Download - Outline Construction Method Statement
![Page 1: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/1.jpg)
APPENDIX K
Dunan Hydro Electric Scheme
Outline Construction Method Statement
19
th March 2013
Revision A
Eugene Craig
07886 401194
DHG Hydro Ltd 7 St James’s Gardens
London
W11 4RB
0131 208 0525
![Page 2: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/2.jpg)
2
INDEX
1 INTRODUCTION ............................................................................................................................. 3
2 SITE ESTABLISHMENT/COMPOUNDS/DELIVERY AREA .......................................................... 3
3 ACCESS TRACK IMPROVEMENT/CONSTRUCTION ................................................................... 4
4 INTAKE CONSTRUCTION .............................................................................................................. 6
5 PIPELINE .......................................................................................................................................... 9
6 POWERHOUSE CONSTRUCTION ...............................................................................................11
7 OUTFALL PIPELINE AND OUTFALL CONSTRUCTION ..............................................................12
8 GRID CONNECTION .....................................................................................................................13
9 ELECTROMECHANICAL INSTALLATION AND COMMISSIONING..........................................14
10 DEMOBILISATION......................................................................................................................14
![Page 3: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/3.jpg)
3
1 Introduction This document describes the Outline Construction Methods. Further detailed, specific
Construction Method Statements that must be submitted by the Contractor (once
appointed)
Some specific hazards and other considerations have been identified by the Designers.
These are listed under each activity and must be included in the Risk Assessment and
Method Statement for that section of the work. For the avoidance of doubt, this must not
be assumed to be a complete list and the team undertaking the Risk Assessment should
address any other hazards which could impact the work.
2 Site Establishment/Compounds/Delivery Area
2.1 Summary of Works/Methods
The site establishment consists of the following:
• Main contractor site office – this is to be located adjacent to the powerhouse
location at approximately 243530,760611
o two portacabin offices,
o Lock-up storage container,
o Site welfare facilities.
• Client offices – to be located adjacent to the main contractor site office
• Pipeline delivery area – Pipes will be delivered to an area (grid reference
247650,757382) adjacent to the B846 approximately 3.25km east of the start of the
access track by Allt Eigheach.
• Pipeline storage area: From this temporary delivery/storage area, pipes will
transported onto site in small loads by tractor and trailer. They will be stored on site
at an area just north of the forestry, approximate grid reference 243480,760940
until required for use.
• Access tracks – the existing access track to the powerhouse location requires some
minor repairs prior to start of works. This includes repair of sections that have been
washed out and ensuring that the two proposed passing areas are safe and
accessible. From the powerhouse location to the intake the existing tracks are in
varying states of repair and some a short new section of track will also be required.
• Watercourse crossings – culverts will be installed in the two tributaries of Allt
Eigheach, to the south of the powerhouse location. A new vehicular bridge crossing
over the Allt Eigheach will be constructed, with a short stretch of new track to link it
to the existing track.
• Intake working area – a small working area near to the Intake will be prepared for:
o Intake area site office portacabin
o Intake area lock-up storage container
o Intake area welfare facilities
• Site notices
2.2 The Method Statements which have been identified for this work are:
• Site Establishment Method Statement
![Page 4: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/4.jpg)
4
Method Statements will be in place prior to any work commencing on this activity and shall
address, as a minimum:
• the preparation for and delivery of plant and materials to the area in question
• the establishment of the initial means of access to the site
• the type and establishment of a temporary welfare facility (until such time that the
full welfare facilities may be established)
• Public Access and Safety
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• the safety of road users when offloading plant
• the safety of pedestrians
• the prevention of debris being deposited on public highway
• the prevention of contact with the overhead power cables
3 Access Track Improvement/Construction
3.1 Summary of Works/Methods
The site is well served with existing access tracks but some improvements are required:
• There is a very good quality, long established track from the public road to the
powerhouse area that requires only minor improvement and the formalisation of
two passing places.
• Vehicular access across the Allt Eigheach is currently via a ford crossing. This is not
appropriate for the level of construction traffic on both practical and environmental
management grounds. A new vehicular bridge crossing is proposed.
• The track from the powerhouse to the intake follows the pipeline route. The
condition of this track is very variable and requires improvement.
The following sections give brief outline procedures for the access works.
1.1.1 Existing access track from public road to powerhouse area
This track is long established, is made of a firm gravel running surface and is in generally very
good condition. The following works are proposed:
• Minor improvement and resurfacing
• Construction of culvert crossing of Allt Gormag – this will require SEPA approval.
This is currently a ford crossing that is in a very poor state of repair.
o This work shall only take place when there is a clear week of dry weather
forecast so the levels of the water in the Allt Gormag are low
o A temporary diversion channel shall be created to dry out the existing ford
crossing area
o The existing concrete ford construction shall be removed and the materials
disposed of appropriately
o A culvert crossing shall be created using a number of 300mm dia pipes. The
crossing shall be a minimum of 4.0m wide. It shall be created a low as
possible and is designed to over-top at high river levels. The pipes shall be
concreted in place and a road surface created over.
![Page 5: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/5.jpg)
5
o The edges of the culvert crossing will be landscaped with large natural
boulders to minimise the visual impact of the concrete.
• Formalisation of two passing places. This is very minor work and simply involves
tidying up of two former borrow pit location.
1.1.2 Vehicular crossing of the Allt Eigheach
Vehicular access across the Allt Eigheach is currently via a ford crossing. This is not
appropriate for the level of construction traffic on both practical and environmental
management grounds. A new vehicular bridge crossing is proposed.
A steel beam construction with a wooden deck and handrail is proposed which requires
simple concrete supports at either side of the burn. The outline construction sequence is
given below:
• Temporary coffer dams are to be built around both the bridge support points
• The area inside the coffer dam is to be cleared down to a firm surface
• Any water accumulating within the coffer dammed area is to be pumped away to a
suitable settling pond to prevent contamination of the watercourse
• The bridge supports are to be shuttered and poured with concrete as required.
• The coffer dams are to be carefully removed
• The area around the bridge supports are to be landscaped with large boulder to
minimise the exposed concrete and lessen any visual impact
• The bridge and deck, which are anticipated to be delivered in a pre-assembled unit,
is installed on to the supports
• Tracks either side of the bridge are to be constructed and the area made good.
1.1.3 Access track from powerhouse to intake
Where the existing access track is on bedrock or subsoil the work required will be limited.
Here the surface will be levelled and widened as necessary to approximately 3.5m. An open
drainage channel will be installed on the upper side to prevent erosion of the track by water.
Culverts under the track will be installed as required. The track will be topped with a layer of
gravel – from either the on-site borrow pit or imported. Post-construction of the intake and
installation of the pipeline the route of the track/pipe will be finished landscaped and the
track width shall be reduced to a minimum. The track verges will be left to re-seed and
regenerate naturally.
Where the existing track is over peat or in the area where new track is required, more
extensive works will be undertaken.
• The vegetation and top layer of soil / peat will be removed as whole turves and
stacked, vegetation layer uppermost. The area removed will be sufficient to lay the
track, drainage channel and where relevant the pipe. Removal of the vegetation with
sufficient soil will protect root layers and prevent drying out. Stacks will be limited in
height to prevent compaction of soil.
• The lower layer of peat along the track length will be removed in blocks and stored
• The subsoil or bedrock will be levelled and surfaced with a gravel topping.
• An open drainage channel will be excavated along the upper side of the track to
prevent erosion from water run-off.
• Where the pipeline runs adjacent to the access track, it will be installed alongside
(further details below)
![Page 6: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/6.jpg)
6
• Turves will also be used to cover over any exposed peat faces next to the drainage
ditch.
• A small amount of surplus peat will be generated by this construction process. This
will be re-used on site for dressing off and reinstating peat on the edges of
constructed infrastructure and for verge reinstatement on the tracks. Any additional
peat will be distributed sensitively around the site.
1.1.4 Borrow Pit
A borrow pit area has been identified at grid ref 243491, 760935. This is shown in Appendix
C.3. This area is already informally used for material to maintain the tracks. It is estimated
that 500m3 of useable material might be available from this location for use the repair of the
tracks. This has significant advantages over bringing in imported material.
The area will be borrowed to the extent that the ground is flat only, i.e. no large hole will be
made. Following removal of the material the area will be landscaped and covered in a layer
of local top soil/organic material to allow the natural regeneration of the area.
3.2 The Method Statements which have been identified for this work are:
• Access Method Statement – Access Track improvement/construction
• Borrow pit use/reinstatement
• Bridge Construction Method Statement – River Works/Bridge Construction
Method Statements will be in place prior to any work commencing on this activity and shall
address, as a minimum:
• the construction of the access tracks and maintaining public access
• the flow diversion works associated with bridge support works
• the installation of formwork for the reinforced concrete walls for bridge supports
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• Safe public access to track during improvement/construction
• the prevention of falls into unattended excavations
• the prevention of falls into watercourses
• the prevention of pollution of the adjacent watercourses (slippage, sediment,
cement, refuelling). See Environmental Management Plan
• the prevention of watercourses inundating the works
• COSSH assessments for fuels and cement
4 Intake Construction
4.1 Summary of Works/Methods
The construction of the intake presents the greatest risk of river contamination. However,
correct procedures and construction methods greatly reduce this risk. The SEPA guide
![Page 7: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/7.jpg)
7
“Engineering in the water environment good practice guide: Temporary construction
methods (WAT-SG-29)” has been applied to the methods.
The following sections give brief outline procedures for the intake constructions.
1.1.5 Intake
The intake has been sited on an area where the stream bed consists mostly of exposed bed
rock, and the area around it is relatively level. All access to the intake shall be from the
southern direction only.
The river at this point is approximately 5-8m wide. The nature of the topography does not
lend itself easily to creating a full working bypass for the construction of the intake structure.
It is therefore proposed to use a “half and half” construction method where half the width of
the river is coffer-dammed off and the flow diverted to one side of the burn, thus allowing
construction of half of the intake. . The eastern side of the river will be coffered off first and
this half of the weir, including the compensation notch, will be constructed. Following this
the river is diverted to the opposite side of the river, through/over the first part of the
construction, thus allowing the remaining half of the intake to be built in the dry.
This ensures both a secure construction and also greatly reduces the risk of sediment
contamination. The construction program will be as follows:
• Prior to construction, a coffer dam will be installed to divert the burn towards the
west bank
- Sandbags will be used to form the coffer dam (a combination of individual
sand band and larger dumpy bags as appropriate)
- The coffer dam will be placed so as to maintain as much width in the river as
possible to reduce the restriction to the water flow
- If required, pumps will be used to keep the working area dry and this will be
discharged to a separate settlement pit dug several meters away from the
burn
• Intake construction (phase 1) – Compensation notch/by-pass section
- Excavation of bed rock if required – some bed rock may need to be removed
to gain sufficient depth
- Rock dowels drilled and installed as required
- The floor slab will then be cast in concrete
- Once cured the remainder of the weir will be shuttered and cast with
reinforced concrete, including being tied into the east bank
- Bank and bed scour protection (gabions and/or boulders in concrete) will be
completed
• Once fully cured, the coffer dam will be moved to divert water through the
constructed compensation notch on the east side of the burn
- The river flow will then pass through the dewatering/compensation notch in
the weir wall (V-notch plate not installed)
• Intake construction (phase 2) – sump and main chamber
- Excavation of the sump and main weir area down to bed rock – some bed
rock may need to be removed to gain sufficient depth
- Rock dowels drilled and installed as required
- The floor slabs will then be cast in concrete
![Page 8: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/8.jpg)
8
- Once cured, the main weir wall and chamber will be shuttered and cast with
reinforced concrete
- Wing walls will be completed, tied into the banks
- Bank and bed scour protection (gabions and/or boulders in concrete) will be
completed
• Installation of fittings
- Intake Coanda screens fitted
- Compensation plate not fitted at this point (this will allow bypass for phase
2)
- Sluice gate installed and locked off
- Access hatch, safety railing and stilling wells fitted
• Re-watering
- The working area will be cleared of any loose debris before re-watering
- The compensation plate can then be installed, thus completing the weir, and
the area upstream will fill up and then flow over the screens
• Reinstate & make good
Outline construction drawings for the Intake along with a drawing showing the proposed de-
watering method is given in Appendix E.
4.2 The Method Statements which have been identified for this work are:
• Intake Method Statement – River Diversion
• Intake Method Statement – Excavation/Construction/Fittings
• Intake Method Statement – River Diversion Removal
Method Statements will be in place prior to any work commencing on this activity and shall
address, as a minimum:
• the excavation work for the intake walls and wells
• the flow diversion works associated with each particular intake
• the installation of formwork for the reinforced concrete walls and wells
• the installation of the reinforcement steel
• the mixing, placing and compaction of the concrete
• the installation of the intake screens
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• the prevention of falls into unattended excavations
• the prevention of falls into watercourses
• the prevention of pollution of the adjacent watercourses (slippage, sediment,
cement, refuelling). See Environmental Management Plan
• the prevention of watercourses inundating the works
• COSSH assessments for fuels and cement
![Page 9: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/9.jpg)
9
5 Pipeline
5.1 Summary of Works/Methods
The pipeline installation shall follow these key guidelines:
• The pipeline corridor will be kept as narrow as possible at all times
• The pipeline will be fully buried
• Where possible vegetation will be stripped off the line of the pipe carefully, with soil
and roots intact, so that it can be used in the re-instatement
• During the excavation of the pipeline, trench top-soil and sub-soil material shall be
kept separate and backfilled in the same order
• Where possible imported backfill material shall be avoided and a selective backfill
method used.
• The trench shall be opened and closed as quickly as possible
• Safe exit routes/ramps will be provided from the trench if a trench is left open
overnight for wildlife
• The pipeline will not alter the drainage characteristic of the land. Clay stopper bungs
will be used as required
The whole pipeline shall be constructed using butt fusion welded HPPE material. Due to the
very restricted nature of the site with most areas off the formal access tracks being wet
grassland or peat bog, the pipes will be delivered to an area (grid reference 247650,757382)
adjacent to the B846 approximately 3.25km east of the start of the access track by Allt
Eigheach which is an existing forestry marshalling area. From this temporary
delivery/storage area, pipes will transported onto site in small loads by tractor and trailer.
They will be stored on site at an area just north of the forestry, approximate grid reference
243480,760940 until required for use.
1.1.6 General installation of butt fusion welded HPPE pipe material
HPPE is an extremely versatile pipeline material. Amongst its benefits are flexibility and a
particularly strong jointing system. The flexibility of the materials allows it to bend and
follow the contours of the ground or avoid obstacles without the need for formal bends and
anchor blocks, thus simplifying the installation.
The pipe sections (usually 12m lengths) are joined using a technique called butt fusion
welding, where the ends of the pipes are heated to melting point and then pushed together
under pressure and allowed to cool. The resulting welded joint is then essentially as strong
as the pipeline material itself. This greatly reduces the risk of pipeline failure. The limit of
this pipeline is 16 Bar pressure, making it suitable for the total pipeline length.
The general procedure is that long sections of the pipe are pre-welded together above
ground. This is either done by moving the welding machine down the pipeline, welding as it
goes, or by leaving the welding machine in one place and pulling the welded pipe sections
through the welder. When the pipeline has been prepared a long section of trench is
excavated, generally 50m-150m. During this excavation the topsoil layer will be removed
and kept separate from any subsoil material. The pipe which is now a single long section is
then lifted and dropped into the trench where it can then be backfilled. Care will be taken to
ensure that only topsoil material will be restored at ground level.
![Page 10: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/10.jpg)
10
HPPE is a relatively strong material which if the ground conditions are good can be buried
directly without the need for imported backfill. If the ground conditions are poor, imported
backfill material might be required to prevent damage to the pipeline. The general ground
conditions are good at the site and the need for imported backfill is expected to be very
limited.
It is not expected that any pipeline trench section will remain exposed for more than 4-5
days. If a trench section is left open overnight a ramp access will be left to allow any animals
that may enter the trench to escape.
Care will be taken to ensure the pipeline does not affect the drainage nature of the land.
Where the pipe crosses under side streams or through any particularly wet areas, clay bungs
will be installed as appropriate to prevent running water scouring along the pipe.
5.2 The Method Statements which have been identified for this work are:
• Pipeline Method Statement – Polyethylene Pipe Laying and Backfilling
• Pipeline Method Statement – Polyethylene Pipe Welding
• Pipeline Method Statement – Pressure Testing
Method Statements will be in place prior to any work commencing on this activity and shall
address, as a minimum:
• the excavation of pipe trenches and pits including temporary storage of materials
• the measures to ensure trench stability
• the procedures for inspection of trenches
• the jointing of pipes
• the laying of pipes
• the bedding and backfilling of pipes
• the reinstatement of trenches
• the testing of pipework
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• the prevention of falls into unattended excavations
• the prevention of spoil or materials accessing the trench
• the prevention of pollution of the adjacent watercourses (sediment, refuelling) see
Environmental Management Plan
• the prevention of excessive crossings of watercourses by vehicles
• the prevention of trench collapses due to vehicles working adjacent
• the prevention of flooding of the trenches from ground or surface waters
• the avoidance the disturbance to the designated areas of archaeological interest
(see Environmental Management Plan)
• COSSH assessments for fuels and cement
![Page 11: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/11.jpg)
11
6 Powerhouse Construction
6.1 Summary of Works/Methods
The powerhouse is sited away from the river and does not involve any de-watering works.
The powerhouse area is adjacent to the existing access track.
The following is the outline for method for the construction of the powerhouse:
• Site preparation
- Removal and storage of vegetation and topsoil
- Excavation of foundations for pipe anchor block, turbine sump and
transformer compound, and for powerhouse wall footings
- If required, pumps will be used to keep the working area dry and this will be
discharged to a settlement pit dug several meters away from the burn.
• Construction
- Cast foundations and main floor slab
- Build superstructure and roof
- Formalise hard-standing area
• Reinstatement and landscaping
Drawings of the proposed powerhouse building are given in Appendix F
6.2 The Method Statements which have been identified for this work are:
• Powerhouse Method Statement - Slab Excavation
• Powerhouse Method Statement - Slab Construction
• Powerhouse Method Statement - Blockwork
• Powerhouse Method Statement - Roof
• Powerhouse Method Statement - Gantry
Method Statements will be in place prior to any work commencing on this activity and shall
address, as a minimum:
• the excavation of the base and foundations for the building
• the installation of formwork for the reinforced concrete slab and sump
• the installation of the reinforcement steel
• the mixing, placing and compaction of the concrete
• the construction of the blockwork building walls
• the construction of the roof
• the installation of the overhead gantry
• the installation of fittings (doors, vents, guttering etc)
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• the prevention of falls into unattended excavations
• the prevention of falls from height
• the prevention of pollution of the adjacent watercourses (sediment, cement,
refuelling) see Environmental Management Plan
• COSSH assessments for fuels and cement
![Page 12: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/12.jpg)
12
• the plant (incl. valid certification) to be used for lifting
7 Outfall pipeline and Outfall Construction
7.1 Summary of Works/Methods
The outfall pipeline runs from the powerhouse building to the outfall.
The outfall itself will be constructed behind a coffer dam. The following is the outline
method for the construction:
• Prior to construction, a coffer dam will be installed to divert the burn towards the
east bank and away from the main construction area.
- Sandbags will be used to form the coffer dam (a combination of individual
sand bags and larger dumpy bags as appropriate)
- The coffer dam will be placed so as to maintain as much width in the river as
possible to reduce the restriction to the water flow
- If required, pumps will be used to keep the working area dry and this will be
discharged to a separate settlement pit dug several meters away from the
burn
- Hay bales/silt net will be placed immediately downstream of the working
area to capture any disturbed sediment
• Outfall construction
- Excavation of the outfall area down to bed rock or solid ground – some bed
rock may need to be removed to gain sufficient depth. Existing bed material
to be placed to one side for reinstatement
- The floor slab will then be cast in concrete
- Once cured the main outfall structure will be shuttered and cast with
reinforced concrete, around the pipes to the turbine sump
- Wing walls will be completed, tied into the banks
- River bed reinstated to original level
- Bank and bed scour protection (gabions and/or boulders in concrete) will be
completed
• Installation of fittings
- Outfall screens fitted
- Safety railing fitted
• Re-watering
- The coffer dam can then gradually be removed and water allowed to flow
slowly past the outfall structure
- Hay bales/Silt nets will remain in place until the water runs clean, and then
the coffer dam can be fully removed
• Reinstate and make good.
Outline construction drawings for the outfall along with a drawing showing the proposed de-
watering method are given in Appendix G
7.2 The Method Statements which have been identified for this work are:
• Outfall Method Statement – River Diversion
![Page 13: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/13.jpg)
13
• Outfall Method Statement – Excavation/construction/fittings
• Outfall Method Statement – River Diversion Removal
• Outfall Method Statement – Pipe Laying and Backfilling
Method Statements will be in place prior to any work commencing on this activity and shall
address, as a minimum:
• the flow diversion works to accommodate the pipe and discharge chamber
• the excavation for the pipe and discharge chamber
• the jointing of pipes
• the laying of pipes
• the bedding and backfilling of pipes
• the reinstatement of trenches
• the installation of formwork for the discharge chamber
• the installation of the reinforcement steel for the discharge chamber
• the mixing, placing and compaction of the concrete for the discharge chamber
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• the prevention of falls into unattended excavations
• the prevention of falls into watercourses
• the prevention of pollution of the adjacent watercourses (sediment, cement,
refuelling) see Environmental Management Plan
• the prevention of watercourses inundating the works
• COSSH assessments for fuels and cement
• the prevention of spoil or materials accessing the trench
• the prevention of excessive crossings of watercourses by vehicles
• the prevention of trench collapses due to vehicles working adjacent
• the prevention of flooding of the trenches from ground or surface waters
• the avoidance the disturbance to the designated areas of archaeological interest.
See Environmental Management Plan
8 Grid Connection
8.1 Summary of Works/Methods
The grid connection is to be provided in full by SSE.
8.2 The Method Statements which have been identified for this work are:
• Grid Connection Method Statement – Overhead Line Works (SSE)
• Grid Connection Method Statement – Buried Line and Substation Works (SSE)
Method Statements will be in place prior to any work commencing on each activity.
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
![Page 14: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/14.jpg)
14
• the organisation and management of multiple sub-contractors on-site
• the systems to ensure sub-contracted staff are competent and qualified
• the exclusion of unauthorised or inexperienced persons in the work areas
• the prevention of falls from height
• the prevention of electrocution
• the prevention of burns
• the prevention of fire
• lifting heavy machinery
• manual handling
9 Electromechanical Installation and commissioning
9.1 Summary of Works/Methods
This work involves the installation of the turbine, generator, control system and grid
connection/protection equipment. This is specialist work and will be carried out by specialist
contractors. All works are contained within the powerhouse building and do not present any
environmental or public hazards.
9.2 The Method Statements which have been identified for this work are:
• Electromechanical Installation Method Statement (specialist contractor)
• Control System Installation Method Statement (specialist contractor)
• System Commissioning Method Statement (specialist contractor)
Method Statements will be in place prior to any work commencing on each activity.
Hazards which will be considered, as a minimum, in the associated Risk Assessment will
include
• the organisation and management of multiple sub-contractors on-site
• the systems to ensure sub-contracted staff are competent and qualified
• the exclusion of unauthorised or inexperience persons in the work areas
• the prevention of falls from height
• lifting heavy machinery
• manual handling
• the prevention of electrocution
• the prevention of burns
• the prevention of fire
10 Demobilisation
The site will be demobilised only after there has been consultation with the landowner and
stakeholders regarding the final reinstatement and timescales/standards agreed for any
matters requiring further attention.
Areas which will be discussed shall be
![Page 15: Outline Construction Method Statement](https://reader035.vdocuments.us/reader035/viewer/2022081805/55cf98a5550346d03398daa1/html5/thumbnails/15.jpg)
15
• final condition of existing tracks
• reinstatement of hard-standings formerly used for storage, welfare, etc.
• reinstatement of fences and gates
• reinstatement of pipe route
• reinstatement of surface water control measures
• general site tidiness (litter, etc.)
• on-going safe visitor access