious schemes.

HA/TEE 09.09.98

AA08.26.98.10 Second set of overflow roof drains connect tomain system. To be confirmed by GrandPrairie.

ELS/CHPA 09.09.98

AA08.26.98.11 Texas Utilities acceptance of currentconfiguration of electrical yard(AA09.09.98.11).

FE 2 09.09.9810.07.98

CombinedBelow

AA09.09.98.01 TAS Accessibility Specialist review to becomplete prior to TAS filing (IA07.15.98.02).

ELS 09.09.98 09.09.98

AA09.09.98.02 Organize TAS submittal documents forinternal and external review (IA07.15.98.03).

HA/ELS 09.09.98 09.09.98

AA09.09.98.03 Define Lighting for site, including fixture typeand configuration/spacing to match Lone StarPark where feasible (IA08.12.98.01).

HA/ELS/NS/TEE

09.09.98 09.09.98

AA09.09.98.04 Confirm LCC estimate such that utilizing 55foot poles (13) for the parking lot lighting,each with 3-1000 watt fixtures, at 300 feeto.c. will result in a net cost savings of $15,000over 40 foot poles (38) with 1-1000 wattfixture.

FE/LCC 09.23.98 09.23.98

AA09.09.98.05 Determine the most effective design/costsolution to provide overflow roof drainage.(AD10.07.98.01)

CHPA/ELS/ LCC

2 09.23.9810.07.98

To MEPF

AA09.09.98.06 Discuss the overflow roof drain situation withCity of Grand Prairie and attempt to negotiatedual system.

NS 09.23.98 09.23.98

AA09.09.98.07 Revise off-site civil design to delete right turnlane from Beltline Road and add a right turnlane on Lonestar Pkwy where it turns ontoBeltline Road, per the City's request.

HA 09.23.98 09.23.98

AA09.09.98.08 Results of testing program to obtain geotechinformation on borrow material. Drilling tocommence 09.10.98.

HA 09.23.98 09.23.98

AA09.09.98.09 Based upon borrow material characteristics,make engineeering determination from 3alternative pavement designs provided. HighPI of borrow material requires inport ofselect fill; choose pavement design based onselect fill specification.

HA 252

09.23.9810.07.9810.21.9811.04.98

11.04.98

AA09.09.98.10 Obtain comparables on fill material fornegotiation with LSP.

HA 5 09.23.9810.23.98

10.21.98

Ballard C-6 Last Planner

AA09.09.98.11 Upon Texas Utilities final design, andacceptance of current configuration ofelectrical yard (AA08.26.98.11);resolve thegeneral electric service/scope of work with TU(loop service w/manual transfer switch).Revised yard layout sent to TU. TU approved.

FE/TEE 2272

09.23.9810.07.9810.21.9811.04.9812.02.98

12.02.98

AA09.09.98.12 Upon final design by Texas Utitlities,determine/coordinate location of easements.

HA 2 09.23.9810.07.98

10.07.98

AA09.09.98.13 Determine location of handicap parkingrelative to main entrance doors; determine ifside doors will be handicap accessible doorsfor either egress or ingress.

ELS/HA 09.23.98 09.23.98

AA09.09.98.14 Complete study and adjustment of civil list ofcost increases.

HA/NS/LCC 09.23.98 09.23.98

AA09.23.98.01 Approval of assistance package by GrandPrairie City Council.

NS/HA 09.23.98 09.23.98

AA09.23.98.02 Followup overflow drain issues with SharonCherry, Building Official, City of GrandPrairie. (AD10.07.98.01)

CHPA 10.07.98 To MEPF

AA09.23.98.03 Confirm depths of 55 foot light pole bases andadded cost to finalize decision to use over 38foot poles.

TEE 10.07.98 10.07.98

AA09.23.98.04 Relocate handicap parking and revise relatedsite grading.

HA 10.07.98 09.25.98

AA10.07.98.01 Prepare documents/Life Safety Issues forinitial TAS review submission(IA07.29.98.02).

ELS 10.07.98 10.07.98

AA10.07.98.02 For city requested right hand turn lane fromBeltline Road to Lone Star Parkway, sendsketch/metes & bounds to CityComptroller/Sports Facilities DevelopmentCorp., A. Cammerata, to make aware of need.

HA 10.07.98 10.07.98

AA10.07.98.03 Review and comment on draft Life Safetydocument prior to initial TAS reviewsubmission.

NS 10.09.98 10.21.98

AA10.07.98.04 Send sketch to Texas Utilities for new locationof on-site pad mouinted equipment(switchgear location, pad sizes).

TEE/FE 10.14.98 To MEPF10.21.98

AA10.07.98.05 Complete revised floor plan background uponwhich to revise underground/underslabutilities/structure.

ELS 10.16.98 10.21.98

AA10.21.98.01 Follow up borrow material availability andcost from Grand Prairie ISD. Should be lessthan $1/CY (IA10.07.98.01).

NS/HA 10.21.98 10.21.98

AA10.21.98.02 Complete paving estimate. HA 10.23.98 11.04.98AA10.21.98.03 Resolve requirements of joint use of single

utility trench. Info sent to TEE.FE 5 11.04.98

12.02.9812.02.98

AA10.21.98.04 Request for Letter from Texas Utilitiesmemorializing service and their agreed uponresponsibilities.

NS 77

11.04.98 12.02.9812.16.98

Ballard C-7 Last Planner

AA10.21.98.05 Sketch of transformer enclosure louvers toTexas Utilities. No longer necessary due toapproval of AA09.09.98.11.

ELS 7 11.04.9812.02.98

12.02.98

AA10.21.98.06 Decide location of Gas Meter. Locationdecided by CHPA plan; not yet approved byTU

HA/TEE/ELS

5 11.04.9812.04.98

12.02.98

AA10.21.98.07 Closing occurred 11.02.98; Final Plat utilitysignatures to be obtained and recorded. Halfcompleted.

HA 25

11.04.98 12.02.9812.16.98

AA11.04.98.01 Complete City land trade; complete landtransfer with City Comptroller/SportsFacilities Development Corp (IA10.21.98.02).

NS/HA 11.04.98 11.04.98

AA11.04.98.01 Negotiate with Kaminsky,LSRP (and, later,GPISD), to purchase common fill borrowmaterial, 30,000 cuyd at $0.75/cuyd in place(IA09.09.98.01); look for sand in Kaminskymaterial.

NS/HA 7 12.02.98 12.16.98

AA12.02.98.01 Texas Utilities approval of gas meter location. HA 12.16.98AA12.02.98.02 Revise site sanitary and storm connection

points to accomodate changes in themechanical/plumbing plan ($10,000 est.addedcost); alternatively, run lines internal to thebuilding.

HA/CHPA 12.16.98

AA12.02.98.03 Resolve proposed program changes to addspecial events power and water to parking lot.

NS/ELS/CHPA/HA

12.16.98

AA12.02.98.04 Decide early construction program. NS/ELS/HA 12.16.98AA12.02.98.05 Decide contracting format for sitework (Gen

Cond, Supplmntl, Conditions of Contract)(IA11.04.98.01).

NS/HA/LCC 12.16.98

AA12.02.98.06 Send copy of Engineering Joint Councildocuments.

HA 12.16.98

AA12.02.98.07 Revise grade change at side of commisary. HA 12.16.98AA12.02.98.08 Landscape not yet released by NS; use HA

budget for pricing.HA 12.16.98

B.Structural

AB09.09.98.01 Complete 3-D model with member sizes anddown load to SPI (IB08.26.98.01). Competewith column sizes; correct download errors..

HW 5 09.23.9810.02.98

09.23.98

AB07.01.98.01 • Provide/fax structural tables for beamsizes/spacing to ELS.

HW 07.02.98 07.02.98

AB07.01.98.02 Resolve balcony structural design and sightlines; requires seating envelope/platform tobe resolved.

ELS/HW 1 07.28.9808.12.98

08.12.98

AB07.01.98.03 Revised low roof slopes required by HW forstructural design.

ELS 07.28.98 07.28.98

AB07.01.98.04 Provide elevator shaft dimensions and ELS 07.07.98 07.13.98

Ballard C-8 Last Planner

structural loads to HW.AB07.01.98.05 Provide preliminary chase locations and sizes

to HW.ELS/CHP

A7 07.07.98

08.12.9808.12.98

AB07.01.98.06 Resolve roof loading from hung structuralplatform, scaffolding live load, and acousticalpanels.

ELS/HW/JHSA

7 07.07.9807.28.98

07.28.98

AB07.01.98.07 Resolve seating platform design, elevations,and structural load; geometry, sight linesrefinement based upon revised seat.

ELS/HW 2 07.07.9808.05.98

08.12.98

AB07.01.98.08 Provide/confirm location and structural loads(confirm) of electrical equipment to HW(greater than 500 lbs).

TEE 7 07.14.9808.12.98

08.12.98

AB07.01.98.09 Provide location and structural loads fortheatrical rigging system to HW. Also, pointloads for proscenium reduction system.Geometry of loading is critical. Set for 3-Dmodel.

TS/AA 07.14.9808.26.98

08.26.98

AB07.01.98.10 Provide/confirm location and structural loadsof speakers/audio equipment to HW.

JHSA 07.14.98 07.29.98

AB07.01.98.11 Provide/confirm location, electrical load, andstructural loads of lighting projectors atbalcony to HW/TEE.

AA 07.14.98 07.29.98

AB07.01.98.12 Provide/confirm location and structural loadsof audience/house and proscenium reductionsystems to HW.

AA 07.14.98 07.29.98

AB07.01.98.13 Confirm receipt of CHPA drawings indicatingduct and pipe locations and loads, includingproscenium deluge system.

HW 07.14.98 07.29.98

AB07.01.98.14 Provide final results of wind tunnel test. ELS/HW 5 07.14.9808.12.98

08.12.98

AB07.15.98.01 Resolve alternative balcony beam sizes andspacing options; integrate with the 3D model.

HW/ELS 5 07.24.98 07.29.98

AB07.15.98.02 Resolve design wind forces/pressures on thebuilding.

HW 5 07.24.9808.12.98

08.12.98

AB07.15.98.03 Prepare 90 day structural steel commitmentand expenditure schedule, include options formillrun steel and warehouse steel.

HSC 3 07.28.9808.26.98

08.26.98

AB07.29.98.01 Resolve concessionaire reprogramming effecton back of house low roof. ELS packagerec'd last week, based on Scheme 'A'.

NS/ELS/VS 08.05.9808.26.98

08.26.98

AB07.29.98.02 Determine effect of delaying 3D model to09.16.98 on project schedule, i.e.fabrication/detailing.

HW/HSC/LCC

08.12.9808.26.98

08.26.98

AB07.29.98.03 Decision required to maintain constructionstart date and approve structural steel orderfor mill run steel and fab shop commitmentwithout 3D Model(IB07.15.98.02).

NS 08.12.98 08.12.98

AB07.29.98.04 Complete new background drawings for backof house.

ELS 08.12.9808.26.98

08.26.98

AB07.29.98.05 Provide all input to HW for structural detail of ELS 08.12.98 08.12.98

Ballard C-9 Last Planner

platform levels.AB08.12.98.01 Review schedule of four weeks for steel

fabrication. (IB07.15.98.03)(AD08.12.98.05)

ELS ASAP 08.12.98

AB08.12.98.02 Offline conference regarding utilizing 'TotalStation' to do computerized field layout.

NS/LCC/ELS/ HW

08.26.98 08.26.98

AB08.26.98.01 Provide HW structural loads for box boomalternate locations.

JHSA/AA/ELS

2 09.01.9809.23.98

09.23.98

AB08.26.98.02 Verify that box boom alternate locations hit4000# support points.

JHSA/AA/ELS/HW

2 09.01.9809.23.98

09.23.98

AB08.26.98.03 Confirm assumptions for proscenium loads.Provide sliding panel information. Majorloads resolved and will be faxed.

AA/ELS/HW

2 09.04.9809.23.98

09.23.98

AB08.26.98.04 Provide preliminary review of 3-D model toHSC/SPI/PB for review of connections andheavy steel members(IB07.01.98.01).

HW 09.04.98 09.09.98

AB08.26.98.05 Review value stream based on mill order steelto determine order lead time.

HSC/LCC 09.04.98 09.09.98

AB08.26.98.06 Coordination meeting upon completion of 3Dmodel to finalize effect of stage and grid onstructure. (IB08.26.98.02)

JHSA/AA/ELS/

HW/LCC

Issues Log 09.09.98

AB08.26.98.07 Define/review the structural detailing in acoordination meeting to develop thesequence/schedule to serve the shopdrawing/fabrication schedule.

HW/HSC/SPI/ PB/LCC

09.09.98 09.09.98

AB09.09.98.01 Complete 3-D model with member sizes anddown load to SPI (IB08.26.98.01). Competewith column sizes; correct download errors.

HW 5 09.23.9810.02.98

09.23.98

AB09.09.98.02 Meeting @ HW on Monday 9/14/98 @ 1:30p.m. to determine detailing input sequenceneeded by HW & SPI to accommodatefabrication schedule shown in 21 month valuestream.

HW/HSC/SPI/ LCC/PB

09.14.98 09.23.98

AB09.09.98.03 Finalize wall design/acoustics for F.O.H.mechanical rooms. CHPA to confirmAHUs/configuration to mitigate wallacoustics; also, alternative wall designs.

JHSA/ELS/ CHPA

2 09.23.9810.07.98

10.07.98

AB09.09.98.04 Review HW 3D model data transmission forsystem compatibility.

HS/SPI 09.23.98 09.23.98

AB09.23.98.01 Schedule work session upon completion of 3Dmodel with structural and theatricalconsultants to address issues and detailing ofstage house and auditorium roof.Coordination meetings set for 09.29.98 and09.30.98. (Formerly AB08.26.98.06)(IB08.26.98.02).

NS/ELS/HW/

HSC/PB/JHSA/

CHPA/TEE/AA/TSC/SP

L/ PA

09.30.98 09.23.98

AB09.23.98.02 Review design/structural implications ofalternate interior wall systems requiringacoustical consideration.

JHSA/HW/ELS

10.07.98 10.07.98

Ballard C-10 Last Planner

AB10.07.98.01 Develop/detail steel platform design for curvedseating format, including curved and slottedriser, and installation of riser mounted seating(involve Irwin Seating). Draw section foreach typical riser height.

ELS/HW/MBS

/AA/LCC

10.09.98 10.21.98

AB10.07.98.02 Revise structure to reflect development of thefly tower and rigging wall. Provide riggingwall section.

HW/ELS/AA

2 10.09.9811.04.98

11.04.98

AB10.07.98.03 Coordination meeting with CC regardingpurlin framing, wall sections, and wind girts(locations relative to interior finishes);fabrication and installation responsibility.Provide plan and wall section.

HW/ELS 10.15.98 10.21.98

AB10.07.98.04 Revise framing to accommodate concreteunder roof top units at BOH, top of offices.

HW/ELS 5 10.21.9811.02.98

11.04.98

AB10.21.98.01 Identify allowable deflection for purlinssupporting interior finishes.

HW 11.04.98 11.04.98

AB10.21.98.02 Resolve purlin design with regard to interiorfinishes.

HW/ELS/CC 11.04.98 11.04.98

AB10.21.98.03 Review riser design with regard to platformconstruction.

MBS 11.04.98 11.04.98

AB10.21.98.04 Establish overall general design for seatingrisers. Resolve concept design reviewed withMBSI.

HW 12

11.04.98 12.02.9812.16.98

AB10.21.98.05 Complete seating platform design to be able tocomplete 3D Model download by 12.11.98(and ABM by 12.18.98) (IB07.15.98.01).Havens currently doing hand take-off forcosting.

ELS 25

11.06.98 12.02.98

AB10.21.98.06 Resolve retaining wall location which has beeninfluenced by the seating platform curve.

ELS/HW/PB/ LCC

77

11.04.98 12.02.9812.16.98

AB10.21.98.07 Review four seating mounting details withIrwin Seating.

ELS 11.04.98 11.04.98

AB10.21.98.08 Resolve the structural support and acousticalrequirements at "meet and greet" areas at westside of building; HVAC Units moved.

ELS/HW/JHSA

11.04.98 11.04.98

AB10.21.98.09 Revisit/update steel detailing value streamsequences to decide how far to proceed.

HW/HS/SPI/LCC

11.04.98 11.04.98

AB11.04.98.01 Revise 3-D Model to reflect curved seatingformat (IB10.07.98.01).

HW 11.04.98 11.04.98

AB12.02.98.01 Review prefab stair utilization(IC08.12.98.02, IB08.12.98.01).Specifications allow the use of prefab stairs atspecific locations.

ELS 12.02.98 12.02.98

AB12.02.98.02 Resolve pricing set coordination issues, i.e.column locations, to be able to complete 3DModel.

ELS/HW 12.16.98

AB12.02.98.03 HW/PB meeting on 12.03.98 to reviewerection sequence on which ABM's are based.

HW/PB 12.16.98

Ballard C-11 Last Planner

AB12.02.98.04 Resolve proposed changes relative to 3DModel, i.e. stage house.

NS/ELS/HW 12.16.98

C. Enclosure/Architectural

AC07.15.98.02 Resolve insulation requirements for shell ofthe building. Refine energy calculations forspecific R value for walls and roof(IC07.01.98.01). Sound/Power ratings ofcooling towers will drive amount ofinsulation or dbl sheet rock.

ELS/JHSA/CHPA

07.28.9808.18.98

08.26.98

AC07.29.98.01 Prepare life safety narrative outline. ELS 08.12.98 08.06.98AC08.12.98.01 Evaluate status of input for structural

detailing. Value stream.HW 08.26.98 08.26.98

AC08.12.98.02 Determine 'R' value for roof considering boththermal insulation and noise. (IC07.15.98.01)(DC08.12.98.01)

ELS/JHSA/CHPA

08.12.98 08.12.98

AC07.15.98.01 Complete louver selection (IC07.01.98.04). ELS/CC 07.22.98 07.29.98AC07.15.98.03 Resolve material selection at the building base. ELS/LCC Issues

Log07.29.98

AC08.12.98.03 Complete roof and wall input conceptdrawings. (IC07.01.98.02) Wal designsshould be complete before roof design begins,and roof drawings will take about ten daysafter that. Scuppers are not an issue.

ELS/CHPA 08.25.98 08.26.98

AC08.26.98.01 Provide metal samples of color and finish forselection (deleting 'and exterior mock ups');two of three received.

CC/ELS 5 09.09.9810.07.98

10.07.98

AC08.26.98.02 Clearly identify on the concept drawings thelocation of each color, and determine quantityof each of the vertical, horizontal and smoothpanels so the cost for custom colors for eachtype can be assessed.

ELS/CC 09.09.98 09.09.98

AC09.09.98.01 ELS issuance of exterior glass and stairdesign package to CC (IC07.01.98.03).

ELS 09.17.98 09.23.98

AC09.09.98.02 ELS to detail the desired exterior wall mock-up and proposed location at the site(IC08.26.98.01).

ELS 4 09.23.9809.30.98

10.07.98

AC09.09.98.03 Determine metal panel custom colors based onELS submitted color chips and quantities foreach of the colors.

CC/ELS 2 10.07.98 10.07.98

AC09.09.98.04 Determine metal panel custom colors premiumcost based on economic order quantities.

ELS/CC 2 10.07.98 10.07.98

AC09.09.98.05 Determine if roof valley lines to drainlocations can be accomplished with concreterather than being built up by PC.

ELS/HW 09.23.98 09.23.98

AC09.23.98.01 Confirm concrete wall and roof deck at backof house low area.

ELS 10.07.98 10.07.98

AC10.07.98.01 Revise exterior wall mock-up detail; propose ELS 10.21.98 10.21.98

Ballard C-12 Last Planner

site location.AC10.07.98.02 Provide drawing of alternate value engineered

BOH metal panels; reduced parapet height.ELS 10.21.98 10.21.98

AC10.07.98.03 Resolve number of layers of gypsum board asalternative to CMU to achieve accousticalobjective - Vomitory, etc. To be included inPricing Documents.

ELSJHSA 2 10.21.9811.06.98

11.04.98

AC10.21.98.01 Provide enclosure mock-up pricing. LCC/CC 5 11.13.98 12.02.98AC10.21.98.02 Coordinate interior finish support (interior

studs and drywall) with high wall metal panelsuport girts.

HW/CC/ELS 11.04.98 11.04.98

AC10.21.98.03 Identify roofing material for each roofingsection, esp. low canopy roof visible fromlobby balcony - aggregate/paver roofscape;provide pricing and samples.

ELS/LCC/PC

76

11.04.98 12.02.9812.16.98

AC11.04.98.01 Resolve mock-up schedule: 2 months tofabricate panels; 2 months to erect mock-up,make changes, and make decision (3 months tofabricate building panels; 120 to 150 daybuilding critical path).

ELS/LCC/CC/ NS

1 12.02.98 12.16.98

AC11.04.98.02 Resolve door acoustical ratings. Will not haveratings.

ELS/JHSA 12.02.98 12.02.98

AC12.02.98.01 Determine if a mock-up(s) of exterior wall willbe required; to be price based. Ordering,fabricating, erecting, and making decisionsbased upon the mock-up are critical pathtasks (IC09.09.98.01).

NS 12.07.98

D. Mechanical/Electrical/Plumbing/FireProtectionAD07.01.98.01 Post Drawings on FTP site. CHPA 3 07.06.98

08.12.9808.12.98

AD07.01.98.02 Provide/confirm audio system powerrequirements to TEE.

JHSA 07.07.98 07.07.98

AD07.01.98.03 Provide/confirm audio system coolingrequirements to CHPA.

JHSA 07.07.98 07.07.98

AD07.01.98.04 Provide/confirm emergency power items toTEE/CHPA.

ELS 07.08.98 07.14.98

AD07.01.98.05 Provide/confirm normal and emergency loadsto TEE.

CHPA 7 07.08.9807.30.98

07.30.98

AD07.01.98.06 Provide/confirm architectural/theatricallighting and video power loads to TEE/CHPA.

AA 07.08.98 07.08.98

AD07.01.98.07 Resolve location of main electrical room (162)and electronics storage and shop (158) tofacilitate piping from cooling tower. LCC toprovide pricing input. Not applicable due tocommissary design change.

ELS/TEE/CHPA/LC

C

5 07.08.9808.12.98

08.12.98

AD07.01.98.08 Provide pipe/duct weights to HW CHPA 07.14.98 07.14.98

Ballard C-13 Last Planner

AD07.01.98.09 Provide concession/food service electricalloads to TEE/CHPA. Revise food serviceloads due to program change. Note:Concession charts were received and showequipment loads and revised floor plan raisethe cost from the current estimate.

NS/ELS 07.08.9808.26.98

08.26.98

AD07.01.98.10 Provide CATV and Data information to TEE. NS/JHSA/AA

IssuesLog

07.29.98

AD07.01.98.11 Provide elevator electrical loads/data to TEE. ELS/LCC 07.08.98 07.08.98AD07.01.98.12 Provide life safety [and exit sign loads] (Rolf

Jensen Assoc.) to TEE.ELS 07.08.98 07.29.98

AD07.01.98.13 Provide/confirm location of raceway loads toHW/TEE/CHPA.

AA/JHSA 5 07.14.9808.12.98

08.12.98

AD07.01.98.14 Provide transformer sizes to TEE. AA/JHSA 07.14.98 07.14.98AD07.01.98.15 Provide/confirm general lighting loads to

CHPA.TEE 07.14.98 07.14.98

AD07.01.98.16 Provide emergency power motor sizes to TEE. CHPA 07.14.98 07.14.98AD07.01.98.17 Provide fire pump information to TEE. WSFP 07.14.98 07.14.98AD07.01.98.18 Provide concession/food service layout

information (Volume Services). Big picturematrix: 3000 SF

NS/ELS 2 07.14.9807.31.98

08.12.98

AD07.01.98.19 Air zones approval; block out areas served byAHU's for review (zones of operation; zonesfor control, ID07.01.98.02).

NS/CHPA/

MMC/ELS

7 07.14.9807.30.98

08.12.98

AD07.15.98.01 Confirm subcontractor participation inevaluating on-line project managementapproach.

FE 07.22.98 07.22.98

AD07.15.98.02 Resolve sheet metal duct work design; provideto JHSA for approval.

CHPA/LL 7 07.20.9807.31.98

08.12.98

AD07.15.98.03 Provide feedback/approval of sheet metalductwork design to ELS (ID07.01.98.01).

JHSA 2 07.22.9808.03.98

08.12.98

AD07.15.98.04 Provide lobby lighting loads to ELS. TEE/AA 07.22.98 07.22.98AD07.15.98.05 Meet with cablevision to explore infrastructure

requirements for in-house television system.NS Thtrcl/Int 07.29.98

AD07.15.98.06 Lighting operations approval; block out areasserved by lighting - zones of operation/control(IE07.01.98.02).

TEE/AA 07.28.98 07.28.98

AD07.15.98.07 Coordinate location of proscenium delugesystem with other systems.

WSFP/HW/

CHPA/AA

6 07.28.9808.05.98

08.12.98

AD07.29.98.01 Follow up proscenium deluge system meeting -operation, pipe size, curtain physical make-up.(ID08.12.98.04)

WSFP/HW/

CHPA/AA/

LCC/ELS

2 Issues Log 08.12.98

AD07.29.98.02 Follow up acoustics meeting after JHSAreviews sheetmetal design. (ID08.12.98.02)

JHSA/ELS/

CHPA/LC

2 Issues Log 08.12.98

Ballard C-14 Last Planner

C

AD07.29.98.03 Resolve safety requirements for prosceniumdeluge system with Rolf Jensen.(ID08.12.98.03)

WSFP/CHPA/

AA/LCC

2 Issues Log 08.12.98

AD07.29.98.04 Resolve supply duct routing from house tomechanical chase/AHU. Reworded as: Houseduct route and outlet locations move to follownew architectural layout. (ID08.12.98.04)

CHPA/JHSA/

ELS/LCC

2 Issues Log 08.12.98

AD07.29.98.05 Resolve additional MEPF requirements foradding commissary kitchen.

CHPA/TEEWSFP/FE/L

CC

08.05.9808.26.98

08.26.98

AD07.29.98.06 Resolve additional requirements foraddition/revision to suite level toilet rooms.Add to floor plan.

CHPA/TEEELS/LCC

08.05.9808.26.98

08.26.98

AD07.29.98.07 Coordinate ceiling acoustical panels and houseair outlets. Now combines withAD07.29.98.04 above, becomingID08.12.98.04.

CHPA/JHSA/ ELS/LCC

Issues Log 08.12.98

AD07.29.98.08 Add acoustics value stream into project valuestream. (ID08.12.98.05)

JHSA/LCC Issues Log 08.12.98

AD07.29.98.09 Meet onsite with Texas Utilities to permanentand temporary electric service.

TEE/ELS/HA/

FE/LCC/NS

08.12.9808.19.98

08.26.98

AD08.12.98.01 Resolve roof drainage design to completeenclosure package. (Related itemAA08.12.98.10)

CHPA/ELS 08.25/98 08.26.98

AD08.12.98.02 Determine ASHRAE design temperatures.Consider adjusting D/FW design standardsdue to temperature change condition.

NS 08.19.98 08.26.98

AD08.12.98.03 Verify exact locations on marked plan to bedesignated 'smoking areas'.

NS 08.19.9809.09.98

09.09.98

AD08.12.98.04 Determine effect of suite smoking areas onmechanical system.

CHPA 2 09.09.9809.16.98

09.23.98

AD08.12.98.05 Reconfigure ductwork at auditorium hardceiling for JHSA/ELS review.

CHPA/MMC/

LL/LCC

5 08.26.9809.10.98

09.23.98

AD08.12.98.06 Team to test assumptions for delivery ductlayouts in complying with acousticrequirements. Note: Revised duct plans willbe available by 4 Sept. 98. Drawings to JHSA09.10.98.

CHPA/MCC/

LL/LCC

2 08.26.9809.17.98

09.23.98

AD08.12.98.07 Prepare summary list of electrical loadrequirements for presentation to TexasUtilities.

TEE 08.19.98 08.26.98

AD08.26.98.01 Determine roof drain pipe routing and resolvepotential pipe and roof drain locationsconflicts.

CHPA 5 09.09.98 10.07.98

AD08.26.98.02 Confirm roof drainage overflow design withGrand Prairie.

CHPA 09.09.98 09.09.98

Ballard C-15 Last Planner

AD08.26.98.03 Follow up proscenium deluge system meeting -operation, pipe size, curtain physical make-up(AD07.29.98.01 & AD07.29.98.07)(ID08.12.98.01).

WSFP/HW/

CHPA/AA/LCC/E

LS

2 09.09.98Move to

Theatrical

09.09.98

AD08.26.98.04 Obtain sound/power ratings and provide toJHSA. Waiting on Cook Fan ratings.

CHPA/MMC

2 09.09.9809.16.98

09.23.98

AD08.26.98.05 Provide concept equipment layout for foodservice areas. Detailed design upon vendorselection.

NS/CI 7 09.09.9809.23.98

09.23.98

AD08.26.98.06 Determine increased power requirements forfood service areas.

NS/CI/TEE 09.09.98 09.09.98

AD09.09.98.01 House duct route and outlet locations move tofollow new architectural layout(AD07.29.98.04, ID08.12.98.04).

CHPA/JHSA/ ELS/LCC

09.09.98 09.09.98

AD09.09.98.02 Determine routing/enclosure of exterior duct atfront of house (ID08.26.98.02).

CHPA 09.09.98 09.09.98

AD09.09.98.03 Review implications of two-hour house/lobbyseparation vs 21,000 cfm lobby smokeexhaust (selected), life safety and cost.

ELS/CHPA/LCC

09.09.9809.23.98

09.23.98

AD09.09.98.04 Provide per Texas barrier-free access, aunisex single toilet for each grouping of mensand womans toilets.

ELS 09.09.9809.23.98

09.23.98

AD09.09.98.05 Provide building infrastructure requirementsfor CATV, theatrical, and Data information toTEE. Identify the spaces within the building;09.29/30.98 Meeting (ID07.01.98.10).

NS/JHSA/AA

09.23.98 09.23.98

AD09.09.98.06 Follow up acoustics meeting after JHSAreviews sheetmetal design (AD07.29.98.02,ID08.12.98.04, ID08.12.98.02).

JHSA/ELS/CHPA/LCC

09.23.98 09.23.98

AD09.09.98.07 Coordinate duct sizing and delivery designoptions.

CHPA/LL 09.23.98 09.23.98

AD09.09.98.08 Review acoustical requirements for mech.equipment wall systems, central plant(formerly AC09.09.98.06) From E/A 09.23.98

ELS/JHSA

5 09.23.98 10.07.98

AD09.09.98.09 Front Mech.Room: CMU walls may beneeded acoustically; currently metalstuds/drywall;may require heavier walls (8"block w/2 layers gypsum) or change inbuilding envelope enlarging mech.room(formerly AC09.09.98.07);JHSA sketch toHW.From E/A 09.23.98

ELS/JHSA

2 09.23.98 10.07.98

AD09.23.98.01 Provide data for small ahu/fan coil unit inbasement mechanical equipment room.

CHPA 09.30.98 10.07.98

AD09.23.98.02 Provide TEE/FE scope of design as a basis forpreconstruction letter agrement and projectedcash flow.

TEE 10.07.98 10.07.98

AD09.23.98.03 Confirm/revise layout of electrical room andelectrical yard.

TEE 10.07.98 10.07.98

Ballard C-16 Last Planner

AD09.23.98.04 Provide for 4 to 6 food service exhaust ductfans and returns in lobby area (originalprogram included 2 to 3). Provide location ofkitchen supply fans(AD10.07.98.04). Holdingfor concession consultant equipment concept.

CHPA/CI/ELS

MMC/LL

112

10.07.98 10.21.9812.01.98

AD10.07.98.01 Determine effect of concession smoking areason mechanical systems. (ID09.23.01)

CHPA 10.07.98 From S/C10.07.98

AD10.07.98.02 Determine the most effective design/costsolution to provide overflow roof drainage.Followup overflow drain issues with SharonCherry, Building Official, City of GrandPrairie (AA09.09.98.05 & AA09.23.98.02).Provide sketch/documentation to GP.

CHPA 257

09.23.9810.07.9810.14.9811.04.98

From S/C10.07.9811.04.98

AD10.07.98.03 Provide revised AHU layout at FOHmechanical rooms.

CHPA 10.21.98 10.21.98

AD10.07.98.04 Meet with cablevision to explore infrastructurerequirements/formats for in-house livebroadcast and closed circuit television system(AD07.15.98.05). Identify options/designresponsibility/proposal/scope of work.

NS # 08.07.9809.23.98

09.23.98

AD10.07.98.05 Revise Food Service/Commissary programincluding upper level food service capabilities(IE07.01.98.01). (Scheme B received fromELS during the meeting.)

NS/VS/ELS 08.05.9808.26.98

08.26.98

AD10.07.98.06 Revise Suite Level toilet roomprogram/design. NextStage to review layouts.

NS/CHPA/ELS

08.05.9808.26.98

08.26.98

AD10.07.98.08 Develop commissary utility metering level. NS/CII 08.14.98 08.26.98AD10.07.98.09 Confirm that structural engineers have

theatrical dimming rack and Audio amplifierrack loads.

JHS/SP 7 08.14.9809.23.98

09.10.98

AD10.07.98.10 Clarify the conceptual design/layout in theconcessions area relative to headroomcondition.

ELS/CI 7 09.09.9809.23.98

09.23.98

AD10.07.98.11 Define type and size of stage rear doors forframing input.

ELSl/AA 09.09.98 09.09.98

AD10.07.98.12 Finalize plan layout as a result of addingcommissary.

ELS/NS 08.14.98 08.26.98

AD10.07.98.13 Provide location of kitchen supply fans. CHPA 1 10.21.9811.04.98

CombinedAbove

AD10.07.98.14 Revise roof drain design to reflect roofchanges.

CHPA 10.21.98 10.21.98

AD10.07.98.15 Review commissary program and confirmfood service exhaust duct fans and returns.New concept.

NS 10.21.98 10.21.98

AD10.07.98.16 Resolve need for fire pump; determine waterpressure required at roof and proscenium.

CHPA/RJA/WSFP/ELS

10.21.98 10.21.98

AD10.07.98.17 Confirm connection of fire pump with respectto main and emergency generator.

TEE/FE 10.21.98 10.21.98

AD10.07.98.18 Provide layout and size of BOH (rear) ductruns for acoustical analysis.

CHPA/LL 2 10.21.9811.04.98

11.04.98

Ballard C-17 Last Planner

AD10.07.98.19 Provide layout showing telephone, data, andCCTV locations to be serviced with emptyconduit. Provide CATV and data informationto TEE (AD07.01.98.10/IE07.29.98.01).

NS 5 10.21.9810.28.9811.04.98

11.04.98

AD10.07.98.20 Meet with telephone company to review theproject. Coordinate with NS. NS to negotiatecosts.

NS/ELS/TEE/ FE

57

10.21.9811.04.9812.02.98

12.02.98

AD10.07.98.21 Review/confirm normal and emergency powerloads. Schedule requires updating.

TEE 22

10.21.9811.04.9812.02.98

12.02.98

AD10.21.98.01 Send sketch to Texas Utilities for new locationof on-site pad mounted equipment (switchgearlocation, pad sizes) (AA10.07.98.04).Develop alternate options for TUconsideration.

TEE/FE 55

10.14.9810.23.9811.04.98

11.04.98

AD10.21.98.02 Provide latest mechanical unit layouts; verifyweight and layout of new units.

CHPA 11.04.98 11.04.98

AD10.21.98.03 Review/mark-up underseat air slot bands. CHPA 11.04.98 11.04.98AD10.21.98.04 Completion of Electrical Pricing Documents,

including complete underground/underslabelectrical construction documents(ID10.07.98.03). One line andrecepticle/power drawings only submitted.

TEE 55

11.09.98 11.16.9812.16.98

AD10.21.98.05 Reconsider deluge system decision/designbased upon Rolf Jensen Associates review.Deluge "A" included in pricing documents.Alternate:"B" closely spaced sprinkler headsreacting individually;also, prosceniumreduction system functions as a fire curtain.

ELS/CHPA/ WSFP

21

11.04.98 12.02.9812.16.98

AD11.04.98.01 Control of AHU noise as it travels down theduct path (ID10.07.98.01). Base unitschanged.

CHPA/JHSA 12.02.98 12.02.98

AD11.04.98.02 Outline options for acoustical consideration(ID10.07.98.02).

CHPA/JHSA 12.02.98 12.02.98

AD11.04.98.03 Followup overflow drain issues with SharonCherry, Building Official, City of GrandPrairie. Awaiting return response.

CHPA 2 12.02.98 12.16.98

AD11.04.98.04 Provide gas meter information - size,clearance.

TSPH/CHPA

5 12.02.98 12.16.98

AD11.04.98.05 Based upon consessionaire design provide gasrequirements for cook areas.

CHPA 2 12.02.98 12.16.98

AD11.04.98.06 Resolve generator requirements. CHPA/TEE 12.02.98 12.02.98AD11.04.98.07 Confirm assumptions regarding lighting

controls (ID12.02.98.01).CHPA/TEE 12.02.98 Issues

Log12.02.98

AD12.02.98.01 Decision regarding code/security acceptanceof open yard flexibility w/o having separationsbetween electrical switch gear, cooling tower,etc.

FE 12.16.98

AD12.02.98.02 Provide Electrical Specifications. TEE 12.16.98

Ballard C-18 Last Planner

E. Theatrical/InteriorsAE07.01.98.01 Send/fax theatrical event proforma to

AA/JHSA.NS 07.02.98 07.02.98

AE07.01.98.02 JHSA and SPL to meet to review audioconcepts.

JHSA/SPL

7 07.07.9808.12.98

08.12.98

AE07.01.98.03 AA and PAL to review theatrical lightingconcepts.

AA/PAL 07.07.98 08.12.98

AE07.01.98.04 Confirmation of theatrical systems based onevent proforma.

AA/PAL/JHSA /SPL

07.07.98 08.12.98

AE07.01.98.05 Confirm/resolve size of mid-house controlposition to ELS.

AA/JHSA/NS

07.07.9808.12.98

08.26.98

AE07.01.98.06 Develop alternative audience/house reductiondesigns based upon new design parameters.

ELS/AA 07.10.98 08.12.98

AE07.15.98.01 Resolve house reduction system options(AF07.01.98.05). Provide loads for bothoptions to HW.

NS 2 07.22.9808.05.98

08.12.98

AE07.15.98.02 Resolve front lighting and vertical side boxboom positions (probably 2). Provide loadsto HW.

AA/PA 5 07.28.9807.31.98

08.12.98

AE07.15.98.03 Resolve seat selection options; obtain chairsamples and confirm dimensional envelope.(IE08.12.98.04)

NS/AA/ELS

5 Issues Log 08.12.98

AE09.09.98.01 Follow up proscenium deluge system meeting -operation, pipe size, curtain physical make-up:Resolve curtain opaque surface.(AD07.29.98.01 &AD07.29.98.07)(ID08.12.98.01)(IE09.23.98.01).

WSFP/HW/

CHPA/AA/

LCC/ELS

2 09.09.9809.23.98

IssuesLog

09.23.98

AE09.09.98.02 Obtain chair samples and confirm withincurrent seating envelope(AE07.15.98.03,IE08.12.98.04). NS to meetwith ELS to make a decision on seating(IE08.12.98.01). Review metal perforated vs.plastic bottom seats, and provide observations/concerns to NS.

AA/JHSA/ELS/LCC

5561

09.23.9810.07.9810.21.9811.04.9812.02.98

12.02.98

AE09.09.98.03 Resolve life safety requirements forproscenium deluge system (wet fire curtain)with Rolf Jensen (AD07.29.98.03)(IE09.23.98.01).

ELS/CHP 09.23.98 IssuesLog

09.23.98

AE09.09.98.04 Resolve alternate designs for mid-housecontrol position. Row of removable seats infront.

AA/JHSA/NS/ ELS

09.23.98 09.23.98

AE09.09.98.05 Resolve structurally and operationally whetherBox Booms will track or be fixed point loads.Will be riggged.

NS/AA/ELS 09.23.98 09.23.98

AE09.09.98.06 Determine effect of image magnification onwalls and ceiling. Provide 2-20 foot diameterscreens; projector to be 30 feet out.

AA/ELS 09.23.98 09.23.98

Ballard C-19 Last Planner

AE09.09.98.07 Prepare conceptual design for commissary andloading dock area, including trash compactorlocation.

CI/ELS 09.23.98 09.23.98

AE09.09.98.08 The commissary/loading dock changes need tobe reflected on the ELS drawings, andprovided to Creative Ind.

ELS 2 09.23.98 10.07.98

AE09.09.98.09 Submit Life Safety Program to Grand Prairie(IE08.12.98.05).

ELS 10.16.98 10.21.98

AE09.23.98.01 Provide layout sketch for other equipment -electrical, ie. disconnects - in theamplifier/dimmer rooms. Review size ofamplifyer/dimmer room (AE10.21.98.01).

TEE 27

10.07.9810.21.9811.04.98

12.02.98

AE10.07.98.01 Resolve forestage rigging grid issue. Confirmboth structurals and 3-D model are based on10' o.c., 4000# pt.lds; maximum grosstonnage, 3300#. (IE08.12.98.03)

AA/JHSA 10.07.98 10.07.98

AE10.07.98.02 Determine the extent of theatrical lightingsystem that is necessary, i.e. dimmer racks,etc. to be provided as a part of the basebuilding capital investment. NS developeddescription of essential equipment.(IE09.09.98.01)

ELS/AAAA/ELS/NS

10.07.98 10.07.98

AE10.07.98.03 Review proscenium deluge system:operation,3in pipe size, volume, curtain makeup:Resolve life safety requirements,(wet firecurtain/curtain opaque surface) with RolfJensen.(AD07.29.98.01 & AD07.29.98.07)(ID08.12.98.01)(AD07.29.98.07)(09.09.98.01/.03).

WSFP/HW/CHPA/AA/LCC/ELS

10.07.98 10.07.98

AE10.07.98.04 Forward acoustical testing reports from IrwinSeating to JHSA.

AA 77

10.14.9810.21.9811.04.98

11.04.98

AE10.07.98.05 Relocate Electrical room to opposite side ofAV Room; identify size of AV Room; and,distribute for verification.

ELS 10.14.98 10.21.98

AE10.07.98.06 Provide revised auditorium backgrounds. ELS 10.18.98 10.21.98AE10.07.98.07 Provide systems plans for each level including

wiring devices and conduit layout.(IE09.23.98.02)

AA/JHSA 10.21.98 10.21.98

AE10.07.98.08 Video//TV broadcast decision.(IE07.15.98.01)

NS/JHSA/AA

10.21.98 10.21.98

AE10.07.98.09 Resolve use of series of gratings instead of "nofall protection."

ELS/AA 2 10.21.9811.04.98

11.04.98

AE10.07.98.10 Review combination of 3-seat sizes by sectionto arrive at a final seating plan; adjust aislesand vomitories (Now Fixed). Irwin Seating tomeet w/NS. Irwin to do seat layout/count.

ELS/AA 9 10.21.9811.04.9812.02.98

12.02.98

AE10.07.98.11 Obtain sample of Irwin metal pan perforatedseat with curved lip. No differential envelope(IE12.02.98.01).

LCC 55

10.21.9811.04.9812.02.98

IssuesLog

12/02.98

Ballard C-20 Last Planner

AE10.21.98.01 Review size of amplifyer/dimmer room. ELS/AA/JHSA

11.04.98 SeeAbove

AE10.21.98.02 Send new pit layout/dimensions to JHSA andAA for review (IE08.26.98.02).

ELS 10.28.98 11.04.98

AE10.21.98.03 Review/revise audience reduction system(IE10.07.98.02).

NS/ELS/AA 11.11.98 11.04.98

AE10.21.98.04 Review design program with NS independentproducer/ reviewer, Peter Wexler. Ongoing.

ELS/AA/JHSA

12.02.98 12.02.98

AE10.21.98.05 Review proposed 3 reconfigurations and sizesfor control booth/ FOH mixing positionnecessitated by radial seating change. Resolveconstraints

AA/JHSA 2 11.04.9812.02.98

12.02.98

AE11.04.98.01 Revisit discussion regarding height of gridabove proscenium. Proscenium: Rock 50 FT,Broadway 32 FT Min. (IE10.07.98.03).

NS 11.04.98 11.04.98

AE12.02.98.01 Send copy of Production Arts Lighting GMPproposal to NS/ELS.

LCC 12.04.98

AE12.02.98.02 Raise Stage House trim height from 80 Ft to81Ft-3In by lightening stage house steel andadjustin roof pitch. Requires addding backrigging pit: 6Ft by 60Ft of basement space,per earlier drawing issue.

ELS/HW 12.16.98

AE12.02.98.03 Send picture and dimensions of typical soundboard to ELS, for selection of appropriatesized sissor lift.

JHSA 12.16.98

AE12.02.98.04 Develop actual speaker locations/'look' of theproscenium; development meeting next weekto generate describing graphics.

JHSA/SPL 12.16.98

AE12.02.98.05 Colors and materials for lobby and housebeign pulled by logo/ color development;colors and materials presentation after January1st.

NS/ELS 01.11.98

F. Project SupportAF07.01.98.01 Approval of audio and theatrical lighting

concepts.NS 07.07.98 07.07.98

AF07.01.98.02 Issue project insurance memorandum fordiscussion.

LCC 07.07.98 07.07.98

AF07.01.98.03 Issue subcontractor preconstructionagreements for discussion, (IF08.26.98.01).(Crown Corr agreement issued).

LCC Issues Log 08.26.98

AF07.01.98.04 Resolve design agreement legal issues andcomplete ELS design agreement. Effortcontinuing. Documents may not be filed forpermits until legal issues are resolved anddesigners can be identified in the drawingtitle block (IF10.21.98.01).

NS/ELS 55

07.10.9810.21.98

IssuesLog

10.21.98

AF07.01.98.05 Approval of audience/house reduction designsolution.

NS Thtrcl/Int 07.29.98

Ballard C-21 Last Planner

AF07.01.98.06 Identify potential national vendor partners.Effort continuing (IF08.26.98.02).

LCC/ELS Issues Log 08.26.98

AF07.01.98.07 Identify project components not currentlyrepresented by team. Effort continuing.

LCC/ELS Issues Log 08.26.98

AF07.01.98.08 Update and issue current project budget, asrevised.

LCC 07.14.98 07.29.98

Project Logs:AF07.01.98.09 • Develop a consistent format for project logs

for review.LCC 07.07.98 07.09.98

AF07.01.98.10 • Refine meeting action items, issue/maintainAction Items Log.

LCC 07.07.98 07.09.98

AF07.01.98.11 • Develop, issue and maintain Issues Log, andDecision Log.

LCC 07.10.98 07.09.98

AF07.01.98.12 Develop, issue and maintain Project DocumentLog.

ELS 07.14.98 07.29.98

AF07.01.98.13 • Approval of project logs and format. NS 07.14.98 07.15.98AF07.15.98.01 Amend log format to show Issue, Action Item,

Decision trail; each item to have a discreteidentity.

LCC/NS 07.29.98 07.29.98

AF07.15.98.02 Probability of construction start date - StatusReport (IF08.26.98.03).

NS Issues Log 08.26.98

AF07.15.98.03 Submit agreement for engineering and otherconsultant services (AF07.15.98.04).

NS/HA Issues Log 08.26.98

AF07.15.98.04 Submit agreement for architectural servicesand other consultant design agreements.

ELS/HA 07.28.98 07.29.98

AF07.15.98.05 Resolve agreement with food serviceconcessionaire.

NS 07.28.98 07.28.98

AF07.15.98.06 Revise estimate schedule for GMP. NS/LCC 07.28.98 07.28.98AF07.29.98.01 Prepare target cash flow estimate for both

consultant design and subcontractor designefforts.

NS/ELS/LCC

08.12.9808.26.98

09.09.98

AF07.29.98.02 Expand current summary project budget todetailed estimate (IF08.26.98.04)

LCC Issues Log 08.26.98

AF07.29.98.03 Electronic communication of projectinformation. Install project documents oncommunication web site server(IF07.15.98.06).

NC/ELS/LCC

7 08.12.9810.07.98

10.07.98

AF07.29.98.04 Include Food Service consultant, CreativeIndustries, in project progress meetings.

NS/LCC 08.12.9808.26.98

08.12.98

AF07.29.98.05 Review and report on the status of documentpreparation.

ELS 08.12.98 08.12.98

AF08.12.98.01 Prepare notes from 8/6/98 meeting with GrandPrairie building officials.

ELS 09.09.98 09.09.98

AF08.12.98.02 Prepare list of proposed permit packages andtimeline. (Timeline preparation moved toIssues Log item IF09.09.98.01.)

ELS/LCC 09.09.98 09.09.98

AF08.26.98.01 Issue Crown Corr Agreement. NS/LCC 09.09.98 09.09.98AF08.26.98.02 Issue Pacific Agreement. NS/LCC 09.09.98 09.09.98AF08.26.98.03 Issue Havens Agreement. NS/LCC 09.09.98 09.09.98AF08.26.98.04 Define format/dates for ELS consultants ELS/LCC Deleted 09.09.98

Ballard C-22 Last Planner

design scope of work. No one recognized thisas an action item or was a duplicate.

AF08.26.98.00 Resolve design agreement legal issues withELS.

NS 09.09.9809.23.98

To AF 07.01.98.04

AF08.26.98.05 Prepare cash flow to January 1999 by monthfor ELS and their consultants based on currentvalue stream (AF10.21.98.01).

ELS 55

09.09.9810.21.98

CombinedBelow

AF08.26.98.06 Prepare cash flow to January 1999 by monthfor LCC and consultants based on currentvalue stream (AF10.21.98.01).

LCC 55

09.09.9810.21.98

CombinedBelow

AF08.26.98.07 Prepare cash flow to January 1999 by monthfor NS and consultants based on current valuestream.

NS 09.09.98 09.09.98

AF08.26.98.08 Issue SPL Agreement letter (IF10.21.98.02). NS/AA/LCC

55

09.09.9810.21.98

IssuesLog

10.21.98AF09.09.98.01 Bob Timmel to review list of cost increases

with Bruce, Pam and Mike on Friday 09.11.98NS/LCC 09.11.98 09.14.98

AF09.09.98.02 Bob Timmel to review list of cost increaseswith Leo3.

NS 09.14.98 09.14.98

AF09.23.98.01 Prepare permit package timeline(AF08.12.98.02/ IF09.09.98.01).

ELS/LCC 10.07.98 10.07.98

AF09.23.98.02 Continuing improvement in the planningprocess: improving ability to make qualityassignments and ability to meet commitments(IF10.07.98.01).

All 10.07.98 IssuesLog

10.07.98

AF10.07.98.01 Review with each team the most effective wayto proceed with the development ofconstruction documents and target cash flows(IF07.15.98.03).

NS/LCC 10.21.98 10.21.98

AF10.21.98.01 Prepare project workplan/target cashflows(w/manhours): design cash flows assume12.21.98 construction start (AF08.26.98.05,AF08.26.98.06, IF10.07.98.02).

ELS/LCC 5 11.04.9812.02.98

12.02.98

AF10.21.98.01 Prepare project workplan/target cashflows(w/manhours): construction cash flowsassume 02.15.98 construction start and18.5month construction schedule.

LCC 7 12.02.98 12.16.98

AF11.04.98.01 Early construction/other work to achievevisual site impact.

NS/ELS/LCC

1 12.02.98 12.16.98

AF11.04.98.02 Develop early value stream for remainingcritical early preconstruction items of work.

LCC/NS/ELS/ HA

7 12.02.98 12.16.98

AF12.02.98.01 Blueline Online: recommendation to notimplement until the site is stable.

ELS 12.16.98

JDK End of Action Items

Ballard D-23 Last Planner

APPENDIX D: NEXT STAGE ISSUES LOG

During Next Stage teleconferences, issues requiring action beyond the coming two week

period were placed in an issues log, from which they then moved onto the action items

log when the timing was appropriate. Issues were numbered in the same way as were

action items, except for the IA, IB, etc. prefix.

Linbeck Next Stage DevelopmentThe Texas ShowPlace

IssuesLog

As Of December 02, 1998 Project Progress Meeting Revised: 12.14.98Date Originated-

Item No.Item Description Action By Target

Date

A.Site/Civil

IA08.26.98.04 Relocation of on-site pad mounted equipment byTexas Utilities.

HA/TEE

IA09.09.98.02 Legal Action filed against NS, by local radio station,re: within 2400 ft, operating since 1950's, 'solestation', fear of our metal building.

NS

IA10.21.98.01 Select electrical yard surface material; if paved, thenconcrete.

HA

IA11.04.98.01 Determine the most effective way to contract for thesite work (AA12.02.98.05).

HA/LCC ActionLog

12.02.98

B.Structural

IB08.12.98.01 Review utilization of prefab stairs (IC08.12.98.02,AB12.02.98.04).

ELS/LCC ActionLog

12.02.98

Ballard D-24 Last Planner

IB09.09.98.03 Review structural connections and heavy steelmembers. (AB08.26.98.04 & IB07.01.98.01)

HSC/SPI/PB

IB09.23.98.01 Holding an 02.15.99 start of construction requiressteel mill order by 01.15.99; detailing to start by02.15.99; fabrication to start 03.29.99, and erectionto start on 05.10.99

NS/LCC/HSC/ SPI

IB09.23.98.02 After 3D Model, Foundation and Structural Permitsubmisssion target 01.04.99 for a 02.05.99 receiptof permit.

HW/ELS

IB12.02.98.01 Mock-up color selection critical; NS moving onother color decisions based on previously selectedbuilding material colors.

NS/ELS

IB12.02.98.02 Select aggregate/paver material for visible low roof;aggregate is more cost effective if wind load is notan issue.

NS/ELS

IB12.02.98.03 Provide for access to lobby by larger equipment,10Ft X 10FT, for automobile, large boom type lift toaccess relamping.

NS/ELS

C. Enclosure/Architectural

IC07.29.98.01 Resolve material selection at the building base(AC08.12.98.04).

ELS/LCC

IC09.09.98.01 Determine if a mock-up(s) of exterior wall will berequired; to be price based (AC12.02.98.01).

NS/ELS ActionLog

12.02.98

D. Mechanical/Electrical/Plumbing/Fire Protection

ID07.15.98.01 File application and pay fees for temporary powerand telephone four weeks before needed.

NS/LCC

ID08.12.98.05 Add acoustics value stream into project valuestream.

JHSA/LCC

ID08.26.98.01 Finalize concession design upon selection ofconcessionaire vendor.

NS/CI/ELS/ CHPA/TEE

ID10.21.98.01 Block diagram equipment layout by LevyRestaurants

NS/LR 12.08.98

ID12.02.98.01 Confirm assumptions regarding lighting controls.Automated M/P systems can control other timedsystems, i.e. parking lighting, etc. Ongoing workissue (AD11.04.98.07).

CHPA/TEE

E. Theatrical/Interiors

IE08.26.98.01 Seating count down from 6900 to 6400. May go upto 6550 plus 256 for suites. Refer to memo of08.27.98.

NS/ELS

IE10.07.98.01 Evaluate continuing scaffolding or working up fromstructural platforms. Method of construction issue

LCC

Ballard D-25 Last Planner

to be decided by LCC.

IE12.02.98.01 Obtain sample of Irwin metal pan perforated seatwith curved lip. No differential envelope(AE10.07.98.11).

LCC

IE12.02.98.02 Irwin Seating critical path, 12 months from design todelivery.

NS

IE12.02.98.03 D.Flannery to layout TV camera positions in thehouse.

NS

IE12.02.98.04 Price Division 16 infrastructure for video andcommunication.

LCC

IE12.02.98.05 Provide video communication equipment price. JHSA

F. Project Support

IF07.01.98.01 Develop post-preconstruction contract documents forreview.

LCC

IF07.15.98.02 Integrate preconstruction agreement with GMPcontract.

LCC

IF07.15.98.04 Develop site utilization/mobilization plan. LCCIF07.29.98.01 Define long term role of food service consultant. NSIF07.29.98.02 Review/revise Value Stream in relation to schedule

revisions, project changes, etc.LCC

IF08.12.98.01 Resolution of project insurance program. AllIF08.26.98.01 Issue subcontractor preconstuction agreements for

discussion, (AF07.01.98.03). Crown Corragreement issued.

All

IF08.26.98.02 Identify potential national vendor partners. Effortcontinuing (AF07.01.98.06).

LCC/ELS

IF08.26.98.03 Probability of construction start date - Status Report(AF07.15.98.02).

NS

IF08.26.98.04 Expand current summary project budget to detailedestimate when 3-D model has beencompleted.(AF07.29.98.02/IF09.09.98.02).

LCC

IF09.09.98.03 Define a point in the design process where it makessense to stop additional work until a definitiveconstruction start date is known; and, independent ofa construction start date.

NS/ELS/CHPA/TEE/LCC

IF09.09.98.04 Define how, and at what point, cost escalationbecomes a consideration.

NS/LCC

IF10.07.98.01 Continuing improvement in the planning process;improving ability to make quality assignments andability to meet commitments (AF09.23.98.02).

All

IF10.21.98.01 Resolve design agreement legal issues and completeELS design agreement. Effort continuing.Documents may not be filed for permits until legalissues are resolved and designers can be identifiedin the drawing title block (AF07.01.98.04).

NS/ELS 11.28.98

IF10.21.98.02 Issue SPL Agreement letter (AF08.26.98.08). NS/AA/LCC 12.16.98

Ballard D-26 Last Planner

IF10.21.98.03 Identify items critical to value stream and followthrough; be clear about what should be on the valuestream.

ALL

IF12.02.98.01 Concession architect:Lawrence Berkely Associates.Plans and room finishes to be sent to NS. Countersand facade to be allowances; LCC to construct shell.

NS

JDK End of Issues

Ballard E-27 Last Planner

APPENDIX E: NEXT STAGE DECISION LOG

Next Stage maintained a log of design decisions, numbered similarly to action items and

issues, but with a DA prefix for Site/Civil, DB for Structural, etc.

Decision Log

As Of December 02, 1998 Project Progress Meeting Revised: 12.14.98Date Originated-ItemNo.

Item Description DecisionBy

DecisionDate

A. Site/Civil

DA07.15.98.01 Retain the services of a TAS AccessibilitySpecialist.

NS:RT 07.15.98

DA07.15.98.02 There will be multiple collection points forstorm and sanitary drainage around the building(IA07.01.98.03).

CHPA:GPHA:JR

07.15.98

DA07.29.98.01 Specify same site and parking lighting fixturesas Lone Star Park, unless not feasible or toocostly.

NS:RT 07.29.98

DA07.29.98.02 Barrier Free Texas selected as AccessibilitySpecialist.

NS:RT/ELS:KS

07.29.98

DA07.29.98.03 Uncertain timetable does not allow takingborrow material from existing sewer contractor.

NS:RT 07.29.98

DA08.12.98.01 Use existing lighting for Road D, rewired fornew/joint operation with Lone Star Park.

NS:RT 08.12.98

DA08.12.98.02 Grading permit approval does not requirearchitectural document submission.

ELS:DF 08.12.98

DA08.26.98.01 Roadway and building relationships are notaffected by the commissary.

HA:JR 08.26.98

DA08.26.98.02 Commissary Scheme A selected (reversal fromScheme B).

NS:BC 08.26.98

DA08.26.98.03 Roof drain overflow to be piped into primarydrainage system.

CHPA:GP 08.26.98

DA09.09.98.01 Commence geotechnical exploration/drilling ofLSP borrow material.

NS:RT 09.09.98

DA10.07.98.01 Utilize 55 foot light poles in parking area. TEE:CS 10.07.98DA11.04.98.01 If GPISD material is available at the start of

construction, then will make an offer forsubgrade material for automobile parking.

NS:RT 11.04.98

Ballard E-28 Last Planner

B. Structural

DB07.15.98.01 Cantilever balcony structure is not practical norfeasible; cross aisles raised to make cantileverwork.

JA:HWKS:ELS

07.15.9808.26.98

DB07.29.98.01 Tapered beams will be utilized to support thebalcony.

HW:JA/ELS:KS

07.29.98

DB08.12.98.01 There will be no electrical point loads in thestructure greater than 500 lbs (AB07.01.98.08).

TEE:CS 08.12.98

DB08.12.98.02 Design criteria for building exterior will bebased upon wind tunnel test results(AB07.01.98.14).

HW:RT 08.12.98

DB08.12.98.03 Resolved audience reduction and box beamloads and location.

ELS:KS /AA:AS

08.12.98

DB08.12.98.04 Proceed with structural design based uponexisting perimeter envelope and seatingplatform.

NS:RT 08.12.98

DB08.12.98.05 Extend four week steel fabrication schedulefrom 4 weeks to 6 weeks (IB07.15.98.03 /AB08.12.98.01).

HSC:JK 08.12.98

DB08.12.98.06 Resolved low roof impact on structural designby selecting concession scheme 'B'. Reversed toScheme A.

NS:BC NS:BC

08.12.9808.26.98

DB08.12.98.07 Project will not start construction 09.15.98;and, will not utilize warehouse steel.

NS:RT 08.12.98

DB08.12.98.08 Acceptable construction tolerance on seating is1/2" per riser, platform to platform.

ELS:KS 08.12.98

DB09.09.98.01 Initial steel mill order must be made 1 monthprior to start of construction.

HSC:JK 09.09.98

DB09.23.98.01 Complete 3D model check; hold-up connectionstudy, detailing, and, trans-mission of 3-Dmodel until resolution of potential seating layoutchange.

NS:RT 09.23.98

DB10.07.98.01 Eliminate CMU walls at FOH mechanicalrooms due to revised AHU layout.

JHSA:RL 10.07.98

DB12.02.98.01 Revise column locations at rear of stage houseto center the door.

BC:NS 12.02.98

C. Enclosure/Architectural

DC07.01.98.01 Construction/shop drawings not necessary toprovide GMP for exterior wall enclosure.

CC:SC 07.01.98

DC07.15.98.01 There is not a food service requirement forlouvers (IC07.01.98.05).

CHPA:GP 07.15.98

DC07.15.98.02 The site has a "quiet area" designation relatingto outside area noise.

JHSA:RL 07.15.98

DC07.15.98.03. GMP for roof can be provided without havingthe roof design completed.

PC:TZ 07.15.98

Ballard E-29 Last Planner

DC08.12.98.01 Walls to be rated R20 & Roof R30 Insulation(IC07.15.98.01 / AC08.12.98.02).

CHPA:GPLCC:BP

08.12.98

DC08.26.98.01 R30 Roof and R20 Wall will be the thermaltransmission ratings used.

08.26.98

DC08.26.98.02 Roof design by Pacific to follow Crown Corrdrawings.

PC:TZ 08.26.98

DC10.07.98.01 Can specify custom metal panel colors basedupon nominal price increase.

NS:RT 10.07.98

D. Mechanical/Electrical/Plumbing/Fire Protection

DD07.15.98.01 TEE:CS to participate in evaluating onlineproject management approach.

TEE:CS 07.15.98

DD07.29.98.01 FE:WMcD to participate in evaluating onlineproject management approach.

FE:WMcD 07.29.98

DD08.12.98.01 The raceway loads will not affect structuralpoint loading (AD07.01.98.13).

TEE:CSHW:RT

08.12.98

DD08.12.98.02 Location of main electrical room and electronicsstorage will maintain existing relationship.

TEE:CSLCC:MI

08.12.98

DD08.12.98.03 The back of the house will be a no smokingarea.

NS:BC 08.12.98

DD08.12.98.04 Utilize 75 KVA as added electrical load fromcommissary.

TEE:CS 08.12.98

DD08.26.98.01 Proceed with concession/commissary MEP design based oncurrent 08.26.98 consultant concept/interim design criteria.

08.26.98

DD08.26.98.02 HVAC design is to be per ASHRAE standards,as shown in current Project System Description.

CHPA:GP 08.26.98

DD08.26.98.03 Provide individual climate control in suites. NS:BC 08.26.98

DD09.09.98.01 Smoking area includes suites and selectconcession areas (Rooms 123,124)

NS:BC 09.09.98

DD09.23.98.01 Proceed with 21,000 cfm lobby smoke exhaustas opposed to a house/lobby rated separation.

NS:BC,ELS:KS

CHPA:GP

09.23.98

E. Theatrical/Interiors

DE07.01.98.01 NC 25 accepted as design criteria. JHSA:CJ 07.01.98DE07.29.98.01 Provide suite level public toilet rooms; eliminate

toilet rooms in suites, but provide infrastructureMEP.

NS:RT 07.29.98

DE07.29.98.02 Provide expanded commissary kitchen andsupport areas.

NS:RT 07.29.98

DE08.26.98.01 Sound and lighting control house mix positioncannot be moved into rear aisle due tohandicapped seating quota. This room requiresthe size shown on sketch current as of 08.26.98.

JHSA:DRELS:KS

08.26.98

DE08.26.98.02 Hold on final concession design for contractedconcessionaire.

NS:RT 08.26.98

Ballard E-30 Last Planner

DE09.23.98.01 Box Booms will be rigged. NS:BC 09.23.98DE10.07.98.01 Change seating configuration to curved format. NS:RT 10.07.98DE10.07.98.02 Provide proscenium deluge system with opaque

curtain.NS:RTELS:KS

10.07.98

DE10.07.98.03 There will not be a front balcony projectionposition.

NS:BC 10.07.98

DE10.07.98.04 Eliminate the rigging pit due to revisedcounterweight design.

AA:AS 10.07.98

DE10.21.98.01 Utilize Video/TV/Broadcast scope prepared byAA/JHSA to define building infrastructure to beprovided.

NS:BC 10.21.98

DE12.02.98.01 Approximately 95% of speakers will be riggedor stacked on stage; all lighting and soundsupport will be within 60 Feet of stage.

NS:BCAA:AS

12.02.98

F. Project Support

DF07.01.98.01 It is not necessary to follow Factory Mutualdesign criteria.

NS:RT 07.01.98

DF07.01.98.02 Project progress meetings will utilize "LastPlanner" style.

NS:RT 07.01.98

DF07.15.98.01 Design process to maintain 21 month valuestream production schedule.

NS:RT 07.15.98

DF07.15.98.02 Multiple submissions will be made to the City tosatisfy the needs of obtaining multiple permitapprovals.

NS:RT 07.15.98

DF09.23.98.01 Keep the design process progressing toward an11.30.98 construction start; the only reason tohold up progress of the drawings is if it is notefficient for the design to proceed.

NS:LL 09.23.98

End of Decisions


Top Related