![Page 1: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/1.jpg)
Project Tracking Update
July 12, 2011MOPC
![Page 2: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/2.jpg)
2
• STEP List (Excel Spreadsheet)– Engineers enter technical data and analysis on upgrades
– Used as a repository for all information on Transmission Upgrades
– Cumbersome and hard to update
– Historical record STEP list contains all upgrade information, even when project is
completed or withdrawn
Project Tracking Tools (Historical)
![Page 3: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/3.jpg)
Project Tracking (New)
• Project Tracking Database – Phase 1– Upgrades tracked from NTC creation to rate recovery
through the life of the Upgrade
– Easier data retrieval Quicker information response
Eliminates multiple data requests
– No impacts to members in Phase 1
– Future phases of project Member database access
Flexible communications for Transmission Owners and SPP
3
![Page 4: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/4.jpg)
Project Tracking – Member Impact
• No impact to members– Members will see no changes in their construction
project interaction with SPP
– SPP employees will gather project information and input into database same as today
– Members have data that is more secure
4
![Page 5: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/5.jpg)
ITP Status Update
July 12, 2011MOPC
![Page 6: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/6.jpg)
2011 ITP10 Stakeholder Activities
• TWG completed the Constraint Assessment
• ESWG approved the resource plans for the two futures– Future 1 – Business as Usual
– Future 2 – EPA Rules with Additional Wind: Adds additional wind generation and approximates the impact of EPA rulemaking by imposing retirements on small coal plants and a tax on carbon emissions
• ESWG authorized calculation and utilization of metrics for ITP10
6
![Page 7: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/7.jpg)
2011 ITP10 Stakeholder Activities
• Metric Calculation
– 9 metrics from ITP20– Adjusted Production Cost
– Value of Improved Available Transfer Capabilities
– Reduced Losses
– Impact on Losses Capacity
– Levelization of LMP’s
– Improved Competition in SPP Markets
– Limited Export/Import Improvements
– Reduction of Emission Rates and Values
– Ability to Serve new Load7
![Page 8: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/8.jpg)
2011 ITP10 Stakeholder Activities
• Metric Calculation– Two additional metrics calculated
Backstop to Catastrophic Events
Value of replacing previously approved projects
8
![Page 9: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/9.jpg)
2011 ITP10 Completed Staff Activities
• Model Development completed– Topology updates, baseline fuel costs, etc.
• Quality Control– Stakeholder Review
– dispatches
– flowgate loadings
– LMP prices
– generator outages
9
![Page 10: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/10.jpg)
2011 ITP10 Upcoming Activities
• Identifying ITP10 potential violations– Reliability analysis of AC models with economic
dispatches
– Economic analysis of security-constrained economic dispatch models List of Top 10 congested constraints will be compiled
– ITP20 projects reviewed as potential ITP10 solutions
– Staff developing strawman for incorporating seams projects
10
![Page 11: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/11.jpg)
2011 ITPNT Activities
• Identification of potential violations
• Developed recommended plan for 100 kV and above upgrades
• Recommended plan will be presented at upcoming SPP Summit
• Developing recommended plan for below 100 kV
11
![Page 12: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/12.jpg)
• July Planning Summit– Dallas, TX on July 21st
– Discuss ITP10 potential violations (reliability, economic, and stability)
– Start selecting ITP10 projects
– Discuss ITPNT upgrades
– Sub-Regional & Local Area Breakout Discussions
• September Planning Summit
ITP Next Steps
12
![Page 13: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/13.jpg)
• October MOPC– Present draft solutions
– 2011 ITP10 & ITPNT Draft Report
• December Workshop– Tentative
• January MOPC– Present final transmission plan
– 2011 ITP10 & ITPNT Final Report
– 2011 STEP Report
ITP Next Steps
13
![Page 14: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/14.jpg)
Generator Interconnection and Aggregate Study Process
Internal review update
14
![Page 15: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/15.jpg)
• Background– General dissatisfaction expressed in customer satisfaction
survey
• Goals for Staff review– Understand concerns driving lower survey results
Staff performance?
Dissatisfaction with results?
Process?
– Identify opportunities for improvement
Background and Purpose
15
![Page 16: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/16.jpg)
• Common themes of feedback to-date– Length of time it takes to get through process and have
certainty in requirements to approve requested service still too long
– Impacts caused by shear volume of wind-related or other “speculative” requests on “ready to-go” projects
– Lack of process to finalize third party impacts
• Staff completing internal process review– Business process review
– Tools
– Resource requirements
Update
16
![Page 17: Project Tracking Update July 12, 2011 MOPC. 2 STEP List (Excel Spreadsheet) –Engineers enter technical data and analysis on upgrades –Used as a repository](https://reader035.vdocuments.us/reader035/viewer/2022070415/5697c0101a28abf838ccadd8/html5/thumbnails/17.jpg)
• Initiatives underway– SPP TSR Coordination with Third Party Systems
– Third Party TSR Coordination with SPP
– DPT Prescreen
– Aggregate Study Withdrawal Costs
• Staff complete internal review
• Work with appropriate committees to assess potential process improvement proposals
• ATP Business Practice
Next Steps
17