![Page 1: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/1.jpg)
Part 1 of 2:
Progressive Design Build for a 5 MG Water Tank?
Tualatin Valley Water District’s Unique Approach for
Replacing a 5 MG Water Tank
Nicholas Augustus, PE, Tualatin Valley Water District
Corie Moolenkamp, PE, West Yost Associates
Vancouver, WA
May 3, 2018
![Page 2: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/2.jpg)
Today’s Agenda
• District Overview
• Project Overview
• Delivery Alternatives Considered
• Delivery Decision Process
• Contractor Selection Process
• Project Progress – Part 1
• Summary / Lessons Learned
• Questions and Discussion
![Page 3: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/3.jpg)
District Overview
![Page 4: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/4.jpg)
Tualatin Valley Water District (TVWD) Overview
• 2nd Largest Water Provider in Oregon
• Population served: ~228,000
• Average Daily Demand ~22 MG
• 752 Miles of pipe
• 67 MG Total Storage
![Page 5: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/5.jpg)
Joint Water Commission
Portland Water Bureau Bull Run
ASR Well
Existing Grabhorn Site
Tualatin Valley Water District (TVWD) Overview
City of Portland
![Page 6: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/6.jpg)
Project Overview
![Page 7: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/7.jpg)
Project Overview
Existing ASR Well
Existing 5 MG Tank
Existing ASR Discharge Pond
N
![Page 8: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/8.jpg)
Project Drivers
• Condition of Existing Water Tank
• Partially buried, constructed in 1971
• Structure is failing
• Schedule Driven by Operations
• Only reservoir in 385 PZ
• Location away from PRVs
![Page 9: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/9.jpg)
Project Overview
• New 5 MG D-110
Concrete Reservoir
• Piping connections
off-site and to ASR
facility
• At-grade valve house
• Access road
• Site restoration
![Page 10: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/10.jpg)
Delivery Alternatives Considered
![Page 11: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/11.jpg)
Project Delivery in Oregon
- 4 types of delivery considered
Design-Build (DB)
Design-Bid-Build (DBB)
Construction Manager/General Contractor (CM/GC)
Progressive Design-Build (PDB)
![Page 12: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/12.jpg)
Why Alternative Delivery?
• Collaborative approach to delivery
• Qualified contractors
• Working around critical assets (ASR Well)
• Contractor feedback up front
• Schedule and cost certainty earlier in process
• Constructability of reservoir and placement on site
![Page 13: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/13.jpg)
Alternative Delivery in Oregon
• Governed by 273C.335 – Competitive bidding
exemptions
• As required by 335.2, findings determined:
• Exemption unlikely to encourage favoritism or substantially diminish
competition
• Awarding under the exemption will likely result in substantial cost
savings and other substantial benefits
• Findings addressed items under 335.2.b
• Public Interest / Hearing
• 14 points to meet
![Page 14: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/14.jpg)
14 Points – Local Contract Board to consider:
1. # of available bidders
2. Construction budget and operating costs
3. Public benefits
4. Value engineering techniques
5. Specialized expertise
6. Public safety
7. Risk reduction
8. Funding source changes
9. Impact of market conditions and project control
10. Size and technical complexity
11. New or remodel of existing structure
12. Occupied versus unoccupied during construction
13. Single or multi-phase construction
14. Necessary expertise to manage alternative contracting method
![Page 15: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/15.jpg)
Project Delivery in Oregon
- 4 types of delivery considered
Design-Build (DB)
Design-Bid-Build (DBB)
Construction Manager/General Contractor (CM/GC)
Progressive Design-Build (PDB)
![Page 16: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/16.jpg)
Procurement
Preliminary Design Detailed Design Construction Contractor Bid Construction CommissioningDesigner RFP
Design Phase Bid Phase Construction Phase
Contractor Involvement
Designer Involvement
• Separate selections
• Low bid construction
• Longest schedule
Design-Bid-Build
Owner
ContractorDesigner
Sub-Contractor(s)Sub-Consultant(s)
![Page 17: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/17.jpg)
• Separate selections
• Price negotiations
Preliminary
DesignDetailed Design
Construction CommissioningCM/GC RFP
Design Construction
Contractor Involvement
Designer Involvement
Designer
RFP
Contractor’s Inputs
& GMP Creation
GMP
Contract
Procurement
CM/GC
Owner
Sub-Consultant(s)
General ContractorDesigner
Sub-Contractor(s)
![Page 18: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/18.jpg)
• Selection
• Schedule
• Innovation
• Lump sum price
Procurement
Detailed
Design
Construction CommissioningOwner’s
Rep RFP
Design Construction
DB Team Involvement
DB
RFQ/RFP
Conceptual Design
/ Pre-Design
Design-Build
Owner / Owner’s
Representative
Design- Build Entity
![Page 19: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/19.jpg)
Procurement
Preliminary Design Detailed Design
Construction Commissioning
Construction Phase
DB Team Involvement
PDB Team RFQ
GMPContract
Early Bidding Package
Design Phase
Progressive Design-Build
• Single selection
• Schedule
• Bid packages
• Owner input
• Negotiated Guaranteed Maximum
Price (GMP)
Design- Build Entity
Owner / Owner’s
Representative
Sub-Contractor(s)
![Page 20: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/20.jpg)
Delivery Decision Process
![Page 21: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/21.jpg)
Decision Matrix/Weighting Criteria
![Page 22: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/22.jpg)
Decision Matrix/Weighting Criteria
![Page 23: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/23.jpg)
Progressive Design Build
• Single point of contact
• Contracting advantages
• Schedule advantages
• Owner control
• Well qualified teams
interested in the project
• Risk advantages
• Used successfully by similar
Oregon utilities
PDB Team
Owner
Team Member
Team Member
![Page 24: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/24.jpg)
Alternative Delivery Schedule Advantages
![Page 25: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/25.jpg)
Contractor Selection Process
![Page 26: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/26.jpg)
Bidding – What the Contractor Needs to
Know
• Have to know it will
work
• Leave room for
innovation
N
![Page 27: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/27.jpg)
Alternative Delivery in Oregon
• Owner encouraged competition
• Solicitation of interest sent to 15 potential respondents
• Request for Letters of Interest published in Daily Journal of
Commerce
• 20 firms responded and expressed interest
![Page 28: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/28.jpg)
Contractor Selection
![Page 29: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/29.jpg)
Guaranteed Maximum Price / Contract Setup
• Open book process for prime and subs
• Allow for clear communication
• Bonus for completing project under budget (shared
savings)
• Risk allocation
• Contracted risk
• Negotiated risk
• Contingency items: Rock Excavation, Lead-Based Paint, Extra
Paving
![Page 30: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/30.jpg)
Project Progress
![Page 32: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/32.jpg)
Summary / Lessons Learned
![Page 33: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/33.jpg)
Summary / Lessons Learned
• TVWD’s First Alternative Delivery Project
• Progressive Design Build preferred
• Four qualified proposers meeting minimum
qualifications
• Did not need to short-list (additional RFQ)
• Contractor led teams
• Preparation of proposals
• Interviews
• Not perfect solution for all projects
• PDB fit well for this project
• Alternative is also termed “collaborative” delivery.
• Project team and collaboration is key
![Page 34: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/34.jpg)
Summary / Lessons Learned
• Consultant expertise / assistance throughout design
• Control of the process
• 30% cost estimate – perform separate
independent estimate prior to review of contractor
submittal (data point)
• Growing pains
• Contract modification
• Development of PDB contract
• Big lift, turned out great
![Page 35: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/35.jpg)
Questions and Discussion
![Page 36: Replacing a 5 MG Water Tank - PNWS-AWWA...Replacing a 5 MG Water Tank Nicholas Augustus, PE, Tualatin Valley Water District Corie Moolenkamp, PE, West Yost Associates Vancouver, WA](https://reader033.vdocuments.us/reader033/viewer/2022042314/5f01ce227e708231d4011f76/html5/thumbnails/36.jpg)
THANK
YOU!