Download - On IP

Transcript
Page 1: On IP

Integrated Project Delivery™

What You Should Know

Sam Spata, AIAArchitect, LEED® [email protected]

Page 2: On IP

“To suffering there is a limit; to fearing, none.”

Page 3: On IP

Spata - 2009©

• Theory• Practice• Tools• Expectations

Agenda

Page 4: On IP

Spata - 2009©

THEORY

A Tale of Two Curves From BIM to PIM

Page 5: On IP

Spata - 2009©

Page 6: On IP

Spata - 2009©

Contractor Architect

Owner

Page 7: On IP

Spata - 2009©

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Time

Satis

facti

on

1960 1970 1980 1990 2000 2010

Low

erH

ighe

r

OwnerExpectations

A/E/CResponse

Page 8: On IP

Spata - 2009©

In recession, A/E/C’s bid low, investment lags

In recession, Owners expect more value for money

Page 9: On IP

Spata - 2009©

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Time

Satis

facti

on

1960 1970 1980 1990 2000 2010

Low

erH

ighe

r

Prog

ram

Man

agem

ent

Cons

truc

tion

Man

agem

ent

Fast

-Tra

ck G-M

ax

?

Page 10: On IP

Spata - 2009©

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Rece

ssio

n

Time

Satis

facti

on

1960 1970 1980 1990 2000 2010

Low

erH

ighe

r

Business as Usual

Page 11: On IP

Spata - 2009©

BIM

Page 12: On IP

Spata - 2009©

Building Information Modeling (BIM)

• data & communication technology tool for object-oriented development using purpose-driven exchange to design & construct a project

Page 13: On IP

Spata - 2009©

Integrated Project Delivery (IPD)

• collaborative method guided by transparency and shared risk & reward to achieve the Owner’s desired outcome

Page 14: On IP

Spata - 2009©

Project Information Management (PIM)

• organized purpose-driven exchange approach to enable project team collaboration using BIM

Page 15: On IP

Spata - 2009©

StructuralEngineer

StructuralEngineer

HVACEngineer

HVACEngineer

CityCity

Constr.Manager

Constr.Manager

FacilitiesManager

FacilitiesManager

BuildingOwner

BuildingOwner

CivilEngineer

CivilEngineer

ArchitectArchitect

StructuralEngineer

StructuralEngineer

HVACEngineer

HVACEngineer

CityCity

Constr.Manager

Constr.Manager

FacilitiesManager

FacilitiesManager

BuildingOwner

BuildingOwner

CivilEngineer

CivilEngineer

ArchitectArchitect

BuildingInformationModel(BIM)

BuildingInformationModel(BIM)

Early BIM

Page 16: On IP

Spata - 2009©

Tekla

CadDuct

Construction Information Model

BIM

AuthorGravity

Wind

Ecotect

4D

5D

Navisworks

ResearchSketch Up

ADTRhinoMaya

3DSMax

Create

TriRiga(IWMS)

Affinity

Hold

Mature BIM

Purpose – built modelsPurpose – driven exchange

Page 17: On IP

Spata - 2009©

Project Information Management

Page 18: On IP

Spata - 2009©

Workflow

Diagram – courtesy of HOK

Page 19: On IP

Spata - 2009©

Imag

e –

cour

tesy

of H

OK

Page 20: On IP

Spata - 2009©

PRACTICE

Challenges Integrated Project Delivery

Page 21: On IP

Spata - 2009©

Building

Binder

BlueprintKnowledge

“…a means

to a means

to an end”

Page 22: On IP

Spata - 2009©

• Owners do projects because they must – not because they want to

• Owners want to create wealth

Outcome

Page 23: On IP

Spata - 2009©

• Cost– value for money

• Velocity– increased speed to market

• Quality– decreased tolerance for error

• Complexity– increased systems integration

• Risk– decreased tolerance for uncertainty

FEARChallenges Owners Face

RISK

Page 24: On IP

Spata - 2009©

DPE

ProfitOverhead

DPELabor & Materials

FeeGeneral Conditions

Contractor Architect

Owner

?

Scope

$Does Not Easily Flow$

Page 25: On IP

Spata - 2009©

O

CDesign Bid Build

A A

O

CGMP

T

O

TDesignBuild

CA

O

C

Novation A

A

O

CIPD

BIM

A

Project Delivery Methods

DesignAssist +

A

O

BIM

C

TA

Page 26: On IP

Spata - 2009©

Design / Construct Integration

Clie

nt In

tera

ction

O

C

Design Bid Build

A

A

O

CGMP

T

O

TDesignBuild

C

A

O

C

NovationA

A

O

T

C

DesignAssist

A

O

CIPD

BIM

A

PFI P3

DesignAssist +

A

O

BIM

C

TA

Page 27: On IP

Spata - 2009©

Design / Construct Integration

Clie

nt In

tera

ction

O

C

Design Bid Build

A

A

O

CGMP

T

O

TDesignBuild

C

A

O

C

NovationA

A

O

T

C

DesignAssist

A

O

CIPD

BIM

A

PFI P3

DesignAssist +

A

O

BIM

C

TA

High Design / Construct Integration

H

igh

Clie

nt In

tera

ction

Page 28: On IP

Spata - 2009©

TOOLS

Form of Agreement Model Progression

Specification Essential Features of IPD

Page 29: On IP

Spata - 2009©

PIMBIM

Agreement

Integrated Project Delivery™

Page 30: On IP

Spata - 2009©

ROLE INTEGRITY

RECIPROCITY

FLEXIBILITY

CREATION OF RESTRAINT ON POWER

IMPLEMENTATION OF PLANNING

CONTRACTUAL SOLIDARITY

PROPRIETY OF MEANS

HARMONIZATION WITH SOCIAL MATRIX

EFFECTUATION OF CONSENT

RESTITUTION, RELIANCE, EXPECTATIONS- David Campbell, “Ian Macneil and the Relational Theory of Contract”

Relational Contract Theory

RelationalOutcome

DiscreteService

Page 31: On IP

Spata - 2009©

Relational Contract• works interactions key to success

Social Capital• mutual trust & respect

Human Nature• few people, short distances, brief

intervals; approach - avoid

Page 32: On IP

Spata - 2009©

AIA 195 / 295 Documents

Page 33: On IP

Spata - 2009©

“Functional” IPD

A 195Owner -

Contractor

B 195Owner – Architect

B 295General

Conditions for Integrated

Project Delivery

Page 34: On IP

Spata - 2009©

Project Phasing

Sche

mati

c D

esig

n

Des

ign

Dev

elop

men

t

Cont

ract

D

ocum

ents

Bid

& N

egoti

ation

Prog

ram

min

g

Cons

truc

tion

Adm

inist

ratio

n

Post

Occ

upan

cy

Crite

riaD

esig

n

Det

aile

dD

esig

n

Impl

emen

tatio

nD

ocum

ents

Fina

l Buy

out

Conc

eptu

aliza

t’n

Cons

truc

t’Ad

min

Clos

eout

Fina

l Age

ncy

Appr

oval

C-O

utlin

e Pr

opos

als

D-D

etai

led

Prop

osal

s

E-Fi

nal P

ropo

sals

F-Pr

oduc

tion

Info

rmati

onG

-Ten

der

Doc

umen

tatio

nH

-Ten

der A

ction

J-M

obili

zatio

nK-

Cons

truc

tion

to

Prac

tical

Co

mpl

etion

L-Aft

er P

racti

cal

Com

pleti

on

A-Ap

prai

sal

B-St

rate

gic

Brie

fing

RIBA

Sta

ges

AIA

Trad

ition

alAI

A 19

5/29

5

Agency ApprovalBuyout

Page 35: On IP

Spata - 2009©

Model Progression Specification

AIA Document

E202™ - 2008

Page 36: On IP

Spata - 2009©

Multi-Party Agreement for IPD

Page 37: On IP

Spata - 2009©

Essential Features of IPD

• Shared Objective• Joint Project Management• Early Participation• Shared Risk & Reward

Source - Howard W. Ashcraft, Jr.; Hanson Bridgett LLP

Page 38: On IP

Spata - 2009©

Shared Objective

Validated Target Cost(with ICL)

Validated Target Schedule

Validated Target Programqualitative & quantitative goals setting the Owner’s project requirements

single sum for all Direct Costs to design & build the project (also sets the ICL)

key task timelines, milestones, target date for Substantial Completion

Page 39: On IP

Spata - 2009©

• Project Management Team– Executive Committee– Direction, approval & decisions

• Project Implementation Team– Design and Build the Project– Key Participants, early as possible

Joint Project Management

Page 40: On IP

Spata - 2009©

Project Management Team

Owner

ArchitectContractor

PMT

• Project Facilitator, if required;

• Jointly selected• Direct project

cost

• No ‘skin-in-game’• Honest broker• Enable the

conversation• Cost• Schedule• Reliability PMT Facilita

tor

Page 41: On IP

Spata - 2009©

Facilitation, not Delegation

Owner

ArchitectContractor

Page 42: On IP

Spata - 2009©

Project Implementation Team

MEP Consultant

HVAC Contractor

ElectricalContractor

SteelFabricator

StructuralEngineer

Curtainwall

CivilEngineer

PIT

Owner

ArchitectContractor

Page 43: On IP

Spata - 2009©

Project Implementation Team

MEP Consultant

HVAC Contractor

ElectricalContractor

SteelFabricator

StructuralEngineer

Curtainwall

CivilEngineer

Cost Reimbursable Consultants & Contractors

Fixed Price Consultants & Contractors

Owner

ArchitectContractor

Page 44: On IP

Spata - 2009©

Early Participation

AgencyOwnerArchitect

EngineersGCSubs

Predesign Schematic Design

Design Development

Construction Documents

Agency Permit / Bidding

Construction Closeout

WHO

REALIZEHOW

WHAT

WHATWHO

HOW

AgencyOwnerArchitect

EngineersGC

Subs

Conceptualization Criteria Design Detailed Design Implementation Documents

Agency Coord / Final Buyout

Construction Closeout

REALIZE

Traditional

Collaborate

- AIA, “Integrated Project Delivery: A Guide”

Key Participants

Page 45: On IP

Spata - 2009©

Shared Risk & Reward

Incentive Compensation Layer (ICL)

Construction Efficiency Adjustment

Project Schedule Adjustment

Project Quality Adjustment

Safeguard against fast & cheap

ICLCEA

PSAPQ

A

OwnerParticipation

Page 46: On IP

Spata - 2009©

C A Owner

C A Owner

Contractor Architect

Cost Reimbursable Consultants & Contractors

Cost Reimbursable…

Cost Reimbursable…

ICLCEA

PSAPQ

AC A OwnerCost Reimbursable…

Page 47: On IP

Spata - 2009©

+$8,000-$1,600

-$3,200-$3,200 20% of ICL, Maximum

+$1,500/day-$100/day

-$200/day-$200/dayLate Penalty @ 1/3 of Early Bonus

$2,000 $2,000 $5,000

$16,000 $16,000

$8,000

$1,000$10,000 savings

$40,000

Hypothetical $1,000,000 VTC

ICLCEA

PSAPQ

A

Page 48: On IP

Spata - 2009©

PQA

Standard

Quality Criteria

Potential Quality Points

Quality Materials: Are the materials installed of the quality, durability and maintainability required by the VTP?

[-6 to +6]

Workmanship: Is the workmanship of the completed Work consistent with the VTP?

[-6 to +6]

Performance: Are the building systems operational and functioning in accordance with the performance requirements stated in the VTP?

[-6 to +6]

Functionality Spatial: Does the Project provide the spaces required by the VTP?

[-6 to +6]

Functional: Does the arrangement of spaces comply with the VTP so that it meets the needs of the Owner’s staff and assist them in carrying out their responsibilities?

[-6 to +6]

Usability: Does the arrangement of spaces comply with the VTP so that it meets the needs of the Owner’s clients and others that will use the space?

[-6 to +6]

Aesthetics Visual Appeal: Does the completed Work provide the visual appeal required by the VTP?

[-6 to +6]

Cultural Expression: Does the completed Work express the Owner’s culture and uniqueness as stated in the VTP?

[-6 to +6]

Sustainability Sustainable Design Objective Achieved: Has the Sustainable Design Objective stated in the VTP been achieved?

[-6 to +6]

Sustainable Design Innovation: Does the completed Work provide sustainable design solutions that are innovative?

[-6 to +6]

QUALITY RATING: [-60 to +60]

Page 49: On IP

Spata - 2009©

FunctionFormCost

Time

Goals Facts Concepts NeedsProblem

Statement

Discovery Analysis Findings

What is it all

about?

What is the idea?

What do you

really need?

Recognize conditions;

state directions.

What do you want

to do? Why?

Courtesy of HOK: Problem-Seeking ™

Information Index

Page 50: On IP

Spata - 2009©

What is Direct Cost?

DPE

Overhead

Brea

keve

n

Profit-Not-at-Risk

Profit-at-Risk (ICL)W

ithin VTC

Reimbursables‘Gua

rant

eed’ Beyond VTC

Page 51: On IP

Spata - 2009©

Shared Pain & Gain

Time

Cost

4%

ICL pays direct costs

Owner pays direct costs

VTC

ICL

Sche

dule

dCo

mpl

etion

Owner pays direct costs Ac

tual

Com

pleti

on

Page 52: On IP

Spata - 2009©

• Design Costs– Architect– Cost Reimbursable Consultants– Fixed-Price Consultants– Reimbursable Expenses

• Construction Costs– General Contractor– Cost Reimbursable Sub-Contractors– Fixed-Price Sub-Contractors– General Conditions

• Other Direct Costs– PMT Facilitator– FF&E

Design and Construct to Objective

Page 53: On IP

Spata - 2009©

EXPECTATIONS

How to Recognize IPD Is it Good for You?

Page 54: On IP

Spata - 2009©

How to Recognize IPD

1. Multi-Party Agreement2. Shared Risk & Reward3. Relational Contract4. Shared Project Objective5. ‘Zero’ Change Orders6. Shared Unitary Fund7. BIM-Optional (in theory)

Page 55: On IP

Spata - 2009©

1 Multi-Party Agreement

• Single, signed agreement– Owner, Designer, Constructor– More parties, counterproductive

• Joint project management– Achieve the project objective as the

Project Management Team (PMT)

• Limited / Waived liability– Among PMT

Page 56: On IP

Spata - 2009©

2 Shared Risk & Reward

• Shared pain & gain based on project outcome– Team performance trumps individual

• Early involvement of key participants– Cost Reimbursable consultants &

contractors

Page 57: On IP

Spata - 2009©

3 Relational Contract

• Agreement defines the working relationship of:– Owner, Designer, Constructor– Roles retain integrity

• Deliver a project outcome, not a service

Page 58: On IP

Spata - 2009©

4 Shared Project Objective

• Validated Target Cost– (VTC)– Incentive Compensation Layer (ICL)

• Validated Target Program– (VTP)

• Validated Target Schedule– (VTS)

Page 59: On IP

Spata - 2009©

5 ‘Zero’ Change Orders

• Owner Directive• Differing Site Conditions• Agreed Scope Change

– Adjust VTP, VTS, VTC, ICL

Page 60: On IP

Spata - 2009©

6 Shared Unitary Fund

• VTC is the single source funding all design & construction direct costs

• Funds ‘flow’ to maximize Owner value– If spending more on design saves much

more on construction, then money moves that way, & vice-versa

Page 61: On IP

Spata - 2009©

7 BIM-Optional (in theory)

• BIM is a tool, IPD a method• IPD without BIM is possible,

but so difficult as to be impractical– BIM technology enables IPD

Page 62: On IP

Spata - 2009©

Is it good for you? Ask, do we…

• use a transparent & immediate decision-making process?

• have knowledge regarding design & construction?

• not delegate our project participation & responsibility?

• know our building type?• enjoy a reputation for reliability?

Page 63: On IP

Spata - 2009©

Thank You


Top Related