![Page 1: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/1.jpg)
Space Systems Engineering: System Hierarchy Module
System Hierarchy and
Work Breakdown Structure Module
Space Systems Engineering, version 1.0
CC532 Collaborate System Design
Fundamentals of Systems Engineering
W4, Spring, 2012 KAIST
![Page 2: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/2.jpg)
Space Systems Engineering: System Hierarchy Module 2
Module Purpose: System Hierarchy
To show how one view of the system architecture is captured
by the product breakdown structure (PBS).
To describe the benefits and costs of creating a system
hierarchy.
To show how to capture all of the work necessary for a project
by adding the non-product work to the PBS to create the work
breakdown structure (WBS).
![Page 3: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/3.jpg)
Space Systems Engineering: System Hierarchy Module 3
One View of the Architecture - The Product Breakdown Structure
The framework and interrelationships of elements of a system. Typically illustrated by both a pictorial and a decomposition diagram depicting the segments and elements and their interfaces and interrelationships.
Architecture is described by the System Hierarchy or Product Breakdown Structure (PBS)
![Page 4: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/4.jpg)
Space Systems Engineering: System Hierarchy Module 4
Why Break a Product Down?
Breaking a large complex problem (project) into smaller pieces makes them
easier to solve since the problems are smaller and specialists can focus
on their functional areas.
But this process of reductionism creates some new problems. Namely,
New interfaces are created between the pieces (subsystems), so they
must be defined and managed.
System resources (e.g., mass or power) must be allocated to the
subsystems and these allocations must be accounted for; and
System performance is also allocated to subsystems, so confidence
must be established that if all of the subsystems perform as desired,
then the system will perform as desired.
The creation of the system architecture, the description and management of
interfaces, the allocation of resources and performances, and
establishing confidence that these allocations are appropriate are all
systems engineering responsibilities.
![Page 5: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/5.jpg)
Space Systems Engineering: System Hierarchy Module 5
More Value to Creating
A System Hierarchy
Organizes the work required
to complete a flight project.
Contains all hardware items,
software items, and
information items (e.g.,
documents, databases).
Provides the basis for
functional analysis.
Characteristics:
• Top-down,
• Product-based,
• Lowest level maps to
cognizant engineer or
manager,
• Branch points in hierarchy
show how elements will be
integrated.
![Page 6: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/6.jpg)
Space Systems Engineering: System Hierarchy Module 6
Hierarchical Level Names and Examples
Hierarchical Level Name Examples
Mission Needs + Objectives + Operation of Everything Necessary to Meet the Objectives
System* Total System = Spacecraft + Launch Vehicle + Ground Support Equipmen t + Communications Systems (TDRSS, etc.) + NASCOM + POC + Science Data Center + ...+ Personnel
Segment Flight = Spacecraft Bus + Instrume nts + Launch Vehicle +...
Element Spacecraft = Structure + Powe r + C&DH + Thermal + ...
Subsystem Power = Solar Arrays + Electronics + Battery + Fuses + ...
Component Solar Arrays = Solar Cells + Interconnects + Cover Glass + ...
Part Solar Cells
* Any given system can be organized into a hierarchy composed of segments and/or
elements of succeedingly lower and less complex levels, which may in themselves be
termed “systems” by their designers. In order to avoid misunderstandings, hierarchical
levels for a given mission must be defined early.
![Page 7: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/7.jpg)
Space Systems Engineering: System Hierarchy Module 7
System Hierarchy (1/2)
Hierarchy/Hierarchical Levels - The relationship of one item of
hardware/software with respect to items above and below in the
relative order of things.
Mission - An individual system or groups of systems operated to
meet a specific set of objectives.
System - A composite of hardware, software, skills, personnel,
and techniques capable of performing and/or supporting an
operational role. A complete system includes related facilities,
equipment, materials, services, software, technical data, and
personnel required for its operation and support to the degree
that it can be considered a self-sufficient unit in its intended
operational and/or support environment.
• The system is what is employed operationally and supported
logistically. (More than one system may be needed to conduct a
mission.)
![Page 8: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/8.jpg)
Space Systems Engineering: System Hierarchy Module 8
System Hierarchy (2/2)
Segment - A grouping of elements that are closely related and
which often physically interface. It may consist of elements
produced by several organizations and integrated by one.
Element - A complete, integrated set of subsystems capable of
accomplishing an operational role or function.
Subsystem - A functional grouping of components that combine
to perform a major function within an element.
Component - A functional subdivision of a subsystem and
generally a self-contained combination of items performing a
function necessary for subsystem operation. A functional unit
viewed as an entity for purpose of analysis, manufacturing,
testing, or record keeping.
Part - A hardware element that is not normally subject to further
subdivision or disassembly without destruction of designated use.
![Page 9: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/9.jpg)
Space Systems Engineering: System Hierarchy Module 9
System Hierarchy Example - Space Shuttle
System hierarchy is also referred to as the Product Breakdown Structure (PBS).
System
Segment
Element
Subsystem
![Page 10: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/10.jpg)
Space Systems Engineering: System Hierarchy Module 10
How complicated it can get…
The yellow boxes represent the bottom-level end products.
![Page 11: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/11.jpg)
Space Systems Engineering: System Hierarchy Module 11
Work Breakdown Structure (WBS)
Definition
A hierarchical breakdown of the work necessary to complete a
project. The WBS should be a product-based, hierarchical
division of deliverable items and associated services.
The WBS is based on the System Hierarchy or Product
Breakdown Structure (PBS), with the specified prime products
at the top, and the systems, segments, subsystems, etc. at
successive lower levels.
At the lowest level are products, such as hardware and
software for which there is a cognizant engineer or manager.
The WBS is built from the PBS by adding (at each level) the
necessary service elements, such as management, systems
engineering, integration and verification, and logistics support.
![Page 12: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/12.jpg)
Space Systems Engineering: System Hierarchy Module 12
Relationship Between PBS and WBS
The Product BreakdownStructure shows thecomponents from whichthe system was formed.
The PBS reflects thework to producethe individualsystem components.
The Work BreakdownStructure shows allwork components necessaryto produce a completesystem.
The WBS reflects thework to integratethe componentsinto a system.
Subsystem A Subsystem B Subsystem C Management Systems
Engineering
Integration,
Test & Verification
Logistics
Support
System
PBS
WBS
![Page 13: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/13.jpg)
Space Systems Engineering: System Hierarchy Module 13
Work Breakdown Structure (WBS)
A Work Breakdown System (WBS) is used for: • Task or work package planning and scheduling
• Cost estimating or budget formulation
• Product development documentation, e.g., documentation tree, systems engineering management plan (SEMP), drawings
• Project status reporting and assessment
The WBS should include:
• All the work in the project life cycle, in-house and/or contracted
• Hierarchical relationships of all work products
• A companion dictionary to describe the content
When should you have a WBS?
• Pre-phase A; conceptual design phase; early mission/project formulation
![Page 14: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/14.jpg)
Space Systems Engineering: System Hierarchy Module 14
NASA Standard WBS at Level 2
Flight Dev elopment
And Operations
Project
Project
Management
01
Sy stems
Engineering
02
Saf ety & Mission
Assurance
03
Science /
Technology
04
Pay load(s)
05
Aircraf t /
Spacecraf t
06
Mission
Operations
07
Launch Vehicle /
Serv ices
08
Ground
Sy stem(s)
09
Sy stems Integration
& Testing
10
Education and
Public Outreach
11
Flight Dev elopment
And Operations
Project
Project
Management
01
Sy stems
Engineering
02
Saf ety & Mission
Assurance
03
Science /
Technology
04
Pay load(s)
05
Aircraf t /
Spacecraf t
06
Mission
Operations
07
Launch Vehicle /
Serv ices
08
Ground
Sy stem(s)
09
Sy stems Integration
& Testing
10
Education and
Public Outreach
11
Standard Level 2 WBS Elements for Space Flight Projects
Space Flight Project
Spacecraft06
![Page 15: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/15.jpg)
Space Systems Engineering: System Hierarchy Module 15
Example: NASA’s SOFIA Project PBS and WBS
Aircraft Element
Telescope Subsystem Electronics Subsystem
Telescope Element
Airborne Facility Science Instruments
Observatory System
Labs/Offices Facility GSE Mission Planning Simulator
Ground Support System
Sofia Project
Management Systems
Engineering
Project
Integration &
Test
Operations
and Logistics
Planning
Science
Support
Mission
Assurance
Observatory
System
Ground
Support
System
Sofia Project
PBS
WBS
![Page 16: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/16.jpg)
Space Systems Engineering: System Hierarchy Module
Pause and Learn Opportunity
View the James Webb Space Telescope (JWST) WBS
& Dictionary Baseline document for example
implementation.
(JWST WBS & Dictionary (Baseline).pdf)
![Page 17: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/17.jpg)
Space Systems Engineering: System Hierarchy Module 17
Techniques for Developing a WBS
Takes several iterations through the life of the project, since the full
extent of the work is not obvious at the outset.
Develop System Hierarchy / PBS first, from the top down
Develop WBS by adding appropriate services, such as management
and systems engineering to the lower levels
Use a similar structure as a starting point for all product elements of
the WBS at all levels
Repeat for all levels, starting with project level
Involve people who will be responsible for the lower level WBS
elements.
Document assumptions, e.g., common spacecraft computer and
software; all operations development costs under mission ops;
testbeds and prototype hardware contained within hardware
element etc.
![Page 18: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/18.jpg)
Space Systems Engineering: System Hierarchy Module 18
Module Summary: System Hierarchy
A product breakdown structure (PBS) captures the hierarchy of the system and is one representation of the system architecture.
Creating a system hierarchy is valuable since it breaks a complex problem into smaller pieces that will be easier to tackle.
But this reductionism, or decomposition has a price:
• New interfaces are created between the pieces (subsystems), so they must be defined and managed.
• System resources (e.g., mass or power) must allocated to the subsystems and these allocations must be accounted for; and
• System performance is also allocated to subsystems, so confidence must be established that if all of the subsystems perform as desired that the system will perform as desired.
The work breakdown structure (WBS) extends the PBS in that it captures all of the work necessary for a project by adding the non-product work necessary for a successful project (e.g., integration, test, logistics support, systems engineering and management).
![Page 19: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/19.jpg)
Space Systems Engineering: System Hierarchy Module
Backup Slides
for System Hierarchy Module
Note slides 26-28 demonstrate some common errors in
PBS and WBS structure. The pilot students found
these useful, so they could be included in the body of
the lecture.
![Page 20: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/20.jpg)
Space Systems Engineering: System Hierarchy Module 20
NASA Space Flight Project Standard WBS Dictionary (1/4)
Element 1 – Project Management: The business and administrative planning, organizing, directing, coordinating, analyzing, controlling, and approval processes used to accomplish overall project objectives, which are not associated with specific hardware or software elements. This element includes project reviews and documentation, non-project owned facilities, and project reserves. It excludes costs associated with technical planning and management and costs associated with delivering specific engineering, hardware and software products.
Element 2 – Systems Engineering: The technical and management efforts of directing and controlling an integrated engineering effort for the project. This element includes the efforts to define the project space flight vehicle(s) and ground system, conducting trade studies, the integrated planning and control of the technical program efforts of design engineering, software engineering, specialty engineering, system architecture development and integrated test planning, system requirements writing, configuration control, technical oversight, control and monitoring of the technical program, and risk management activities. Documentation products include requirements documents, interface control documents (ICDs), Risk Management Plan, and master verification and validation (V&V) plan. Excludes any design engineering costs.
Element 3 – Safety and Mission Assurance: The technical and management efforts of directing and controlling the safety and mission assurance elements of the project. This element includes design, development, review, and verification of practices and procedures and mission success criteria intended to assure that the delivered spacecraft, ground systems, mission operations, and payload(s) meet performance requirements and function for their intended lifetimes. This element excludes mission and product assurance efforts directed at partners and subcontractors other than a review/oversight function, and the
direct costs of environmental testing.
![Page 21: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/21.jpg)
Space Systems Engineering: System Hierarchy Module 21
NASA Space Flight Project Standard WBS Dictionary (2/4)
Element 4 – Science / Technology: This element includes the managing, directing, and controlling of the science investigation aspects, as well as leading, managing, and performing the technology demonstration elements of the Project. The costs incurred to cover the Principal Investigator, Project Scientist, science team members, and equivalent personnel for technology demonstrations are included. Specific responsibilities include defining the science or demonstration requirements; ensuring the integration of these requirements with the payloads, spacecraft, ground systems, and mission operations; providing the algorithms for data processing and analyses; and performing data analysis and archiving. This element excludes hardware and software for onboard science investigative instruments/payloads.
Element 5 – Payload: This element includes the equipment provided for special purposes in addition to the normal equipment (i.e., GSE) integral to the spacecraft. This includes leading, managing, and implementing the hardware and software payloads that perform the scientific experimental and data gathering functions placed on board the spacecraft, as well as the technology demonstration for the mission.
Element 6 – Spacecraft(s): The spacecraft that serves as the platform for carrying payload(s), instrument(s), humans, and other mission-oriented equipment in space to the mission destination(s) to achieve the mission objectives. The spacecraft may be a single spacecraft or multiple spacecraft/modules (i.e., cruise stage, orbiter, lander, or rover modules). Each spacecraft/module of the system includes the following subsystems, as appropriate: Crew, Power, Command & Data Handling, Telecommunications, Mechanical, Thermal, Propulsion, Guidance Navigation and Control, Wiring Harness, and Flight Software. This element also includes all design, development, production, assembly, test efforts, and associated GSE to deliver the completed system for integration with the launch vehicle and payload. This element does not include integration and test with payloads and other project systems.
![Page 22: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/22.jpg)
Space Systems Engineering: System Hierarchy Module 22
NASA Space Flight Project Standard WBS Dictionary (3/4)
Element 7 - Mission Operations System: The management of the development and implementation of personnel, procedures, documentation, and training required to conduct mission operations. This element includes tracking, commanding, receiving/processing telemetry, analyses of system status, trajectory analysis, orbit determination, maneuver analysis, target body orbit/ephemeris updates, and disposal of remaining end-of-mission resources. The same WBS structure is used for Phase E Mission Operation Systems but with inactive elements defined as “not applicable.” However, different accounts must be used for Phase E due to NASA cost reporting requirements. This element does not include integration and test with the other project systems.
Element 8 – Launch Vehicle / Services: The management and implementation of activities required to place the spacecraft directly into its operational environment, or on a trajectory towards its intended target. This element includes launch vehicle, launch vehicle integration, launch operations, any other associated launch services (frequently includes an upper-stage propulsion system), and associated ground support equipment. This element does not include the integration and test with the other project systems.
![Page 23: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/23.jpg)
Space Systems Engineering: System Hierarchy Module 23
NASA Space Flight Project Standard WBS Dictionary (4/4)
Element 9 – Ground System(s): The complex of equipment, hardware, software, networks, and mission-unique facilities required to conduct mission operations of the spacecraft systems and payloads. This complex includes the computers, communications, operating systems, and networking equipment needed to interconnect and host the Mission Operations software. This element includes the design, development, implementation, integration, test, and the associated support equipment of the ground system, including the hardware and software needed for processing, archiving, and distributing telemetry and radiometric data and for commanding the spacecraft. Also includes the use and maintenance of the project testbeds and project-owned facilities. This element does not include integration and test with the other project systems and conducting mission operations.
Element 10 – Systems Integration and Testing: This element includes the hardware, software, procedures, and project-owned facilities required to perform the integration and testing of the project’s systems, payloads, spacecraft, launch vehicle/services, and mission operations.
Element 11 – Education and Public Outreach: Provide for the education and public outreach (EPO) responsibilities of NASA’s missions, projects, and programs in alignment with the Strategic Plan for Education. Includes management and coordinated activities, formal education, informal education, public outreach, media support, and website development.
![Page 24: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/24.jpg)
Space Systems Engineering: System Hierarchy Module 24
Standard WBS for a JPL Mission
Foreign Travel/ITAR
01.07
Facilities
01.06
Review Support
01.05
Project Plng Spt
01.04
Risk Mgmnt
01.03
Business Mgmnt
01.02
Project Mgmnt01.01
Project Management
01
Project V&V
02.08
Launch Sys Eng
02.07
Planetary Protection
02.06
Config Mgmnt
02.05
Information Systems
02.04
Project SW Eng
02.03
Mission & Nav Design
02.02
Project Sys Eng02.01
Project Sys Eng
02
SW IV&V03.09
Contamination Control
03.08
SW Q&A
03.07
HW Q&A
03.06
EEE Parts Eng
03.05
Reliability
03.04
Environments
03.03
System Safety
03.02
MA Mgmnt03.01
Mission Assurance
03
Education & Outreach
04.06
Sci Environment
Characterization04.05
Sci Investigatio
& Ops Spt
04.04
Sci Data Support
04.03
Science Team
04.02
Science Mgmnt04.01
Science
04
P/L I&T
05.06
Common P/L Systems
05.05
Instrument N
05.04
Instrument 1
05.03
P/L Sys Eng
05.02
P/L Mgmnt05.01
Payload
05
Spacecraft assembly
test & verification
06.12
Testbeds
06.11
Spacecraft Flt SW
06.10
GN&C Subsys06.09
Propulsion Subsys06.08
Thermal Subsys
06.07
Mechanical Subsys
06.06
Telecomm Subsys
06.05
Command & Data S/s
06.04
Power Subsys
06.03
Flt Sys - Sys Eng
06.02
Flt Sys Mgmnt
06.01
Spacecraft Contract06.00
Flight System
06
MOS V&V
07.05
Operations
07.04
Ground Data Sys
07.03
MOS Sys Eng
07.02
Mission Ops Mgmnt07.01
Mission Ops System
07
Launch Services08.01
Launch System
08
Project Name
WB
S L
eve
ls
1
2
3
![Page 25: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/25.jpg)
Space Systems Engineering: System Hierarchy Module 25
Rules for the NASA Standard WBS
1. The Project Name will be WBS Level 1.
2. The title of each WBS Level 2 element can be modified to facilitate project-unique titles, but the content of each must remain the same. If the linkage of the project-unique title to the standard title is not intuitive, the project-unique title is cross-referenced to the standard.
3. If the set of standard WBS Level 2 elements does not comprise an exhaustive set of WBS elements, additional WBS elements may be added horizontally (i.e., at Level 2) as long as their content does not fit into the content of any existing standard WBS elements.
4. For each standard WBS Level 2 element, the subordinate (children) WBS elements at Level 3 and lower will be determined by the project.
5. The Level 3 and lower elements can differ from project to project but will include only work that rolls up to the standard WBS Dictionary definition of the Level 2 element. (See back-up for definitions.)
6. If there is no work to fit into a standard WBS element, then an inactive placeholder element (and an inactive placeholder financial code) will be established.
7. A single WBS will be used for both technical/business management and reporting.
8. The management assigned to each WBS element may differ from project to project.
![Page 26: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/26.jpg)
Space Systems Engineering: System Hierarchy Module 26
Common WBS Errors (1/3)
Management Engineering Fabrication Verification
Project
Error 1: Functions without products.
•The WBS describes functions not products.
•This makes the project manager the only one formally
responsible for products.
![Page 27: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/27.jpg)
Space Systems Engineering: System Hierarchy Module 27
Common WBS Errors (2/3)
Software Hardware
Distributed
Information
System
Error 2: Inappropriate branches
• The WBS has branch points that are not consistent with how
the WBS elements will be integrated.
• Inappropriate to separate hardware and software as if they are
separate systems to be integrated at the system level.
• This makes it difficult to assign accountability for integration
and to identify the costs of integrating and testing components
of a system.
![Page 28: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/28.jpg)
Space Systems Engineering: System Hierarchy Module 28
Common WBS Errors (3/3)
Telescope
Assembly
Optics/Mirror
Subsystem
Error 3: Inconsistency with PBS
• The WBS is inconsistent with the PBS.
• This makes it possible that the PBS will not be fully
implemented, and complicates the management process.
XXX YYY
ZZZ Optics/Mirror
Telescope
Assembly
Subsystem
The Work Breakdown System The Product Breakdown System
![Page 29: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/29.jpg)
Space Systems Engineering: System Hierarchy Module
Additional information for WBS module
related to organizational structure
![Page 30: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/30.jpg)
Space Systems Engineering: System Hierarchy Module 30
Relationship Between WBS and Organization
Organizational structure for a program and/or project
usually aligns with the WBS. Although the staffing of
the functions can be addressed in a variety of ways
based on the culture and size of the organization.
Good reference on engineering organizational
structures: “Systems Engineering Management” by
Benjamin Blanchard (chapter 7)
• Matrix organization structure (section 7.3.3)
• Producer organization (combined project-functional structure)
(section 7.3.4)
Examples:
• Exploration Systems (see next chart)
![Page 31: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/31.jpg)
Space Systems Engineering: System Hierarchy Module 31
Organizational Structure for Exploration
Suppliers
National
Subcontractor
National
Prime Contractor
Lockheed-Martin
National
Service Module
GRC
Ohio
Launch Escape
System
LaRC
Virginia
Non-Prime
(in-house) work
CEV/Orion Project Office
JSCHouston, TX
Ares 1 Launch Vehicle Project Office
MSFCHuntsville, AL
Launch Systems Project Office
KSCFlorida
Constellation Program Office
Johnson Space Center (JSC)
Houston, TX
NASA Headquarters
Exploration Systems Mission Directorate
Washington, DC
Level 1
Level 2
Level 3
Level 4
Example for NASA human spaceflight effort.
Reflects derivation of authority from HQ to
Program to Projects.
Requirements flow in same top-down direction.
![Page 32: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/32.jpg)
Space Systems Engineering: System Hierarchy Module 32
Organizational Structure of Level 2 Box
![Page 33: System Hierarchy and Work Breakdown Structure Modulesmslab.kaist.ac.kr/Course/CC532/2012/LectureNote/2012/W4-1. Sys... · System Hierarchy and Work Breakdown Structure Module Space](https://reader030.vdocuments.us/reader030/viewer/2022020121/5ca3e80788c993fb118bd237/html5/thumbnails/33.jpg)
Space Systems Engineering: System Hierarchy Module 33
SE&I Director Chris Hardcastle
Deputies Charlie Lundquist-Transition & Integration
David Petri – Planning & Performance
CoS Organization Jason Weeks (A)
Secretary-Tina Cobb (C) Secretary-LaNell Cobarruvias (C)
Constellation Program Systems Engineering & Integration (SE&I)
SE&I Offices, CxP Offices & Center SE&I Focals
Technical Staff CoST/CxAT Focal - John Baker (M)
Chief Architect: Bret Drake** Verification: John Kennedy
SIP/Time Phased Capability: Keith Williams Avionics & SW: Jeff Stephenson
Horizontal Integration TBD/Tracy Hom
Vertical Integration
Burt Laws/ Steve Meacham (M)/
Renee Cox (M)
Supportability/Operability/Affordability Kevin Watson/TBD
Level I & Level 3 Projects
SW & Avionics Integration Office Chief: Monte Goforth Deputy: Don Monell
CSCP/M&SWG
DSILWG
Analysis, Trades & Architecture
Chief: Neil Lemmons Chief: Dave Forrest (A) Deputy: Deb Ludban (A)
AWG
Process, Requirements & Interface Mgt Office
Chief: Michele DiGiuseppe
Deputy: Debbie Korth
RICWG
PSE Office
CxAT
Jerry Hill (M) - Ares 1-X SE&I Interface & SERP Rep
* = Technical Mgr for all MSFC Level II Program SEI activities in support of SE Office Chiefs. ** = Post LAT 2 Team Assignment M = Matrixed A = Acting C = Contractor
Steve Meacham (M) -Technical Mgr Integ. MSFC*
Program Technical Integration
Chief: Margarita Sampson Deputy: Nancy Srb
Deputy: Kerri Knotts **
PTI Forum
ZF211
ZF111
ZF311 ZF411 ZF511
In these Numbers: Partial funding provided by NASA HQ & some Procurement S (converted to Eps here) ALL to be scrubbed as apart of Pending PPBE/ITA revision
SECB