Download - Project Status Project Phasing Questions
![Page 1: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/1.jpg)
![Page 2: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/2.jpg)
• Project Status
• Project Phasing
• Questions
2
![Page 3: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/3.jpg)
As of Today
• Project released for Bid February 7, 2011
• Notice of Bid sent to 80+ Contractors on February 2, 2011
• C&S occupied the field office on January 18, 2011
• Architectural Approval from SED on December 17, 2010
3
![Page 4: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/4.jpg)
Moving Forward • Contractor walk through scheduled for February 22,
2011
• Project Bids accepted March 3, 2011
• Contractor recommendations to the BOE on March 8, 2011
• Contractor mobilization beginning in early April, 2011
4
![Page 5: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/5.jpg)
Phasing : • Scheduling Goals:• Minimize disruption to students / staff during the
school year• Upgrade HVAC systems by September 2011
• Main Campus Overall Staging Area• Large Permanent Staging Area in gravel lot below
the District Office • Summer Lay Down Areas at both the High School
and Wheeler Elementary School 5
![Page 6: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/6.jpg)
HIGH SCHOOL : • TWO PHASES SUMMER 2011 & SUMMER 2012
• SUMMER 2011 • HVAC UPGRADES• MAIN OFFICE/GUIDANCE/HEALTH SUITE• FIRST FLOOR CLASSROOM RENOVATIONS• SINGLE SCEINCE CLASSROOM RENOVATION• ROOFING
6
![Page 7: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/7.jpg)
HIGH SCHOOL : • SUMMER 2012 • TWO SCIENCE CLASSROOMS • SECOND FLOOR CLASSROOM RENOVATIONS• MEDIA CENTER RENOVATIONS• SITEWORK
7
![Page 8: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/8.jpg)
TECHNOLOGY BUILDING: • UPGRADES COMPLETED BY SEPTEMBER 2011
8
![Page 9: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/9.jpg)
WHEELER ELEMENTARY: • SUMMER 2011• PROJECT COMPLETED• HVAC UPGRADES• ROOFING • CLASSROOM RENOVATIONS
9
![Page 10: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/10.jpg)
ROCKWELL ELEMENTARY: • TWO PHASES – SUMMER 2011 & SUMMER 2012
• SUMMER LAY DOWN AREA
• SUMMER 2011• HVAC UPGRADES COMPLETED • ROOFING • ADMINSTRATIVE AREA • SECOND FLOOR WEST WING CLASSROOMS
10
![Page 11: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/11.jpg)
ROCKWELL ELEMENTARY: • SUMMER 2012• FIRST FLOOR CLASSROOMS• SECOND FLOOR EAST CLASSROOMS• SITEWORK
11
![Page 12: Project Status Project Phasing Questions](https://reader034.vdocuments.us/reader034/viewer/2022051118/5681602f550346895dcf479b/html5/thumbnails/12.jpg)
Questions
12