Replacement of the Cracked Rowland Man Winder Drum Shaft
Presented by: W.C. StemmetRowland Shaft Engineer
![Page 2: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/2.jpg)
Contents1 Synopses2 Winder History3 Incident4 Analysis, planning and scheduling5 Actions prior to the replacement program6 Preparation work7 Safety8 Replacement over Christmas break9 Lessons learned10 Closure and Recognitions
![Page 3: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/3.jpg)
Synopses
The daily safe transportation of our workforce to and from the underground levels is seen as just another activity in the mining cycle. This view changed when a crack was detected in the clutch spline of the Man Winder drum shaft.
The presentation:
Provides the framework and analysis that was used for the planning and scheduling of the temporary and permanent actions required to restore the defective drum shaft without affecting production.
It describes in detail the challenges faced, the technology and systems used to successfully conduct the repair.
![Page 4: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/4.jpg)
Winder History
• Built by English Steel Corporation in 1929 for Rand Mines as a bi-cylindro-conical with a small drum diameter of 12ft and a large drum diameter of 24ft and a single clutch.
• Installed underground at Crown Mines at 16A shaft.
• In the early 1970’s it was relocated to Prieska as their man winder and retained in the bi-cylindro-conical form.
• Subsequently it was bought by Lonrho about 25 years ago and converted by Lebus Engineers to cylindrical drums and used as the kibble winder for sinking Western Plats 4 shaft.
• Currently in use as the men/material winder at Rowland Shaft Lonmin Platinum.
![Page 5: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/5.jpg)
Incident
• During the weekly winder examination on 23 February 2006 an anomaly was detected in the winder drum shaft at the clutch spline.
• The affected area was thoroughly cleaned and investigated.• Metallock, Anglo Field Services and FFE Minerals-Vecor were
contacted to assist in the assessment of the failure. • A decision was taken to open the clutch area over the weekend
of 25 February 2006 to inspect the full extent of the crack. • The area on the shaft was marked to monitor any crack
propagation. • All clutching operations were suspended on the winder.
![Page 6: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/6.jpg)
Cracked Shaft
Clutch outer line when fully engaged
![Page 7: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/7.jpg)
Analysis, planning and scheduling
1. Metal stitching the cracked shaft
2. Machining out the cracked area
• FEA done on shaft
3. Replacing the drum shaft
![Page 8: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/8.jpg)
Metal stitching the cracked shaft
175m
280mm
Metallock Industrial Services –Offered to gouge out the crack and weld it up in position.
![Page 9: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/9.jpg)
Machining out the cracked area
Area targeted to be milled out in the shaft and replaced in the clutch slider
![Page 10: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/10.jpg)
Finite Element Analysis of the Shaft (FEA)
• The FEA modelling was carried out on the shaft dovetail interface with the clutch slider using the maximum expected load from a single brake retarding a down going load.
• The FEA results show that there are no geometric modifications to the dovetail that will reduce the peak stresses on the cracked portion.
• The cracked dovetail is stressed at 74% more than the un-cracked face.
• The increase in stresses leads to high contact forces approaching yield on the cracked face.
![Page 11: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/11.jpg)
Finite Element Analysis of ShaftA full length contact
367 MPa196 MPa
636 MPa340 MPa
Full face radius
193 MPa103 MPA
667 MPa357 MPa
Full face in contact
Average expected stresses over face.
Maximum stresses recorded / expected
Shaft results
Expected/normal clutch torque of 1.07 MNm
![Page 12: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/12.jpg)
Finite Element Analysis of ShaftA partial face contact
667 MPa357 Mpa
1156 MPa619 MPa
Partial face radius
336 MPa180 MPa
1612 MPa863 MPa
Partial face in contact
Average stresses over
face.
MaximumStresses
Recorded / expectedShaft results
![Page 13: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/13.jpg)
FEA Recommendations
• Leave the current cracked piece in place• Continue to monitor the crack in the shaft to see if the
crack propagated any further. • Daily and weekly visual examinations.• 2 Monthly stripping of the clutch with NDT and 3D
mapping of the area.• Review the current clutch design to determine if the
design is adequate for worst case braking operations. • Replace the cracked shaft and install a newly designed
clutch.
![Page 14: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/14.jpg)
Replacing the Drum Shaft
• The used spare shaft in the store at Rowland Shaft was sent to FFE Minerals-Vecorwhere it was cleaned for inspection.
• A complete metal particle inspection, run out and ultrasonic test was carried out and the bearing and drum bush journals were machine polished and sized.
• Replacement was planned for the 2006 Christmas break
![Page 15: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/15.jpg)
Actions prior to the replacement program
• Repair programme drawn up for 15 days.
• Christmas break was scheduled for 11 days.
• Retainers to keep machine shops open.
• Low bed access and road embargo.
• Craneage / Winder house roof.
• Motor and drum supports
• Drawings
![Page 16: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/16.jpg)
Preparation work
• Additional overhead crane.
• Removal of drum and brake path bolts.
• Bolt manufacturing.
• Pre-fitting of spare bearings.
• Casting of drum bushes.
• Clutch design review.
• Lock nuts.
![Page 17: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/17.jpg)
Safety
Man Hours Worked = 6084
LTI’s = 0
MTC’s = 0
Incident/Near miss = 1• Crane long travel motor failure
![Page 18: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/18.jpg)
Scope of Work
•Refurbishment and delivery of the drum shaft.•Supply:
•A new set of bolts with final line bore machining done on site.•New drum bushes.
•Clutch thrust faces, thrust collar and monkey ring machined and refurbished.
•Strip winder, replace drum shaft and commission in12 days.
•Level 1 audit and dynamic tests.•Supply as built engineering drawings.•Design and manufacture new clutch.
![Page 19: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/19.jpg)
Project
Winder before project
![Page 20: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/20.jpg)
Shaft Delivery
19/12/2006
![Page 21: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/21.jpg)
Bearings/Bolts Delivery
21/12/2006
![Page 22: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/22.jpg)
Taking off the Ropes
Doubling down ropes and securing conveyances.
23/12/2006
![Page 23: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/23.jpg)
Removing the drums and brake paths
![Page 24: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/24.jpg)
Winder being stripped
![Page 25: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/25.jpg)
Lifting out the old shaft
![Page 26: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/26.jpg)
Where is the winder ??
![Page 27: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/27.jpg)
Fitting the new shaft and bearings
![Page 28: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/28.jpg)
Rebuilding the winder
![Page 29: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/29.jpg)
Winder completely repaired05/01/2007
![Page 30: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/30.jpg)
Lessons Learned
• To use all resources
• Necessity of drawings and plans
• Movement and distortion when dismantling old equipment
• Measurements and assumptions
Bolts inserted with Liquid Nitrogen on drums and brake paths
![Page 31: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/31.jpg)
Lessons Learned
Frozen drum bolts on hubs
Clutch clamping on the drum shaft
Joint faces still open, bolts not
tight
To plan for possible Eskom power outages
![Page 32: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/32.jpg)
Closure
Project finished 40 hours behind schedule due to the following delays:•Drum halves opened up and twisted on the joint flanges.
•Eskom power failure.•Old refurbished clutch not fitting on the new shaft.
![Page 33: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/33.jpg)
Recognitions
• Lonmin Platinum Marikana Division• DME• The team• Shogun Construction• FFE Minerals-Vecor• Anglo Field Services• AMRE
![Page 34: Replacement of the Cracked Rowland Man Winder Drum Shaft · Winder History • Built by English Steel Corporation in 1929 for Rand Mines as a bi- cylindro-conical with a small drum](https://reader034.vdocuments.us/reader034/viewer/2022052017/602ffcff32168b34e03a6eb7/html5/thumbnails/34.jpg)
Thank You
Any Questions
???