START UP FORM PACKETEvaporator
DIVISIONS OF RAE CORPORATION
4492 Hunt St. - Pryor, OK 74361 - (918) 825-7222 - Fax (918) 825-6366www.RAE-corp.com
RAE Corporation Evaporator Start-Up Form
Unit Model #: Unit Serial #:
Unit #: Evaporator Serial #:
Voltage/PH/Hz: Refrigerant:
First Day of Start-Up: Last Day of Start-Up:
Job Name: Job Street Address:
Job City: Job State and ZIP:
Century Refrigeration Technical Systems Refrigeration Systems
Equipment Installation Service Company Information:
Company Name: Company Address:
Company City: Company State and ZIP:
Maintenance & Labor Warranty Service Company Information:
Company Name: Company Address:
Company City: Company State and ZIP:
Has the unit been checked for shipping damage? Yes No
If there is any shipping damage, please list all damage in detail:
PART A - Pre Start-Up System Check:
Model #: Serial #:
Model #: Serial #:
Model #: Serial #:
Model #: Serial #:
Model #: Serial #:
Model #: Serial #:
RAE Corporation Evaporator Information (Copy page for additional units if necessary):
Voltage L1 to L2: Voltage L2 to L3: Voltage L3 to L1:
Voltage L1 to G: Voltage L2 to G: Voltage L3 to G:
Main fuse or breaker size: amps
Main Voltage Check:
Control Voltage Check:
PART B - Start-Up:
Voltage H to N: Voltage H to G: Voltage N to G:
Space temperature: °F Setpoint: °F
Amount of refrigerant in system: lbs. of R- in each circuit.
Has the evaporator been checked for proper clearance?
Has all piping been thoroughly leak checked? Yes No
Has all field connected main power and control wiring been completed and checked? Yes No
Has a grounded conductor been installed from the main panel to earth ground? Yes No Has the unit been solidly mounted to the mounting structure? Yes No
Has the unit been charged with the proper refrigerant? Yes No
If hot gas bypass is used, what is it set at?
What percentage of load was available at start-up?
If a VFD is used, what are the basic settings on the VFD, and/or what was changed on the VFD during start-up and why? N/A
Safety Check:Have evaporator overloads been verified correct? Yes No N/A
Settings: #1 #2 #3 #4Has the evaporator been verified as functional with even refrigerant distribution? Yes No
Is evaporator drain line trapped outside of box? Yes No
Is the evaporator drain line sloped 1/2” per foot? Yes No
Yes No
Are all evaporators individually trapped? Yes No
Area all drain lines heated and insulated in sub-freezing spaces? Yes No
Controller Check:Are controllers labeled and correspond to the diagram? Yes No N/A
Was a program downloaded in the field? Yes No N/A
If program was field downloaded, what version was used?
Have controllers been scrolled through line by line ensuring that all transducers, sensors, inputs and outputs read correctly? Yes No N/A
List any fields not reading correctly:
Have all changes to any parameter been documented? Yes No N/A
List any parameters or settings that were changed:
Have all adjustable refrigeration valves been adjusted appropriately? Yes No N/A
Which valves were adjusted?
Evaporator Model # Evaporator Serial # Fan Amps/leg Defrost Amps/leg Superheat
/ / / / °F
/ / / / °F
/ / / / °F
/ / / / °F
/ / / / °F
/ / / / °F
Ambient Temperature: °F Design Suction Temperature: °F
Design Box Temperature: °F Thermostat Setting: °F
Defrost Setting 1: /day Clock Fail-Safe:
Defrost Setting 2: /day Clock Fail-Safe:
Compressor Discharge Pressure: PSIG Compressor Discharge Pressure: PSIG
Compressor Suction Pressure: PSIG Compressor Suction Pressure: PSIG
Suction Line Temp. at Compressor: °F Suction Line Temp. at Compressor: °F
Superheat at Compressor: °F Superheat at Compressor: °F
Suction Line Temp. at Evaporator: °F Suction Line Temp. at Evaporator: °F
Superheat at Exaporator: °F Superheat at Exaporator: °F
System Data:
Other:
Does any work need to be completed on the unit after start-up? Yes No
Please list any additional work in detail:
Start-Up Notes:
Start-up performed by (Print):
Start-up performed by (Signature):
Date:
To validate equipment parts warranty, return completed form within (10) day of start-up to:RAE Corporation
Attn: Service Department4492 Hunt St.
Pryor, OK 74361(918) 825-7222
Contact Phone Number: Contact Email:
4492 Hunt St. - Pryor, OK 74361 - (918) 825-7222 - Fax (918) 825-6366
www.rae-corp.com
Bulletin# EVAP-START UP-0518