![Page 1: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/1.jpg)
S04 Ninfield Road Overbridge – Installation of the permanent diversion of telecoms across the bridge deck.
![Page 2: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/2.jpg)
S04 Ninfield Road Overbridge – Permanent diversion connection manholes for foul water pipes next to the bridge deck.
![Page 3: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/3.jpg)
S04 Ninfield Road Overbridge – Permanent diversion connection manholes for foul water pipes next to the bridge deck.
![Page 4: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/4.jpg)
S04 Ninfield Road Overbridge – Installation of the permanent diversion of foul water pipes through the bridge deck.
![Page 5: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/5.jpg)
S04 Ninfield Road Overbridge – Reinforced concrete lining of the abutment walls in advance of brick facing.
![Page 6: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/6.jpg)
S04 Ninfield Road Overbridge – Remedial works to reinforced concrete lining of the abutment walls.
![Page 7: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/7.jpg)
S04 Ninfield Road Overbridge – Brick faced lining of the abutment walls underway.
![Page 8: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/8.jpg)
S04 Ninfield Road Overbridge – Brick faced lining of the abutment walls underway.
![Page 9: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/9.jpg)
Looking east along the railway cutting from Glover’s Lane Bridge. Kerbs and sub-base laid.
Looking east along the railway cutting from Glover’s Lane Bridge. Kerbs and sub-base laid.
![Page 10: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/10.jpg)
Looking west along the railway cutting towards the Ninfield Road Overbridge. Kerbing and CBGM already placed.
![Page 11: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/11.jpg)
Glover’s Lane Bridge resurfaced.
![Page 12: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/12.jpg)
Glover’s Lane Bridge – Removal of scaffold foundations.
![Page 13: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/13.jpg)
Looking west along the railway cutting towards the refurbished Glover’s Lane Bridge.
![Page 14: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/14.jpg)
Looking west along the railway cutting towards the refurbished Glover’s Lane Bridge. CBGM now laid.
![Page 15: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/15.jpg)
Start of the equestrian route near Glover’s Lane Bridge under construction.
![Page 16: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/16.jpg)
Equestrian route east of the Combe Haven ford being constructed.
![Page 17: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/17.jpg)
Glover’s Roundabout – Removal of soft spot beneath east side of roundabout being excavated.
![Page 18: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/18.jpg)
Glover’s Roundabout – Connecting in to the NEBGR spine road.
![Page 19: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/19.jpg)
S07 Combe Haven Underbridge – Preparing for bridge deck surfacing and verge works.
![Page 20: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/20.jpg)
Arrival of the Cement Bound Granular Material (CBGM) batching plant.
![Page 21: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/21.jpg)
CBGM batching plant in full production.
![Page 22: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/22.jpg)
S09 Watermill Stream Underbridge – Preparing western wing wall and deck stringcourse concrete pours.
![Page 23: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/23.jpg)
Cement Bound Granular Material laying trial.
![Page 24: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/24.jpg)
1.2Km of Cement Bound Granular Material laid to Southbound lane viewed from Glover’s Roundabout.
![Page 25: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/25.jpg)
Cement Bound Granular Material being laid to the Northbound lane viewed from Acton’s cut.
![Page 26: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/26.jpg)
Greenway – Construction underway east of Acton’s Farm. Equestrian route is on left hand side.
![Page 27: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/27.jpg)
Greenway – Construction underway east of Acton’s Farm. Equestrian route is on right hand side.
![Page 28: S04 Ninfield Road Overbridge – Installation of the ... · Title: Bexhill to Hastings Link Road - Progress Photographs July to August 2015 Author: Bob Pape Subject: Project Board](https://reader030.vdocuments.us/reader030/viewer/2022041015/5ec75f8e236dc135c330aa48/html5/thumbnails/28.jpg)
Greenway – View from the Acton’s Farm section.