Project Scope, Budget and Schedule
![Page 3: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/3.jpg)
• 15 distinct projects spread over three DMC campuses
• $500 million dollars total project cost
• Project budgets range from $2.3 million dollars to $126 million dollars (construction cost)
• Complex projects built in an operating hospital environment requiring a high degree of skill and experience
Capital Building Program
![Page 4: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/4.jpg)
Central CampusHarper University Hospital
![Page 5: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/5.jpg)
Harper/ Hutzel Unified Lobby
Project Specifics:
• Renovation and New Construction• $8.5 million construction• 18 month project duration• Summer 2011 start date
Project Specifics:
• Renovation and New Construction• $8.5 million construction• 18 month project duration• Summer 2011 start date
![Page 6: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/6.jpg)
Surgical Services Renovation
Project Specifics:
• Phased renovation • $16.9 million construction• 28 month project duration•Fall 2011 start date
Project Specifics:
• Phased renovation • $16.9 million construction• 28 month project duration•Fall 2011 start date
Pre & Post Operative CarePre & Post Operative Care
Operating RoomsOperating Rooms
LabsLabs
OR Storage & Support
OR Storage & Support
LockersLockers
OR Storage & Support
OR Storage & Support
LockersLockers
Surgery Recept & Waiting
Surgery Recept & Waiting
KCCKCC
Nuclear Medicine
Nuclear Medicine
Nuclear Medicine
Nuclear Medicine
LabsLabs
![Page 7: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/7.jpg)
CentralPrep/ Recovery
Ultrasound
InterventionalRadiology
Reception &Check-In
Radiology
CT ScanSupport
Ground Floor Masterplan Project
Project Specifics:
• Phased renovation • $9.8 million construction• 26 month project duration• Spring 2013 start date
Project Specifics:
• Phased renovation • $9.8 million construction• 26 month project duration• Spring 2013 start date
HUH Webber Memorial Hospital Ground FloorN
![Page 8: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/8.jpg)
HUH Unit Renovations
Project Specifics:
•Phased renovation•$4.3 million construction•15 month project duration• Summer 2011 start date
Project Specifics:
•Phased renovation•$4.3 million construction•15 month project duration• Summer 2011 start date
![Page 9: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/9.jpg)
Harper ED Expansion
Project Specifics:
•Phased renovation and new construction
•$2.3 million construction•12 month project duration•Start Date TBD
Project Specifics:
•Phased renovation and new construction
•$2.3 million construction•12 month project duration•Start Date TBD
![Page 10: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/10.jpg)
Central CampusChildren’s Hospital of Michigan
![Page 11: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/11.jpg)
CHM Patient Tower & Carls MOB
Project Specifics:
• New construction and renovation
• $126 million construction• 58 month project
duration• Start Date TBD
Project Specifics:
• New construction and renovation
• $126 million construction• 58 month project
duration• Start Date TBD
![Page 12: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/12.jpg)
CHM Pediatric Specialty Center
Project Specifics:
• New construction • $24.6 million construction• 16 month project duration• Fall ‘10 start date
Project Specifics:
• New construction • $24.6 million construction• 16 month project duration• Fall ‘10 start date
![Page 13: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/13.jpg)
Central CampusDetroit Receiving Hospital
![Page 14: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/14.jpg)
DRH Inpatient Renovations
Project Specifics:
• Phased renovation • $13.9 million construction• 48 month project duration• Summer 2012 start date
Project Specifics:
• Phased renovation • $13.9 million construction• 48 month project duration• Summer 2012 start date
![Page 15: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/15.jpg)
DRH New OR & Pre/Post-OpProject Specifics:
• New construction and phased renovation
• $4.4 million construction• 12 month project
duration• Fall 2011 start date
Project Specifics:
• New construction and phased renovation
• $4.4 million construction• 12 month project
duration• Fall 2011 start date
![Page 16: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/16.jpg)
Central CampusRehabilitation Institute of Michigan
![Page 17: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/17.jpg)
RIM 6th Floor Renovation
Project Specifics:
• Renovation project• $3.15 million construction• 12 month project duration• Spring 2012 start date
Project Specifics:
• Renovation project• $3.15 million construction• 12 month project duration• Spring 2012 start date
![Page 18: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/18.jpg)
Central CampusCardiovascular Institute and HUH Multispecialty Building
![Page 19: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/19.jpg)
Cardiovascular Institute & Multispecialty Building
Project Specifics:
• New construction• $58 million construction• 34 month project
duration• Fall 2011 start date
Project Specifics:
• New construction• $58 million construction• 34 month project
duration• Fall 2011 start date
![Page 20: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/20.jpg)
Central CampusNew Parking Structure
![Page 21: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/21.jpg)
New Parking Structure
Project Specifics:
• New construction• $30.6 million construction• 20 month project duration• Winter 2012 start date
Project Specifics:
• New construction• $30.6 million construction• 20 month project duration• Winter 2012 start date
![Page 22: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/22.jpg)
NorthWest Detroit CampusSinai Grace Hospital
![Page 23: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/23.jpg)
SGH ED, ICU & Radiology
Project Specifics:
• New construction and Phased Renovation
• $52.6 million construction• 36 month project duration• Fall 2011start date
Project Specifics:
• New construction and Phased Renovation
• $52.6 million construction• 36 month project duration• Fall 2011start date
![Page 24: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/24.jpg)
Commerce Township CampusHuron Valley Sinai Hospital
![Page 25: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/25.jpg)
Renovations to Private Rooms
Project Specifics:
• Phased Renovation• $4.6 million construction• 11 month project duration• Early 2011 start date
Project Specifics:
• Phased Renovation• $4.6 million construction• 11 month project duration• Early 2011 start date
![Page 26: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/26.jpg)
HVSH Additional ICU Beds
Project Specifics:
• Phased Renovation• $2.3 million construction• 10 month project duration• Early 2012 start date
Project Specifics:
• Phased Renovation• $2.3 million construction• 10 month project duration• Early 2012 start date
![Page 27: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/27.jpg)
Projects with A/E award and currently in design:
SGH ED, ICU, Radiology & Unified Lobby Project- SmithGroup/Hamilton Anderson/Scales
DRH New OR and Pre-Op/ Post-Op Project- Stucky Vitale/T2 Design/Wade Trim
Harper/ Hutzel Unified Lobby Project- Neumann Smith/BEI./TYJT
HUH Surgical Services Renovations- HKS Inc./Hamilton Anderson/Desai
Nasr
HUH Patient Unit Renovations- Stucky Vitale/T2
Design/Wade Trim
CVI & HUH Multispecialty Bldg & Parking Structure- Harley Ellis Devereaux Metco,BEI,
DPRA, Centric Design
Project Teams and Awards
![Page 28: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/28.jpg)
Projects with CM award and currently in construction:
Children’s Hospital Pediatric Specialty Center Brinker, LLC
HVSH Inpatient Rooms MIG/Auch
Projects recently Awarded for CM Services:
DRH New OR and Pre-Op/ Post-Op Project DeMaria/C.S Farmer
Harper/ Hutzel Unified Lobby Project Walbridge/DIG
Projects currently out to bid for CM services:
SGH ED, ICU, Radiology & Unified Lobby Project 3/25 award
HUH Surgical Services Renovations 4/11 award
CVI & HUH Multispecialty Building & Parking Structure 4/11 award
![Page 29: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/29.jpg)
Projects awaiting release:
RIM 6th floor Renovation12/2011 start
HVSH Additional ICU Beds 08/2011 start
DRH Patient Care Unit Renovations05/2011 start
CHM Tower Project TBD
HUH Ground Floor Masterplan05/2013 start
HUH Patient Unit Renovations construction05/2011 start
![Page 30: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/30.jpg)
Project Labor Agreement(PLA)
![Page 31: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/31.jpg)
•A Project Labor Agreement will be entered into between The Detroit Medical Center and the Greater Detroit Building and Construction Trades Council, (GDBTC), acting on its own behalf and on behalf of its respective affiliates, and signatory unions.
•The purpose of this agreement will be to assure that all construction work shall proceed economically, efficiently, safely, continuously, without interruption and with due consideration for the protection of labor standards, wages and working conditions.
•The GDBTC shall work with its respective signatory unions to promote hiring practices that promote DMC’s commitment to inclusion.
![Page 32: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/32.jpg)
Owner Controlled Insurance Program(OCIP)
![Page 33: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/33.jpg)
The Detroit Medical Center will enter into an agreement to provide and administer an Owner Controlled Insurance Program (OCIP). This will be a multi-site and multi-year program. This program will apply to all contractors and subcontractors providing services for these projects.
![Page 34: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/34.jpg)
Community Commitment
![Page 35: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/35.jpg)
The DMC has made a commitment to the Community by setting significant goals for inclusion:
• 30% of all construction dollars will be awarded to minority-owned (MBE), women-owned (WBE) and Detroit based businesses (DHB, DBB)
• A minimum of 25% of all hours worked on construction projects will be by a Minority
• 25% of all hours worked on construction projects will be by City of Detroit Residents
• 50% of all hours worked on construction projects will be by Wayne County Residents
• A minimum of 25% of hours worked by apprentices on construction projects will be by Minorities
![Page 36: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/36.jpg)
Tracking & Reporting Progress
The Detroit Medical Center has engaged the services of the MMSDC to oversee the collection and compilation of data supplied by all contracted firms relative to MBE, WBE, DBB/ DHB and residency requirements.
This information will be supplied by each contracted firm on an on-line application and submitted monthly to the MMSDC for verification, compilation and the reporting of progress toward committed goals.
![Page 37: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/37.jpg)
Contractor Prequalification Requirements
![Page 38: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/38.jpg)
General Bidder PreQualification
As a prerequisite to working at the Detroit Medical Center, all firms must complete a BIDDER
PREQUALIFICATION FORM and must be pre-approved.
• Go to DMC.ORG and Click on the Construction Update Icon.
• Prequalification helps to insure streamlined access to opportunities to participate in the Capital Building Program.
• Companies who are prequalified will be posted on the DMC and Schooner Consulting Websites.
• Prequalification is not a guarantee of work. It is a tool to help develop a pool of qualified contractors/ vendors.
![Page 39: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/39.jpg)
Non Capital Building Program Construction
The DMC posts all requests for proposals on the DMC Website .
• Go to DMC.ORG and click on the Vendors Link at the bottom of the page.
• At the Material Resource Management page click on view RFPs on the right side of the page.
![Page 40: NAMC March 2011. Project Scope, Budget and Schedule](https://reader030.vdocuments.us/reader030/viewer/2022032703/56649d0c5503460f949dfd8d/html5/thumbnails/40.jpg)
Questions