PARBATI H.E. PROJECTS
NHPC Limited( A Govt. of India Enterprise)
Dam of Parbati-III
3rd Regional Customer Meet forEsteemed Beneficiaries
Welcomes
Delegates ofDam of Parbati-II
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
2/32
Projects under construction by NHPCin Kullu valley
PARBATI H. E. PROJECT STAGE-II ( 800 MW )
PARBATI H. E. PROJECT STAGE-III ( 520 MW )
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
3/32
PARBATI H. E. PROJECT STAGE-III ( 520 MW )
VIEW OF DAM AREA
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
4/32
SCHEMATIC DIAGRAM OF PROJECT
Lot-1 (M/s Patel-L&T Consortium) Lot-2 (M/s Jagger-Gammon JV)
De-silting ChambersIntake Tunnels
HRT
SFT
Intake
Diversion Tunnels
TRT
TRT Outlet
PowerHouse
D/s SurgeChamber
GIS cumTransformer
Spillway
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
5/32
SALIENT FEATURES
DIVERSION TUNNEL - 2 Nos. 6.75 m Dia
- 391 m & 440 m Length
DAM - Rock fill 43m High 218 m LongSPILLWAY - Orifice Type 2Nos. 7.2m Wide
with 2 Radial Gates of 7.2m X14m
DESILTING CHAMBERS - 2 Nos. 12.2m X 22.5m X 250m
HEAD RACE TUNNEL- 7.25m Dia. 7869m Long
SURGE SHAFT - Restricted Orifice Type 13m
Dia 147m High
VERTICAL PRESSURE SHAFT - 2 Nos. Steel Lined 4.5m Dia 310m
POWERHOUSE - Underground Machine Hall of Size 123mX22mX43.6m
TAILRACE TUNNEL - 8.1m Size, 2713m Long
COMPLETION SCHEDULE - July.2012
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
6/32
SALIENT FEATURES
ANNUAL ENERGY GENERATION 1963 MU
Unit Tariff(Current CERC notification and prevailinginterest rate)
Rs. 2.97
CCEA CLEARED PROJECT COST
(AT MAY 2005 PRICE LEVEL) 2304.55 Cr.
CUMMULATIVE EXPENDITURE
(Up to Aug 2011- Provisional)
1539.02
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
7/32
M.O.U (Govt. of HP & NHPC) : 20 Nov.1998
Techno-Economic Clearance by CEA : 12 Nov. 2003
Environment Clearance by MOEF, : 16 Apr. 2005
Forest Clearances by MOEF : 13 Jun 2005
CCEA Clearance (Govt. of India) : 09 Nov.2005
Environment Clearance by SCST&E,
Shimla (Govt. of H.P) : 26 Dec.2005
Consent by HP SPCB : 20 Jan. 2006
CHRONOLOGY OF CLEARANCE
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
8/32
MAJOR HIGHLIGHTS
1. DT cum Spillway Tunnels including Lining
2. DT Intake Structure including HM gates
3. Cut-off wall
4. Overt lining of both Branch tunnels
5. Excavation of HRT From Face-1,2,3 & 4
6. Concreting of Power Intake structure7. Intake Structure area concrete
8. Spillway Control Structure Concrete
WORKS COMPLETED (DAM)
WORKS COMPLETED (POWER HOUSE)
1. All Major Excavation Works.2. Barrel Concrete of Unit-1 & 2.
3. Control Block Concrete
4. TRT U/s Overt Concrete
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
9/32
MAJOR HIGHLIGHTS
1. Plunge Pool Excavation
2. HRT Concrete Lining
WORKS UNDER PROGRESS (DAM)
WORKS UNDER PROGRESS (POWER HOUSE)
1. HRT Concrete Lining
2. Surge Shaft Concrete Lining3. Pressure Shafts Concrete Lining
4. Transformer Cavern Concreting
5. Power House Unit-3 & 4 Concreting
6. Surge Chamber & Draft Tube Concreting
7. TRT D/s Concrete Lining
WORKS UNDER PROGRESS (E&M)
1. Assembling of Unit-1
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
10/32
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
11/32
Damages due to recent Cloud Burst near Adit-2
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
12/32
Damages due to recent unexpected rainfall
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
13/32
PARBATI H.E. PROJECT, STAGE - II
(4x200MW)
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
14/32
LAYOUT PLAN PARBATI H.E. PROJECTSTAGE-II (800 MW)
Intake structure
Diversion
Tun
nel
Pa
rbatiRiver
Head Race Tunnel
Adit 1
Pancha Nallah Trench Weir
Feeder Tunnel
Power House
Adit 2 Adit 3
Adit 4Adit 5
Jiwa NallahSainj River
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
15/32
PARBATI H.E. PROJECT, STAGE-II (800MW)
The Parbati Hydroelectric project Stage-II is a run off the river and inter-basin transfer scheme and is spread over four valleys namely Manikaran
valley, Garsa Valley, Sainj Valley and Jiwa Valley in Kullu district ofHimachal Pradesh.
Date of Signing of MOU/PIA: Project taken over from
HPSEB on 20.11.1998
DPR of Parbati Stage-II cleared Oct-2000
TEC accorded Jan-2001
Environmental Clearance June-2001
RR Plan Approved Feb-2002
Date of Signing of ImplementationAgreement (IA) Sept-2002 (as perCCEA)
Schedule Commissioning as per IA Sept-2009 (as per CCEA)
Date of start of construction date Sept-2002
Proposed Commissioning Date Aug-2014
Chronology of Events
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
16/32
SALIENT FEATURES
DAM83.7m high Concrete Gravity across river
Parbati
SPILLWAY 3 Nos. Orifice type, 6m x 9m Radial Gates
DIVERSION TUNNEL 7.5 Dia., 275m long
DESILTING CHAMBERS 3 Nos., 15m X 16m X 170m
HEAD RACE TUNNEL6m Dia., 31.5 km long (22.5 km by DBM &
9.05 km by TBM)
SURGE SHAFT 17m Dia., 130m depth
PRESSURE SHAFT2 Nos., 3.5m Dia Steel lined 2150m &
2133m length (1546m Inclined)
POWERHOUSE Surface, Size 123m x 47m x 44m
UNITS 4 Nos. of 200 MW each, Pelton Turbine
RATED HEAD 789m (Gross Head 867m)
ANNUAL ENERGY GENR. 3108 MU
ESTIMATED COST Rs. 3919.59 Crs.
TARIFF Rs. 3.54 per KWH
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
17/32
PARBATI H.E. PROJECT STAGE-II (800MW)
UNIQUE HIGHLIGHTS
1. Two inclined pressure shafts of 1546M length each at an
inclination of 300 successfully bored for the first time in the
world by using Tunnel Boring Machine and completed in record
time of 16 months.
2. Concreting & Grouting in the inclined pressure shafts, behind the
steel liners had been done up to a height of 800 meter by using
Schwing pump for the first time in World.
3. Total length of Head Race Tunnel is 31.52 km which is the longest
hydro tunnel in Indiabeing constructed.
4. In the Dam area, the weak zone of the hill (Fossil Valley) grouted
successfully up to a depth of 120 m in two stages with ultra fine
cement of high Blaine value imported from Japan, for the first
time in India.
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
18/32
PARBATI H.E. PROJECT STAGE-II (800MW)
STATUS OF WORKS
ITEMS UNIT TOTAL COMPLETED
Dam & Intake
Concreting
cum 1.96Lakhs 1.78Lakhs
(90.8%)
HRT Excavation km 31.525 26.61 (84%)
HRT Lining km 31.525 15.586 (49.4%)
Surge Shaft
Excavation
m 130 Completed (100%)
Surge Shaft Lining m 130 50.9 (39.15%)
Pressure Shaft
Excavation
m 2 x 1546 Completed
(100%)
Pressure Shaft
Steel Lining and
Concreting
m 2 x 1545 Completed
(100%)
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
19/32
PARBATI H.E. PROJECT STAGE-II (800MW)
STATUS OF WORKS
ITEMS UNIT TOTAL EXECUTED
Power House Sub-
Structure Concreting
cum 28416 28416 (100%)
Power House Super-Structure Concreting
cum 25000 3398 (13.6%)
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
20/32
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
21/32
PARBATI H.E. PROJECT STAGE-II (800MW)
DAM CONCRETING
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
22/32
INTAKE STRUCTURE CONCRETING
PARBATI H.E. PROJECT STAGE-II (800MW)
PARBATI H E PROJECT STAGE II (800MW)
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
23/32
CONCRETING IN DESILTING CHAMBER
PARBATI H.E. PROJECT STAGE-II (800MW)
PARBATI H E PROJECT STAGE II (800MW)
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
24/32
Status of Head Race Tunnel (Excavation)
(Drawing not to scale)
Inlet Adit
F-3F-2F-1F-0 F-8 F-11
Total 31.525 Km
6251m 13099m 2038m 7375m 2434m
F-4 F-6 F-7 F-9 F-10
Adit-II Adit-III
Adit-IV Adit-V
215m
LEGEND
COMPLETED 26610m
BALANCE 4915 m
PARBATI H.E. PROJECT STAGE-II (800MW)
Adit-I
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
25/32
PARBATI H.E. PROJECT STAGE-II (800MW)
POWER HOUSE CONCRETING WORK
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
26/32
PARBATI H.E. PROJECT STAGE-II (800MW)
POWER HOUSE CONCRETING WORK
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
27/32
Inclined Pressure Shaft (Right)
Total Length- 1545 m
Excavation Completed- 1545 m (100 %)
Lining Completed (100%).
INCLINED PRESSURE SHAFTS
Inclined Pressure Shaft
2 Nos., Steel Lined 3.5m Dia.
Each bifurcating into two Nos. 3m Dia.Penstocks near Power House
Inclined Pressure Shaft (Left)
Total Length- 1545 m
Excavation Completed- 1545 m (100 %)
Lining Completed -1545 m (100%)
300 300
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
28/32
PARBATI H.E. PROJECT STAGE-II (800MW)
Problems Encountered During Execution of Project
A. Head Race Tunnel :
Severe Rock Bursting due to high superincumbent cover
(upto 1.6 km)
Heavy sudden ingress of water of the order of 8000 lpm
with 7000 cum discharge of silt encountered in the tunnel
which had buried and damaged the TBM.
TBM refurbished and the fault zone treatment being taken
up in consultation with international experts.
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
29/32
PARBATI H.E. PROJECT STAGE-II (800MW)
Submergence of TBM due to sudden heavy ingress of water
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
30/32
PARBATI H.E. PROJECT STAGE-II (800MW)
Submergence of TBM due to sudden heavy ingress of water
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified
31/32
PARBATI H.E. PROJECT STAGE-II (800MW)
Problems Encountered During Execution of Project
B. Powerhouse :
Occurrence of three major slides of Power House Back slope during
Apr04, Jun06 and Feb07.
C. Dam :
Ban on Aggregates:
Hon'ble High Court H.P had imposed ban on 03.08.07 onprocurement of aggregate from any mining source in Distt. Kullu
for all mega projects, which was lifted in March 2008. The work of
Dam and other concreting was stopped during this period of 7
months.
-
8/4/2019 Presentation 2011 Sept PHEP3 Modified