Download - SSR 4504BU Pulai Heights Rev B
Document No
1/001 53-IPA 458 9397 UenDate Rev.
B
IPOH
4504BU PULAI HEIGHTS
SUB REGION: xxxx
XXXXXX
2010-03-18
DiGi 3G PHASE 3A
TECHNICAL SITE SURVEY REPORT
GENERAL INFORMATIONPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1095-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
ABSTRACT
This report consists of the following documents:
Document Document number Revision
Site Survey Report 1/001 53-IPA 458 9397 Uen BG l I f ti 1095 IPA 458 9397 U B
For the different activities and their responsibilities, not mentioned in this document, refer to the contractual document between DiGi Telecommunications Sdn. Bhd and Ericsson (M) Sdn Bhd in the Supply and Installation Agreement section.
2010-03-18
The aim of this report is to provide the basis for a mutual agreement between DiGi Telecommunications Sdn. Bhd and Ericsson (M) Sdn Bhd regarding the final design of the Radio Base Stations for Digi GSM 2G/WCDMA 3G. (The plant specification is excluded from the agreement. It's only included as information to Digi)
General Information 1095-IPA 458 9397 Uen BSituation Plan 153 38-IPA 458 9397 Uen AConfiguration Data 1/127 04-IPA 458 9397 Uen AFloor Plan Drawing 193 05-IPA 458 9397 Uen ACable Way Drawing 193 24-IPA 458 9397 Uen AAntenna Placement Information 153 12-IPA 458 9397 Uen BSite Photos 1/2883-IPA 458 9397 Uen BObstacle Diagram 2/2883-IPA 458 9397 UenPlant Specification A
Revision History
Rev A First IssueRev B Second Issue
GENERAL INFORMATIONPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1095-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Summary of Digi responsibilities before installation of Ericsson's scope of workFor details please refer to the rest of the Site Survey Report
RBS/Node BPreparation of the site, for equipment delivery: Yes NoNew DC rectifier Yes NoNew ACPDB (RBS 6201 & RBS 3418) Yes NoNew Fuses Yes NoNew DDF Yes NoTransmission to Site Yes NoOther: Yes, listed below No
Site AccessIs site location information provided adequate? Yes NoKeys: List any entry issues
√√
√
√√
√
√√
List any entry issues.
Antenna SystemPreparation of the site, due to security issues. Yes NoOther: Yes, listed below No
Safety HazardsRooftop/Tower is secured enough for TI works Yes NoAny water leakage on rooftop/cabin Yes NoAir Conditioning Faulty / High Temperature inside Cabin Yes NoRectifier/Batteries are safe enough for power termination Yes NoOther:
√√
√√
√√
SITUATION PLANPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 153 38-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
Address: 27A, Persiaran sengat Baru 2Tmn Bersatu, 31300 Ipoh Perak
Geographical coordinates:Map Datum: WGS 84
N 4.54720° E 101.11973°
2010-02-09
Crane/Sky lift: NODetails :
4504BU PULAI HEIGHTS
CONFIGURATION DATAPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/127 04-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
1 GENERAL
1.1 Survey date
1.2 Ericsson Survey Participants Yicky Leong 019-2211843Elson Chua 012-3982910Lau Weng Hong 019-2065817
1.3 Type of Site
1.4 Type of building1.4.1 Height of building (m.a.g.l.)
1.5 Type of Tower / Mast Monopole1.5.1 Tower / Mast height (m.a.g.l.)
1.6 RBS location Outdoor RBS1.6.1 Material Ceiling N/A
Wall N/AFloor N/A
2 NODE B RBS TECHNICAL DATA
2.1 No. of sector 3
N/A
45m
N/A
2010-02-09
20101-02-02
Outdoor Monopole
2.1 No. of sector 32.2 No. and type of Radio Cabinets 1, RBS 3418 ( 1 Main Unit, 3 x RRUW)2.3 Hardware configuration per cabinet 3x22.4 Radio Configuration (on air) 3x12.5 No. of Channel Elements 962.6 No. of E1 ports N/A (LAN connection)2.7 No of connected E1's 52.8 EACU Yes/No2.9 Access Mode IP / ATM
3 FLOOR LOAD3.1 RBS cabinet (kg) MU@ 25Kg , RRUW@20kg
4 ELECTRICAL DATA4.1 Rectifier Make/Model Propose Eltek TRM4.1.1 V Out -53.5V4.1.2 Rectifier Capacity (Modules), A 120A4.1.3 Capacity Output, A 50A4.1.4 Load, % 35%4.1.5 Required Breakers 1 x 80A4.1.6 Battery capacity (aH) 150aH4.1.7 Year installed for battery4.1.8 Number of battery bank 2
4.2 ADDITIONAL INFORMATION{Survey captured for both equipment (RBS 3418 & 6601)}
2005
CONFIGURATION DATAPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/127 04-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
5 ANTENNA SYSTEM 2G
5.1 EXISTING ANTENNA 2G5.1.1 Antenna height (m.a.g.l..)5.1.2 Antenna Azimuth5.1.3 Antenna Mechanical Tilting5.1.4 Antenna Electrical Tilting5.1.5 No. of antennas (pcs)
5.1.6 Vendor/Model of antenna5.1.7 Type of antennas
5.1.8 Antenna Support
5.1.9 Support Leg Size
5.2 EXISTING FEEDERS 2G5.2.1 Type of feeder5.2.2 Feeder length, m
(If need to relocate Antenna)5.2.3 Jumper Length, m
(If need to relocate Antenna)
5.3 ADDITIONAL INFORMATION
Single Band
Monopole Boom
45
Boom @ 2m
72mm
7/8"
33 3
7/8"45 45
RFS
Single Band
Monopole Boom
72mm
Boom @ 2m
7/8"
72mm
Boom @ 2m
Single Band
Monopole Boom
Sector 2
110°
Sector 3
37 37 37
10°
Sector 1
50° 200° 290°0° 0° 0°
0°
APX18-206512-T0RFS RFS
APX18-206512-T0 APX18-206512-T0
CONFIGURATION DATAPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/127 04-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
6 ANTENNA SYSTEM
6.1 PROPOSED ANTENNA 3G6.1.1 Antenna height (m.a.g.l..)6.1.2 Antenna Azimuth6.1.3 Antenna Mechanical Tilting6.1.4 Antenna Electrical Tilting6.1.5 No. of antennas (pcs)
6.1.6 Vendor/Model of antenna6.1.6.1 Type of antennas
Dual Band Dual Band
6.1.7 Antenna gain6.1.8 Antenna dimensions (mm)6.1.9 Max. wind load @ 42m/s (frontal)6.1.10 Weight of antennas (kg)6.1.11 Antenna Support
6.1.12 P-TMA Qty
6.2 PROPOSED FEEDERS6.2.1 Type of feeder6.2.2 Feeder length (unit x length)
0 0
N/A
0
New Boom
N/AOIL OIL OILN/A
Boom @ 2.5m Boom @ 2.5mNew Boom
0°50° 290°
Sector 1 Sector 2
742 236 742 236
16.5 kg
Sector 3
37.0
1 1 1
0° 0°+6° (3G) / 0° (2G) +6° (3G) / 0° (2G)
16.5 kg
17.8dBi1319 / 323 / 71
Dual Band
Kathrein
16.5 kg
742 236
37.037.0
Kathrein Kathrein
600N
200°
+6° (3G) / 0° (2G)
17.8dBi1319 / 323 / 71600N
17.8dBi1319 / 323 / 71
Boom @ 2.5m
600N
New Boom
g ( g )6.2.3 Weight of feeder (kg/m)6.2.4 Min. bending radius (mm)6.2.5 Antenna jumper6.2.6 ASC jumper
6.2.8 *OIL Feeders6.2.8.1 Feeder length (unit x length)
* OIL= Optical Interface Link OIL Type = Single Mode Fiber (G.652)
6.2.9 DC Power Cable for RRUW 6.2.9.1 Cable length (unit x length)
6.3 ADDITIONAL INFORMATION
0 0 02 x 6m
200N/A
200N/A N/A2002 x 6m
1 x 50m
2 x 6m
1 x 50m1 x 50m
1 x 50m 1 x 50m1 x 50m
CONFIGURATION DATAPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/127 04-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
7 QUALIFICATION SUMMARY
Yesxx
x
* if no for above, please insert comments below.
Comments:1) 3G S1 = Sector 1- Lake
2) 3G S2 = Intended to cover Main Road & housing area
3) 3G S3 = Intended to cover Main Road & housing area
x
Are there enough space for feeder cable?
Does this site need RET?(RET would be needed if the accessibility of the site is very difficult.E.g.Tower
sites,long application time for site access,need 'skylift' for site access.
NoIs there space for RBS?
Are there space for Antenna
Site ID 4504BU
Site Name PULAI HEIGHTS
Region NORTHERN ( IPOH )
ASP ECOM SOLUTIONS
UOM Request Installed Extra Faulty Ttl Return Decomm Remarks102/BFM 901290 RBS 6201 EA - - - - - - 11/COH 109 2082 RBS 3418 3 x 1 EA 1 - - - - - 11/COH 109 2082 RBS 3418 2 x 1 EA - - - - - - 11/COH 109 2082 RBS 3418 1 x 1 EA - - - - - -
ROJ1192315/1 ETMFX Card EAKRC118 42/2 RRUW (Pole Mounted) EA 3 - - - - - KRC118 42/2 RRUW (Wall mounted) EA - - - - - - TFL492324/0 DC Power for RRUW M 150 - - - - -
F4RNA-PDMDM-1M-E1 Antenna Jumper 1m (1/2" Superflex Jumper come with 2 x 7/16 straight connectors) EA - - - - - -
F4RNA-PDMDM-2M-E1 Antenna Jumper 2m (1/2" Superflex Jumper come with 2 x 7/16 straight connectors) EA - - - - - -
F4RNA-PDMDM-2M-E1 TMA Jumper 2m (1/2" Superflex Jumper come with 2 x 7/16 straight connectors) EA - - - - - -
F4RNA-PDMDMR-3M-E1 Node B Jumper 3m (1/2" Super flex jumper come with 1 side 7/16 Din right angle & 1 side with 7/16 Straight connector) EA - - - - - -
F4RNA-PDMDM-2M-E1 RRUW Jumper 2m (1/2" Superflex Jumper come with 2 x 7/16 straight connectors) EA - - - - - -
F4PDMV2-C Connector, 7/16 Male for 1/2" Superflex Feeder EA 12 - - - - - 78EZDF 7/8 connector EA - - - - - -
158EZDF 1 5/8" connector EA - - - - - - FSJ4-50B 1/2" Superflex M 36 - - - - - FXL-780 7/8" Feeder Cable (Aluminum) M - - - - - -
FXL-1873 1 5/8" Feeder Cable (Aluminum) M - - - - - - SG78-06B2A 7/8" Grounding Kits EA - - - - - -
SG158-06B2A 1 5/8" Grounding Kits EA - - - - - - 860 10045 RCU EA 3 - - - - - 860 10008 RCU Cable 2m EA - - - - - - 860 10029 RCU Cable 3m EA - - - - - - 860 10010 RCU Cable 10m EA 3 - - - - - 860 10011 RCU Cable 25m EA - - - - - -
742 215 Antenna 742 215 EA - - - - - - 742 236 Antenna 742 236 EA 3 - - - - - 742 265 Antenna 742 265 EA - - - - - - 742 272 Antenna 742 272 EA - - - - - -
KRY 112 144/1 P-TMA EA - - - - - - KRC 115 032/1 RIU EA - - - - - -
RPM2533577/20M OIL cable 20M EA - - - - - -
Material No. Item DescriptionQty
RPM2533577/50M OIL cable 50M EA 3 - - - - - RPM2533577/70M OIL cable 70M EA - - - - - -
RPM2533577/100M OIL cable 100M EA - - - - - - Eltek 10A Eltek Breaker 10A EA 1 - - - - - Eltek 32A Eltek Breaker 32A EA 3 - - - - - Eltek 50A Eltek Breaker 50A EA
Eltek 100A Eltek Breaker 100A EA - - - - - - Eltek 150A Eltek Breaker 150A EA - - - - - -
Emerson Classic 10A Emerson Breaker 10A EA - - - - - - Emerson Classic 32A Emerson Breaker 32A EA - - - - - - Emerson Classic 50A Emerson Breaker 50A EA
Emerson Classic 100A Emerson Breaker 100A EA - - - - - - Emerson Classic 150A Emerson Breaker 150A EA - - - - - - Emerson Modern 10A Emerson Breaker 10A EAEmerson Modern 32A Emerson Breaker 32A EAEmerson Modern 50A Emerson Breaker 50A EA
Emerson Modern 100A Emerson Breaker 100A EAEmerson Modern 150A Emerson Breaker 150A EA
19" Rack 19" Rack EA - - - - - - EACU EACU EA
Triplexer Triplexer EA - - - - - - Dummy Load Dummy Load EA - - - - - - F4PDMV2-C Connector, 7/16 Male for 1/2" Superflex Feeder (2G) EA 12 - - - - -
78EZDF 7/8" Connector (2G) EA - - - - - - 158EZDF 1 5/8" Connector (2G) EA - - - - - - FSJ4-50B 1/2" Superflex (2G) M 24 - - - - - FXL-780 7/8" Feeder Cable (Aluminum) (2G) M - - - - - -
FXL-1873 1 5/8" Feeder Cable (Aluminum) (2G) M - - - - - - SG78-06B2A 7/8" Grounding Kits (2G) EA - - - - - - SG158-06B2A 1 5/8" Grounding Kits (2G) EA - - - - - -
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09 A
Site View Location
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Site Access & Equipment Handling
Site Access & Equipment Handling
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Lorry/Crane/Skylift Suitable Parking Location
Existing GSM RBS Location
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Proposed 3G RBS Location
Proposed New Eltek Rectifier
Proposed RBS 3418
Proposed 3x32A DCBreaker for 3 units RRUWin side New Eltek Rectifier
Proposed 1x10A DCBreaker for RBS 3418 insideNew Eltek Rectifier
Proposed plinth 1000mm(W)x1000mm(D)x150mm(H) for new Eltek TRM
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Existing DDF Location
AC Distribution Panel
Proposed 1 x32A 3phase 3 pole breaker for new Eltek
Rectifier
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Propose Breaker
Proposed New Eltek Rectifier
Proposed RBS 3418
Proposed 3x32A DCBreaker for 3 units RRUWin side New Eltek Rectifier
Proposed 1x10A DCBreaker for RBS 3418 insideNew Eltek Rectifier
Proposed plinth1000mm(W) x 1000mm(D)
x 150mm (H) for Eltek TRM
Existing Baterry
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Feeder Inlet Internal
Feeder Inlet External
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Internal Grouding
External Grounding
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Proposed New 3G Antenna Sector 1 : 50 Deg
Proposed to swap existing 2G antennato new 3G antenna Kathrein 742 236(Dual band)with new RET, 2.5m sub‐boom andreuse existing bracketHeight: 37m AGLDirection: 50º
Proposed New RRUW for Sector 1
Proposed new RRUW with new 1msub‐boom and bracketHeight: 37m AGL
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Proposed Cable Route for New 3G Antenna Sector 1
Proposed OIL cablewith new 3 ‐in 1clamps
Proposed DC cablewith new 3 ‐in 1clamps
Proposed NewEltek Rectifier
Proposed new 200mm cable ladder from TRM cabinetuntil the existing cable ladder.
Proposed Cable Route for New 3G Antenna Sector 1
pEltek Rectifier
Proposed OILcable inside 50mm x 50mm HDG trunking
Proposed DCcable inside50mm x 50mmHDG trunking
Proposed HDG trunkinglay on new 200mm cable ladder.
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Proposed New 3G Antenna Sector 2 : 200 Deg
Proposed to swap existing 2G antennato new 3G antenna Kathrein 742 236(Dual band) with new RET, 2.5m sub‐boom and reuse existing bracketHeight: 37m AGL Direction: 200º
Proposed New RRUW for Sector 2
Proposed new RRUW with new 1msub‐boom and bracketHeight: 37m AGL
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Proposed Cable Route for New 3G Antenna Sector 2
Proposed OIL cablewith new 3 ‐in 1clamps
Proposed DC cablewith new 3 ‐in 1clamps
Proposed NewEltek Rectifier
Proposed new 200mm cable ladder from TRM cabinettill the existing cable ladder.
Proposed Cable Route for New 3G Antenna Sector 2
Proposed NewEltek Rectifier
Proposed OILcable inside 50mm x 50mm HDG trunking
Proposed DCcable inside50mm x 50mmHDG trunking
Proposed HDG trunkinglay on new 200mm cable ladder.
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Proposed New 3G Antenna Sector 3 : 290 Deg
Proposed to swap existing 2G antennato new 3G antenna Kathrein 742 236(Dual band) with new RET, 2.5m sub‐boom and reuse existing bracketHeight: 37m AGL Direction: 290º
Proposed New RRUW for Sector 3
Proposed new RRUW with new 1msub‐boom and bracketHeight: 37m AGL
SITE PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK B
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-03-18
Proposed Cable Route for New 3G Antenna Sector 3
Proposed New
Proposed OIL cablewith new 3 ‐in 1clamps
Proposed DC cablewith new 3 ‐in 1clamps
Proposed new 200mm cable ladder from TRM cabinettill the existing cable ladder.
Proposed Cable Route for New 3G Antenna Sector 3
Proposed NewEltek Rectifier
Proposed OILcable inside 50mm x 50mm HDG trunking
Proposed DCcable inside50mm x 50mmHDG trunking
Proposed HDG trunkinglay on new 200mm cable ladder.
EXISTING 2G PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
Existing 2G Antenna Sector 1 : 50 Deg
2010-02-09
Existing 2G Antenna Sector 2 : 200 Deg
EXISTING 2G PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Existing 2G Antenna Sector 3 : 290 Deg
Existing 2G Antenna Sector 1 Mechanical Tilt Existing 2G Antenna Sector 2 Mechanical Tilt
Existing 2G Antenna Sector 3 Mechanical Tilt
Existing 2G Antenna Sector 3 : 290 Deg
0˚0˚
0˚
EXISTING 2G PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Existing 2G Antenna Sector 1 Electrical Tilt Existing 2G Antenna Sector 2 Electrical Tilt
Existing 2G Antenna Sector 3 Electrical Tilt Existing 2G Antenna Sector 1 Label
Existing 2G Antenna Sector 2 Label Existing 2G Antenna Sector 3 Label
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Antenna View for Existing 2G System Sector 2: 200 deg.
Antenna View for Existing 2G System Sector 1: 50 deg.
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Antenna View for Existing 2G System Sector 3: 290 deg.
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
Intended Coverage was taken at proposed antenna location
Intended Coverage for 3G System Sector 2: 200 deg. Intended Coverage was taken at proposed antenna location
Intended Coverage for 3G System Sector 1: 50 deg.
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
0 degree
Intended Coverage for 3G System Sector 3: 290 deg. Intended Coverage was taken at proposed antenna location
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
30 degree
60 degree
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
90 degree
120 degree
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
150 degree
180 degree
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
240 degree
210 degree
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
270 degree
300 degree
PANORAMIC PHOTOSPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 1/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
330 degree
OBSTACLE DIAGRAMPrepared (also subject responsible if other) Subject Responsible Document No.
ECM/ECOM/LEONG 2/2883-IPA 458 9397 UenDoc respons/Approved Checked Date Rev. File
ECM/GR/B SZE CHEE KEK A
Project: Digi 3G Phase 3ASite: 4504BU PULAI HEIGHTS
2010-02-09
100m
0°
30°
60°
90°
300°
330°
270°
N
2
1
4
3
#123456
Azimuth Distance Height Description
300-340 50m
100-140 100m240-250 250m
Tree on hill.15m
260-280 50m>60m>60m>60m
HotelCondoCondo
200m
100m
0°
30°
60°
90°
120°
150°
240°
210°
180°
300°
330°
270°
N
300m
400m
500m
2
1
4
3