Transcript

Research ArticleEngineering Change Orders Design Using Multiple VariablesLinear Programming for VLSI Design

Yu-Cheng Fan Chih-Kang Lin Shih-Ying Chou Chun-Hung WangShu-Hsien Wu and Hung-Kuan Liu

Department of Electronic Engineering National Taipei University of Technology Taipei 10608 Taiwan

Correspondence should be addressed to Yu-Cheng Fan skystarntutedutw

Received 7 June 2014 Accepted 18 July 2014 Published 24 August 2014

Academic Editor Chih-Cheng Lu

Copyright copy 2014 Yu-Cheng Fan et al This is an open access article distributed under the Creative Commons Attribution Licensewhich permits unrestricted use distribution and reproduction in any medium provided the original work is properly cited

An engineering change orders design using multiple variable linear programming for VLSI design is presented in this paper Thisapproach addresses themain issues of resource between spare cells and target cellsWe adopt linear programming technique to planand balance the spare cells and target cells to meet the new specification according to logic transformation The proposed methodsolves the related problem of resource for ECO problems and provides a well solution The scheme shows new concept to managethe spare cells to meet possible target cells for ECO research

1 Introduction

Engineering change orders (ECO) are important technolo-gies used for changes in integrated circuit (IC) layout andcompensate for design problems Traditionally when chipshows errors it often requires new photomasks for all layersHowever photomasks of deep-submicron semiconductorfabrication process are very expensive In order to savemoney ECO technology modifies only a few of the metallayers (metal-mask ECO) to reduce the cost of photomasksfor all layers [1]

To perform the ECO IC designers adopt sprinklingmanyunused logic gates during IC design flow When chip ismanufactured and shows design errors IC designers modifythe gate-level net-list using the presprinkling unused logicgates At the same time the designers track and verify themodification to check formal equivalence after ECO processThe designers must guarantee the revised design matchingthe revised specification

How to achieve ECO efficiently There are some litera-tures that address this problem and provide related solutionIn literature [2] Tan and Jiang describe a typical metal-only ECO flow with four steps that include placement andspare cell distribution logic difference extraction metal-only

ECO synthesis and ECO routing [2] Kuo et al insert sparecells with constant insertion for engineering change anddescribe an iterative method to determine feasible mappingsolutions for an EC problem [3] Besides in order to per-form ECO efficiently literature [4ndash9] adopt minimal changeEC equations automatically Brand proposed incrementalsynthesis method [4] Huang presented a hybrid tool forautomatic logic rectification [5] Lin et al addressed logicsynthesis techniques for engineering change problems [6]Shinsha et al performed incremental logic synthesis throughgate logic structure identification [7] Swamy et al achievedminimal logic resynthesis for engineering change [8]Watan-abe and Brayton presented another kind of incrementalsynthesis technique for engineering changes [9] Howeverfew researchers discuss the resource between spare cells andtarget cells Therefore in order to solve the problems weadopt linear programming technique to plan and balance thespare cells and target cells in this paperThe proposed schememeets the new specification according to logic transformationand overcomes the related problems of resource for ECOresearch

This paper is organized as follows In Section 2 weaddress typical ECO design flow In Section 3 logic trans-formation is discussed In Section 4 multiple variables linear

Hindawi Publishing CorporationVLSI DesignVolume 2014 Article ID 698041 5 pageshttpdxdoiorg1011552014698041

2 VLSI Design

Old net-listECONew registertransfer level

ECO New net-list

ECO editing

Old registertransfer level

Logic synthesis DFT Placement

and routing

Figure 1 A typical ECO design flow

Find out patch logic

Mapped patch logic

Patch logic

MappingAvailable spare cell list

Equivalent and timing check

Figure 2 Two-phase ECO design flow

programming for VLSI design is presented In Section 5 wediscuss the advantage and disadvantage of the related worksFinally we conclude this paper in Section 6

2 Typical ECO Design Flow

Before describing the proposed method we address a typ-ical manual ECO design flow in Figure 1 IC designersperform the change in register transfer level and verifyfixed code matching the new specification at first Thenold net-list is scanned to search the possible fix pointsAfter the possible fix points are searched IC designersmodify the net-list and check the functionally equiva-lent between new net-list and new register transfer level[10ndash14]

Next we describe two-phase ECOdesign flow in Figure 2To patch the logics of the modified circuit we prepareavailable spare cell list According to logic function themodified circuit is mapped to specified logics After patchinglogic equivalent check and timing check are performed tomake sure that the new function met the new specification

However there are some important problems that appearduring patching logic Are there enough spare cells and typesto satisfy the consumption of patch logic How to estimatethe quantity and logic types of ECO procedure In orderto solve this problem we proposed an engineering changeorders design using multiple variables linear programmingfor VLSI design in this paper

3 Logic Transformation

Before discussing the engineering change orders designusing multiple variables linear programming we addressedECO logic transformation Figure 3 describes an ECO prob-lem with an equation out = (119860 + (119861119862)1015840)1015840 Figure 3(b) liststhe available spare cells According to the list we discoverthe available spare cells are not enough In order to solvethe problem we adopt another mapping solution with anequation out = (1198601015840119861119862) instead of the original equation inFigure 3(c) It requires one AND and one INV gate Themapping solution in Figure 3(c) requires gates fewer thanthe available spare cells and is constructed with the availablespare cells

However most of spare cells only provide basic logicalfunctions that include AND OR NOT NAND and NORHalf Adder (HA) Full Adder (FA) And-Or-Inverter (AOI)and Or-And-Inverter (OAI) can provide complex logicalfunctions We can adopt these logical cells to perform ECOfunction For example AOI22 can be implemented by twoNAND and one AND cells in Figure 4 According to theexisting resources of spare cells we can resynthesize thechanged function lists

4 Multiple Variables Linear Programming forVLSI Design

Although logic transformation skill makes the ECO technol-ogy come true a chip often does not own enough spare cellsto modify the function to meet a new specification Howto allocate limited resource We should estimate quantity ofspare cells and logic transformation rule to perform optimalengineering charge orders

In Figure 5 it describes the engineering change ordersdesign using multiple variables linear programming for VLSIdesign and relation of logic transformation ldquoLogic 119860rdquo is onekind of spare cells that can be transformed into ldquoLogic 119886rdquoor ldquoLogic 119887rdquo Similarly ldquoLogic 119861rdquo can be transformed intoldquoLogic 119886rdquo ldquoLogic 119887rdquo or ldquoLogic 119888rdquo ldquoLogic 119862rdquo performs ECOfunction instead of ldquoLogic 119888rdquo or ldquoLogic 119889rdquo Besides Logic119863 istransformed into ldquoLogic 119888rdquo or ldquoLogic 119889rdquo Equivalently ldquoLogic119864rdquo is transformed to ldquoLogic 119889rdquo or ldquoLogic 119890rdquo to achieve ECOfunction

We assume 1198831 1198832 1198833 1198834 and 119883

5are the number of

spare cells Logic 119860 Logic 119861 Logic 119862 Logic 119863 and Logic 119864Let 1198841 1198842 1198843 1198844 and 119884

5be the desired number of target

cells Logic 119886 Logic 119887 Logic 119888 Logic 119889 and Logic 119890Besides 119860119886 is the number of spare cells (Logic 119860) to

be transformed into Logic 119886 and 119860119887 is the number of sparecells (Logic 119860) to be transformed into Logic 119887 Similarly119861119886 119861119887 and 119861119888 are the number of spare cells (Logic 119861) tobe transformed into Logic 119886 Logic 119887 and Logic 119888 In a similarway 119862119888 and 119862119889 are the number of spare cells (Logic 119862) tobe transformed into Logic 119888 and Logic 119889 119863119888 and 119863119889 are thenumber of spare cells (Logic119863) to be transformed into Logic119888 and Logic 119889 and 119864119889 and 119864119890 are the number of spare cells(Logic 119864) to be transformed into Logic 119889 and Logic 119890

VLSI Design 3

A

A

B

C

BC

(a)

Type Spare cellsAND 2OR 2INV 1

NAND 1

(b)

A

B

C

A

(c)

Figure 3 Example of an ECO problem (a) EC equation output = (119860 + (119861119862)1015840)1015840 (b) Spare cells (c) Mapping output = (1198601015840119861119862)

(a) (b)

Figure 4 AOI22 can be implemented by two NAND and one AND cells

X1

Y1

X2

Y2

X3

Y3

X4

Y4

X5

Y5

Logic A

Logic B

Logic C

Logic D

Logic E

Logic a

Logic b

Logic c

Logic d

Logic e

Aa

Ab

Ba

Bb

Bc

Cc

Cd

Dc

Dd

Ed

Ee

Figure 5 ECO design using multiple variables linear programmingfor VLSI design and relation of logic transformation

Therefore the restriction rule of the number of spare cellsand transformed target cells in Figure 5 is written as follows

1198831= 119860119886 + 119860119887

1198832= 119861119886 + 119861119887 + 119861119888

1198833= 119862119888 + 119862119889

1198834= 119863119888 + 119863119889

1198835= 119864119889 + 119864119890

(1)

Besides the restriction rule of the engineering changeorders design usingmultiple variables linear programming inFigure 5 is written as follows

119860119886 + 119861119886 ≧ 1198841 (2)

119860119887 + 119861119887 ≧ 1198842 (3)

119861119888 + 119862119888 + 119863119888 ≧ 1198843 (4)

119862119889 + 119863119889 + 119864119889 ≧ 1198844 (5)

119864119889 + 119864119890 ≧ 1198845 (6)

However spare cells are not often enough designershould balance the spare cell allocation to meet all require-ments of desirable cells

We assume one case when 119861119887 ≦ 1198842 In order to provide

enough spare cells we should increase the number of 119860119887 toachieve 119860119887 + 119861119887 ≧ 119884

2

Similarly when 119862119888 + 119863119888 ≦ 1198843 we should increase 119861119888

number to meet 119861119888 + 119862119888 + 119863119888 ≧ 1198843

Therefore we define another restriction rule of the engi-neering change orders design which is written as follows

119860119886 = 1198831minus 119860119887

119861119886 = 1198832minus 119861119887 minus 119861119888

(7)

4 VLSI Design

Table 1 ECO methods comparison

Method Traditional ECO Proposed methodCell resource prediction Constraint based Multiple variables linear programmingPredictive precision of patching logic number Normal precision High precisionBalance between spare cells and target cells Low balance High balanceRestriction rule Not define DefineResource optimization Not define DefineSolution boundary Not define Define

According to formulas (2) and (7) we can balance thenumber of 119860119887 119861119887 and 119861119888 to achieve the target number 119884

1

Consider the following

1198831minus 119860119887 + 119883

2minus 119861119887 minus 119861119888 ≧ 119884

1 (8)

In a similar way we define the restriction rule of theengineering change orders design which is written as follows

119861119888 = 1198832minus 119861119886 minus 119861119887

119862119888 = 1198833minus 119862119889

119863119888 = 1198834minus 119863119889

(9)

According to formulas (4) and (9) we can balance thenumber of 119861119888 119862119888 and 119863119888 to achieve the target number 119884

3

Consider

1198832minus 119861119886 minus 119861119887 + 119883

3minus 119862119889 + 119883

4minus 119863119889 ≧ 119884

3 (10)

We model the engineering change orders problems usingmultiple variables linear programming According to thefunctions we can understand the engineering change ordersrelation between supply and requirementThen designer canestimate and perform ECO using spare cell efficiently

5 Discussion

In this Section we discuss the advantage and disadvantage ofthe related works Table 1 shows ECO method comparisonThe proposed approach designs a multiple variable linearprogramming ECO for VLSI design Ourmethod can predictcell resource accurately using multiple variable linear pro-gramming techniques Traditional ECO is not to predict itwell Besides our scheme provides a high accurate predictionof patching logic number to balance between spare cells andtarget cells It is hard for traditional ECOmethod to do theseMoreover we define restriction rule resource optimizationand solution boundary of ECO problem to increase theefficiency of the proposed ECO method and provide a wellsolution

6 Conclusion

In this paper we proposed an engineering change ordersdesign using multiple variables linear programming for VLSIdesign The paper discusses typical ECO design flow logic

transformation and multiple variables linear programmingfor VLSI designThe presented scheme estimates the resourceof spare cells and provides a well solution of ECO problems

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This work was supported by the National Science Council ofTaiwan under Grant nos NSC 101-2221-E-027-135-MY2 and102-2622-E-027-008-CC3 The authors gratefully acknowl-edge the Chip Implementation Center (CIC) for supplyingthe technology models used in IC design

References

[1] J A Roy and I L Markov ldquoECO-system embracing the changein placementrdquo IEEE Transactions on Computer-Aided Design ofIntegrated Circuits and Systems vol 26 no 12 pp 2173ndash21852007

[2] C Tan and I H Jiang ldquoRecent research development inmetal-only ECOrdquo in Proceedings of the 54th IEEE InternationalMidwest Symposium on Circuits and Systems (MWSCAS rsquo11) pp1ndash4 August 2011

[3] Y M Kuo Y T Chang S C Chang and M Marek-SadowskaldquoSpare cells with constant insertion for engineering changerdquoIEEE Transactions on Computer-Aided Design of IntegratedCircuits and Systems vol 28 no 3 pp 456ndash460 2009

[4] D Brand A Drumm S Kundu and P Narain ldquoIncrementalsynthesisrdquo in Proceedings of the IEEEACM International Con-ference on Computer-Aided Design pp 14ndash18 1994

[5] S Huang K Chen and K Cheng ldquoAutoFix A hybrid tool forautomatic logic rectificationrdquo IEEE Transactions on Computer-Aided Design of Integrated Circuits and Systems vol 18 no 9 pp1376ndash1384 1999

[6] C Lin K Chen and M Marek-Sadowska ldquoLogic synthesisfor engineering changerdquo IEEE Transactions on Computer-AidedDesign of Integrated Circuits and Systems vol 18 no 2-3 pp282ndash292 1999

[7] T Shinsha T Kubo Y Sakataya J Koshishita and K IshiharaldquoIncremental logic synthesis through gate logic structure identi-ficationrdquo in Proceedings of the IEEEACM Conference on DesignAutomation pp 391ndash397 Jun 1986

[8] G Swamy S Rajamani C Lennard and R K Brayton ldquoMini-mal logic re-synthesis for engineering changerdquo in Proceedings of

VLSI Design 5

the IEEE International Symposium on Circuits and Systems pp1596ndash1599 1997

[9] Y Watanabe and R K Brayton ldquoIncremental synthesis forengineering changesrdquo in Proceedings of the IEEE InternationalConference on Computer Design VLSI in Computers and Pro-cessors (ICCD rsquo91) pp 40ndash43 Cambridge Mass USA October1991

[10] J Wang Finding the Minimal Logic Difference for FunctionalECO Taiwan Cadence Design Systems 2012

[11] Y C Fan and H W Tsao ldquoWatermarking for intellectualproperty protectionrdquo IEE Electronics Letters vol 39 no 18 pp1316ndash1318 2003

[12] Y Fan and H Tsao ldquoBoundary scan test scheme for IPcore identification via watermarkingrdquo IEICE Transactions onInformation and Systems vol E88-D no 7 pp 1397ndash1400 2005

[13] Y Fan ldquoTesting-based watermarking techniques for intellectual-property identification in SOC designrdquo IEEE Transactions onInstrumentation and Measurement vol 57 no 3 pp 467ndash4792008

[14] Y Fan and Y Chiang ldquoDiscrete wavelet transform on colorpicture interpolation of digital still camerardquo VLSI Design vol2013 Article ID 738057 9 pages 2013

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Submit your manuscripts athttpwwwhindawicom

VLSI Design

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation httpwwwhindawicom

Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Modelling amp Simulation in EngineeringHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

DistributedSensor Networks

International Journal of

2 VLSI Design

Old net-listECONew registertransfer level

ECO New net-list

ECO editing

Old registertransfer level

Logic synthesis DFT Placement

and routing

Figure 1 A typical ECO design flow

Find out patch logic

Mapped patch logic

Patch logic

MappingAvailable spare cell list

Equivalent and timing check

Figure 2 Two-phase ECO design flow

programming for VLSI design is presented In Section 5 wediscuss the advantage and disadvantage of the related worksFinally we conclude this paper in Section 6

2 Typical ECO Design Flow

Before describing the proposed method we address a typ-ical manual ECO design flow in Figure 1 IC designersperform the change in register transfer level and verifyfixed code matching the new specification at first Thenold net-list is scanned to search the possible fix pointsAfter the possible fix points are searched IC designersmodify the net-list and check the functionally equiva-lent between new net-list and new register transfer level[10ndash14]

Next we describe two-phase ECOdesign flow in Figure 2To patch the logics of the modified circuit we prepareavailable spare cell list According to logic function themodified circuit is mapped to specified logics After patchinglogic equivalent check and timing check are performed tomake sure that the new function met the new specification

However there are some important problems that appearduring patching logic Are there enough spare cells and typesto satisfy the consumption of patch logic How to estimatethe quantity and logic types of ECO procedure In orderto solve this problem we proposed an engineering changeorders design using multiple variables linear programmingfor VLSI design in this paper

3 Logic Transformation

Before discussing the engineering change orders designusing multiple variables linear programming we addressedECO logic transformation Figure 3 describes an ECO prob-lem with an equation out = (119860 + (119861119862)1015840)1015840 Figure 3(b) liststhe available spare cells According to the list we discoverthe available spare cells are not enough In order to solvethe problem we adopt another mapping solution with anequation out = (1198601015840119861119862) instead of the original equation inFigure 3(c) It requires one AND and one INV gate Themapping solution in Figure 3(c) requires gates fewer thanthe available spare cells and is constructed with the availablespare cells

However most of spare cells only provide basic logicalfunctions that include AND OR NOT NAND and NORHalf Adder (HA) Full Adder (FA) And-Or-Inverter (AOI)and Or-And-Inverter (OAI) can provide complex logicalfunctions We can adopt these logical cells to perform ECOfunction For example AOI22 can be implemented by twoNAND and one AND cells in Figure 4 According to theexisting resources of spare cells we can resynthesize thechanged function lists

4 Multiple Variables Linear Programming forVLSI Design

Although logic transformation skill makes the ECO technol-ogy come true a chip often does not own enough spare cellsto modify the function to meet a new specification Howto allocate limited resource We should estimate quantity ofspare cells and logic transformation rule to perform optimalengineering charge orders

In Figure 5 it describes the engineering change ordersdesign using multiple variables linear programming for VLSIdesign and relation of logic transformation ldquoLogic 119860rdquo is onekind of spare cells that can be transformed into ldquoLogic 119886rdquoor ldquoLogic 119887rdquo Similarly ldquoLogic 119861rdquo can be transformed intoldquoLogic 119886rdquo ldquoLogic 119887rdquo or ldquoLogic 119888rdquo ldquoLogic 119862rdquo performs ECOfunction instead of ldquoLogic 119888rdquo or ldquoLogic 119889rdquo Besides Logic119863 istransformed into ldquoLogic 119888rdquo or ldquoLogic 119889rdquo Equivalently ldquoLogic119864rdquo is transformed to ldquoLogic 119889rdquo or ldquoLogic 119890rdquo to achieve ECOfunction

We assume 1198831 1198832 1198833 1198834 and 119883

5are the number of

spare cells Logic 119860 Logic 119861 Logic 119862 Logic 119863 and Logic 119864Let 1198841 1198842 1198843 1198844 and 119884

5be the desired number of target

cells Logic 119886 Logic 119887 Logic 119888 Logic 119889 and Logic 119890Besides 119860119886 is the number of spare cells (Logic 119860) to

be transformed into Logic 119886 and 119860119887 is the number of sparecells (Logic 119860) to be transformed into Logic 119887 Similarly119861119886 119861119887 and 119861119888 are the number of spare cells (Logic 119861) tobe transformed into Logic 119886 Logic 119887 and Logic 119888 In a similarway 119862119888 and 119862119889 are the number of spare cells (Logic 119862) tobe transformed into Logic 119888 and Logic 119889 119863119888 and 119863119889 are thenumber of spare cells (Logic119863) to be transformed into Logic119888 and Logic 119889 and 119864119889 and 119864119890 are the number of spare cells(Logic 119864) to be transformed into Logic 119889 and Logic 119890

VLSI Design 3

A

A

B

C

BC

(a)

Type Spare cellsAND 2OR 2INV 1

NAND 1

(b)

A

B

C

A

(c)

Figure 3 Example of an ECO problem (a) EC equation output = (119860 + (119861119862)1015840)1015840 (b) Spare cells (c) Mapping output = (1198601015840119861119862)

(a) (b)

Figure 4 AOI22 can be implemented by two NAND and one AND cells

X1

Y1

X2

Y2

X3

Y3

X4

Y4

X5

Y5

Logic A

Logic B

Logic C

Logic D

Logic E

Logic a

Logic b

Logic c

Logic d

Logic e

Aa

Ab

Ba

Bb

Bc

Cc

Cd

Dc

Dd

Ed

Ee

Figure 5 ECO design using multiple variables linear programmingfor VLSI design and relation of logic transformation

Therefore the restriction rule of the number of spare cellsand transformed target cells in Figure 5 is written as follows

1198831= 119860119886 + 119860119887

1198832= 119861119886 + 119861119887 + 119861119888

1198833= 119862119888 + 119862119889

1198834= 119863119888 + 119863119889

1198835= 119864119889 + 119864119890

(1)

Besides the restriction rule of the engineering changeorders design usingmultiple variables linear programming inFigure 5 is written as follows

119860119886 + 119861119886 ≧ 1198841 (2)

119860119887 + 119861119887 ≧ 1198842 (3)

119861119888 + 119862119888 + 119863119888 ≧ 1198843 (4)

119862119889 + 119863119889 + 119864119889 ≧ 1198844 (5)

119864119889 + 119864119890 ≧ 1198845 (6)

However spare cells are not often enough designershould balance the spare cell allocation to meet all require-ments of desirable cells

We assume one case when 119861119887 ≦ 1198842 In order to provide

enough spare cells we should increase the number of 119860119887 toachieve 119860119887 + 119861119887 ≧ 119884

2

Similarly when 119862119888 + 119863119888 ≦ 1198843 we should increase 119861119888

number to meet 119861119888 + 119862119888 + 119863119888 ≧ 1198843

Therefore we define another restriction rule of the engi-neering change orders design which is written as follows

119860119886 = 1198831minus 119860119887

119861119886 = 1198832minus 119861119887 minus 119861119888

(7)

4 VLSI Design

Table 1 ECO methods comparison

Method Traditional ECO Proposed methodCell resource prediction Constraint based Multiple variables linear programmingPredictive precision of patching logic number Normal precision High precisionBalance between spare cells and target cells Low balance High balanceRestriction rule Not define DefineResource optimization Not define DefineSolution boundary Not define Define

According to formulas (2) and (7) we can balance thenumber of 119860119887 119861119887 and 119861119888 to achieve the target number 119884

1

Consider the following

1198831minus 119860119887 + 119883

2minus 119861119887 minus 119861119888 ≧ 119884

1 (8)

In a similar way we define the restriction rule of theengineering change orders design which is written as follows

119861119888 = 1198832minus 119861119886 minus 119861119887

119862119888 = 1198833minus 119862119889

119863119888 = 1198834minus 119863119889

(9)

According to formulas (4) and (9) we can balance thenumber of 119861119888 119862119888 and 119863119888 to achieve the target number 119884

3

Consider

1198832minus 119861119886 minus 119861119887 + 119883

3minus 119862119889 + 119883

4minus 119863119889 ≧ 119884

3 (10)

We model the engineering change orders problems usingmultiple variables linear programming According to thefunctions we can understand the engineering change ordersrelation between supply and requirementThen designer canestimate and perform ECO using spare cell efficiently

5 Discussion

In this Section we discuss the advantage and disadvantage ofthe related works Table 1 shows ECO method comparisonThe proposed approach designs a multiple variable linearprogramming ECO for VLSI design Ourmethod can predictcell resource accurately using multiple variable linear pro-gramming techniques Traditional ECO is not to predict itwell Besides our scheme provides a high accurate predictionof patching logic number to balance between spare cells andtarget cells It is hard for traditional ECOmethod to do theseMoreover we define restriction rule resource optimizationand solution boundary of ECO problem to increase theefficiency of the proposed ECO method and provide a wellsolution

6 Conclusion

In this paper we proposed an engineering change ordersdesign using multiple variables linear programming for VLSIdesign The paper discusses typical ECO design flow logic

transformation and multiple variables linear programmingfor VLSI designThe presented scheme estimates the resourceof spare cells and provides a well solution of ECO problems

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This work was supported by the National Science Council ofTaiwan under Grant nos NSC 101-2221-E-027-135-MY2 and102-2622-E-027-008-CC3 The authors gratefully acknowl-edge the Chip Implementation Center (CIC) for supplyingthe technology models used in IC design

References

[1] J A Roy and I L Markov ldquoECO-system embracing the changein placementrdquo IEEE Transactions on Computer-Aided Design ofIntegrated Circuits and Systems vol 26 no 12 pp 2173ndash21852007

[2] C Tan and I H Jiang ldquoRecent research development inmetal-only ECOrdquo in Proceedings of the 54th IEEE InternationalMidwest Symposium on Circuits and Systems (MWSCAS rsquo11) pp1ndash4 August 2011

[3] Y M Kuo Y T Chang S C Chang and M Marek-SadowskaldquoSpare cells with constant insertion for engineering changerdquoIEEE Transactions on Computer-Aided Design of IntegratedCircuits and Systems vol 28 no 3 pp 456ndash460 2009

[4] D Brand A Drumm S Kundu and P Narain ldquoIncrementalsynthesisrdquo in Proceedings of the IEEEACM International Con-ference on Computer-Aided Design pp 14ndash18 1994

[5] S Huang K Chen and K Cheng ldquoAutoFix A hybrid tool forautomatic logic rectificationrdquo IEEE Transactions on Computer-Aided Design of Integrated Circuits and Systems vol 18 no 9 pp1376ndash1384 1999

[6] C Lin K Chen and M Marek-Sadowska ldquoLogic synthesisfor engineering changerdquo IEEE Transactions on Computer-AidedDesign of Integrated Circuits and Systems vol 18 no 2-3 pp282ndash292 1999

[7] T Shinsha T Kubo Y Sakataya J Koshishita and K IshiharaldquoIncremental logic synthesis through gate logic structure identi-ficationrdquo in Proceedings of the IEEEACM Conference on DesignAutomation pp 391ndash397 Jun 1986

[8] G Swamy S Rajamani C Lennard and R K Brayton ldquoMini-mal logic re-synthesis for engineering changerdquo in Proceedings of

VLSI Design 5

the IEEE International Symposium on Circuits and Systems pp1596ndash1599 1997

[9] Y Watanabe and R K Brayton ldquoIncremental synthesis forengineering changesrdquo in Proceedings of the IEEE InternationalConference on Computer Design VLSI in Computers and Pro-cessors (ICCD rsquo91) pp 40ndash43 Cambridge Mass USA October1991

[10] J Wang Finding the Minimal Logic Difference for FunctionalECO Taiwan Cadence Design Systems 2012

[11] Y C Fan and H W Tsao ldquoWatermarking for intellectualproperty protectionrdquo IEE Electronics Letters vol 39 no 18 pp1316ndash1318 2003

[12] Y Fan and H Tsao ldquoBoundary scan test scheme for IPcore identification via watermarkingrdquo IEICE Transactions onInformation and Systems vol E88-D no 7 pp 1397ndash1400 2005

[13] Y Fan ldquoTesting-based watermarking techniques for intellectual-property identification in SOC designrdquo IEEE Transactions onInstrumentation and Measurement vol 57 no 3 pp 467ndash4792008

[14] Y Fan and Y Chiang ldquoDiscrete wavelet transform on colorpicture interpolation of digital still camerardquo VLSI Design vol2013 Article ID 738057 9 pages 2013

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Submit your manuscripts athttpwwwhindawicom

VLSI Design

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation httpwwwhindawicom

Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Modelling amp Simulation in EngineeringHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

DistributedSensor Networks

International Journal of

VLSI Design 3

A

A

B

C

BC

(a)

Type Spare cellsAND 2OR 2INV 1

NAND 1

(b)

A

B

C

A

(c)

Figure 3 Example of an ECO problem (a) EC equation output = (119860 + (119861119862)1015840)1015840 (b) Spare cells (c) Mapping output = (1198601015840119861119862)

(a) (b)

Figure 4 AOI22 can be implemented by two NAND and one AND cells

X1

Y1

X2

Y2

X3

Y3

X4

Y4

X5

Y5

Logic A

Logic B

Logic C

Logic D

Logic E

Logic a

Logic b

Logic c

Logic d

Logic e

Aa

Ab

Ba

Bb

Bc

Cc

Cd

Dc

Dd

Ed

Ee

Figure 5 ECO design using multiple variables linear programmingfor VLSI design and relation of logic transformation

Therefore the restriction rule of the number of spare cellsand transformed target cells in Figure 5 is written as follows

1198831= 119860119886 + 119860119887

1198832= 119861119886 + 119861119887 + 119861119888

1198833= 119862119888 + 119862119889

1198834= 119863119888 + 119863119889

1198835= 119864119889 + 119864119890

(1)

Besides the restriction rule of the engineering changeorders design usingmultiple variables linear programming inFigure 5 is written as follows

119860119886 + 119861119886 ≧ 1198841 (2)

119860119887 + 119861119887 ≧ 1198842 (3)

119861119888 + 119862119888 + 119863119888 ≧ 1198843 (4)

119862119889 + 119863119889 + 119864119889 ≧ 1198844 (5)

119864119889 + 119864119890 ≧ 1198845 (6)

However spare cells are not often enough designershould balance the spare cell allocation to meet all require-ments of desirable cells

We assume one case when 119861119887 ≦ 1198842 In order to provide

enough spare cells we should increase the number of 119860119887 toachieve 119860119887 + 119861119887 ≧ 119884

2

Similarly when 119862119888 + 119863119888 ≦ 1198843 we should increase 119861119888

number to meet 119861119888 + 119862119888 + 119863119888 ≧ 1198843

Therefore we define another restriction rule of the engi-neering change orders design which is written as follows

119860119886 = 1198831minus 119860119887

119861119886 = 1198832minus 119861119887 minus 119861119888

(7)

4 VLSI Design

Table 1 ECO methods comparison

Method Traditional ECO Proposed methodCell resource prediction Constraint based Multiple variables linear programmingPredictive precision of patching logic number Normal precision High precisionBalance between spare cells and target cells Low balance High balanceRestriction rule Not define DefineResource optimization Not define DefineSolution boundary Not define Define

According to formulas (2) and (7) we can balance thenumber of 119860119887 119861119887 and 119861119888 to achieve the target number 119884

1

Consider the following

1198831minus 119860119887 + 119883

2minus 119861119887 minus 119861119888 ≧ 119884

1 (8)

In a similar way we define the restriction rule of theengineering change orders design which is written as follows

119861119888 = 1198832minus 119861119886 minus 119861119887

119862119888 = 1198833minus 119862119889

119863119888 = 1198834minus 119863119889

(9)

According to formulas (4) and (9) we can balance thenumber of 119861119888 119862119888 and 119863119888 to achieve the target number 119884

3

Consider

1198832minus 119861119886 minus 119861119887 + 119883

3minus 119862119889 + 119883

4minus 119863119889 ≧ 119884

3 (10)

We model the engineering change orders problems usingmultiple variables linear programming According to thefunctions we can understand the engineering change ordersrelation between supply and requirementThen designer canestimate and perform ECO using spare cell efficiently

5 Discussion

In this Section we discuss the advantage and disadvantage ofthe related works Table 1 shows ECO method comparisonThe proposed approach designs a multiple variable linearprogramming ECO for VLSI design Ourmethod can predictcell resource accurately using multiple variable linear pro-gramming techniques Traditional ECO is not to predict itwell Besides our scheme provides a high accurate predictionof patching logic number to balance between spare cells andtarget cells It is hard for traditional ECOmethod to do theseMoreover we define restriction rule resource optimizationand solution boundary of ECO problem to increase theefficiency of the proposed ECO method and provide a wellsolution

6 Conclusion

In this paper we proposed an engineering change ordersdesign using multiple variables linear programming for VLSIdesign The paper discusses typical ECO design flow logic

transformation and multiple variables linear programmingfor VLSI designThe presented scheme estimates the resourceof spare cells and provides a well solution of ECO problems

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This work was supported by the National Science Council ofTaiwan under Grant nos NSC 101-2221-E-027-135-MY2 and102-2622-E-027-008-CC3 The authors gratefully acknowl-edge the Chip Implementation Center (CIC) for supplyingthe technology models used in IC design

References

[1] J A Roy and I L Markov ldquoECO-system embracing the changein placementrdquo IEEE Transactions on Computer-Aided Design ofIntegrated Circuits and Systems vol 26 no 12 pp 2173ndash21852007

[2] C Tan and I H Jiang ldquoRecent research development inmetal-only ECOrdquo in Proceedings of the 54th IEEE InternationalMidwest Symposium on Circuits and Systems (MWSCAS rsquo11) pp1ndash4 August 2011

[3] Y M Kuo Y T Chang S C Chang and M Marek-SadowskaldquoSpare cells with constant insertion for engineering changerdquoIEEE Transactions on Computer-Aided Design of IntegratedCircuits and Systems vol 28 no 3 pp 456ndash460 2009

[4] D Brand A Drumm S Kundu and P Narain ldquoIncrementalsynthesisrdquo in Proceedings of the IEEEACM International Con-ference on Computer-Aided Design pp 14ndash18 1994

[5] S Huang K Chen and K Cheng ldquoAutoFix A hybrid tool forautomatic logic rectificationrdquo IEEE Transactions on Computer-Aided Design of Integrated Circuits and Systems vol 18 no 9 pp1376ndash1384 1999

[6] C Lin K Chen and M Marek-Sadowska ldquoLogic synthesisfor engineering changerdquo IEEE Transactions on Computer-AidedDesign of Integrated Circuits and Systems vol 18 no 2-3 pp282ndash292 1999

[7] T Shinsha T Kubo Y Sakataya J Koshishita and K IshiharaldquoIncremental logic synthesis through gate logic structure identi-ficationrdquo in Proceedings of the IEEEACM Conference on DesignAutomation pp 391ndash397 Jun 1986

[8] G Swamy S Rajamani C Lennard and R K Brayton ldquoMini-mal logic re-synthesis for engineering changerdquo in Proceedings of

VLSI Design 5

the IEEE International Symposium on Circuits and Systems pp1596ndash1599 1997

[9] Y Watanabe and R K Brayton ldquoIncremental synthesis forengineering changesrdquo in Proceedings of the IEEE InternationalConference on Computer Design VLSI in Computers and Pro-cessors (ICCD rsquo91) pp 40ndash43 Cambridge Mass USA October1991

[10] J Wang Finding the Minimal Logic Difference for FunctionalECO Taiwan Cadence Design Systems 2012

[11] Y C Fan and H W Tsao ldquoWatermarking for intellectualproperty protectionrdquo IEE Electronics Letters vol 39 no 18 pp1316ndash1318 2003

[12] Y Fan and H Tsao ldquoBoundary scan test scheme for IPcore identification via watermarkingrdquo IEICE Transactions onInformation and Systems vol E88-D no 7 pp 1397ndash1400 2005

[13] Y Fan ldquoTesting-based watermarking techniques for intellectual-property identification in SOC designrdquo IEEE Transactions onInstrumentation and Measurement vol 57 no 3 pp 467ndash4792008

[14] Y Fan and Y Chiang ldquoDiscrete wavelet transform on colorpicture interpolation of digital still camerardquo VLSI Design vol2013 Article ID 738057 9 pages 2013

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Submit your manuscripts athttpwwwhindawicom

VLSI Design

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation httpwwwhindawicom

Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Modelling amp Simulation in EngineeringHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

DistributedSensor Networks

International Journal of

4 VLSI Design

Table 1 ECO methods comparison

Method Traditional ECO Proposed methodCell resource prediction Constraint based Multiple variables linear programmingPredictive precision of patching logic number Normal precision High precisionBalance between spare cells and target cells Low balance High balanceRestriction rule Not define DefineResource optimization Not define DefineSolution boundary Not define Define

According to formulas (2) and (7) we can balance thenumber of 119860119887 119861119887 and 119861119888 to achieve the target number 119884

1

Consider the following

1198831minus 119860119887 + 119883

2minus 119861119887 minus 119861119888 ≧ 119884

1 (8)

In a similar way we define the restriction rule of theengineering change orders design which is written as follows

119861119888 = 1198832minus 119861119886 minus 119861119887

119862119888 = 1198833minus 119862119889

119863119888 = 1198834minus 119863119889

(9)

According to formulas (4) and (9) we can balance thenumber of 119861119888 119862119888 and 119863119888 to achieve the target number 119884

3

Consider

1198832minus 119861119886 minus 119861119887 + 119883

3minus 119862119889 + 119883

4minus 119863119889 ≧ 119884

3 (10)

We model the engineering change orders problems usingmultiple variables linear programming According to thefunctions we can understand the engineering change ordersrelation between supply and requirementThen designer canestimate and perform ECO using spare cell efficiently

5 Discussion

In this Section we discuss the advantage and disadvantage ofthe related works Table 1 shows ECO method comparisonThe proposed approach designs a multiple variable linearprogramming ECO for VLSI design Ourmethod can predictcell resource accurately using multiple variable linear pro-gramming techniques Traditional ECO is not to predict itwell Besides our scheme provides a high accurate predictionof patching logic number to balance between spare cells andtarget cells It is hard for traditional ECOmethod to do theseMoreover we define restriction rule resource optimizationand solution boundary of ECO problem to increase theefficiency of the proposed ECO method and provide a wellsolution

6 Conclusion

In this paper we proposed an engineering change ordersdesign using multiple variables linear programming for VLSIdesign The paper discusses typical ECO design flow logic

transformation and multiple variables linear programmingfor VLSI designThe presented scheme estimates the resourceof spare cells and provides a well solution of ECO problems

Conflict of Interests

The authors declare that there is no conflict of interestsregarding the publication of this paper

Acknowledgments

This work was supported by the National Science Council ofTaiwan under Grant nos NSC 101-2221-E-027-135-MY2 and102-2622-E-027-008-CC3 The authors gratefully acknowl-edge the Chip Implementation Center (CIC) for supplyingthe technology models used in IC design

References

[1] J A Roy and I L Markov ldquoECO-system embracing the changein placementrdquo IEEE Transactions on Computer-Aided Design ofIntegrated Circuits and Systems vol 26 no 12 pp 2173ndash21852007

[2] C Tan and I H Jiang ldquoRecent research development inmetal-only ECOrdquo in Proceedings of the 54th IEEE InternationalMidwest Symposium on Circuits and Systems (MWSCAS rsquo11) pp1ndash4 August 2011

[3] Y M Kuo Y T Chang S C Chang and M Marek-SadowskaldquoSpare cells with constant insertion for engineering changerdquoIEEE Transactions on Computer-Aided Design of IntegratedCircuits and Systems vol 28 no 3 pp 456ndash460 2009

[4] D Brand A Drumm S Kundu and P Narain ldquoIncrementalsynthesisrdquo in Proceedings of the IEEEACM International Con-ference on Computer-Aided Design pp 14ndash18 1994

[5] S Huang K Chen and K Cheng ldquoAutoFix A hybrid tool forautomatic logic rectificationrdquo IEEE Transactions on Computer-Aided Design of Integrated Circuits and Systems vol 18 no 9 pp1376ndash1384 1999

[6] C Lin K Chen and M Marek-Sadowska ldquoLogic synthesisfor engineering changerdquo IEEE Transactions on Computer-AidedDesign of Integrated Circuits and Systems vol 18 no 2-3 pp282ndash292 1999

[7] T Shinsha T Kubo Y Sakataya J Koshishita and K IshiharaldquoIncremental logic synthesis through gate logic structure identi-ficationrdquo in Proceedings of the IEEEACM Conference on DesignAutomation pp 391ndash397 Jun 1986

[8] G Swamy S Rajamani C Lennard and R K Brayton ldquoMini-mal logic re-synthesis for engineering changerdquo in Proceedings of

VLSI Design 5

the IEEE International Symposium on Circuits and Systems pp1596ndash1599 1997

[9] Y Watanabe and R K Brayton ldquoIncremental synthesis forengineering changesrdquo in Proceedings of the IEEE InternationalConference on Computer Design VLSI in Computers and Pro-cessors (ICCD rsquo91) pp 40ndash43 Cambridge Mass USA October1991

[10] J Wang Finding the Minimal Logic Difference for FunctionalECO Taiwan Cadence Design Systems 2012

[11] Y C Fan and H W Tsao ldquoWatermarking for intellectualproperty protectionrdquo IEE Electronics Letters vol 39 no 18 pp1316ndash1318 2003

[12] Y Fan and H Tsao ldquoBoundary scan test scheme for IPcore identification via watermarkingrdquo IEICE Transactions onInformation and Systems vol E88-D no 7 pp 1397ndash1400 2005

[13] Y Fan ldquoTesting-based watermarking techniques for intellectual-property identification in SOC designrdquo IEEE Transactions onInstrumentation and Measurement vol 57 no 3 pp 467ndash4792008

[14] Y Fan and Y Chiang ldquoDiscrete wavelet transform on colorpicture interpolation of digital still camerardquo VLSI Design vol2013 Article ID 738057 9 pages 2013

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Submit your manuscripts athttpwwwhindawicom

VLSI Design

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation httpwwwhindawicom

Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Modelling amp Simulation in EngineeringHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

DistributedSensor Networks

International Journal of

VLSI Design 5

the IEEE International Symposium on Circuits and Systems pp1596ndash1599 1997

[9] Y Watanabe and R K Brayton ldquoIncremental synthesis forengineering changesrdquo in Proceedings of the IEEE InternationalConference on Computer Design VLSI in Computers and Pro-cessors (ICCD rsquo91) pp 40ndash43 Cambridge Mass USA October1991

[10] J Wang Finding the Minimal Logic Difference for FunctionalECO Taiwan Cadence Design Systems 2012

[11] Y C Fan and H W Tsao ldquoWatermarking for intellectualproperty protectionrdquo IEE Electronics Letters vol 39 no 18 pp1316ndash1318 2003

[12] Y Fan and H Tsao ldquoBoundary scan test scheme for IPcore identification via watermarkingrdquo IEICE Transactions onInformation and Systems vol E88-D no 7 pp 1397ndash1400 2005

[13] Y Fan ldquoTesting-based watermarking techniques for intellectual-property identification in SOC designrdquo IEEE Transactions onInstrumentation and Measurement vol 57 no 3 pp 467ndash4792008

[14] Y Fan and Y Chiang ldquoDiscrete wavelet transform on colorpicture interpolation of digital still camerardquo VLSI Design vol2013 Article ID 738057 9 pages 2013

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Submit your manuscripts athttpwwwhindawicom

VLSI Design

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation httpwwwhindawicom

Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Modelling amp Simulation in EngineeringHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

DistributedSensor Networks

International Journal of

International Journal of

AerospaceEngineeringHindawi Publishing Corporationhttpwwwhindawicom Volume 2014

RoboticsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Active and Passive Electronic Components

Control Scienceand Engineering

Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

International Journal of

RotatingMachinery

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporation httpwwwhindawicom

Journal ofEngineeringVolume 2014

Submit your manuscripts athttpwwwhindawicom

VLSI Design

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Shock and Vibration

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Civil EngineeringAdvances in

Acoustics and VibrationAdvances in

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Electrical and Computer Engineering

Journal of

Advances inOptoElectronics

Hindawi Publishing Corporation httpwwwhindawicom

Volume 2014

The Scientific World JournalHindawi Publishing Corporation httpwwwhindawicom Volume 2014

SensorsJournal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Modelling amp Simulation in EngineeringHindawi Publishing Corporation httpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Chemical EngineeringInternational Journal of Antennas and

Propagation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

Navigation and Observation

International Journal of

Hindawi Publishing Corporationhttpwwwhindawicom Volume 2014

DistributedSensor Networks

International Journal of


Top Related