Download - OHSE Daily Obsrvn Report 12.10.15.pdf
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 1/7
Project Management, India
SI No. OHSE Observations Area \ Location Action Required Action By Complaince by date Remarks
1
Material kept in front of fire point blocking the access to fire
point.
3rd Floor Entrance
gate.
Remove the material from there
and make the access to the fire
point neat & clean.
Ambience Today
2
Damaged ladder is being used at site.
3rd Floor Entrance
gate.
Instructed to replace the damge
ladder by safe one.Dynaaircon Today
Daily OHSE Observation,Site instruction/Compliance Report
Project Name : Amex
Contractor : All vendors
Area\location of site inspected : All Around The site
CBRE South Asia Pvt. Ltd. Page 1 of 7
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 2/7
Project Management, India
3
Worker working at height without hand rail and mid rail in
the scaffolding.
3rd Floor.Provide hand rail and mid rail to
the scaffolding.Ambience Today
4
Insertion of electrical wire without top plug.
3rd floor near lift
lobbyinstructed to provide top plug. Ambience Today
CBRE South Asia Pvt. Ltd. Page 2 of 7
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 3/7
Project Management, India
5
The height of the stacking material is more than 1.5 m and
the stacked materials are not barricaded.
3rd floor near dyna
office
Instructed to provide soft
barrication around materials kept
on the floor.
Dynaaircon Today
6
Gas cylinders laying on the floor.
3rd floor near dyna
office
Instructed to provide trolley and
keep the cylinders on the trolley
only.
Dynaaircon Today
7
Materials scattered on the floor showing poor housekeeping
of the floor.
3rd floor south area
Remove unwanted materials from
floor and keep the materials to be
used at site in proper barricaded
area.
DSCPL Today
CBRE South Asia Pvt. Ltd. Page 3 of 7
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 4/7
Project Management, India
8
Unwanted materials stacked on the floor.
3rd floor near ups
room
remove all the unwanted
materials from the floor to make
the floor in presentable.
Emerssion Today
9
Gas cylinders kept on the floor without any protection.
3rd floor near
comms room
Instructed to provide trolley and
keep the cylinders on the trolley
only.
Emerssion Today
CBRE South Asia Pvt. Ltd. Page 4 of 7
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 5/7
Project Management, India
10
Poor housekeeping of the floor.
4th floor south area
remove all the unwanted
materials from the floor to make
the floor in presentable.
ALL Today
11
Poor housekeeping of the floor.
4th floor south area
remove all the unwanted
materials from the floor to make
the floor in presentable.
ALL Today
CBRE South Asia Pvt. Ltd. Page 5 of 7
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 6/7
Project Management, India
12
Poor housekeeping of the floor.
4th floor near toilet
area.
remove all the unwanted
materials from the floor to make
the floor in presentable.
Ambience Today
13
Worker doing height work without any protection.
2nd floorProvide hand rail and mid rail to
the scaffolding.Ambience Today
CBRE South Asia Pvt. Ltd. Page 6 of 7
7/24/2019 OHSE Daily Obsrvn Report 12.10.15.pdf
http://slidepdf.com/reader/full/ohse-daily-obsrvn-report-121015pdf 7/7
Project Management, India
14
Gas cylinders laying on the floor.
2nd floor
Instructed to provide trolley and
keep the cylinders on the trolley
only.
Ambience Today
Format No. L006-OHS-DO-Fr-006/Rev02/May2015
CBRE South Asia Pvt. Ltd. Page 7 of 7