Santa Maria Groundstation
Validation and Support to Ariane-5 ATV
OPS-G Forum
Gerhard Billig
15 July 2008
ESOC OPS-ONV
Page 2
Agenda
1. Groundstation Validation2. Infrastructure3. Operational Setup and Preparations4. Launch Operations5. Outlook
- Upgrade of Perth groundstation- Support to other Launcher families
ESOC OPS-ONV
Page 3
Groundstation Validation- Internally Tested Subsystems -
• Tracking Tests with Caltower / Satellites• Dedicated Autotrack Tests
• Monitoring and Control• TM reception and processing
ESOC OPS-ONV
Page 4
Autotrack Validation
• Angular velocity of launcher (as seen from the groundstation) was much higher than that of satellites
• Autotrack (dual frequency) was mandatory and primary mode of tracking
• Aircraft was chosen as carrier for transmitters• Trajectory was down-scaled to meet aircraft constraints:
• Height: ≈ 1200m
• Speed: ≈ 200km/h• Placement of antennas and power connection was difficult
ESOC OPS-ONV
Page 5
Track of Ariane-5 over SMA• 1st pass:
Min Slant Range: ≈ 180km at elevation 48°
• 2nd pass: Min Slant Range: 1100 km at elevation 10°
ESOC OPS-ONV
Page 6
Actual Flightpath
ESOC OPS-ONV
Page 7
ESOC OPS-ONV
Page 8
Antenna positioning in aircraft
ESOC OPS-ONV
Page 9
Equipment Installation
ESOC OPS-ONV
Page 10
ESOC OPS-ONV
Page 11
SMA Infrastructure Development: Original View
ESOC OPS-ONV
Page 12
Finalised Installation at SMA
ESOC OPS-ONV
Page 13
ESOC OPS-ONV
Page 14
ESOC OPS-ONV
Page 15
Inauguration
ESOC OPS-ONV
Page 16
Operations Preparations and
Launch Support
ESOC OPS-ONV
Page 17
Requirements for Launch Support from SMA
• Tracking: Dual-frequency AutotrackDO-Programtrack
• TM Reception and Storage• TM Extraction and Forward to CSG• Event Detection and Forward• Voice Communications
Comms
Acores
Voice
S-band
CSG/Kourou
TM Receiver
Voice
TM (CVI)
Pointing (DO)
Antenna Control
ESOC OPS-ONV
Page 18
Ariane-5 ATV: Mission Overview
ESOC OPS-ONV
Page 19
Ariane-5 ATV Tracking Network - Drivers -
• Mission Duration: 1.5 Orbits (0.5 orbits for GTO)• Long Cruise Phases complicate accurate orbit prediction
(Ariane inertial platform sensors)
• Inclusion of Radars at Europe resolved predication accuracy problems
• ISS was used as tracking target to exercise network-wide tracking campaigns
ESOC OPS-ONV
Page 20
Santa Maria Groundstation: Schedule for Operations
• March 2007: Meeting with CNES/CSG• May 2007: Operational Training with CNES• October 2007: Operations KoM with CNES at SMA
Start of Operational Preparations• November 2007: Stand-Alone Tests• January 2008: Operational Qualification with CNES• February 2008: Mission Readiness Tests (internal)• 9th March 2008: Launch of Ariane-5 ATV
ESOC OPS-ONV
Page 21
ESOC OPS-ONV
Page 22
ESOC OPS-ONV
Page 23
ESOC OPS-ONV
Page 24
ESOC OPS-ONV
Page 25
ESOC OPS-ONV
Page 26
ESOC OPS-ONV
Page 27
Outlook: Upgrade of Perth groundstation
-90
-60
-30
0
30
60
90
-180 -150 -120 -90 -60 -30 0 30 60 90 120 150 180
Ariane 5-ECA+Fregat
Soyuz+Fregat
CAR
NAN
KSH
PERT
REDUAUS
ACO
BAT
KRUBAN
TRI
KRN
-90
-60
-30
0
30
60
90
-180 -150 -120 -90 -60 -30 0 30 60 90 120 150 180
AR5 SSO
1500_sso
1200_sso
700_sso500_sso300_sso
PARE
MIG
PERT
SPIT
WAL
BER
STH
ANT
KRU
MASUOKI
DONG
KER
REF ELV
ESOC OPS-ONV
Page 28
Outlook: Support to other Launcher Families
• Vega SSO launch trajectory
• Vega Maiden Launch
• Soyuz