Department of Mechanical Engineering 1
![Page 2: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/2.jpg)
PRESENTED BY
A.Balasubramani(08030610017)
M.Devarajan(08030610026)
G.Kanagaraj(08030610049)
SUPERVISOR
Mr. R. SATHIYA MOORTHY, M.E, (Ph.D)
Assistant Professor
Dept. of Mechanical Engineering,
Anna University of Technology,
Coimbatore – 641047.
2 Department of Mechanical Engineering
![Page 3: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/3.jpg)
Department of Mechanical Engineering 3
Objective
Reducing rejection rate in pump casing assembly
line process by using TPM.
![Page 4: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/4.jpg)
Methodology Available To Solve Problems TPM
CFT approach
10 step approach
Quality circle
6 sigma
Department of Mechanical Engineering 4
![Page 5: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/5.jpg)
TPM Methods to solve problem PDCA Cycle
Cause and Effect Analysis
Gap Analysis
Why-Why Analysis
Kaizen
Department of Mechanical Engineering 5
![Page 6: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/6.jpg)
Our Method of Solving
Department of Mechanical Engineering 6
![Page 7: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/7.jpg)
Department of Mechanical Engineering 7
Product Process Flow
Welding-1 • Projection Welding
Welding-2 • Spot Welding
Welding-3 • Projection Welding
![Page 8: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/8.jpg)
Department of Mechanical Engineering 8
Problem Details
Product rejection rate in pump casing assembly line
is 539ppm.
![Page 9: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/9.jpg)
Stage 1- Plan
Pump Casing Assembly Line Process is Selected For Our Project, Due to More Rejection Found (539 ppm)
Department of Mechanical Engineering 9
![Page 10: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/10.jpg)
Department of Mechanical Engineering 10
Sl.No Process Rejection PPM
1 Projection Welding-1 92
2 Spot Welding 364
3 Projection Welding-2 83
Total 3-Process 539
Process wise Rejection Status
![Page 11: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/11.jpg)
Department of Mechanical Engineering 11
Process Defect Rejection Qty Per 5000
Nos Rejection PPM
Projection Welding-1
Product Missed Weld 0.34 68
Dislocating 0.05 10
Improper Parameter 0.07 14
Spot Welding Misaligned Welding 1.75 350
Improper Parameter 0.07 14
Projection Welding-2
Product Missed Weld 0.305 61
Dislocating 0.05 10
Improper Parameter 0.06 12
Defect wise Rejection Details
![Page 12: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/12.jpg)
In Spot Welding Process Misaligned Welding Rejection is more found.
Department of Mechanical Engineering 12
![Page 13: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/13.jpg)
Department of Mechanical Engineering 13
Misaligned Welding Rejection product
![Page 14: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/14.jpg)
Existing Method of Operating
Department of Mechanical Engineering 14
![Page 15: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/15.jpg)
Goal is to eliminate the spot welding process rejection in pump assembly casing assembly to zero ppm within a ppm of one month
Department of Mechanical Engineering 15
Goal:-
![Page 16: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/16.jpg)
Stage-2:- Do Analyzing the Facts :
By using Cause and effect analysis Possible causes of misaligned welding found.
By using the why-why analysis finding the solutions for the causes.
Department of Mechanical Engineering 16
![Page 17: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/17.jpg)
Cause and Effect Analysis For Misaligned Welding
Department of Mechanical Engineering 17
![Page 18: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/18.jpg)
Causes of Misaligned Welding
Product locating method.
Improper handling method.
Machine Operating Speed.
Training to the operators.
Human Fatigue.
Machine Parameters.
Department of Mechanical Engineering 18
![Page 19: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/19.jpg)
Why-Why Analysis
Q1:Why Product Locating Method is Wrong?
Ans : Product Locating depends on operator
Q: Why Product Locating depends operator?
Ans : There is no proper locating fixture
Department of Mechanical Engineering 19
![Page 20: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/20.jpg)
Solutions For Misaligned Welding
Department of Mechanical Engineering 20
Sl.No Machine Causes of Misaligned Welding Countermeasure
1 Spot Welding Product Dislocating. Providing new fixture to locating the product with proper
welding path radius
2 Spot Welding Improper handling. Providing new fixture to holding & welding the product.
3 Projection Weld Fixture material strength. Providing new fixture with proper material strength.
4 Spot Welding Machine Speed. Providing flow control valve for the incoming Compressed
air.
5 Spot Welding Operator Training. Providing enough training to the operator.
6 Spot Welding Human Fatigue. Providing new fixture to holding the product.
![Page 21: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/21.jpg)
By Providing the proper locating Fixture the 350ppm of rejecting can be eliminated in spot welding process.
Department of Mechanical Engineering 21
Stage 3: Check
![Page 22: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/22.jpg)
Proposed Fixture
Department of Mechanical Engineering 22
![Page 23: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/23.jpg)
Department of Mechanical Engineering 23
![Page 24: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/24.jpg)
Department of Mechanical Engineering 24
Process Defect Rejection Qty Per 5000
Nos Rejection PPM
Projection Welding-1
Product Missed Weld 0.2 40
Dislocating 0.05 10
Improper Parameter 0.07 14
Spot Welding Misaligned Welding 0 0
Improper Parameter 0.03 6
Projection Welding-2
Product Missed Weld 0.2 40
Dislocating 0.03 6
Improper Parameter 0.06 12
Defect wise Rejection Details After Implementation of New Fixture
Stage 4 :- Act
Monitoring the solution
![Page 25: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/25.jpg)
Kaizen Idea Sheet
Department of Mechanical Engineering 25
![Page 26: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/26.jpg)
Result By implementing the new welding fixture for spot
welding process rejection rate in pump assembly casing assembly is reduced to zero ppm
Department of Mechanical Engineering 26
![Page 27: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/27.jpg)
Future Enhancement By using the electric, hydraulic, pneumatic, and
hydro-pneumatic control systems and also with the help of robots handling this operation .Also this process can be integrated with machine, so man power is not required for handling the component. The component can be moved to weld the required path by using PLC programming.
Department of Mechanical Engineering 27
![Page 28: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/28.jpg)
References Kaizen complied by Masaaki Imai “TPM introduction,
implementation, kaizen, PDCA-Cycle”
Design of jigs, fixtures, and press tool Complied By Erik Karl Henriksen “Fixture design principles, locating principles”
Statistical quality control by Steven M.Zimmerman,Marjorie L “7 Quality tools, check sheets, pareto analysis”
Department of Mechanical Engineering 28
![Page 29: Reducing Rejection Rate in Pump Casing Assembly by Using Tpm](https://reader034.vdocuments.us/reader034/viewer/2022051109/54801f55b379593f2b8b5a7d/html5/thumbnails/29.jpg)
Department of Mechanical Engineering 29
Thank You