Proposed Amendments for Terrestrial Wind Regulation in the
New Jersey Coastal Zone
Kevin HassellCoastal Management Office
NJDEP
Rule Amendments On September 8, 2009, the DEP published in the NJ Register a
proposal to amend the Coastal Permit Program rules:1. add a new permit-by-rule and two new coastal general permits for
the construction of wind turbines on land;2. describes the situations in which construction of a wind turbine
does not require a coastal permit. The Department is also proposing amendments to the Coastal
Zone Management rules, N.J.A.C. 7:7E, to facilitate the construction of wind turbines in the coastal zone in appropriate locations, identify particular areas where construction of large scale wind turbines would not be appropriate, and set forth monitoring, habitat evaluation and impact assessment requirements for birds and bats.
In addition, the Department is proposing amendments to the Flood Hazard Area Control Act Rules, N.J.A.C. 7:13, to add a new permit-by-rule for the construction of wind turbines on land.
Initial Stakeholder Meeting The New Jersey Department of Environmental Protection
(NJDEP) conducted a stakeholder meeting on Thursday, December 11, 2008, 2:00 pm - 4:00 pm in the Public Hearing Room.
The meeting focused on gathering information and concerns about natural resource considerations from stakeholders regarding the development of terrestrial wind turbines in New Jersey, with a focus on the coastal area, and a general overview of the Department’s activities in this regard.
Regulate Based on Size
Initial proposed size classes Type A
Less than 150’ high and 3 turbines or fewer
Type B 150’ – 250’ high and less than 20,000 square feet wind
swept area
Type C Greater than 250’ high
Regulate Based on Size
The proposal utilizes a tiered approach, with wind turbine development having the lowest potential impacts qualifying for authorization
under a permit-by-rule and the level of Department review increasing as the potential
impacts caused by the location, height or construction method of the wind turbine
increases.
Tier 1 1-3 wind turbines< 200 ft. tall and < 2000 sq. ft. cumulative
rotor swept area
Permit type * Permit evaluation
Monitoring
Permit-by-rule No submission to Department required.
Standards include setbacks, areas off-limits, no lattice or guy wires >100’ tall, lighting restrictions.
Pre-construction surveys: None.Post-construction surveys: None.
*Where standards for a permit-by-rule are not met, applicant may qualify for a general permit or apply for an individual permit.
Tier 2 1-3 wind turbines< 200 ft. tall and 2000-4000 sq. ft.
cumulative rotor swept area
Permit type* Permit evaluation Monitoring
General permit
Application for general permit demonstrating compliance with standards. Include setbacks, areas off-limits, E&T and Critical Wildlife habitat rule compliance, no lattice or guy wires >100’ tall, lighting restrictions.
Through permit condition, can curtail operations in certain specified conditions that pose a high bird or bat mortality threat.
Pre-construction
surveys:
None.
Post-construction
surveys:
One year bird and bat
carcass search for
first 15 projects
constructed.
*Where standards for a general permit are not met, applicant may apply for an individual permit.
Tier 3 Turbines < 250 ft. tall and ≤ 20,000 sq. ft. cumulative rotor
swept area
Permit type Permit evaluation Monitoring
General permit.
Not in or w/in ¼ mile of mapped areas due to operational impacts on wildlife.
Include setbacks, areas off-limits, no lattice or guy wires >100’ tall, lighting restrictions
Through permit condition, can curtail operations in certain specified conditions that pose a high bird or bat mortality threat.
Pre-construction
Surveys:
None.
Post-construction
Surveys:
One year bird and bat carcass search
*Where standards for a general permit are not met, applicant may apply for an individual permit.
Tier 4Turbines ≥ 250 ft. tall or > 20,000 sq. ft. cumulative rotor
swept area
Permit type Permit evaluation Monitoring
Individual permit.
Not in mapped areas due to
operational impacts on wildlife.
Applicable CZM rules.
No lattice or guy wires >100’ tall
Pre-construction surveys: 1 year Pre-construction
Post-construction surveys:2 years Post-construction
Additional rule amendments Amend Atlantic City rule to allow turbines ≤
200’ tall on piers Amend Energy use rule to reduce setback
from the water for wind from 500’ to 50’. Amend High rise structures rule so as not to
apply to wind turbines Amend Scenic resources and design rule to
delete setback requirement for wind turbines
Web Address
www.state.nj.us/dep/landuse/windturbine.htmlor
www.state.nj.us/dep/cmp/czm_news.html
Rule Proposal Technical Manual for Evaluating Wildlife
Impacts Large Scale Wind Turbine Siting Map Report Link to Large Scale Wind Turbine Siting Map
data
Comments?Public Hearing
Wednesday, October 14, 2009 at 1 P.M.New Jersey Department Of Environmental Protection
Public Hearing Room401 East State Street
Trenton, NJ 08060
Submit written comments by November 7, 2009 to:Gary J. Brower, Esq.Office of Legal Affairs
Attn: DEP Docket Number 12-09-08/734NJ Department of Environmental Protection
401 East State Street, Floor 4P.O. Box 402
Trenton, NJ 08625-0402
For pre-application meetings and other permitting issues, please contact the Division of Land Use Regulation Tech Center at 609-777-0454