2
As of Today
• Project released for Bid February 7, 2011
• Notice of Bid sent to 80+ Contractors on February 2, 2011
• C&S occupied the field office on January 18, 2011
• Architectural Approval from SED on December 17, 2010
3
Moving Forward • Contractor walk through scheduled for February 22,
2011
• Project Bids accepted March 3, 2011
• Contractor recommendations to the BOE on March 8, 2011
• Contractor mobilization beginning in early April, 2011
4
Phasing : • Scheduling Goals:• Minimize disruption to students / staff during the
school year• Upgrade HVAC systems by September 2011
• Main Campus Overall Staging Area• Large Permanent Staging Area in gravel lot below
the District Office • Summer Lay Down Areas at both the High School
and Wheeler Elementary School 5
HIGH SCHOOL : • TWO PHASES SUMMER 2011 & SUMMER 2012
• SUMMER 2011 • HVAC UPGRADES• MAIN OFFICE/GUIDANCE/HEALTH SUITE• FIRST FLOOR CLASSROOM RENOVATIONS• SINGLE SCEINCE CLASSROOM RENOVATION• ROOFING
6
HIGH SCHOOL : • SUMMER 2012 • TWO SCIENCE CLASSROOMS • SECOND FLOOR CLASSROOM RENOVATIONS• MEDIA CENTER RENOVATIONS• SITEWORK
7
TECHNOLOGY BUILDING: • UPGRADES COMPLETED BY SEPTEMBER 2011
8
WHEELER ELEMENTARY: • SUMMER 2011• PROJECT COMPLETED• HVAC UPGRADES• ROOFING • CLASSROOM RENOVATIONS
9
ROCKWELL ELEMENTARY: • TWO PHASES – SUMMER 2011 & SUMMER 2012
• SUMMER LAY DOWN AREA
• SUMMER 2011• HVAC UPGRADES COMPLETED • ROOFING • ADMINSTRATIVE AREA • SECOND FLOOR WEST WING CLASSROOMS
10
ROCKWELL ELEMENTARY: • SUMMER 2012• FIRST FLOOR CLASSROOMS• SECOND FLOOR EAST CLASSROOMS• SITEWORK
11
Questions