Download - PGCL 1
-
8/10/2019 PGCL 1
1/6
Attachment-1
-1/6-
Seventh Five Year Plan (2016-2020)Goals, Targets Activities and Indicative Costs
Ministry: Power, Energy & Mineral Resource MinistryDivision: Energy & Mineral Resource Division
Corporation: Bangladesh Oil, Gas & Mineral Corporation (Petrobangla)Executing Agency: Pashchimanchal Gas Company Limited (PGCL)
Sl.No. Goals Targets
Activities(Policy / Program / Project)
Program /Projects wise
indicative cost(lakh Tk at 2014-
15 prices)(1) (2) (3) (4) (5)01. Gas Distribution
Network at Belkuchiand ChauhaliUpazila
Implementing Year:2017~2019
Implementation of the proposed 65.00 Km (2 to 8dia) gas distribution pipelineis required to supply naturalgas for domestic,commercial, industrial, CNGand captive power consumerat Belkuchi and Chauhaliupazila of the country.
1. Pipeline route survey, IEE, EIA, RP and soil investigation,rent for project office, rent for godown, rent for microbus,training for officers, insurance Pre-Shipment Inspection(PSI), Insurance, Clearing & Forwarding (C&F), Carrying /Mobilization of materials and other supplies.
2. Acquisition of 1.25 acres and requisition /road cutting permission from concerned road owners authority forinstalling 65.00 Km pipelines.
3. Procurement of line pipe and pipeline materials (fittings,wrapping materials), valves, CP materials, DRS & TBSmaterials, local gas connection materials, office equipment.
4. Construction and installation including testing &commissioning of 65.00 Km (2 to 8 dia) gas distribution
pipeline & 02 nos. TBS & DRS and their cathodic protection system.5. Associated civil construction works.
Estimated cost ofthe Project (inLakh Taka) Total7,500.00 (GOB)considering 100%Equity
Project Period:July 2017 to June2019
02. Gas Distribution Network AtKamarkhandaUpazila.
Implementation of the proposed 30 .00 Km (2 to 8dia) gas distribution pipelineis required to supply natural
1. Pipeline route survey, IEE, EIA, RP and soil investigation,rent for project office, rent for godown, rent for microbus,training for officers, insurance Pre-Shipment Inspection(PSI), Insurance, Clearing & Forwarding (C&F), Carrying /
Estimated cost ofthe Project (inLakh Taka) Total4,000.00 (GOB)
-
8/10/2019 PGCL 1
2/6
Attachment-1
-2/6-
Sl.No. Goals Targets
Activities(Policy / Program / Project)
Program /Projects wise
indicative cost(lakh Tk at 2014-
15 prices)(1) (2) (3) (4) (5)
Implementing Year:2018~2020
gas for domestic,commercial, industrial, CNGand captive power consumerat Kamarkhanda upazila ofthe country.
Mobilization of materials and other supplies.2. Acquisition of 0.75 acres and requisition /road cutting
permission from concerned road owners authority forinstalling 65.00 Km pipelines.
3. Procurement of line pipe and pipeline materials (fittings,wrapping materials), valves, CP materials, DRS & TBSmaterials, local gas connection materials, office equipment.
4. Construction and installation including testing &commissioning of 30 .00 Km (2 to 8 dia) gas distribution
pipeline & 02 nos. TBS & DRS and their cathodic
protection system.5. Associated civil construction works.
considering 100%Equity
Project Period:July 2018 to June2020
03. Vertical Extension ofBogra office building.Bogra (1 st & 2 nd Floor)
Implementing Year:2015~2016
Implementation of thevertical extension of BograOffice for providing theoffice facility to theemployees of Bogra SalesSection.
1. Drawing, Designing and Estimation of the VerticalExtension of 2-storied Office building at Bogra.
2. Preparation of tender document, tender invitation, tenderopening and tender evaluation etc.
3. Also implementation the Vertical Extension of 2-storiedOffice building at Bogra.
Estimated cost ofthe Project (inLakh Taka) Total40.00 (CompanyRevenue Budget)
04. Gas Distribution Network at Natore
Town andLalpurUpazila
Implementing Year:2018~2020
Implementation of the proposed 145.00 Km (1 to
8 dia) gas distribution pipeline is required to supplynatural gas for domestic,commercial, industrial, CNGand captive power consumerat Natore Town andLalpurUpazila.
1. Pipeline route survey, IEE, EIA, RP and soil investigation,rent for project office, rent for godown, rent for microbus,
training for officers, insurance Pre-Shipment Inspection(PSI), Insurance, Clearing & Forwarding (C&F), Carrying /Mobilization of materials and other supplies.
2. Acquisition of 2.00 acres and requisition /road cutting permission from concerned road owners authority forinstalling 145.00 Km pipelines.
3. Procurement of line pipe and pipeline materials (fittings,
Estimated cost ofthe Project (in
Lakh Taka) Total120,00.00 (GOB)considering 100%Equity
Project Period:July 2018 to June
-
8/10/2019 PGCL 1
3/6
Attachment-1
-3/6-
Sl.No. Goals Targets
Activities(Policy / Program / Project)
Program /Projects wise
indicative cost(lakh Tk at 2014-
15 prices)(1) (2) (3) (4) (5)
wrapping materials), valves, CP materials, DRS & TBSmaterials, local gas connection materials, office equipment.
4. Construction and installation including testing &commissioning of 145.00 Km (1 to 8 dia) gas distribution
pipeline, 02 nos. TBS & 02 nos.DRS and theircathodicprotection system.
5. Associated civil construction works.
2020
05. Gas Distribution Network at RangpurCity and its adjoining
area.
Implementing Year:2018~2020
Implementation of the proposed 160 .00 Km (1 to8 dia) gas distribution
pipeline is required to supplynatural gas for domestic,commercial, industrial, CNGand captive power consumerat Rangpur City and itsadjoining area.
1. Pipeline route survey, IEE, EIA, RP and soil investigation,rent for project office, rent for godown, rent for microbus,training for officers, insurance Pre-Shipment Inspection
(PSI), Insurance, Clearing & Forwarding (C&F), Carrying /Mobilization of materials and other supplies.2. Acquisition of 2.00 acres and requisition /road cutting
permission from concerned road owners authority forinstalling 160.00 Km pipelines.
3. Procurement of line pipe and pipeline materials (fittings,wrapping materials), valves, CP materials, DRS & TBSmaterials, local gas connection materials, office equipment.
4. Construction and installation including testing &commissioning of 160 .00 Km (1 to 8 dia) gas distribution
pipeline, 02 nos. TBS & 02 nos.DRS and their
cathodicprotection system.5. Associated civil construction works.
Estimated cost ofthe Project (inLakh Taka) Total
135,00.00 (GOB)considering 100%Equity
Project Period:July 2018 to June2020
06. Gas supply toSirajganj 225 MWCombined CyclePower Plant (2 nd unit-Dual Fuel)
Implementation of the proposed 12 100.00 M 1000 psig service pipelineand installing interconnectingfacilities is required to supply
1. Pipeline route survey, IEE, EIA, RP and soil investigation,insurance Pre-Shipment Inspection (PSI), Insurance,Clearing & Forwarding (C&F), Carrying / Mobilization ofmaterials and other supplies.
2. Requisition /road cutting permission from concerned road
Estimated cost ofthe Project (inLakh Taka) Total3,542.40(Depository Fund
-
8/10/2019 PGCL 1
4/6
Attachment-1
-4/6-
Sl.No. Goals Targets
Activities(Policy / Program / Project)
Program /Projects wise
indicative cost(lakh Tk at 2014-
15 prices)(1) (2) (3) (4) (5)
Implementing Year:2014~2017
Natural gas for Sirajganj 225MW Combined Cycle PowerPlant (2 nd Unit Dual Fuel)under NWPGCL.
owners authority for installing 12 100.00 M 1000 psig service lines.
3. Procurement of line pipe and pipeline materials (fittings,wrapping materials), valves, CP materials, RMS materials,local gas connection materials, office equipment.
4. Construction and installation including testing &commissioning of 12 100.00 M 1000 psig serviceline, 01 nos. RMS and their cathodic protection system.
5. Associated civil construction works.
by NWPGCL)
07. Construction of 10 bar
ring main (8 140 psig10.00 Km) andDRS Modification atBogra Town.
Implementing Year:2016~2020
Implementation of proposed
8 140 psig 10.00 Km)ring main Bogra Town forenhancement of the capacityof existing Bogra gasnetwork.
1. Pipeline route survey, land acquisition land development
2. Requisition /road cutting permission from concerned roadowners authority for installing 10.00 Km pipelines.3. Procurement of line pipe and pipeline materials fitting,
wrapping materials, valves, CP materials, DRS & TBSmaterials ,Local gas materials
4. Construction and installation including testing &commissioning of 10.00 Km gas distribution, DRS &cathotic protection system.
5. Associated civil construction works.
Estimated cost of
the Project (inLakh Taka) Total900.00 (CompanyRevenue Budget)
08. Construction of 2-Storied office
Building (6-storiedfoundation) forSirajganj sales sectionat Sirajganj Town.
Implementing Year:2016~2019
Implementation of theConstruction of 2-Storied
office Building (6-storiedfoundation) for providing theoffice facility to theemployees of Sirajganj SalesSection.
1. Acquisition of 1.00 acres area in Sirajganj Town.2. Land Development, Drawing, Designing and Estimation of
the construction of 2-storied office building (6-storiedfoundation) for Sirajganj Sales Section.
3. Preparation of tender document, tender invitation, tenderopening and tender evaluation etc.
4. Implementation of Construction of 2- storied Head Office building (6-storied foundation) at Nalka complex, Nalka,Sirajganj.
Estimated cost ofthe Project (in
Lakh Taka) Total450.00 (CompanyRevenue Budget)
-
8/10/2019 PGCL 1
5/6
Attachment-1
-5/6-
Sl.No. Goals Targets
Activities(Policy / Program / Project)
Program /Projects wise
indicative cost(lakh Tk at 2014-
15 prices)(1) (2) (3) (4) (5)
5. Construction of Boundary Wall, Internal Road, AreaLightening etc. works.
09. Gas supply toSirajganj 367 MWCombined Cycle IPP
Implementing Year:2015~2018
Implementation of the proposed 20 5.50 Km 1000 psig service pipelineand installing interconnectingfacilities is required to supply
Natural gas for Sirajganj 367MW Combined Cycle IPP.
1. Pipeline route survey, IEE, EIA, RP and soil investigation,insurance Pre-Shipment Inspection (PSI), Insurance,Clearing & Forwarding (C&F), Carrying / Mobilization ofmaterials and other supplies.
2. Requisition /road cutting permission from concerned roadowners authority for installing 20 5.50 M 1000 psigservice lines.
3. Procurement of line pipe and pipeline materials (fittings,
wrapping materials), valves, CP materials, RMS materials,local gas connection materials, office equipment.4. Construction and installation including testing &
commissioning of 20 5.50 M 1000 psig service line,01 nos. RMS and their cathodic protection system.
5. Associated civil construction works.
Estimated cost ofthe Project (inLakh Taka) Total6,000.00(CustomerDepository Fund)
10. Gas supply toSirajganj 214 MWCombined CyclePower Plant
Implementing Year:2016~2019
Implementation of the proposed 12 2.00 Km 1000 psig service pipelineand installing interconnectingfacilities is required to supply
Natural gas for Sirajganj 214MW Combined Cycle PowerPlant.
1. Pipeline route survey, IEE, EIA, RP and soil investigation,insurance Pre-Shipment Inspection (PSI), Insurance,Clearing & Forwarding (C&F), Carrying / Mobilization ofmaterials and other supplies.
2. Requisition /road cutting permission from concerned road
owners authority for installing 12 2.00 M 1000 psigservice lines.
3. Procurement of line pipe and pipeline materials (fittings,wrapping materials), valves, CP materials, RMS materials,local gas connection materials, office equipment.
4. Construction and installation including testing &commissioning of 12 2.00 M 1000 psig service line,
Estimated cost ofthe Project (inLakh Taka) Total4,600.00(Customer
Depository Fund)
-
8/10/2019 PGCL 1
6/6
Attachment-1
-6/6-
Sl.No. Goals Targets
Activities(Policy / Program / Project)
Program /Projects wise
indicative cost(lakh Tk at 2014-
15 prices)(1) (2) (3) (4) (5)
01 nos. RMS and their cathodic protection system.5. Associated civil construction works.