1
Outline
• Just-in-Time (JIT)• Examples of Waste• Some Elements of JIT
LESSON 24: JUST-IN-TIME
![Page 2: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/2.jpg)
2
• Producing only what is needed and when it is needed
• A philosophy
• An integrated management system
Just-in-time
![Page 3: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/3.jpg)
3
• Theme: eliminate all waste including the ones caused by:– inventory management – supplier selection– defective parts– scheduling of production and delivery– information system
Just-in-time
![Page 4: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/4.jpg)
4
Examples Of Waste
• Watching a machine run• Waiting for parts• Counting parts• Overproduction• Moving parts over long
distances• Storing inventory• Looking for tools• Machine breakdown• Rework
![Page 5: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/5.jpg)
5
Some Elements Of JIT
1. Focused factory networks 2. Grouped Technology: Cellular layouts 3. Quality at the source
4. Flexible resources5. Pull production system6. Kanban production control7. Small-lot production and purchase8. Quick setups9. Supplier networks
![Page 6: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/6.jpg)
6
Cellular Layouts
• Group dissimilar machines in a cell to produce a family of parts
• Reduce setup time and transit time• Send work in one direction through the cell (resembling
a small assembly line)• Adjust cycle time by changing worker paths
![Page 7: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/7.jpg)
7
Cellular Layouts
Enter
Worker 1
Worker 2Worker
3
Exit
Key: Product routeWorker route
Machines
![Page 8: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/8.jpg)
8
Original Process Layout
12
1
2
3
4
5
6 7
8
9
10
11
A B C Raw materials
Assembly
![Page 9: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/9.jpg)
9
Part Routing Matrix
Parts 1 2 3 4 5 6 7 8 9 10 11 12A x x x x xB x x x xC x x xD x x x x xE x x xF x x xG x x x xH x x x
Machines
![Page 10: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/10.jpg)
10
Part Routing Matrix - Reordered
Parts 1 2 4 3 5 6 7 8 9 10 11 12A x x x x xB x x x xC x x xD x x x x xE x x xF x x xG x x x xH x x x
Machines
![Page 11: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/11.jpg)
11
Parts 1 2 4 3 5 6 7 8 9 10 11 12A x x x x xD x x x x xB x x x xC x x xE x x xF x x xG x x x xH x x x
Machines
Part Routing Matrix - Reordered
![Page 12: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/12.jpg)
12
Parts 1 2 4 8 3 5 6 7 9 10 11 12A x x x x xD x x x x xB x x x xC x x xE x x xF x x xG x x x xH x x x
Machines
Part Routing Matrix - Reordered
![Page 13: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/13.jpg)
13
Parts 1 2 4 8 3 5 6 7 9 10 11 12A x x x x xD x x x x xF x x xB x x x xC x x xE x x xG x x x xH x x x
Machines
Part Routing Matrix - Reordered
![Page 14: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/14.jpg)
14
Parts 1 2 4 8 10 3 5 6 7 9 11 12A x x x x xD x x x x xF x x xB x x x xC x x xE x x xG x x x xH x x x
Machines
Part Routing Matrix - Reordered
![Page 15: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/15.jpg)
15
Parts 1 2 4 8 10 3 6 9 5 7 11 12A x x x x xD x x x x xF x x xC x x xG x x x xB x x x xE x x xH x x x
Machines
Part Routing Matrix - Reordered
![Page 16: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/16.jpg)
16
Cellular Layout Solution
12
12 3
4
5
6
7
8 910
11
A BCRaw materials
Cell1 Cell 2 Cell 3
Assembly
![Page 17: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/17.jpg)
17
Advantages of Cellular Layouts
• Reduced material handling and transit time
• Reduced setup time
• Reduced work-in-process inventory
• Better use of human resources
• Easier to control
• Easier to automate
![Page 18: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/18.jpg)
18
Disadvantages of Cellular Layouts
• Inadequate part families
• Poorly balanced cells
• Expanded training and scheduling of workers
• Increased capital investment
![Page 19: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/19.jpg)
19
Quality At The Source
• Jidoka is the authority to stop a production line• Andon lights signal quality problems• Undercapacity scheduling allows for planning,
problem solving & maintenance• Visual control makes problems visible• Poka-yoke prevents defects
![Page 20: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/20.jpg)
20
Kaizen
• Continuous improvement• Requires total employment involvement• The essence of JIT is the willingness of workers to
• spot quality problems,• halt production when necessary,• generate ideas for improvement,• analyze problems, and • perform different functions
![Page 21: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/21.jpg)
21
Flexible Resources
• Multifunctional workers
• General purpose machines
• Study operators & improve operations
![Page 22: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/22.jpg)
22
Flexible Resources
![Page 23: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/23.jpg)
23
Flexible Resources
Worker 1 Worker 2
Worker 3
Cell 1
Cell 5Cell 3
Cell 2
Cell 4
![Page 24: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/24.jpg)
24
Pull Production System
• In a push system, a schedule is prepared in advance and as soon as one process completes its work, its products are sent to the next process.
• In a pull system, workers take the parts or materials from the preceding stations as needed.Workers at the preceding stations may produce the next unit only after their outputs are taken by the workers in the subsequent processes.
• Although the concept of pull production seems simple, it can be difficult to implement. Kanbans are introduced to implement the pull system.
![Page 25: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/25.jpg)
25
Kanban Production Control
• A kanban is a card that indicates quantity of production
• Kanbans maintain the discipline of pull production– - A production kanban authorizes production– - A withdrawal kanban authorizes the movement of goods
MachiningM-2
AssemblyA-4
Part no.: 7412Description: Slip rings
From : To:
Box capacity 25
Box Type A
Issue No. 3/5
![Page 26: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/26.jpg)
26
The Origin Of Kanban
Q = order quantityR = reorder point = demand during lead time
Bin 1 Bin 2
Q - RR
Reorder Card
Kanban
a. Two-bin inventory system b. Kanban Inventory System
![Page 27: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/27.jpg)
27
A Single-Kanban System
![Page 28: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/28.jpg)
28
A Single-Card Kanban System
Consider the fabrication cell that feeds two assembly lines.
1. As an assembly line needs more parts, the kanban card for those parts is taken to the receiving post and a full container of parts is removed from the storage area.
2. The receiving post accumulates cards for both assembly lines and sequences the production of replenishment parts.
![Page 29: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/29.jpg)
29
A Dual Kanban System
![Page 30: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/30.jpg)
30
1. When the number of tickets on the withdrawal kanban reaches a predetermined level, a worker takes these tickets to the store location.
2. The workers compares the part number on the production ordering kanban at the store with the part number on the withdrawal kanban.
3. The worker removes the production ordering kanban from the containers, places them on the production ordering kanban post, and places the withdrawal kanbans in the containers.
4. When a specified number of production ordering kanbans have accumulated, work center 1 proceeds with production.
A Two-Card System
![Page 31: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/31.jpg)
31
5. The worker transports parts picked up at the store to work center 2 and places them in a holding area until they are required for production.
6. When the parts enter production at work center 2, the worker removes the withdrawal kanbans and places them on the withdrawal kanban post.
![Page 32: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/32.jpg)
Kanban Squares
X X X
XX
X
Flow of workFlow of information
![Page 33: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/33.jpg)
Kanban Racks
407 409 410 412
408
411
![Page 34: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/34.jpg)
Signal Kanban
407
408
409
407 408 409
![Page 35: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/35.jpg)
Kanban Post Office
65 66 67 68 69 70 71
72 73 74 75 76 77 78
79 80 81 82 83 84 85
86 87 88 89 90 91 92
93 94 95 96 97 98 99
100 101 102 103 104 105 106
![Page 36: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/36.jpg)
Types Of Kanbans
• Kanban Square– marked area designed to hold items
• Signal Kanban– triangular kanban used to signal production at the
previous workstation• Material Kanban
– used to order material in advance of a process• Supplier Kanban
– rotates between the factory and supplier
![Page 37: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/37.jpg)
Determining Number Of Kanbans
where– y = number of kanbans or containers
– = average demand over some time period– L = lead time to produce parts– w = safety stock, usually 10% of the demand during
lead time– a = container size
avg.demand during lead time + safety stockcontainer size
No. of kanbans =
a
wLDy
D
![Page 38: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/38.jpg)
Kanban Calculation Example
Problem statement:
= 150 bottles per hour L = 30 minutes = 0.5 hours
= (150)(0.5) = 75 w = 10% of
a = 25 bottles
Solution:
Round up to 4 (allow some slack)
or down to 3 (force improvement)
D
LDLD
containers Kanban .))(.(
3325
751075
a
wLDy
![Page 39: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/39.jpg)
39
Small-Lot Production
• Requires less space & capital investment
• Moves processes closer together
• Makes quality problems easier to detect
• Makes processes more dependent on each other
![Page 40: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/40.jpg)
40
Small-lot Production
and Purchase
![Page 41: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/41.jpg)
41
Reducing Setup Time
• Preset desired settings
• Use quick fasteners• Use locator pins• Prevent
misalignments• Eliminate tools• Make movements
easier
![Page 42: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/42.jpg)
42
Trends In Supplier Policies
1. Locate near to the customer
2. Use small, side loaded trucks and ship mixed loads
3. Consider establishing small warehouses near to the customer or consolidating warehouses with other suppliers
4. Use standardized containers and make deliveries according to a precise delivery schedule
5. Become a certified supplier and accept payment at regular intervals rather than upon delivery
![Page 43: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/43.jpg)
43
Benefits Of JIT
1. Reduced inventory
2. Improved quality
3. Lower costs
4. Reduced space requirements
5. Shorter lead time
6. Increased productivity
7. Greater flexibility
8. Better relations with suppliers
9. Simplified scheduling and control activities
10. Increased capacity
11. Better use of human resources
12. More product variety
![Page 44: Outline Just-in-Time (JIT) Examples of Waste Some Elements of JIT](https://reader035.vdocuments.us/reader035/viewer/2022062314/56813b38550346895da40d13/html5/thumbnails/44.jpg)
44
READING AND EXERCISES
Lesson 24
Reading: Section 7.6 pp. 387-395 (4th Ed.) pp. 377-384 (5th Ed.)
Exercise: 37 p. 395 (4th Ed.), p. 384 (5th Ed.)