![Page 1: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/1.jpg)
PLYMOUTH CREEK CENTER FINAL DESIGN PRESENTATIONJUNE 23, 2020
![Page 2: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/2.jpg)
2©2020 HGA | 06.23.2020
AGENDA
1. Project Milestones
2. Project Budget
3. Bidding Process Overview
4. Site Plan
5. Floor Plans
6. Exterior Renderings
7. Interior Renderings
8. B3 Summary
![Page 3: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/3.jpg)
3©2020 HGA | 06.23.2020
City of Plymouth – Plymouth Creek Center
Pre-Construction Milestone Schedule 6/12/20
Pre-Construction
• Construction Bid Documents Complete June 19, 2020
• City Council Meeting/Approval for Bid June 23, 2020
• Issue Advertisement to Bid June 24, 2020
• Bid Period June 24 – July 28, 2020
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August TBD
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
City of Plymouth – Plymouth Creek Center
Pre-Construction Milestone Schedule 6/12/20
Pre-Construction
• Construction Bid Documents Complete June 19, 2020
• City Council Meeting/Approval for Bid June 23, 2020
• Issue Advertisement to Bid June 24, 2020
• Bid Period June 24 – July 28, 2020
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August 18, 2020
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
• Phase 2 Renovation Existing Building October 2021 – March 2022
• Phase 3 West Fitness Addition November 2021 – August 2022
![Page 4: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/4.jpg)
4©2020 HGA | 06.23.2020
City of Plymouth – Plymouth Creek Center
Pre-Construction Milestone Schedule 6/12/20
Pre-Construction
• Construction Bid Documents Complete June 19, 2020
• City Council Meeting/Approval for Bid June 23, 2020
• Issue Advertisement to Bid June 24, 2020
• Bid Period June 24 – July 28, 2020
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August 18, 2020
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
City of Plymouth – Plymouth Creek Center
Pre-Construction Milestone Schedule 6/12/20
Pre-Construction
• Construction Bid Documents Complete June 19, 2020
• City Council Meeting/Approval for Bid June 23, 2020
• Issue Advertisement to Bid June 24, 2020
• Bid Period June 24 – July 28, 2020
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August 18, 2020
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
• Phase 2 Renovation Existing Building October 2021 – March 2022
• Phase 3 West Fitness Addition November 2021 – August 2022
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August 18, 2020
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
• Phase 2 Renovation Existing Building October 2021 – March 2022
• Phase 3 West Fitness Addition November 2021 – August 2022
• Phase 3 South Parking Lot Expansion November 2021 – August 2022
City of Plymouth – Plymouth Creek Center
Pre-Construction Milestone Schedule 6/12/20
Pre-Construction
• Construction Bid Documents Complete June 19, 2020
• City Council Meeting/Approval for Bid June 23, 2020
• Issue Advertisement to Bid June 24, 2020
• Bid Period June 24 – July 28, 2020
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August 18, 2020
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
![Page 5: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/5.jpg)
5©2020 HGA | 06.23.2020
City of Plymouth – Plymouth Creek Center
Estimate Update 6/12/20
• Construction Estimate Update - $44,219,188
• Soft Costs Estimate Update - $7,752,363
• Total Project Estimate Update - $51,971,551
• Project Total Budget Target - $51,974,500
• Above numbers include contingencies, labor and material escalation, and completion in
2022
City of Plymouth – Plymouth Creek Center
Pre-Construction Milestone Schedule 6/12/20
Pre-Construction
• Construction Bid Documents Complete June 19, 2020
• City Council Meeting/Approval for Bid June 23, 2020
• Issue Advertisement to Bid June 24, 2020
• Bid Period June 24 – July 28, 2020
• Bid Opening (1:00pm) July 28, 2020
• Meet w/Team to Review Bids July 30, 2020
• Packet to City Council Agenda August 11, 2020
• City Council Meeting/Approval to Award August 18, 2020
Construction
• Phase 1 Construction Start August 2020
• Phase 1 East Gym/Playground Addition August 2020 – November 2021
• Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021
• Phase 2 Renovation Existing Building October 2021 – March 2022
• Phase 3 West Fitness Addition November 2021 – August 2022
![Page 6: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/6.jpg)
6©2020 HGA | 06.23.2020
SITE PLAN
Stormwater Basin
West Entrance
Pedestrian Promenade
Pedestrian Crossing
Waiting Area
Turf Grass Program Area
Two Way Traffic +Drop Off Lane
Drop Off Lane
East Entrance
![Page 7: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/7.jpg)
7©2020 HGA | 06.23.2020
GROUND FLOOR PLANLEVEL 01
UP
BU
COMMUFITNESS
OFFICEPLAY
PLAY SUPPORT
INDOOR PLAY
YOUTH
GE
WOMEN
MEN
LARGE FITNESS
STORAGE
STORAGE
BOILER /MECHANICAL
OFFICE
WORKROOM
RECEPTION
STAFF
TLT
STORAGE
GENERATOR
TRASH/ STR
CHANGING CHANGING
CHNG/ SHWR
CHNG/ SHWR CHNG/ SHWR
CHNG/ SHWR
FITNESS WAITING
OFFICE
STORAGE
STOR.
CHANGING
LOCKERS
STAIR F
VESTIBULE
STORAGE
FIRST FLOOR PLAN
MAIN ENTRY
SECONDARY FITNESS ENTRY
EXISTING BUILDING
EXISTING SOCCER FIELD / DOME
POTENTIAL FUTURE
GYMNASIUM
LINE OF TRACK ABOVE
![Page 8: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/8.jpg)
8©2020 HGA | 06.23.2020
UPPER LEVEL PLANLEVEL 02
![Page 9: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/9.jpg)
9©2020 HGA | 06.23.2020
LOWER LEVEL PLANLOWER LEVEL
![Page 10: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/10.jpg)
10©2020 HGA | 06.23.2020 MAIN ENTRY
![Page 11: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/11.jpg)
11©2020 HGA | 06.23.2020 MAIN ENTRY AT DUSK
![Page 12: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/12.jpg)
12©2020 HGA | 06.23.2020 VIEW FROM MILLENIUM GARDENS
![Page 13: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/13.jpg)
13©2020 HGA | 06.23.2020 EARLY EVENING VIEW FROM MILLENIUM GARDENS
![Page 14: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/14.jpg)
14©2020 HGA | 06.23.2020 VIEW FROM EXISTING FIELDHOUSE
![Page 15: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/15.jpg)
15©2020 HGA | 06.23.2020 FITNESS ENTRY
![Page 16: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/16.jpg)
16©2020 HGA | 06.23.2020 EVENING VIEW OF FITNESS ENTRY
![Page 17: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/17.jpg)
17©2020 HGA | 06.23.2020 ENTRY LOBBY & RECEPTION |VIEW NORTH
![Page 18: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/18.jpg)
18©2020 HGA | 06.23.2020 ENTRY LOBBY & RECEPTION | VIEW WEST
![Page 19: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/19.jpg)
19©2020 HGA | 06.23.2020 PLYMOUTH ROOM PREFUNCTION SPACE
![Page 20: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/20.jpg)
20©2020 HGA | 06.23.2020 WEST LOUNGE
![Page 21: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/21.jpg)
21©2020 HGA | 06.23.2020 INDOOR PLAY SPACE
*Note: Play equipment and floor surface colors pending final selection and coordination with playground vendor.
![Page 22: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/22.jpg)
22©2020 HGA | 06.23.2020 UPPER LEVEL FITNESS & TRACK | VIEW EAST
![Page 23: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/23.jpg)
23©2020 HGA | 06.23.2020 GYMNASIUM & TRACK
![Page 24: PLYMOUTH CREEK CENTER · 2020-06-15 · • Phase 1 East Gym/Playground Addition August 2020 – November 2021 • Phase 1 East Parking Lot Expansion Sept 2020 – Sept 2021 ©2020](https://reader036.vdocuments.us/reader036/viewer/2022081406/5f156460341b450a0e271106/html5/thumbnails/24.jpg)
SITE & WATER MATERIALS & WASTE
PLYMOUTH CREEKCENTER RENOVATION
INDOORENVIRONMENTAL QUALITY
LOW EMITTING MATERIALS
DAYLIGHT
VENTILATION DESIGN
THERMAL COMFORT
EFFECTIVE ACOUSTICS
BIRD SAFE BUILDING
HABITAT MANAGEMENT
WATER EFFICIENCY:
OF MATERIALS USED
DIVERSION
WASTE MANAGEMENT
HEALTH
ENVIRONMENTALLYPREFERRED MATERIALS
BUILDING COMMISSIONING
OPERATIONS MANAGEMENT PLAN
POST-OCCUPANCYEVALUATION
SITE & WATER MATERIALS & WASTE
ENERGY & ATMOSPHERE
PERFORMANCEMANAGEMENT
BIRD SAFE BUILDING
HABITAT MANAGEMENT
WATER EFFICIENCY:
OF MATERIALS USED
DIVERSION
920THOUSAND
LBS/YR
WASTE MANAGEMENT
HEALTH
ENVIRONMENTALLYPREFERRED MATERIALS
ENERGY COST SAVINGS
PEAK ELECTRIC SAVINGS:
CARBON EMISSIONS
PROJECTED UTILITY REBATE:
Values are estimates Based upon current design and are subject to change.
BUILDING COMMISSIONING
OPERATIONS MANAGEMENT PLAN
POST-OCCUPANCYEVALUATION
ENAT
PERFORMANCEMANAGEMENT
Values are estimates Based upon current design and are subject to change.