Monkstown Village Traffic Management Improvement Scheme
UPDATE
March 2016
History• Non Statutory Public Consultation took place in August and
September 2012 and 78 submissions were received.
• A meeting with a representative group of businesses and residents was held in January 2013.
• A Report on the submissions received was presented to the 4th March 2013 DLAC meeting
• A presentation on the revised proposals including the public realm elements was given to the Dun Laoghaire Area Committee in April 2015
• Project update to Dun Laoghaire Councillors given prior to the Council Meeting in October 2015
• Detailed Design commenced Dec 2015
Scheme:
Architecture & Culture Department
![Page 2: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME](https://reader034.vdocuments.us/reader034/viewer/2022051300/579076b91a28ab6874ba81a3/html5/thumbnails/2.jpg)
24/03/2016
2
End
Additional element:
Level difference at restaurants
- Reduce carriageway to 6m
- Widen path at restuarants
- Indented parking bays
- Planting
- Discrete drainage
- Crossing point at Avoca
Current Situation
Current Situation:
Avoca
![Page 3: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME](https://reader034.vdocuments.us/reader034/viewer/2022051300/579076b91a28ab6874ba81a3/html5/thumbnails/3.jpg)
24/03/2016
3
Proposed Current Situation
Existing street lighting and cablesImpact on parking
Existing Proposed
Clifton Avenue
+9 spaces
Impact on
parking
Monkstown Crescent: - Loading bays reduced in size - 1 car space lost adjacent to shops - 2 spaces lost opposite Avoca. 3 additional space at Link Road.
![Page 4: MONKSTOWN VILLAGE TRAFFIC MANAGEMENT IMPROVEMENT SCHEME](https://reader034.vdocuments.us/reader034/viewer/2022051300/579076b91a28ab6874ba81a3/html5/thumbnails/4.jpg)
24/03/2016
4
Carrickbrennan Road
+1 spaceOverall gain of
10 no. spaces
Next steps…….
- Engage with business on Monkstown Crescent
- Detailed design completed July 2016
- Contractor appointed September 2016
- Contract duration approximately 6 months
Questions?