N. Burleson St. – Status Update
I. Typical Sections & Pavement DesignII. Budget and Preliminary Cost EstimatesIII. Schedule
SEPTEMBER 16, 2014
Proposed Typical Sections
Miller St. to Lockhart St.
OPTION 1
OPTION 2
20 year pavement designs
Location Map
Proposed Typical SectionsLockhart St. to Marketplace
OPTION 2
OPTION 1
Proposed Typical SectionsLockhart St. to Marketplace
OPTION 3
OPTION 4
Location Map
Location Map
Location Map
Proposed Typical SectionsIH 35 Connector
OPTION 1
OPTION 2
Location Map
Budget and Cost Estimate Update
Miller St. to Lockhart St.Project Activity Authorized
Option 1 Option 2Budget Amts 2 Lanes 3 Lanes
Rdway ConstructionRoadway Construction $7,300,000.00 365,000$ 509,000$ Utility Improvements ---- 18,000$ 75,000$ ROW Acquisition $225,000.00 -$ -$ ROW Services $0.00 -$ -$ Contingency $0.00 18,250$ 25,450$ Construction Sub- Totals $7,525,000.00 401,250$ 609,450$
Rdway DesignRoadway Design ----Utility Engineering ---- 3,000$ 5,000$
Black Base Pvmt Option Add'l Cost 7,100.00$ 9,200.00$
N Burleson StMiller to Lockhart
ROW Impacts
Miller St. to Lockhart St.
Option 2 • Major impacts to business parking• Parking reduced from 34 spaces to approximately 20 spaces• Traffic signals at Center relocated• ADA facilities relocated/reconstructed
N Burleson St (Miller to Lockhart) - Option 1 0 SF 0 parcelsN Burleson St (Miller to Lockhart) - Option 2 0 SF 0 parcels
Option 1 Water conflicts – 260 LF W/W conflicts – 0 LF
Option 2 Water conflicts – 350 LF W/W conflicts – 0 LF
Budget and Cost Estimate Update
Lockhart St. to MarketplaceProject Activity Authorized
Option 1 Option 2 Option 3 Option 4
Budget Amts3 Lns (6-ft SW
E & W)10-ft Path
No E SW 3 Lns
No E SW Mostly 2 Lns
Rdway ConstructionRoadway Construction $7,300,000.00 4,346,000$ 4,451,000$ 4,176,000$ 3,431,000$ Utility Improvements ---- 415,000$ 415,000$ 415,000$ 80,000$ ROW Acquisition $225,000.00 117,405$ 172,026$ 18,608$ 3,717$ ROW Services $0.00 262,500$ 273,000$ 115,500$ 42,000$ Contingency $0.00 217,300$ 222,550$ 208,800$ 171,550$ Construction Sub- Totals $7,525,000.00 5,358,205$ 5,533,576$ 4,933,908$ 3,728,267$
Rdway DesignRoadway Design ----Utility Engineering ---- 60,000$ 60,000$ 60,000$ 12,000$
Black Base Pvmt Option Add'l Cost 75,300.00$ 75,300.00$ 75,300.00$ 54,800.00$
N Burleson StLockhart to Marketplace
Option 4 – 3 lanes Lockhart to North; Southbound right turn lanes at North St. and Spring Branch.
ROW Impacts
Lockhart St. to MarketplaceN Burleson St (Lockhart to Marketplace) - Option 1 26,090 SF 25 parcels (residential)N Burleson St (Lockhart to Marketplace) - Option 2 38,228 SF 26 parcels (residential)N Burleson St (Lockhart to Marketplace) - Option 3 4,135 SF 11 parcels (residential)N Burleson St (Lockhart to Marketplace) - Option 4 826 SF 4 parcels (residential)
Most property acquisitions approximately 9 feet from existing ROW to proposed ROW
Option 1 Water conflicts – 3365 LF W/W conflicts – 1545 LF
Option 2 Water conflicts – 3365 LF W/W conflicts – 1545 LF
Option 3 Water conflicts – 3365 LF W/W conflicts – 1545 LF
Option 4 Water conflicts – 2000 LF W/W conflicts – 0 LF
Logical termini for Phase 1 before RR – requires 2 PS&E packages; additional design fee.Phase 2 – RR to IH 35 Connector and cul-de-sac at low water crossing
Budget and Cost Estimate Update
IH 35 ConnectorProject Activity Authorized
Option 1 Option 2
Budget Amts 3 Lanes 4 Lanes
Rdway ConstructionRoadway Construction $7,300,000.00 1,177,000$ 1,445,000$ Utility Improvements ---- -$ -$ ROW Acquisition $225,000.00 613,450$ 702,360$ ROW Services $0.00 10,500$ 10,500$ Contingency $0.00 58,850$ 72,250$ Construction Sub- Totals $7,525,000.00 1,859,800$ 2,230,110$
Rdway DesignRoadway Design ----Utility Engineering ----
Black Base Pvmt Option Add'l Cost 14,600.00$ 17,800.00$
IH 35 ConnectorBurleson to IH 35 SBFR
ROW Impacts
IH 35 Connector
IH 35 Connector - Option 1 61,345 SF 1 parcel (commercial)IH 35 Connector - Option 2 70,236 SF 1 parcel (commercial)
No utility conflicts
Cost Estimate Comparisons
RR Quiet Zone – approximately $50K
Burleson Option Combinations Est. Cost Difference
Option 1, 1, 1 $8,641,947.00 -$141,947.00
Option 2, 2, 2 $9,397,828.00 -$897,828.00
Option 1, 2, 1 $8,817,318.00 -$317,318.00
Option 1, 2, 2 $9,187,628.00 -$687,628.00
Option 2, 1, 1 $8,852,147.00 -$352,147.00
Option 2, 2, 1 $9,027,518.00 -$527,518.00
Option 1, 3, 1 $8,217,649.50 $282,350.50
Option 1, 3, 2 $8,587,959.50 -$87,959.50
Option 1, 4, 1 $6,964,009.00 $1,535,991.00
Option 1, 4, 2 $7,334,319.00 $1,165,681.00
Option 2, 3, 1 $8,427,849.50 $72,150.50
Option 2, 3, 2 $8,798,159.50 -$298,159.50
Option 2, 4, 1 $7,174,209.00 $1,325,791.00
Option 2, 4, 2 $7,544,519.00 $955,481.00
Authorized Budget $8,500,000
Cost Estimate Comparisons
Option Combinations Within Budget
Location Option CommentsMiller to Lockhart 1 2 lanesMiller to Lockhart 2 3 lanes
Lockhart to Marketplace 1 3 lanes w/sidewalksLockhart to Marketplace 2 3 lanes sidewalk & shared pathLockhart to Marketplace 3 3 lanes 1 sidewalkLockhart to Marketplace 4 2 & 3 lanes, 1 sidewalk
IH 35 Connector 1 3 lanesIH 35 Connector 2 4 lanes
Within Budget Burleson Option
CombinationsEst. Cost Difference
Option 1, 3, 1 $ 8,217,649.50 $ 282,350.50
Option 1, 4, 1 $ 6,964,009.00 $ 1,535,991.00
Option 1, 4, 2 $ 7,334,319.00 $ 1,165,681.00
Option 2, 3, 1 $ 8,427,849.50 $ 72,150.50
Option 2, 4, 1 $ 7,174,209.00 $ 1,325,791.00
Option 2, 4, 2 $ 7,544,519.00 $ 955,481.00
Authorized Budget $8,500,000
Alternate Cost Estimate Comparisons
Within Budget Burleson Option
CombinationsEst. Cost Difference Alternate
Pavement Design Revised Difference
Option 1, 3, 1 $ 8,217,649.50 $ 282,350.50 $ 8,314,649.50 $ 185,350.50
Option 1, 4, 1 $ 6,964,009.00 $ 1,535,991.00 $ 7,040,509.00 $1,459,491.00
Option 1, 4, 2 $ 7,334,319.00 $ 1,165,681.00 $ 7,414,019.00 $1,085,981.00
Option 2, 3, 1 $ 8,427,849.50 $ 72,150.50 $ 8,526,949.50 $ (26,949.50)
Option 2, 4, 1 $ 7,174,209.00 $ 1,325,791.00 $ 7,252,809.00 $1,247,191.00
Option 2, 4, 2 $ 7,544,519.00 $ 955,481.00 $ 7,626,319.00 $ 873,681.00
Authorized Budget $8,500,000
Location Option CommentsMiller to Lockhart 1 2 lanesMiller to Lockhart 2 3 lanes
Lockhart to Marketplace 1 3 lanes w/sidewalksLockhart to Marketplace 2 3 lanes sidewalk & shared pathLockhart to Marketplace 3 3 lanes 1 sidewalkLockhart to Marketplace 4 2 & 3 lanes, 1 sidewalk
IH 35 Connector 1 3 lanesIH 35 Connector 2 4 lanes
Schedule of Activities
Project letting could vary with City engaging the services for proposed ROW surveying and appraisals.
Last 9 months of RR Coordination is for material procurement by UPRR.
Potential risk for contractor claim if RR coordination is delayed and/or City elects to remove RR work from project after letting.