Transcript

SANDAG Transnet Wetland Mitigation RFP

Presented by J. Whalen AssociatesMike Sweesy, Dudek

Verne Freeman, VFA, LLC.

Team Members• Jim Whalen, President – J. Whalen

Associates

• Rich Geisler, Vice President – J. Whalen Associates

• Verne Freeman, Owner, VFA, LLC

• Mike Sweesy, Landscape Architect, Dudek

• Frank Florez, Owner, Florez Engineering

Project Vicinity

Project Location

Previous Fire Damage

Project Overview

Preliminary Cross Section

Dollars

0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90

Months

Pay for Performance

Raw Land Purchase Easement to SDRP

Permits Completed

Payments at 33%, 66% completion.

90% full payment and endowment at completion of restoration.

Fund PermittingProcess &

Restoration Effort

February 25, 2010 Confidential

Final 10% paid upon 5yr success criteria.

Figure 1

Questions and Comments


Top Related