Soil Compaction
Topic I
Topic I
![Page 2: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/2.jpg)
Success of Embankment
• Proper preparation of foundation.
• Use of suitable materials.
• Proper placing working and compacting of materials.
Topic I
![Page 3: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/3.jpg)
Proper Preparation of Foundation
• Clear and grub area• Cut vegetation• Remove perishable material• Strip and stockpile• Compact area
Topic I
![Page 4: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/4.jpg)
Suitable Materials
• Rock• Sand• Silt• Clay• See Standard specifications list
Topic I
![Page 5: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/5.jpg)
Unsuitable Materials
• Organic soils should not be used as embankment or subgrade material.
Topic I
![Page 6: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/6.jpg)
Proper Placement and Compaction
• Placing layers
• Placing in marsh
• Placing rock
Topic I
![Page 7: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/7.jpg)
Placing Layers
• The maximum thickness of a layer should not exceed 8 inches loosely placed.
• 8 inch lifts
Topic I
![Page 8: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/8.jpg)
Placing Layers
• Compact each layer
• Level each layer
• Parallel
Topic I
![Page 9: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/9.jpg)
Placing in Marsh
• Typically in wet marsh excavations WisDOT allows for marsh backfill to be end dumped into excavation and “surged” down into the excavation with a bulldozer until above water level.
Topic I
![Page 10: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/10.jpg)
Topic I
![Page 11: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/11.jpg)
Topic I
![Page 12: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/12.jpg)
Topic I
![Page 13: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/13.jpg)
Placing Rock
• No end dumping• Bulldozed or shoved into position• Various sizes• When placing rock all voids must be filled with
finer material.
Topic I
![Page 14: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/14.jpg)
Topic I
![Page 15: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/15.jpg)
Principles of Compaction
1. Decrease future settlements
2. Increase shear strength
3. Decrease permeability
4. Increase stability
Topic I
![Page 16: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/16.jpg)
Not Achieving Compaction?Solutions
• Increase compaction effort–Compaction equipment
• Change soil moisture content–Optimum moisture content
Topic I
![Page 17: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/17.jpg)
Figure 1: Compaction Equipment
Topic I
![Page 18: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/18.jpg)
Figure 1: Compaction Equipment
Topic I
Static smooth drum roller works well for sealing subgrades after the days grading operations are complete.
Doesn’t work well on clay soils.
![Page 19: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/19.jpg)
Standard Compaction
• Embankment compaction
Topic I
![Page 20: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/20.jpg)
Special Compaction
• Density tests–Sand Cone Method–Nuclear Method
• Minimum frequency
Topic I
![Page 21: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/21.jpg)
Moisture Control
• Proper moisture conditions are essential for the efficient compaction of earth embankments. Satisfactory moisture conditions almost always are specified in relation to the optimum moisture content for a standard laboratory compaction test.
Topic I
![Page 22: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/22.jpg)
Moisture Control
• Discs for wet cohesive soils
• Blade crown on surface
• Mixed
Topic I
![Page 23: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/23.jpg)
Documentation- Cut sections
• Excavated proper grade• Frost susceptible materials• Compaction• EBS• Drainage• Proper disposal
Topic I
![Page 24: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/24.jpg)
Documentation- Embankments
• Preparation of foundation
• Soils utilized
• Placing and compacting of materials
Topic I
![Page 25: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/25.jpg)
Documentation-Entries
• Soil type• Moisture content• Layer thickness• Drying or wetting• Routing pattern
Topic I
![Page 26: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/26.jpg)
Earthwork Equipment
• Hauling• Leveling• Aerating• Compacting
Topic I
![Page 27: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/27.jpg)
Figure 2: Track Dozer
Topic I
![Page 28: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/28.jpg)
Track Dozer
• Track Dozers are not to be used as compaction equipment.
• Used to level lifts of fill.
Topic I
![Page 29: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/29.jpg)
Subgrade Care
Topic I
![Page 30: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/30.jpg)
Topic I
![Page 31: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/31.jpg)
Topic I
![Page 32: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/32.jpg)
Figure 3:Disc Drying
Topic I
![Page 33: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/33.jpg)
Disc Drying
• Drying of wet soils is necessary and can be accomplished by using graders, discs or harrows.
• Aeration of the soil• Necessary for compaction
Topic I
![Page 34: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/34.jpg)
Figure 4: Rubber Tire Dozer
Topic I
![Page 35: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/35.jpg)
Rubber Tire Dozer/Scrapers
• Hauling, Leveling and Compacting
Topic I
![Page 36: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/36.jpg)
![Page 37: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/37.jpg)
![Page 38: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/38.jpg)
![Page 39: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/39.jpg)
![Page 40: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/40.jpg)
![Page 41: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/41.jpg)
![Page 42: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/42.jpg)
![Page 43: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/43.jpg)
![Page 44: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/44.jpg)
Figure 5: Sheepsfoot Imprint
Topic I
![Page 45: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/45.jpg)
![Page 46: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/46.jpg)
Sheepsfoot Imprint
• Optimum moisture–High volume compaction
• Lower water content–Increase soil surface
• Cohesive and semi-cohesive soils
Topic I
![Page 47: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/47.jpg)
Figure 5: Motor-Grader
Topic I
![Page 48: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/48.jpg)
Motor-Grader
• Aerates and levels
• Takes out ruts
• Not for compaction
Topic I
![Page 49: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/49.jpg)
Figure 6: Solid Subgrade
Topic I
![Page 50: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/50.jpg)
Solid Subgrade
• Keeps subgrade bladed up.• Keeps ruts out.
Topic I
![Page 51: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/51.jpg)
Figure 7: Excessive Rutting
Topic I
![Page 52: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/52.jpg)
Topic I
![Page 53: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/53.jpg)
Excessive Rutting
• Material too wet• Solutions:
–Motor-grader– Tractor–Disc
Topic I
![Page 54: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/54.jpg)
Figure 8: Embankment construction
Topic I
![Page 55: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/55.jpg)
Embankment Construction Equipment
• Dozer
• Tamping Roller
• Motor-Grader
Topic I
![Page 56: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/56.jpg)
Figure 9: Dumping and Leveling
Topic I
![Page 57: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/57.jpg)
Dumping and Leveling
• Firm and unyielding support.• Prior to first lift.
Topic I
![Page 58: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/58.jpg)
Figure 10: Tamping Virbratory Roller
Topic I
![Page 59: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/59.jpg)
Tamping Vibratory Roller
• “Dry”, bony material doesn’t stick.
Topic I
![Page 60: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/60.jpg)
Figure 11: Excellent Material
Topic I
![Page 61: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/61.jpg)
Excellent Material
• Dry and granular• Some rock• Imprints stand out• Not common in WI
Topic I
![Page 62: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/62.jpg)
Figure 12: Good Conditions
Topic I
![Page 63: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/63.jpg)
Good Conditions
• Back tire of grader is not sinking.
Topic I
![Page 64: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/64.jpg)
Figure 13: Scraper End Dumping
Topic I
![Page 65: Soil Compaction Topic I. Success of Embankment Proper preparation of foundation. Use of suitable materials. Proper placing working and compacting of materials](https://reader037.vdocuments.us/reader037/viewer/2022110103/56649f165503460f94c2d0d1/html5/thumbnails/65.jpg)
Scraper End Dumping
• Pushed into wet area.–Granular material
• Seal first lift• Don’t trap unstable soil in embankment.
Topic I