PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO34 PROPOSED DAIS FOR PARADE SQUARE AT NAVAL BASED 1ST BATTALION, MUARA
1 Feb 2011 1 Jun 2011
PO35 PROPOSED VIP DRIVEWAY TO PARADE SQUARE AT BERAKAS GARRISON
4/4/2011 16/05/2011
PO36 PROPOSED MODIFICATION TO ROAD WORKS AT BERAKAS GARRISON
14 Mar 2011 14 May 2011
PO37 DAILY COLLECTION OF RUBBISH FROM ROADSIDE COLLECTION CENTRE IN BRUNEI MUARA DISTRICT FOR A PERIOD OF TWO MONTHS
30 Apr 2011 30 Jun 2011
PO38 DAILY HOUSEKEEPING TERM CONTRACT FOR THE 3RD BATTALION CAMP AT LUMUT, MINDEF FOR A PERIOD OF TWO MONTHS
15 May 2011 14 Jul 2011
PO38.1 DAILY HOUSEKEEPING TERM CONTRACT OR THE 3RD BATTALION CAMP AT LUMUT, MINDEF FOR A PERIOD OF ONE MONTHS
15 Jul 2011 14 Aug 2011
PO38.2 DAILY HOUSEKEEPING TERM CONTRACT FOR THE 3RD BATTALION CAMP AT LUMUT, MINDEF FOR A PERIOD OF SIX MONTHS
15 Aug 2011 14 Feb 2012
PO39
PROPOSED DESIGN, BUILD,FABRICATE AND INSTALL UNDERGROUND SOLID WASTE COLLECTION MANAGEMENT SYSTEM FOR TAMU KIANGGEH WASTE COLLECTION CENTRE BANDAR SERI BEGAWAN
2 Jan 2011
PO40 KERJA-KERJA PEMBAIKAN TANAH SUSUR BAGI MENARA ELETRIK DI SPG 1080 KG SINAUT
7 Jan 2011
PO42 REPAIRED WORKS AND MINOR SLOPE PROTECTION TO TANAH PERKUBURAN ISLAM KATIMAHAR
24 Apr 2012
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO46 LANDSCAPE AND ASSETS MAINTENANCE TO SUNGAI BASONG RECREATIONAL PARK, TUTONG DISTRICT FOR A PERIOD OF 12 MONTHS
8 Mar 2011 7 Mar 2012
PO47 DAILY COLLECTION OF RUBBISH FROM ROADSIDE COLLECTION CENTRES IN BRUNEI MUARA DISTRICT FOR A PERIOD OF TWO MONTHS
1 Mar 2011 29 Apr 2011
PO48 DAILY COLLECTION OF RUBBISH FROM ROADSIDE COLLECTION CENTRES IN BRUNEI MUARA DISTRICT FOR A PERIOD OF TWO MONTHS
1 Jul 2011 31 Aug 2011
PO49 CADANGAN BANGUNAN BARU UNIT KESIHATAN DAN ALAM SEKITAR BAGI PENANJONG GARRISON- MINDEF
17 Jul 2012 16 Nov 2012
PO50 KERJA-KERJA TANAH DAN PEMASANGAN PAGAR DI PUSAT PEMEROSESAN MAKANAN DI KAMPONG KILANAS
15 Jul 2011 14 Nov 2011
PO51 UPGRADING OF PARKING SPACES AT JALAN RESIDENCY ( NEAR KUBUR DAGANG ) BANDAR SERI BEGAWAN
3 Oct 2011 2 Dec 2011
PO52 MENYEDIAKAN KEMUDAHAN-KEMUDAHAN RIADAH DAN BERSUKAN DI STKRJ TELISAI, TUTONG
12 May 2012 25 Feb 2013
PO53 KEBENARAN BAGI PERKHIDMATAN PEMBERSIHAN BAGI PERKAMPUNGAN AARM DI PERKHEMAHAN TUTONG
PO54 REFURBISHMENT OF 11KV / 415V DISTRIBUTION SUBSTATION AT KG PENGKALAN GADONG
- -
PO55 PROPOSED NEW WALKWAY AND FOOT BRIDGE CONNECTING MALE GYMNASIUM AND POC AT BOLKIAH GARRISON
12 Feb 2013 11 Mar 2013
PO56 MANAGE AND ARANGE USED TYRES AT BUKIT UDAL DUMPING GROUND IN TUTONG DISTRICT FOR THREE MONTHS
2 Feb 2013 2 May 2013
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO57 MULTI NATIONAL COORDINATION CENTRE AT MUARA CAMP - BASE COURSE PREPARATION WORKS TO INTERNAL ROADS - MNCC
13 May 2013 3 Jun 2013
PO58 PROPOSED GABION WALL FOR SOIL SETTLEMENT OR SOIL EROSION AT LUMUT CAMP
17 Jun 2013 16 Sept 2013
PO59 REFFUSED GARBAGE COLLECTION SERVICESS AT JABATAN PERDANA MENTERI FOR A PERIOD 4 MONTHS - JPM
PO60 EXPANSION JOINTS AND CONCRETE REPAIR AT UNDERGROUND SERVICES TUNNEL, UBD
12 Jan 2013 11 Jan 2014
PO61 TERM CONTRACT FOR REPAIR OF ROOF LEAKS AND REPLACEMENT OF DAMAGE CEILING AT UBD
12 Dec 2012 -
PO62 CONSTRUCTION OF ADDITIONAL CARPARKS AT CHANCELLOR HALL AND FACULTY OF SCIENCE TUNNEL, UBD
14 Dec 2012 13 Dec 2013
PO66 DAILY HOUSEKEEPING FOR CALIBRATION CENTRE AT BOLKIAH GARRISON FOR ONE YEARS
9 Aug 2011 7 Aug 2012
PO67
RUBBISH COLLECTION FOR PERUMAHAN POLIS DIRAJA BRUNEI AT KAWASAN BALAI POLIS KG.AIR, KAWASAN BALAI POLIS LIMAU MANUS,POS POLIS SG.BUNGA,POS POLIS PERPINDAHAN BOLKIAH ' A',POS POLIS KASAT,POS POLIS PUTAT, POLIS POLIS LUMAPAS AND POLIS POLIS BEBULUH LOCATION 4. - ROYAL BRUNEI POLIS FORCE
10 Jan 2011 9 Jan 2014
PO68 KERJA-KERJA KUTIPAN DAN PEMBUANGAN SAMPAH DI JABATAN PENERBANGAN AWAM - AIRPORT
1 Jan 2012 14 Jan 2013
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO69 2 YEARS TERM CONTRACT FOR RUBBISH COLLECTON FOR RELIGIOUS SCHOOLS AT ZONE 'I' TUTONG DISTRICT - TUTONG UGAMA SCHOOLS
11 Jan 2011 11 Jan 2013
PO70
KEBENARAN UNTUK MENGENDALIKAN WASTE DISPOSAL SERVICES FOR BOLKIAH GARRISEN FOR A PERIOD FIVE YEARS CONTRACT BOLKIAH SAMPAH
1 Mar 2011 28 Feb 2016
PO71
KEBENARAN UNTUK MENGENDALIKAN WASTE DISPOSAL SERVICES FOR TUTONG GARRISEN FOR A PERIOD FIVE YEARS CONTRACT TUTONG GARRISON SAMPAH
01 Mar 2012 28 Feb 2017
PO72 DAILY COLLECTION AND DISPOSAL OF WASTES FROM WASTE COLLECTION CENTRES INI BRUNEI MUARA DISTRICT FOR A PERIOD OF FIVE YEARS - BIN CENTRE
31 Oct 2011 30 Sept 2016
PO73
TERM CONTRACT FOR THE DAILY COLLECTION OF RUBBISH FROM THE ROADSIDE RUBBISH COLLECTION CENTRE IN TEMBURONG DISTRICT FOR A PERIOD (3) THREE YEARS - TEMBURONG SAMPAH
29 Jan 2013 28 Jan 2016
PO74 KONTRAK PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH DIPEJABAT BIRO KAWALAN NARKOTIK DAERAH TUTONG BAGI TEMPOH 12 BULAN - BKN
1 May 2013 31 Apr 2014
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO75
PERKHIDMATAN BANTUAN KEPADA JABATAN ALAM SEKITAR,TAMAN DAN REKREASI - RUBBISH COLLECTION AND CLEANING AT ANY VICINITY AND PLACES IN BRUNEI MUARA DISTRICT UNTUK 12 BELAS BULAN - BRUNEI MUARA VICINITY
9 Jul 2013 8 Jul 2014
PO76
PERKHIDMATAN BANTUAN KEPADA JABATAN ALAM SEKITAR,TAMAN DAN REKREASI - RUBBISH COLLECTION AND CLEANING AT ANY VICINITY AND PLACES IN BRUNEI MUARA DISTRICT UNTUK 12 BELAS BULAN - TUTONG VICINITY
26 Aug 2013 25 Aug 2014
PO77 MUARA SECURITY BUILDING Aug 2013 Feb 2014
PO78 THREE YEARS CONTRACT FOR RUBBISH COLLECTION IN SERIA MUNICIPAL - MUNICIPAL AREA SERIA BBS/1/RCSMA/2012-2016
2013 2016
PO79 RUBBISH COLLECTION AT TELEKOM BRUNEI BERHAD 15 SEPT 2013 29 SEPT 2018
PO80 2 YEARS TERM CONTRACT FOR RUBBISH COLLECTON FOR RELIGIOUS SCHOOLS AT ZONE 'H' TUTONG DISTRICT - TUTONG UGAMA SCHOOLS
1 Oct 2013 30 Sept 2015
PO81 RUBBISH COLLECTION VARIOUS CILINIC IN BRUNEI MUARA AND TUTONG DISTRICT FOR A PERIOD 3 MONTH - CILINIC RIPAS
26 Sept 2013 25 Dec 2013
PO83 RUBBISH REFUSE COLLECTION FOR ISB SCHOOL 1 Oct 2013 Aug 2017
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO84 TERM CONTRACT FOR REPAIR OF LOOSE, SUNKEN PAVIOUR BLOCK AND REPLACEMENT OF LOOSE FLOOR / WALL TILE FOR MALE AND FAMALE - UBD
13 Nov 2014 12 Nov 2015
PO85
REPAIRED WORKS AT THE DAMAGE TIBER FLOORING, GALVANISED G1 PLATE OF GANGWAY BRIDGES AND FRONT RUBBER FENDERS AT THE JETTYPONTOON TERMINAL SERASA MUARA - PORT DEPARTMENT
20 Nov 2013 19 Dec 2013
PO86 SUPPLY & DELIVERY REMOVABLE SECURITY BARRIER FOR BRADIEX AREA - MINDEF
20 Nov 2013 30 Nov 2013
PO87 CONSTRUCTION SURAU BUILDING AT MUARA PORT 20 Nov 2013 19 Dec 2013
PO88 CARPARK FACAULTY OF SCIENCE AT UBD
PO89
DOMESTIC WASTE COLLECTION AND DISPOSAL
SERVICES FOR THE RAJA ISTERI PENGIRAN ANAK
SALEHA (RIPAS) HOSPITAL THE KIARONG CHILD
DEVELOPMENT CENTRE, THE KIARONG MENTAL HEALTH
DAY CARE CENTRE, THE KIARONG PHARMACEUTICAL
DRUG PRODUCTION SECTION, THE KIARONG DIALYSIS
AND HEALTH CENTRE AND THE RIMBA DIALYSIS CENTRE
FOR A PERIOD OF FIVE (5) YEARS- KK/275/2013
(UPP/JPR) (TC)
28 DEC 2013
27 DEC 2018
(EOT UNTIL MAR 2019)
PO90 KERJA-KERJA PEMBAIKAN CLASS G
PO91 ADDITIONAL CARPARKS TO NATIONAL DENTAL CENTRE, OLD AIRPORT BERAKAS
PO92 PROPOSED R.C. CAR PARKS AREA AT TAMAN REKREASI MENTERI BESAR
PO93
JPM 3 Project IN ONE FILE : 1. CHANGE NEW LOCKSET AND SPRING FOR TEMPERED GLASS AT KG BERIBI OFFICE. 2. EXTENSION WORKS OF OFFICE ROOM AT FLAT B1 BERIBI
23 Dec 2013 Mar 2014
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO94 MENGUSAI PERUMAHAN KAKITANGAN PELABUHAN 2 UNIT KELAS D,1 UNIT KELAS E, 5 UNIT KELAS F DAN 1 UNIT KELAS G.
06 Feb 2014 May 2014
PO95 CADANGAN BAGI PENYEDIAN REKABENTOK & PEMBINAAN LOT 30502 KG KATOK MATA
8 Jul 2015
PO97 RUBBISH COLLECTION AND CLEANING AT VICINITY AND PLACE IN TUTONG AREA FOR 12 MONTH
Mar 2014 28 Feb 2015
PO98 STONEVILLE HOTEL SDN BHD - SAMPAH COLLECTION 28 Jan 2016
PO99 PROPOSED SLOPE PROTECTION WORK FOR LOT 30520 8 Jul 2014 4 Aug 2014
PO100 BKN I). BKN HQ TUTONG II). BKN JLN TUTONG KUPANG III). BKN HQ GADONG
PO101 PROPOSED SURAU AT ROYAL BRUNEI AIRFORCE BASE, RIMBA Jun 2014 May 2015
PO102 PROPOSED RENOVATION WORKS TO OLD GYM TOILET AT BLK 13, SG AKAR CAMP
6 May 2014 3 Jun 2014
PO103 LANDSCAPING MAINTENANCE JLN PENGHUBONG TUNGKU 1 May 2014 31 Apr 2016
PO104 PERKHIDMATAN KUTIOAN SAMPAH TEPI PANTAI KUALA BELAIT May 2014 Oct 2014
PO105 Domestic Waste Collection and Disposal Services for Suri Seri
Begawan Hospital (SSBH) Kuala Belait for a Period of Three (3) Years- KK/359/2013 (SSBH)(TC)
May 2014 April 2017
PO106 NEW PARKING AT SUMBILING TELEPHONE HOUSE 23 Jun 2014 22 Jul 2014
PO107 ONE YEAR CONTRACT CLEANING RUBBISH/WASTE COLLECTION SERVICE AT MUARA CONVENTIONAL TERMINAL WHARF AREA
Sept 2014 Aug 2015
COMPLETED PROJECTS
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO108 WASTE DISPOSAL COLLECTION SERVICES FOR 2 TEMBURONG UGAMA SCHOOL - SUBCON FROM RKS
1 Oct 2014 30 Sept 2016
PO109 TO SUPPLY DELIVER AND INSTALL NEW STAINLESS STEEL HAND RAILING AND SHOE RACK FOR MINI SURAU AT CONVENTIONAL WHARF
Oct 2014
PO110 STKRJ TELISAI PLAY GROUND 20 Aug 2014 19 Dec 2014
PO111
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. SEKOLAH RENDAH PUTAT II. RUMAH GURU S.R. BENGKURONG III. FLAT S.R BENGKURONG
1 Nov 2014 31 Jan 2015
PO112
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. SEKOLAH RENDAHTUMPUAN TELISAI II. SEKOLAH RENDAH DANAU III. SEKOLAH RENDAH BUKIT PANGGAL
1 Nov 2014 31 Jan 2015
PO113
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. SEKOLAH RENDAH LUBOK PULAU II. SEKOLAH RENDAH ABDUL RASHID TANJONG MAYA III. SEKOLAH MENENGGAH TANJONG MAYA
1 Nov 2014 31 Jan 2015
PO114
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. PUSAT TINGKATAN ENAM MERAGANG II. RUMAH GURU SEKOLAH RENDAH SERASA III. RUMAH GURU SEKOLAH SUAS SERASA
1 Nov 2014 31 Jan 2015
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO115
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. FLAT UPK/FLAT C5 DAN C6 II. SEAMEO VOTEC III. FLAT C12 DAN C13 PERUMAHAN KIARONG
1 Nov 2014 31 Jan 2015
PO116
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. PUSAT TINGKATAN SENGKURONG II. RUMAH GURU SEKOLAH RENDAN SENGKURONG III. RUMAH GURU KELAS C SEKOLAH MENENGAH SAYYIDINA HUSSAIN JERUDONG IV. SEKOLAH RENDAH MASIN
1 Nov 2014 31 Jan 2015
PO119 PROPOSED SLOPE REMEDIAL WORKS AND DRAINAGE WORKS AT OFFICER'S MESS BERAKAS GARRISON
1 Dec 2014 31 May 2015
PO120 PROPOSED MAINTENANCE REPAIR TO SHOOTING RANGE GALLERY 1,GALLERY 2, ETR, IBSR MTT AT PENANJONG GARRISON
12 Dec 2014 11 Jan 2015
PO121 EXTERNAL WORK AT SUMBILING AT SUMBILING TH 18 Dec 2014 17 Feb 2015
PO122
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I. SEKOLAH RENDAH KAMPONG BUKIT
II.SEKOLAH RENDAH KAMPONG MENENGAH III.SEKOLAH RENDAH PENAPAR IV.SEKOLAH RENDAH BUKIT UDAL
01 Jan 2015 28 Feb 2015
PO123
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI SEKOLAH I.SEKOLAH RENDAH SUNGAI TERABAN II.SEKOLAH RENDAH KUALA BELAIT III.SEKOLAH RENDAH AHMAD TAJUDDIN
01 Jan 2015 28 Feb 2015
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO124 RUBBISH COLLECTION FOR JERUDONG PARK MEDICAL CENTRE
01 Feb 2015
PO125
PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI
SEKOLAH I. FLAT UPK/FLAT C5 DAN C6 II. SEAMEO VOTEC III. FLAT C12 DAN C13 PERUMAHAN KIARONG
1 Nov 2014 31 Jan 2015
PO126 MAJOR CIVIL RECTIFICATION WORK AT TUNGKU SUBMARINE CABLE STATION
2 Jan 2015
PO127 REPAIR DAMAGE CONCRETE AT BAREK TELBRU Mar 2015 Apr 2015
PO132 RUBBISH COLLECTION AT KOREAN EMBASSY
PO133
PERKHIDMATAN BANTUAN KEPADA JABATAN ALAM SEKITAR TAMAN DAN REKREASI ('RUBBISH COLLECTION AND CLEANING AT ANY VICINITY AND PLACES IN TUTONG DISTRICT') UNTUK 12 BULAN
PO134
ONE (1) YEARS TERM CONTRACT FOR RUBBISH COLLECTION FOR PERUMAHAN POLIS DIRAJA BRUNEI JABATAN SIASATAN DAN KAWALAN LALULINTAS (JKSLL) GADONG AND KAWASAN PERUMAHAN POLIS KAWALAN DIRAJA, JALAN BABU RAJA, KG BERIBI GADONG
10.5.2015 09.05.2016
P0135 CONSTRUCTION OF REINFORCED SLOPE @ HOUSE NO 81,SPG 701, KG SALAMBIGAR
9 May 2015 8 June 2015
PO136
PERKHIDMATAN BANTUAN KEPADA JABATAN ALAM SEKITAR TAMAN DAN REKREASI ('RUBBISH COLLECTION AND CLEANING AT ANY VICINITY AND PLACES IN BELAIT DISTRICT') UNTUK 12 BULAN
22.05.2015 21 May 2016
PO137
TUT ZONE 1 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.R BAKIAU 2. S.R MENENGAH, RIPAS 3. S.R ORG KAYA ALI WANIKA SETIA DIRAJA, KUPANG
2 Jun 2015 1 Jun 2017
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO128
THREE (3) YEARS TERM CONTRACT FOR RUBBISH COLLECTION - PROC[09]/HQ/2015-RC 1. PERUMAHAN POLIS DIRAJA BRUNEI KAWASAN DAERAH BERAKAS, 2. PERPINDAHAN BURONG PINGGAI BERAKAS DAN 3.POS POLIS PERPINDAHAN LAMBAK KANAN, 4.KAWASAN PERUMAHAN POLIS KONDOMINIUM SEJAHTERA KG PULAIE
APR 2015 30 JUN 2018
PO129
THREE (3) YEARS TERM CONTRACT FOR RUBBISH COLLECTION - PROC[10]/HQ/2015-RC 1. PERUMAHAN POLIS DIRAJA BRUNEI KWSN DAERAH JERUDONG/SENGKURONG, 2.KWSN PERUMAHAN POLIS ISTANA DARULHANA.
3.KWSN PERUMAHAN POLIS ISTANA NURUL IZZAH. 4.KWSN PERUMAHAN POLIS TELANAI JLN TUTONG. 5.KWSN PERUMAHAN POLIS SPG 166 KG.JERUDONG.(49 LOKASI)
APR 2015 30 JUN 2018
PO130
THREE (3) YEARS TERM CONTRACT FOR RUBBISH COLLECTION -PROC[07]/HQ/2015-RC 1. PERUMAHAN POLIS DIRAJA BRUNEI KWSN DAERAH POLIS MUARA. 2.IBU PEJABAT POLIS MERIN. 3. POS POLIS MENTIRI
APR 2015 30 JUN 2018
PO131
THREE (3) YEARS TERM CONTRACT FOR RUBBISH COLLECTION- PROC[08]/HQ/2015-RC 1.PERUMAHAN POLIS KG. AIR. 2. POLIS POS SUNGAI BUNGA. 3. PERPINDAHAN BOLKIAH A. 4.KASAT. 5.PUTAT. 6.LUMAPAS. 7.BEBULUH
APR 2015 30 JUN 2018
PO133
PERKHIDMATAN BANTUAN KEPADA JABATAN ALAM SEKITAR TAMAN DAN REKREASI ('RUBBISH COLLECTION AND CLEANING AT ANY VICINITY AND PLACES IN TUTONG DISTRICT') UNTUK 12 BULAN
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO138
TUT ZONE 2 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.R. BIRAU 2. S.R KIUDANG 3. S.R BATANG MITUS
2 Jun 2015 1 Jun 2017
PO139
TUT ZONE 5 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.R SAGING UKONG 2. S.R PENAPAR
2 Jun 2015 1 Jun 2017
PO140
TUT ZONE 6 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.R ABDUL RASHID TANJONG MAYA 2. S.M TANJONG MAYA 3. S.R LUBOK PULAU
2 Jun 2015 1 Jun 2017
PO141
TUT ZONE 7 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.R BUKIT PANGGAL 2. S.R SINAUT 3. S.R KERIAM 4. S.R PENANJONG
2 Jun 2015 1 Jun 2017
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO142
TUT ZONE 8 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN
DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.M MUDA HASHIM 2. S.M SUFRI BOLKIAH 3. S.R MUDA HASHIM
2 Jun 2015 1 Jun 2017
PO143
TUT ZONE 9 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1.S.R SENGKARAI 2. S.R PG. MUDA MAHKOTA JLN KG. PENABAI
2 Jun 2015 1 Jun 2017
PO144
TUT ZONE 10 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. S.R PERPINDAHAN BUKIT BERUANG II 2. S.R PG. KESUMA NEGARA, BUKIT BERUANG 3. S.M SAYYIDINA OTHMAN
2 Jun 2015 1 Jun 2017
PO145
TUT ZONE 11 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. PUSAT TINGKATAN ENAM BUKIT BERUANG 2. S.R TUMPUAN TELISAI 3. S.R DANAU
2 Jun 2015 1 Jun 2017
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO146
TUT ZONE 12 KONTRAK PENGGAL BAGI PERKHIDMATAN PENGANGKUTAN DAN PEMBUANGAN SAMPAH BAGI MAKTAB/ SEKOLAH/ ASRAMA/PEJABAT/ PERUMAHAN DIBAWAH KEMENTERIAN PENDIDIKAN, NEGARA BRUNEI DARUSSALAM 1. FLAT C305- C312 KAWASAN SG. BESAR, TUTONG
2 Jun 2015 1 Jun 2017
PO147 KERJA-KERJA PENGUTIPAN DAN PEMBUANGAN SAMPAH DI PEJABAT - PEJABAT POS DAN RUMAH PANGSA PEJABAT POS UNTUK 2 TAHUN
16.08.2015 15.7.2017
PO148 PERKHIDMATAN KUTIPAN SAMPAH DARI RUMAH KERUMAH DI KG AIR UNTUK TIGA (3) BULAN
29 Aug 2015 28 Nov 2015
PO149 ROOF GUTTER WALL CORING, JPMC 5 Jan 2016
P0150 PROPOSED NEW MRS AT BOLKIAH GARRISON
PO152 VICINITY BRUNEI MUARA 12 MONTH
PO153 REPAIR WORK TO C4 JLN BELANTARA AND B6 JLN TEMENGGONG AT BERAKAS
8 Nov 2015
PO154 RECTIFICATION WORKS AT BERAKAS EXCHANGE 9 Nov 2015 28 Dec 2015
PO155 RUBBISH COLLECTION SERVICE FOR 1 YEARS - HARTA
PO156 PROPOSED SLOPE FAILURE REMEDIAL WORKS AT JALAN DATO SIMPSON (INFRONT OF C2 HOUSE) BERAKAS GARRISON
28 Dec 2015 1 Nov 2017
PO157 PROPOSED SLOPE FAILURE REMEDIAL WORKS AT JALAN PASIR (REAR OF C3 HOUSE) PHASE 1
10 Dec 2015 Sep 2016
PO159 PERKHIDMATAN PEMBERSIHAN BAGI BANGUNAN PERUMAHAN BAITULMAL, LOT 9203, KG KERIAM, TUTONG
03/04/2016 31/03/2018
PO160 PERKONOMIAN TAMU KIANGEH - DEMOLISHING AND CLEANING WORKS
1 Jun 2016
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
PO162
CADANGAN BAGI PEYEDIAAN REKABENTUK DAN PEMBINAAN 1 UNIT PERUMAHAN BADAN TAMIAH JENIS 3 TINGKAT , LOT 48227 KG. PENGKALAN GADONG MUKIM GADONG NBD (06/2015/BT/MUI/PPP/13/2014 PT. 1) Note: Additional works included.
25 Aug 2016 March 2018
PO163 PROP. CONSTRUCTION OF R.C DRAIN NEAR SINGLE SOLDIER ACCOMODATION BOLKIAH GARRISON (JPPK/SH/31/2016-2017)
Jan 2017
PO164
CADANGAN BAGI PENYEDIAAN REKABENTUK DAN PEMBINAAN 1 UNIT PERUMAHAN BADAN TAMIAH JENIS 3 TINGKAT, LOT 48227 KG. PENGKALAN GADONG MUKIM GADONG NBD (06/2015/BT/MUI/PPP/13/2014 PT. 1)
8/25/2016 ETC: 24 Nov 2017
P198 GENERAL PFFICE TERM MAINTENANCE FOR A PERIOD OF TWELVE (12) MONTHS FOR BATANG DURI CAMP, OUTWARD BOUNDARY BRUNEI DARUSSALAM (REQUOTATIONS)
P210
056/RBPF-HQ/2017-B ONE (1) YEAR TERM CONTRACT FOR RUBBISH COLLECTIONS FOR ROYAL BRUNEI POLICE HOUSING AT JABATAN SIASATAN & KAWALAN LALULINTAS (JSKLL) GADONG DAN POLIS ROYAL GUARD HOUSEING, JALAN BABU RAJA, KG BERIBI GADONG
6 SEPT 2017 5 SEPT 2018
P223
JASTRE/QTN022/2018 PERKHIDMATAN BANTUAN KEPADA JABATAN ALAM SEKITAR, TAMAN DAN RECREASI (WASTE COLLECTIONS AND CLEANING AT ANY VICINITY AND PLACES IN BRUNEIDARUSSALAM ) UNTUK
ENAM (6) BULAN
10 FEB 2018 9 AUG 2018
P228 JASTRE/QTN044/2018
P229
JASTRE/QTN048/2018 COLLECTION AND DISPOSAL OF WASTE SUNDERNEATH HOUSES AND AT THE BAKUT AREAS IN MUKIM SABA, KG AYER FOR A PERIOD OF FOUR (4) MONTHS
16 APR 2018 25 AUG 2018
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
P230
JASTRE/QTN051/2018 COLLECTION AND DISPOSAL OF WASTE UNDERNEATH HOUSES AND AT THE BAKUT AREAS IN MUKIM BURUNG PINGAI AYER, KG AYER FOR A PERIOD OF FOUR (4) MONTHS
16 APR 2018 25 AUG 2018
P233
KHEDN/BPE/Q1043/2018 6 MONTHS TERM CONTRACT FOR THE GRASS CUTTING AND WEEDING WORKS, TAMAN MAHKOTA JUBLI EMAS
21 FEB 2018 20 AUG 2018
P235
KHEDN/BPE/Q1065/2018 6 MONTHS TERM CONTRACT FOR RUBBISH COLLECTION AT KG LIMBONGAN (END OF TMJE BRIDGE?) AND PULAU SALAT, BANDAR SERI BEGAWAN
7 MAY 2018 6 NOV 2018
P236
KHEDN/BPE/Q1065/2018 6 MONTHS TERM CONTRACT FOR RUBBISH COLLECTIONS AT RIVER BANK AT KG PINTU MALIM, JALAN KOTA BATU
7 MAY 2018 6 NOV 2018
P237
KHEDN/BPE/Q1066/2018 6 MONTHS TERM CONTRACT FOR RUBBISH COLLECTION AT RIVER BANK OF KG. SUNGAI BESAR, KOTA BATU
7 MAY 2018 6 NOV 2018
P239
KHEDN/BPE/Q1074/2018 6 MONTHS TERM CONTRACT FOR RUBBISH COLLECTION AT RIVER BANK OF MAKAN DIRAJA
7 MAY 2018 6 NOV 2018
P240
JASTRE/QTN053/2018 DAILY COLLECTION AND DISPOSAL OF WASTES FROM ROADSIDE WASTE COLLECTION CENTRES IN BELAIT DISTRICT FOR A PERIOD OF THREE (3) MONTH
18 MAY 2018 17 AUG 2018
P244
JASTRE/BPP/T016/2017 DAILY COLLECTION AND DISPOSAL OF FLOATING WASTES ALONG SUNGAI BRUNEI FOR A PERIOD OF SIX (6) MONTHS
26 MAY 2018 25 SEPT 2018
COMPLETED PROJECTS
COMPLETED PROJECTS
PROJECT NO. PROJECT TITLE DATE OF
COMMENCEMENT DATE OF COMPLETION
P250
JASTRE/QTN062/2018 BACK-UP SERVICE FOR A WASTE COLLECTION AND CLEANING WORKS AT ANY VICINITY AND PLACES IN BRUNEI DARUSSALAM FOR A PERIOD OF SIX (6) MONTHS
04 JUN 2018 18 DEC 2018
P251 AWLIYA ENTERPRISE
P252
BKN(A)/PENT/113
KONTRAK KERJA PENGANGKUTAN DAN PEMBUANGAN
SAMPAH, PUSAT AL-ISLAH, BIRO KAWALAN NARKOTIK,
NEGARA BRUNEI DARUSSALAM
23 FEB 2018 22 FEB 2019
P255
KHEDN/BPE/Q10098/2018 6 MONTHS TERM CONTRACT FOR RUBBISH COLLECTIONS AT RIVER BANK OF MASJID KG PINTU MALIM AND KG SUNGAI LAMPAI, JALAN KOTA BATU
15 JULY 2018 14 JAN 2019
P256 KHEDN/BPE/BPE/Q1101/2018 6 MONTHS TERM OF RUBBISH NETTING AT MAKAM DIRAJA KG TAMOI
15 JULY 2018 14 JAN 2019
P257 KHEDN/BPE/Q1102/2018 6 MONTHS RENTAL OF RUBBISHNETTING AT KG SUNGAI LAMPAI, JALAN KOTA BATU
15.JULY 2018 14 JAN 2019
P258 JASTRE/QTN076/2018 DAILY HOUSE TO HOUSE COLLECTION AT KAMPONG AYER FOR A PERIOD OF TWO (2) MONTHS
P259
JASTRE/QTN085/2018 SUPPLY,DELIVERY,COMMISSION,OPERATION AND MAINTENANCE OF ONE (1) NO. OF FLOATING DEBRIS BOOM AT AREA 1 OF KG SABA DARAT 'B'
09.08.2018 11.09.2018
P260
JASTRE/QTN086/2018 SUPPLY,DELIVERY,COMMISSION,OPERATION AND MAINTENANCE OF ONE (1) NO. OF FLOATING DEBRIS BOOM AT AREA 2 OF KG SABA DARAT 'B'
09.08.2018 11.09.2018
P261
JASTRE/QTN092/2018 SUPPLY , DELIVERY, COMMISSION, OPERATION AND MAINTENANCE OF THREE (3) NO. OF FLOATING DEBRIS BOOM ALONG THE DESIGNATED AREAS OF SUNGAI BRUNEI
01.09.2018 14.10.2018
P264 JASTRE/QTN099/2018 DAILY HOUSE TO HOUSE COLLECTION AT KG AYER FOR A PERIOD OF TWO (2) MONTHS
19 OCT 2018 18 DEC 2018
P266 JASTRE/QTN133/2018 DAILY COLLECTION AND DISPOSAL OF WASTE ALONG SUNGAI BRUNEI FOR A PERIOD OF THREE (3) MONTHS
16.01.2019 15.04.2019