Project PlanningMclean Farms Pvt. Ltd.
Upcoming ProjectsUpcoming Projects
1. MF Labelling System2. Moba Integration
Moba Client Data Import to PFMS Database Import Cracked, Dirt and licker data to PFMS
Database Off grade Alert & tracking system
3. Supervisor’s Performance Tracking System
MF Labelling SystemMF Labelling System
1. TUN Labelling System2. Pallet tag Labeling System
Regular Pallet tag Promo Pallet tag 1st/2nd grade Pallet tag Pulp vats Pallet tag
3. Settings Printer Settings Barcode detail settings
1. TUN Labelling System1. TUN Labelling System
Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary and Tejas
Design Specification 1 Days Rosemary and Tejas
Approval 1 Day Rosemary
Development 5 Days Rosemary & TJ
Testing 1 Day Tejas & Rosemary
Create User Guide 1 Day Tejas
Total Estimate Time 10 DaysLive Environment: Install Application on Front Room PC
Training 5 Day Tejas and Supervisors
Total Project time including Training: 15 Days (3 Weeks)
Project Estimate TimeProject Estimate Time
2. Pallet tag labelling System2. Pallet tag labelling System
TASK DURATION in Days (7Hr/Day) Total Working
Days
Team Member
sREGULAR
PROMO 2ND RADE
PULP VATS
Settings
Roughly Design Planning
1 1 1/2 1/2 1 4 RG, TJ, Byron
Design Specification
1 1 1 1 1 4 RG & TJ
Approval 1 12 1/2 1/2 1/2 3 RG
Development
10 8 3 3 5 29 RG & TJ
Testing 1 1 1 1 1 5 RG & TJ
User Guide
1 1 1 1 1 5 TJ
Total Estimate Time: 50 Working Days
Training 5 5 5 5 20 RG & TJ
Total estimate Project time including Training: 70 Working Days (3 Month + 2 Weeks)
Project Estimate TimeProject Estimate Time
2. MOBA Integration
Off Grade Tracking & Alert SystemOff Grade Tracking & Alert System
• What is Off grade eggs? If MOBA system detects eggs with …..
Cracked Blood Dirt
called Off grade eggs.
Machine Speed: Nearly 3 Dozen per Second (36 Eggs)
Off Grade Track & Alert SystemOff Grade Track & Alert System
Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary, Byron and
Tejas
Design Specification 1 Days Rosemary and Tejas
Approval 1 Day Rosemary
Development 10 Days Rosemary & Tejas
Testing 1 Day Rosemary & Tejas
Create User Guide 1 Day TejasTotal Estimate Time 15 Days
Live Environment: Install Application on Spare TV (PC) on PF
Training 5 Day Tejas and Maintenance
Total Project time including Training: 20 Days (4 Weeks)
Project Estimate TimeProject Estimate Time
3. Performance Tracking System
Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary, Byron and
Tejas
Design Specification 1 Days Rosemary and Tejas
Approval 1 Day Rosemary
Development 20 Days Rosemary & Tejas
Testing 1 Day Rosemary & Tejas
Create User Guide 1 Day Tejas
Total Estimate Time 25 DaysLive Environment: Install Application on Byron’s PC
Training 1 Day Tejas
Total Project time including Training: 26 Days (5 Weeks)
Project Estimate TimeProject Estimate Time
SummarySummary
Projects DurationMF Labelling System 17 Weeks (4 Months + 1 Week)
MOBA: Off grade Tracking & Alert System 04 Weeks (1 Month)
Performance Tracking system 05 Weeks (1 Month + 1 Week)
Total Estimate Development time: 6 Month + 2 Weeks (910 Hours)