Operations Management
Short-Term SchedulingChapter 15
![Page 2: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/2.jpg)
Learning ObjectivesWhen you complete this chapter, you
should be able to :Identify or Define:
– Gantt charts– Assignment method– Sequencing rules– Johnson’s rules– Bottlenecks
![Page 3: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/3.jpg)
Learning Objectives - continuedWhen you complete this chapter, you
should be able to :
Describe or Explain:– Scheduling– Sequencing– Shop loading– Theory of constraints
![Page 4: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/4.jpg)
Delta Airlines• 10% of Delta’s flights disrupted per year -
half of those by weather
• Cost: $440-million in:– lost revenue– overtime pay– food and lodging vouchers
• $33-million hi-tech nerve center– 18 staff– $35-million savings (per year)
![Page 5: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/5.jpg)
Strategic Implications of Short-Term Scheduling
• By scheduling effectively, companies use assets more effectively and create greater capacity per dollar invested, which, in turn, lowers cost
• This added capacity and related flexibility provides faster delivery and therefore better customer service
• Good scheduling is a competitive advantage which contributes to dependable delivery
![Page 6: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/6.jpg)
• Deals with timing of operations
• Short run focus: Hourly, daily, weekly
• Types
TodayToday Due Date
BB EE
Forward SchedulingForward Scheduling
TodayToday Due Date
BB EE
Backward SchedulingBackward Scheduling
Short-Term Scheduling
![Page 7: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/7.jpg)
• Hospital– Outpatient treatments– Operating rooms
• University– Instructors– Classrooms
• Factory– Production– Purchases
© 1984-1994 T/Maker Co.
Short-Term Scheduling Examples
![Page 8: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/8.jpg)
Organization Managers Must Schedule
Operating room usePatient admissionNursing, security, maintenance staffsOutpatient treatments
Classrooms and audiovisual equipmentStudent and instructor schedulesGraduate and undergraduate courses
Production of goodsPurchase of materialsWorkers
Scheduling Decisions
• Mount Sinai Hospital
• Indiana University
• Lockheed-Martin Factory
![Page 9: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/9.jpg)
Organization Managers Must Schedule
Chefs, waiters,bartendersDelivery of fresh foodsEntertainersOpening of dining areas
Maintenance of aircraftDeparture timetablesFlight crews, catering, gate, and ticketing personnel
Scheduling Decisions
• Hard Rock Cafe
• Delta Airlines
![Page 10: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/10.jpg)
Capacity Planning, Aggregate Scheduling, Master Schedule, and Short-Term Scheduling
Capacity Planning 1. Facility size 2. Equipment procurement
Aggregate Scheduling 1. Facility utilization 2. Personnel needs 3. Subcontracting
Master Schedule 1. MRP 2. Disaggregation of master plan
Long-term
Intermediate-term
Short-term
Intermediate-term
Short-term Scheduling 1. Work center loading 2. Job sequencing
![Page 11: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/11.jpg)
Forward and Backward Scheduling
• Forward scheduling: begins the schedule as soon as the requirements are known– jobs performed to customer order
– schedule can be accomplished even if due date is missed
– often causes buildup of WIP
• Backward scheduling: begins with the due date of the final operation; schedules jobs in reverse order– used in many manufacturing environments, catering,
scheduling surgery
![Page 12: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/12.jpg)
The Goals of Short-Term Scheduling
• Minimize completion time
• Maximize utilization (make effective use of personnel and equipment)
• Minimize WIP inventory (keep inventory levels low)
• Minimize customer wait time
![Page 13: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/13.jpg)
Types of Planning Files
• Item master file - contains information about each component the firm produces or purchases
• Routing file - indicates each component’s flow through the shop
• Work-center master file - contains information about the work center such as capacity and efficiency
![Page 14: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/14.jpg)
• Assigning jobs to work centers• Considerations
– Job priority (e.g., due date)– Capacity
• Work center hours available• Hours needed for job
• Approaches– Gantt charts (load & scheduling) - capacity– Assignment method - job to specific work center
Loading Jobs in Work Centers
![Page 15: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/15.jpg)
Options for Managing Facility Work Flow
• Correcting performance
• Increasing capacity
• Increasing or reducing input to the work center by:– routing work to or from other work centers
– increasing or decreasing subcontracting
– producing less (or more)
![Page 16: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/16.jpg)
Gantt Scheduling ChartStart of an activity
Scheduled activity time allowed
Point in time when chart is reviewed
S T W T F SDay
Job
Job A
Job B
Job C
Maintenance
Now
End of an activity
Actual work progress
Non-production time
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
![Page 17: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/17.jpg)
• Assigns tasks or jobs to resources
• Type of linear programming model– Objective
• Minimize total cost, time etc.
– Constraints• 1 job per resource (e.g., machine)
• 1 resource (e.g., machine) per job
Assignment Method
![Page 18: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/18.jpg)
Production Control Production
Which job do I run next?
Dispatch ListOrder Part Due QtyXYZ 6014 123 100ABC 6020 124 50
Job PacketJob XYZ
Order release
Sequencing Challenge
![Page 19: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/19.jpg)
• Specifies order jobs will be worked• Sequencing rules
– First come, first served (FCFS)– Shortest processing time (SPT)– Earliest due date (EDD)– Longest processing time (LPT)– Critical ratio (CR)– Johnson’s rule
Sequencing
![Page 20: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/20.jpg)
Priority Rules for Dispatching Jobs First come, first served The first job to arrive at a work center is processed first Earliest due date The job with the earliest due date is processed first
Shortest processing time The job with the shortest processing time is processed first
Longest processing time The job with the longest processing time is processed first Critical ratio The ratio of time remaining to required work time remaining is calculated,
and jobs are scheduled in order of increasing ratio.
FCFS
EDD
SPT
LPT
CR
![Page 21: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/21.jpg)
• Process first job to arrive at a work center first
• Average performance on most scheduling criteria
• Appears ‘fair’ & reasonable to customers– Important for service organizations
• Example: Restaurants
First Come, First Served Rule
![Page 22: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/22.jpg)
Shortest Processing Time Rule
• Process job with shortest processing time first.
• Usually best at minimizing job flow and minimizing the number of jobs in the system
• Major disadvantage is that long jobs may be continuously pushed back in the queue.
![Page 23: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/23.jpg)
Longest Processing Time Rule
• Process job with longest processing time first.
• Usually the least effective method of sequencing.
![Page 24: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/24.jpg)
• Process job with earliest due date first
• Widely used by many companies– If due dates important– If MRP used
• Due dates updated by each MRP run
• Performs poorly on many scheduling criteria
Earliest Due Date Rule
![Page 25: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/25.jpg)
Ratio of time remaining to work time Ratio of time remaining to work time remainingremaining
• Process job with smallest CR first
• Performs well on average lateness
CR Time remainingWork days remaining
Due date - Today' s dateWork (lead ) time remaining
=
=
Critical Ratio (CR)
![Page 26: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/26.jpg)
Advantages of the Critical RatioScheduling Rule
Use of the critical ratio can help to:– determine the status of a specific job
– establish a relative priority among jobs on a common basis
– relate both stock and make-to-order jobs on a common basis
– adjust priorities and revise schedules automatically for changes in both demand and job progress
– dynamically track job progress and location
![Page 27: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/27.jpg)
Job Sequencing Example
Job Job Work
Processing time in days
Job Due Date (day)
A 6 8
B 2 6
C 8 18
D 3 15
E 9 23
![Page 28: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/28.jpg)
Summary
Rule Average Completion
Time (days)
Utilization (%)
Average Number of Jobs in the
System
Average Lateness (Days)
FCFS 15.4 36.4 2.75 2.2
SPT 13.0 43.1 2.32 1.8
EDD 13.6 41.2 2.43 1.2
LPT 20.6 27.2 3.68 9.6
![Page 29: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/29.jpg)
Critical Ratio (CR)Job Job Work
Processing time in
days
Job Due Date (day)
Critical Ratio
A 6 8 0.75
B 2 6 0.33
C 8 18 0.44
D 3 15 0.20
E 9 23 0.39
Sequence
A
C
E
B
D
![Page 30: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/30.jpg)
• Used to sequence N jobs through 2 machines in the same order
© 1995 Corel Corp.
© 1995 Corel Corp.
Saw Drill
Job AJob A
Job BJob B
Job CJob C
Jobs (N = 3)
Johnson’s Rule
![Page 31: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/31.jpg)
Graphical Depiction of Job Flow
B E D C A
B E D C A
Work center 1
Work center 2
0 3 10 20 28 33
0 3 9 10 20 22 28 29 33 35Time =>
Time =>
B E D C A
= Job completed= Idle
![Page 32: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/32.jpg)
Limitations of Rule-Based Dispatching Systems
• Scheduling is dynamic; therefore, rules need to be revised to adjust to changes in process, equipment, product mix, etc.
• Rules do not look upstream or downstream; idle resources and bottleneck resources in other departments may not be recognized
• Rules do not look beyond due dates
![Page 33: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/33.jpg)
Finite Scheduling System
![Page 34: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/34.jpg)
• Deals with factors limiting company’s ability to achieve goals
• Types of constraints– Physical
• Example: Machines, raw materials
– Non-physical• Example: Morale, training
• Limits throughput in operations
Theory of Constraints
![Page 35: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/35.jpg)
Theory of ConstraintsA Five Step Process
Identify the constraintsDevelop a plan for overcoming the identified
constraintsFocus resources on accomplishing the constraints
identified in step 2Reduce the effects of the constraints by off-
loading work or by expanding capabilityOnce one set of constraints is overcome, return to
the first step and identify new constraints
![Page 36: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/36.jpg)
• Bottleneck work centers have less capacity than prior or following work centers
• They limit production output
© 1995 Corel Corp.
Bottleneck Work Centers
![Page 37: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/37.jpg)
Techniques for Dealing With Bottlenecks
1. Increase the capacity of the constraint2. Ensure well-trained and cross-trained employees are
available to operate and maintain the work center causing the constraint
3. Develop alternate routings, processing procedures, or subcontractors
4. Move inspections and tests to a position just before the constraint
5. Schedule throughput to match the capacity of the bottleneck
![Page 38: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/38.jpg)
The 10 Commandments for Correct Scheduling
1. Utilization of a non-bottleneck resource is determined not by its own capacity but by some other constraint in the system
2. Activating a resource is not synonymous with utilizing a resource
3. An hour lost at a bottleneck is an hour lost of the whole system
4. An hour saved at a non-bottleneck is a mirage5. The transfer batch may not, and many times
should not, be equal to the process batch
![Page 39: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/39.jpg)
The 10 Commandments for The 10 Commandments for Correct SchedulingCorrect Scheduling
6. The amount processed should be verifiable and not fixed
7. Capacity and priority need to be considered simultaneously, not sequentially
8. Damage from unforeseen problems can be isolated and minimized
9. Plant capacity should not be balanced
10. The sum of the local optimums is not equal to the global optimum
![Page 40: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/40.jpg)
Scheduling for Services
• Appointment systems - doctor’s office
• Reservations systems - restaurant, car rental
• First come, first served - deli
• Most critical first - hospital trauma room
![Page 41: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/41.jpg)
Cyclical Scheduling
• Plan a schedule equal in weeks to the number of people being scheduled
• Determine how many of each of the least desirable off-shifts must be covered each week
• Begin the schedule for one worker by scheduling the days off during the planning cycle (at a rate of 2 days per week on average)
![Page 42: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/42.jpg)
Cyclical Scheduling - Continued
• Assign off-shifts for the first worker• Repeat this pattern for each other worker,
but offset by one week from the previous• Allow each worker to pick his/her “slot” or
“line” in order of seniority• Mandate that any changes from the chosen
schedule are strictly between the personnel wanting to switch
![Page 43: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/43.jpg)
Operations Management
Just-in-Time and Lean Production Systems
Chapter 16
![Page 44: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/44.jpg)
Learning Objectives
When you complete this supplement, you should be able to :
Identify, Describe or Explain:– Just-in-Time (JIT) philosophy– Lean Production
![Page 45: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/45.jpg)
Waste is ‘anything other than the minimum amount of equipment, materials, parts, space, and worker’s time, which are absolutely essential to add value to the product.’
— Shoichiro Toyoda President, Toyota
© 1995 Corel Corp.
Introductory Quotation
![Page 46: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/46.jpg)
Green Gear Cycling
• Designs and manufacturers high performance travel bicycles (bike-in-a-suitcase!)
• Strategy is mass customization with low inventory, work cells, and elimination of machine setups.
• Major focus on JIT and supply-chain management.
• Two lines with seven work cells• One day throughput time• Focus on quality
![Page 47: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/47.jpg)
• Management philosophy of continuous and forced problem solving
• Supplies and components are ‘pulled’ through system to arrive where they are needed when they are needed.
What is Just-in-Time?
![Page 48: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/48.jpg)
Lean Production
• Lean Production supplies customers with exactly what the customer wants, when the customer wants, without waste, through continuous improvement.
![Page 49: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/49.jpg)
• Overproduction
• Waiting
• Transportation
• Inefficient processing
• Inventory
• Unnecessary motion
• Product defects
Types of Waste
![Page 50: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/50.jpg)
Variability Occurs Because• Employees, machines, and suppliers produce units
that do not conform to standards, are late, or are not the proper quantity
• Engineering drawings or specifications are inaccurate
• Production personnel try to produce before drawings or specifications are complete
• Customer demands are unknown
![Page 51: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/51.jpg)
Results
• Queue and delay reduction, speedier throughput, freed assets, and winning orders
• Quality improvement, reduces waste and wins orders• Cost reduction increases margin or reduces selling price• Variability reductions in the workplace reduces waste
and wins orders• Rework reduction, reduces waste and wins orders
![Page 52: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/52.jpg)
Yielding
Faster response to the customer at lower cost and higher quality
A competitive advantage!
![Page 53: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/53.jpg)
Suppliers
Preventive Maintenance
Layout
Inventory
Scheduling
Quality
Employee Empowerment
JIT
Just-in-TimeSuccess Factors
![Page 54: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/54.jpg)
Goals of JIT partnerships
Elimination of unnecessary activitiesElimination of in-plant inventoryElimination of in-transit inventoryElimination of poor suppliers
![Page 55: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/55.jpg)
• Diversification
• Poor customer scheduling
• Frequent engineering changes
• Quality assurance
• Small lot sizes
• Physical proximity
Concerns of Suppliers
![Page 56: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/56.jpg)
• Traditional: inventory exists in case problems arise
• JIT objective: eliminate inventory• JIT requires
– Small lot sizes– Low setup time– Containers for fixed number of parts
• JIT inventory: Minimum inventory to keep system running
Inventory
![Page 57: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/57.jpg)
• Japanese word for card– Pronounced ‘kahn-bahn’ (not ‘can-ban’)
• Authorizes production from downstream operations– ‘Pulls’ material through plant
• May be a card, flag, verbal signal etc.• Used often with fixed-size containers
– Add or remove containers to change production rate
Kanban
![Page 58: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/58.jpg)
• JIT exposes quality problems by reducing inventory
• JIT limits number defects with small lots• JIT requires TQM
– Statistical process control– Worker involvement
• Inspect own work• Quality circles
– Immediate feedback
Quality
![Page 59: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/59.jpg)
JIT Quality Tactics
• Use statistical process control
• Empower employees
• Build failsafe methods (poka-yoke, checklists, etc.)
• Provide immediate feedback
![Page 60: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/60.jpg)
• Get employees involved in product & process improvements– Employees know job best!
• JIT requires– Empowerment
– Cross-training
– Training support
– Few job classifications
© 1995 Corel Corp.
Employee Empowerment
![Page 61: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/61.jpg)
JIT in ServicesAll the techniques
used in manufacturing are used in services
SuppliersSuppliers
LayoutsLayouts
InventoryInventory
SchedulingScheduling
![Page 62: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/62.jpg)
Attributes of Lean Producers - They
• use JIT to eliminate virtually all inventory• build systems to help employees product a perfect part
every time• reduce space requirements• develop close relationships with suppliers• educate suppliers• eliminate all but value-added activities• develop the workforce• make jobs more challenging• reduce the number of job classes and build worker
flexibility
![Page 63: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/63.jpg)
Operations Management
Maintenance and ReliabilityChapter 17
![Page 64: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/64.jpg)
Learning ObjectivesWhen you complete this chapter, you
should be able to :
Identify or Define: – Maintenance– Mean time between failures– Redundancy– Preventive maintenance– Breakdown maintenance– Infant mortality
![Page 65: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/65.jpg)
Learning Objectives - continued
When you complete this chapter, you should be able to :
Describe or Explain:– How to measure system reliability– How to improve maintenance– How to evaluate maintenance
performance
![Page 66: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/66.jpg)
NASA• Maintenance of space shuttles• Columbia:
– 86,000,000 miles on odometer– 3 engines each the size of a VW– expected to make dozens more launches
• Maintenance requires– 600 computer generated maintenance jobs– 3-month turnaround– More than 100 people
![Page 67: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/67.jpg)
• All activities involved in keeping a system’s equipment working
• Objective: Maintain system capability & minimize total costs
© 1995 Corel Corp.
Maintenance Management
![Page 68: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/68.jpg)
The Strategic Importance of Maintenance and Reliability
• Failure has far reaching effects on a firm’s– operation– reputation– profitability– customers– product– employees– profits
![Page 69: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/69.jpg)
Maintenance Procedures
Employee Involvement
Maintenance PerformanceMaintenance Performance
© 1995 Corel Corp.
© 1995 Corel Corp.
Maintenance Performance
![Page 70: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/70.jpg)
Good Maintenance & Reliability Strategy• Requires:
– Employee involvement– Maintenance and reliability procedures
• To yield:– Reduced inventory– Improved quality– Improved capacity– Reputation for quality– Continuous improvement
![Page 71: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/71.jpg)
Lower operating
costs
Continuous improvement
Faster, more dependable throughput
Higher productivity
Improved quality
Improved capacity
Reduced inventory
Maintenance
Maintenance Benefits
![Page 72: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/72.jpg)
• How much preventive & breakdown maintenance
• Who performs maintenance– Centralized, decentralized, operator etc.– Contract or in-house
• When to replace or repair• How much to replace
– Individual or group replacement
Maintenance Decisions
![Page 73: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/73.jpg)
Preventive Breakdown
Routine inspection & servicing
Prevents failures Bases for doing
Time: Every day Usage: Every 300 pieces Inspection: Control chart
deviations
• Non-routine inspection & servicing
• Remedial
• Basis for doing– Equipment failure
Types of Maintenance
![Page 74: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/74.jpg)
A Computerized Maintenance System
![Page 75: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/75.jpg)
Contract for Preventive Maintenance
• Compute the expected number of breakdowns without the service contract
• Compute the expected breakdown cost per month with no preventive maintenance contract
• Compute the cost of preventive maintenance
• Compare the two options
![Page 76: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/76.jpg)
Operations Manager Must Determine How Maintenance Will
be Performed
Operator Maintenance Department
Manufacturer’s field service
Depot Service (return equipment)
Competence is higher as we more
to the rightPreventive maintenance costs less and is faster as we move to the left
![Page 77: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/77.jpg)
A Key To Success
High utilization of facilities, tight scheduling, low inventory and consistent quality demand reliability - total preventive maintenance is the key to reliability.
![Page 78: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/78.jpg)
Techniques for Establishing Maintenance Policies
• Simulation - enables one to evaluate the impact of various maintenance policies
• Expert systems - can be used by staff to help diagnose faults in machinery and equipment
![Page 79: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/79.jpg)
Lets finish with Discussion Questions
Page 632
Questions 1-5 & 10
![Page 80: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/80.jpg)
1. The objective of maintenance and reliability is to maintain the capability of the system while controlling costs.
2. Candidates for preventive maintenance can be identified by looking at the distributions for MTBF (mean time between failure).
If the distributions have a small standard deviation, they are usually a candidate for preventive maintenance.
3. Infant mortality refers to the high rate of failures that exists for many products when they are relatively new.
![Page 81: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/81.jpg)
4. Simulation is an appropriate technique with which to investigate maintenance problems because failures tend to occur randomly, and the probability of occurrence is often described by a probability distribution that is difficult to employ in a closed-form mathematical solution.
![Page 82: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/82.jpg)
5. Training of operators to perform maintenance may improve morale and commitment of the individual to the job or organization. On the other hand, all operators are not capable of performing the necessary maintenance functions or they may perform them less efficiently than a specialist. In addition, it is not always cost effective to purchase the necessary special equipment for the operator’s use.
![Page 83: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/83.jpg)
10. Only when preventive maintenance occurs prior to all outliers of the failure distribution will preventive maintenance preclude all failures. Even though most breakdowns of a component may occur after time, some of them may occur earlier. The earlier breakdowns may not be eliminated by the preventive maintenance policy. A distribution of natural causes exists.
![Page 84: Operations Management Short-Term Scheduling Chapter 15](https://reader033.vdocuments.us/reader033/viewer/2022050701/56649d4c5503460f94a2a954/html5/thumbnails/84.jpg)
Best wishes on your final!More than that – I wish you
success in your careers!
• Chapters– 1&2
– 11-17
• Be sure to bring!– Blue Book
– Scan-tron• Short form