Transcript
Page 1: Steve Wake earned value sets you free

Steve WakeEarned Value Sets You Free

maybe.

Page 2: Steve Wake earned value sets you free

What do we all want our projects to do?

Page 3: Steve Wake earned value sets you free

SUCCEED!

Page 4: Steve Wake earned value sets you free

How many projects failin the uk?

Page 5: Steve Wake earned value sets you free
Page 6: Steve Wake earned value sets you free

What is a project failure?

Page 9: Steve Wake earned value sets you free
Page 10: Steve Wake earned value sets you free
Page 11: Steve Wake earned value sets you free
Page 13: Steve Wake earned value sets you free

Politics is the art of the possible.And so is project management.Focus on what you can influence.

Page 14: Steve Wake earned value sets you free

14

StakeholdersEnablersDisablers

Who is?

SponsorCompetitionCustomerProject ManagerChampionHealth and SafetyRival team

Remember this from PMI Portugal 2003?

Page 15: Steve Wake earned value sets you free

What can we do?

Page 16: Steve Wake earned value sets you free

Pay attentionThis is the only slide with any practical

advice!

Project Management nearly always appears on the WBS.It is normally shown as level of effort (NVA)

RENAME that WBS box “COMMUNICATIONS”.Define them as with any other deliverable.Place these communications on the schedule.And Project Manage them.The reason we communicate poorly is because it’s not in

the plan!

Page 17: Steve Wake earned value sets you free

Can I go home now?

Page 18: Steve Wake earned value sets you free

What makes a successful project?

Page 19: Steve Wake earned value sets you free

Widespread agreement that it is a success

Page 20: Steve Wake earned value sets you free

What is the reality of Consensus?

Page 21: Steve Wake earned value sets you free

What is success for us?

Realisation of the benefits.Financial and/or Social.Commonly agreed.Even if you are not a beneficiary.

Page 22: Steve Wake earned value sets you free

How do we do this with projects?

Page 23: Steve Wake earned value sets you free

We clearly define the benefits.

primeiro

Page 24: Steve Wake earned value sets you free

segundoWe Program the changes requiredto achieve the benefits.

Page 25: Steve Wake earned value sets you free

terceiroWe clearly define the projects needed to achieve the changes.

Page 26: Steve Wake earned value sets you free

What have I just described?

Page 27: Steve Wake earned value sets you free
Page 28: Steve Wake earned value sets you free

The Problem with P3

• We just don’t do it!(properly).• Projects are created without reference to

benefit.• Portfolios do not retain their dynamic links with

the projects they created.• The Board and senior management just look at

the Portfolio and assume the links with the project are there.

Page 29: Steve Wake earned value sets you free

The Result is project failure

Lots of effort. No result.

Page 30: Steve Wake earned value sets you free

Portfolios today are generally houses built on sand,and that is why projects continue to fail.

Page 31: Steve Wake earned value sets you free

We live in a world where we accept this as normal behaviour

Page 32: Steve Wake earned value sets you free

We lie or cheat to win business

Page 33: Steve Wake earned value sets you free

We have to decide who we are

or

Page 34: Steve Wake earned value sets you free

We must become Professional

In English Professional can mean ,Someone who acts with integrity.Someone who is mercenary and cynical.

Page 35: Steve Wake earned value sets you free

Integrity 1

Page 36: Steve Wake earned value sets you free

Integrity 2

Page 37: Steve Wake earned value sets you free

Integrity 3

Page 38: Steve Wake earned value sets you free

Interestingly for leaders

Page 39: Steve Wake earned value sets you free
Page 40: Steve Wake earned value sets you free

We have to become trusted for the accuracy and reliability of the data under our control.ThenManagement can manage.

Page 41: Steve Wake earned value sets you free

But always remember…

there are some you can never trust!

Page 42: Steve Wake earned value sets you free

What is Project Management?

Page 43: Steve Wake earned value sets you free

Cost Time ScopeQualityTo Budget

Page 44: Steve Wake earned value sets you free

What is the best project management

can do?

Page 45: Steve Wake earned value sets you free
Page 46: Steve Wake earned value sets you free

Status

•It tells us where we are•How much we’ve done

Page 47: Steve Wake earned value sets you free

How do we work out where we are?

What if we can’t?

Page 48: Steve Wake earned value sets you free

•Build a plan•Freeze the plan•Measure progress

Page 49: Steve Wake earned value sets you free

1. DEFINE THE WORK SCOPE

2. SCHEDULE THE WORK

3. ALLOCATE BUDGETS TO SCHEDULE

EVM: Performance Measurement Baseline

100

40

60

80

PMB

PMB

TIME

£

CONTRACT BUDGET BASE

MR

Page 50: Steve Wake earned value sets you free

0

500

1000

1500

2000

2500

3000

J F M A M J J A S O N D J F M A M J J A S O N D J F

Actual Costs

Budget (Plan) Reporting Cut-off Date

Where are we?

?

Total Project Budget

Page 51: Steve Wake earned value sets you free
Page 52: Steve Wake earned value sets you free

•Build a plan and baseline it.

•Calculate physical progress

Page 53: Steve Wake earned value sets you free

Physical progress

•How much do I want to spend?•How much have I spent?•What have I got to show for it?

Page 54: Steve Wake earned value sets you free

0

500

1000

1500

2000

2500

3000

J F M A M J J A S O N D J F M A M J J A S O N D J F

Work Performed (Earned Value)

Actual Costs

Budget (Plan)Reporting Cut-off Date

Cost Variance

Schedule Variance(Currency)

What does this tell us?

Total Project Budget

Page 55: Steve Wake earned value sets you free

• I planned to spend £1300• I spent £1500• I’ve achieved £1100• I am completing 73p of work for every £1 planned.• It is costing me £1.36 to earn £1of work.

Page 56: Steve Wake earned value sets you free

The Earned Value line

• Is an additional line• Tracks physical completeness. What has been done.• It should not be treated as a discretionary add-on.• It is not possible to manage a project well without it.• And yet some project managers say they don’t need

earned value.

Page 57: Steve Wake earned value sets you free

Earned Value is the best way to determine the status of a project.And yet….

Page 58: Steve Wake earned value sets you free

If you don’t know where you are.

How do you manage?

Page 59: Steve Wake earned value sets you free

If a portfolio manager does not know the true status of the projects which drive the portfolio.

Is this OK?

Page 60: Steve Wake earned value sets you free
Page 61: Steve Wake earned value sets you free

Earned Value sets you free

Because• With poor status data your job is to fix and defend the

data.• With good status data you and your stakeholders can

make good solid management decisions.• Earned value is not a miracle but it does make good

managers better.

Page 62: Steve Wake earned value sets you free

EVOr notEV?

Page 63: Steve Wake earned value sets you free

Conclusion

• If project managers focus on becoming professionals with integrity they will always be part of the solution.

• Earned Value status provides the firm foundations portfolios need for effective delivery of benefits.

• If project managers remain ‘pragmatic’ then projects will continue to fail at 73%. And project managers along with their stakeholders will continue to perpetuate the mess this planet and its macro economy is in now and for the foreseeable future.

Page 64: Steve Wake earned value sets you free

May 2014


Top Related