Download - Method Statement and Risk Assessments
![Page 1: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/1.jpg)
Page 1 of 45
Grand Union: MS-01 Rev 00
GCL, 2-3 Little Burrows, Welwyn Garden City, Herts Al7 4SP
Prepared By:
Tara Quinn
H&S Manager
Reviewed by:
Stuart Rawlins
Project Manager
Final Review:
Richard Milverton Head of Construction
Approved by:
Matt Cain
Project Manager
St George Ltd
Signed on Behalf of St George Ltd
Matt Cain
Sign:
Signed on Behalf of GCL
Stuart Rawlins
Sign:
Original 24/09/21 Enabling works RAMS
Note: All amendments are highlighted in yellow
CLIENT
St George Ltd
PRINCIPAL CONTRACTOR St George Ltd
CONTRACT TITLE Grand Union – phase 2
CONTRACT NO. 0423
SITE ADDRESS: Grand Union Project Office, Wycombe Road, HA0 1RH
GROUND
CONSTRUCTION LTD
Ground House
2-3 Little Burrows
Welwyn Garden
City Herts AL7 4SP
Tel: 020 8238 7000
Email:
[email protected] Project Manager [email protected] Head of Construction
COMMENCE OF WORKS:
TASK DURATION
November 2021
As per programme
Enabling works & Installation of Piling Mat
Method Statement and Risk Assessments
![Page 2: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/2.jpg)
Page 2 of 45
Grand Union: MS-01 Rev 00
GCL, 2-3 Little Burrows, Welwyn Garden City, Herts Al7 4SP
CONTROLLED COPY NO. JOB TITLE
01 Stuart Rawlins – GCL Project Manager (Tel: 07887 325634)
02 VJ – GCL Project Engineer (Tel: 07944 682042)
03 Anne Fennessy – GCL H&S Director (Tel: 07903 756982)
04 Tara Quinn – GCL Health & Safety Manager (Tel: 07908 163082)
05 Richard Milverton – Head of Construction (Tel: 07903 764639)
06
Matt Cain – Project Manager (St George Ltd)
Monthly Review By: Name: Signature: Date: Outcome / Status
![Page 3: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/3.jpg)
Page 3 of 45
Grand Union: MS-01 Rev 00
GCL, 2-3 Little Burrows, Welwyn Garden City, Herts Al7 4SP
Introduction – Scope of Works
Reference Documents
Pre-commencement Requirements
Resources
Materials
Plant
Supervision / Labour
Methodology
Site Layout/ Traffic Management
Programme
Quality
Safety
PPE RISK ASSESSMENTS COSHH
Fire Temporary Works Working at height
Environment
Emergency Procedures and First Aid
Training
1.0 COSHH Assessments
2.0 HAV’s Assessments
3.0 RAMS Briefing Sheet
Contents
Appendices/ Risk Assessments
![Page 4: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/4.jpg)
Page 4 of 45
Grand Union: MS-01 Rev 00
GCL, 2-3 Little Burrows, Welwyn Garden City, Herts Al7 4SP
1.0 Introduction – Scope of Works
This document outlines the proposed method for the enabling works, installation of piling mat, piling attendance
at Phase 2 of the Grand Union project for St George Ltd.
Phase 1 works are still ongoing on the site, which are being completed by others, however the works remain under the control of St George Ltd.
Access to the Phase 1 works will be required throughout the duration of Ground Construction Ltd.’s (GCL) works, and this access will be provided by the existing haul road on site.
GCL will have access to this haul road for the duration of the works and GCL must ensure that this road is maintained and free of mud/ debris.
This Method Statement and Risk Assessment is specific for the construction of the below works:
Site set up
Enabling works
Breaking hardstanding
Reduce dig
Installation of Piling Mat
2.0 Reference Documents / Permits
Construction issue drawings will be issued before work commences and stored in the site folder.
Relevant permits will be issued by St George Ltd. All permits will be applied for each day with a briefing with the operatives, the permit with the drawing location will be copied and a set put on the permit board.
3.0 Pre-Commencement Requirements
This Method Statement together with the associated Risk Assessments and COSHH Assessments must be
communicated to all involved in the works.
All operatives must sign the Briefing Register at the end of the document to confirm that they have understood and agreed to comply with the requirements and safe working practices detailed within.
If the workforce feel the RAMS is not suitable or feel what they are asked to do is unsafe then they may stop work and bring this to the attention of the Project Manager / H&S Manager
The Project Manager may alter this document but it must be approved by the GCL H&S Manager before deviations take place.
All personnel arriving on site will attend the project induction given by St George as Principal Contractor; all operatives will be trained in their role with CSCS / CPCS cards copied to at induction stage.
Following the St George induction, operatives will then attend the GCL induction and be briefed on the RAMS.
Access into site will be via the site security office and through the turnstile. Visitors will be required to sign in/out.
Once inducted, security cards will be required to access the works via turnstiles.
Access to the work areas will be restricted to GCL personnel involved in the tasks using barriers/fences and signage as deemed necessary by site management. GCL will demarcate walkways in their work areas and ensure they are free from excess materials and equipment.
All lifting equipment/accessories will have current thorough examination certificates with Safe Working Load (SWL) clearly identified. Records of regular inspections are to be retained on site and all lifting equipment is to be inspected before use, they will also be thoroughly inspected every 6 months as required by LOLER.
All lifting operations will be in accordance with the s ite Lifting Plan for excavators and tower cranes. Schedule of lifts will be part of the lift plan issued by GCL Appointed Person.
![Page 5: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/5.jpg)
Page 5 of 45
Grand Union: MS-01 Rev 00
GCL, 2-3 Little Burrows, Welwyn Garden City, Herts Al7 4SP
All H&S related documentation will be issued to St George on a weekly basis
There will be no parking on site.
COVID-19 government guidelines & St George’s site rules will be adhered to. Face coverings will be worn when moving around site welfare at all times under St George site rules.
4.0 Resources
4.1 Materials
Sheet piles
Trench boxes
Timber/ plywood
Rebar of different sizes as to confirm to the Construction issue drawings.
Concrete as per the design specification.
Waterproofing membranes
Waterproofing admixtures to concrete
Drainage pipes, services ducts and associated accessories.
Timber and plywood as required, with FSE & PEFC certs to be provided.
4.2 Plant / Equipment
Excavators 3te-38te / Dumpers 3-9te / Bombag roller
Compressors / Generators / CP9 / SK12 handheld breakers
Pile Cropper / Water pumps and hoses
CAT & Genny Set / Insulated Hand Digging Tools
Barriers and signage / Proprietary access steps
Slings, Chains & Bow Shackles
Fuel Safe Bowers (bunded & spill kits)
110v electrical tools - Various hammer drills, saws etc. Hand tools – hammers, shovels etc.
Combi Safe / Edge Protection
Timber pole Ladders and access stairs
110v power tools
Engineering Equipment
Power saw with a diamond tipped blade (petrol)
Hand tools
Compressors / generators (complete with drip tray) 4.3 Supervision / Labour
Stuart Rawlins is Project Manager, based on site
V J is Project Engineer, based on site
Construction Manager will be on site to supervise the works and ensure the safe system of work is followed; operatives will range from 25 at current levels to 150 or more depending on progress of the works.
Additional Supervisors will be required as the work volume increases.
Tara Quinn will be the visiting Health & Safety Manager and Richard Milverton will be a visiting Head of Construction
![Page 6: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/6.jpg)
Page 6 of 45
Grand Union: MS-01 Rev 00
GCL, 2-3 Little Burrows, Welwyn Garden City, Herts Al7 4SP
GCL STAFF STRUCTURE
The table below outlines the staff hierarchy and line of management from the main office transferred to site supervision.
![Page 7: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/7.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 7 of 45
St George Ltd, Grand Union, Phase 2 00
Spoil Types
This plan has been prepared to facilitate the beneficial reuse of all material, ensuring that the offsite removal of spoil is minimised where practical.
Cut and fill material will generally not be stockpiled but will be removed from the excavation site and transported directly to the construction face for immediate reuse as compacted fill. Unsuitable excavated material will primarily be transported to identified locations within the haul road corridor.
Wherever possible, select material will be sourced on site and kept segregated as necessary until incorporated in the works
Programme or logistics constraints may prevent the use of reusing cut and fill material and therefore the decision may be taken to remove such material from site for the benefit of the project overall.
Spoil Strategy The existing stockpile on site will be tested to determine whether the material is of suitable quality for use and incorporation into the piling mat. The following provides an overview of the GCL strategy for achieving the key spoil management objectives:
Minimise the amount of spoil generated.
Maximise the beneficial reuse of spoil on site based on its classification (both contamination category and geotechnical characteristics).
Dispose of spoil off site based on its contamination classification.
Manage the excavation, storage, transport, reuse and disposal of spoil to minimise impacts and meet other environmental requirements.
Holes and Excavation Protection
All works are to be demarcated and cordoned off using solid physical fencing or half height HERAS fencing. Tubular posts at regular intervals with fixed guardrails will be used at a safe distance away from excavations by a competent operative. All handrails will be double handrails minimum height 950mm minimum gap between rails 470mm.
Access into excavations will be via:
A proprietary set of access stairs (below photo)
Reverse blinded earth with a ramp or steps cut into the batter
No spoil will be stored within 2m of the edge of an open excavation.
Haul roads will be 5m away from open excavations unless a TW design has been carried out.
11. FUEL & L.P.G.’S
Typical stepped access walkway
with handrails that GCL put in place
for access to open excavations
where possible
![Page 8: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/8.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 8 of 45
St George Ltd, Grand Union, Phase 2 00
Fuel and Spillage Management
Fuel will be stored in a lockable bunded bowser/ COSHH Store set up in an area highlighted on the logistics drawing. Drip trays are to be placed under static plant and refuelling only allowed at the designated areas. Refuelling is to be carried out in one single location by a designated operative to avoid fuel being moved freely around site and contaminating the ground. Refuelling operative must wear approval overalls and PPE at all times. Overalls must be removed before the refuelling operative moves onto another task. No hot works to take place anywhere near the refuelling zone and all hot works permits must make note of this enforced exclusion zone. Refuelling operative must not carry out hot works at any time. Drip trays will also be in place when refuelling is taking place. All containers to display “No Smoking”,” Highly flammable liquid” and “No naked flame” signs.
All excavators to carry spill kits for ease of access in the event of a spillage occurring.
![Page 9: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/9.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 9 of 45
St George Ltd, Grand Union, Phase 2 00
The spill response plan will be displayed in all areas where there is a risk of a spill pollution incident. Spill kits will also be in place
![Page 10: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/10.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 10 of 45
St George Ltd, Grand Union, Phase 2 00
Delivery, Storage and Distribution of Materials Unloading of materials is to be carried out using the excavator & Hiab and must be under the control of a competent and qualified Slinger/Signaller. Safe working loads of lifting plant and accessories will be checked against the weight of the items being lifted. All chains and slings to be regularly inspected tested & certified (6 monthly test certificate). Vehicular access to site will be in conjunction with site access plan. Material will be delivered on a “Just in time bases” to maintain access throughout site. GCL Project Manager will hold weekly logistics meetings and all deliveries will be booked in with St George. Fall protection must be in place before anyone is allowed to access unprotected delivery lorries. No person is allowed to climb onto the back of an unprotected delivery lorry. St George’s CLOCS Policy to be adhered to.
If for some reason a delivery vehicle arrives on site with inadequate edge protection, the following will be adhered to:
A Kelly block will be located near the unloading area. An alsipercha Fall Arrest systems will be fixed to the Kelly block with a 6m inertia reel attached to the anchor point. This system will be used to protect against falls from height when unloading delivery vehicles (if required).
For delivery lorries with loads that are not pre- slung or no handrails in place, the CPCS trained slinger/ signaller will wear a full body harness with 300mm lanyard. The operator’s full body harness is attached to the retractable element via a harness extender before he/she access the vehicle.
He/she will use access steps to access the back of delivery lorry. He/she will be secured via the Alsipercha fall arrest system, whilst on the delivery lorry, at all times.
The slinger/ signaller will attach the lifting accessories to the load.
Loads which are not pre-slung, will be double wrapped before being lifted unless they have designated lifting points. Stand clear of the load when lifting.
At no point will the slinger/ signaller remove the fall protection while on the back of the delivery lorry.
The S/S will unclip the fall protection once he has climbed down from the back of the lorry The project vehicular gate will be managed by St George’s Traffic Marshals and GCL will take possession of the vehicle once it has entered the site.
Delivery vehicles will have handrails and access steps in place
![Page 11: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/11.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 11 of 45
St George Ltd, Grand Union, Phase 2 00
PERMIT TO ENTER/ WORK/ DIG MEASURES FOR AVOIDING UNDER GROUND SERVICES
A relevant permit will be required by GCL before undertaking any work on site. GCL are to provide a signed permit indicating that all cables, pipes etc. have been removed or are clearly marked and that the area of works is safe for site operations. A NO PERMIT, NO WORK system shall be adopted. Where services have been identified or assumed to be present, safe digging practices will be adopted. GCL are to hand dig and expose all services using a shovel. Services will be marked using spray until a UXO survey is complete.
Obtain a copy the service drawing showing the location of the services on site. Trained operative to carry out a scan of the area using a cable avoidance tools
If services are shown or detected in the vicinity. Hold Point – GCL Manager to determine the location.
YES
Trial hole will be carried out to expose each service using hand tools (Refer to section 17.1 of this document for safe digging practices around services). Once the services are exposed they will be offered for inspection to GCL Site Management.
Once all the services are exposed as per service drawing and a scan of the area indicates no additional services present.
YES
NO
GCL Site Manager will issue a permit to dig. All ground penetrations will be carried out in accordance with the permit. No mechanical digging within 500mm of a known or detected
service
NO
If the location of the services is not proven by the trail holes suspend work and inform the GCL Site Management.
The excavator operator, banksman and the person who carries out the scan of the area will sign the permit.
Ground penetration can now commence using mechanical digging. No mechanical digging within 500mm either side of a known or detected service
![Page 12: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/12.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 12 of 45
St George Ltd, Grand Union, Phase 2 00
Safe Digging Practices Around Live Services
No ground penetration will take place until a permit to dig has been issued by St George
Service drawing needs to be attached to the permit.
Once a locating device has been used to determine cable positions and routes, mark the location of the route of the detected service using spray-line paint.
Works Supervisor must brief the operatives involved in the works and ensure all operatives sign the permit to dig.
A copy of the permit to dig must be kept with the Works Supervisor throughout the duration of works.
Excavation may take place, with trial holes dug using suitable insulated tools.
Excavate alongside the service rather than directly above it.
Final exposure of the service by horizontal digging is recommended as the force applied to hand tools can be controlled more effectively.
HSG 47 to be adhered to as a minimum.
Works to be Done covered by these RAMS:
Site survey/set up
Enabling Works
Reduced dig
Piling mat installation
5.0 Methodology
5.1 Site Survey
A site surveys will be carried out using an electronic distant measurement instrument (EDM) by the GCL engineer.
The EDM will be fully calibrated before delivering to site; calibration certs will be issued with the instrument.
A competent engineer will set up and use the instrument. It will be positioned on a tripod and legs adjusted to suit the user.
St George will issue coordinates and a system of grid lines for GCL engineers to work from.
Once received a local coordinate system will be set up on site using retro targets to allow the engineers find their location.
Once established and all necessary checks are completed, the EDM is ready to use and the site survey can commence.
They will be cross referenced against the drawings issued by St George
Discrepancies between GCL findings and information issued by St George will be highlighted to the GCL and St George Project Managers and the appropriate action taken.
.
![Page 13: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/13.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 13 of 45
St George Ltd, Grand Union, Phase 2 00
5.2 Site Set up
Access to phase 2 from the site welfare will be via a designated route, with access/ egress controlled by turnstiles. Other trades are not permitted into GCL work areas. A physical barrier (half height heras fencing) will be set up with signage displayed. The site is also protected with a 2.4m hoarding, by St George.
If GCL need to work on the existing access routes which are being used by other trades on previous phases, the sequence of works will be discussed with St George and route altered to suit where possible.
Pedestrian barriers will be installed to create pedestrian routes to all work areas. Pedestrian routes must have a level and compacted surface under foot and black mats must be used in external areas. Red hoop gated crossing points will be installed where pedestrian footpaths cross vehicle routes. All gates will open internally to ensure operatives have to stop before they pass through the hoop, on to the vehicle route.
Permit/ hazard board signage etc. will also be set up in locations agreed between GCL and St George.
The first task will be to secure GCL’s work area. This will be done with 1m high heras fencing (installed as per the manufactures instructions) with warning signs displayed. Fencing will be dropped off by the Hiab as to reduce manual handling, feet will be manually placed, fencing erected braced and clipped/ tied together as required by two operatives. A Temporary Works design will be required to check the wind loading upon the fencing and the foundations required. The area will need to be large enough to store, storage containers, materials and plant, as well as allow for adequate working space.
St George will first confirm to GCL that the works area has been made safe for works to proceed.
Containers for GCL storage of materials, tools, equipment and hazardous substances in an enclosed compartment will be delivered.
An office container plus office furniture and equipment will be delivered and set up in the agree location.
Bunded, lockable fuel storage containers capable of containing 110%, set up on a hardstanding surface.
Skips for general waste, timber and steel will be delivered to site and segregated, see below image.
![Page 14: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/14.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 14 of 45
St George Ltd, Grand Union, Phase 2 00
A TW design check will be completed by the GCL temporary works department before a Hiab commences rigging on an intended area.
Concrete will be installed to the main walkways, long term storage areas & to office foundations as designed by GCL TW Department.
Footpaths and storage/ laydown areas will be marked out and created using half height heras fencing/ mesh panels or tube and fitting.
Reduced Dig:
GCL Site Management will first confirm that the works area has been made safe for works to proceed including that all services have been disconnected.
A service drawing will be obtained from St George to determine the extent of the known existing services.
The GCL site supervisor will inspect the site to ensure that this has taken place prior to works commencing. A full visual survey will first be conducted and the sequence of works will be discussed before any works commence.
All plant and equipment will be off-loaded onto site via the Road adjacent to Aerodrome Road site entrance only.
The entire works area will be scanned for underground services with the use of a CAT scanner and generator. The process will commence from the perimeter inwards in a zig-zag fashion
Particular reference will be made to any existing services drawings. Locations of any services will be marked using spray paint and hand excavations will be carried out to prove services.
Care will be taken not to disturb these services.
The locations of these services will also be recorded on a site general arrangement drawing and be used for future reference/as-built purposes.
Before the reduced dig can commence, the existing stockpile of material will be mucked away from site.
All spoil will be loaded directly onto haulage wagons or will be taken via the dumpers to areas designated by GCL for stockpiling.
Stockpiles will not be sited near open excavations or embankments to prevent ground collapse.
The appropriate excavator will load the spoil into 8-wheel tipper Lorries that will then transfer the material off site to a certified spoil site.
On the stockpile the excavator will work from a platform on the heap, it will be compacted down with the back of the bucket to make a stable platform. The platform will be a maximum of 2meters high and extend the length of the spoil heap.
The excavator will always remain a minimum of 1 meter from the stockpile edge.
There will be a bucket changing area set up to store and change the buckets of the machines.
Loading will be restricted to an area with no pedestrians allowed into this area.
While the excavators are moving, the buckets will be positioned so the driver has a clear view of his route. Under no circumstances will the excavator move until the buckets have been checked to ensure they are securely in place.
Once the stockpile has been removed, the extent of the reduced dig will then be set out.
Permit to dig will be issued by St George before any ground penetrations take place.
![Page 15: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/15.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 15 of 45
St George Ltd, Grand Union, Phase 2 00
Existing concrete slab will be broken out using the hydraulic breaker attached to the 20t excavator. Area will be cordoned off with barriers and signage to prevent unauthorised access. This area will be a mandatory hearing protection zone and adequate signage will be displayed highlighting this to operatives.
Topsoil/ hard standing strip will then be undertaken, followed by the bulk dig and removal of surplus soil.
GCL will issue a dig sequence before the bulk dig commences, and this will be briefed to the Groundworks Foreman.
Edge protection will be required once the excavation has commenced.
Handrails will consist of tube and fitting with the top rail 950mm high with no greater gap between rails of 470mm, and this will either be driven into the ground or built into A frame scaffolds.
There will be a segregated pedestrian walkway for operative access, with bulk timbers in place either side of vehicle routes.
The material is to be reduced incrementally over the excavated areas to prevent any localised dangerous High/ Low spots being formed.
After completion of a sizeable area, an appropriate compaction roller will be used to compact the area.
All soft spots are to be excavated, filled and levelled off with compacted the site-crushed concrete or as otherwise specified. This area will then be inspected by GCL Site Management.
Once the reduced dig has been completed, and inspected by GCL’s Engineer, the piling mat can be constructed.
Piling Mat Construction
Piling mat is to be installed as per St George’s specification for piling safely & GCL’s Temporary Works Design check.
Before the Piling Mat is constructed, the Project Manager will ensure an unexploded ordnance survey has taken place, and all necessary procedures have taken place as a result of this survey.
The GCL engineer, using the main control stations, will set out lines & levels of the pile mat layers.
Once this is complete, the site will be probed for obstructions in required areas. The piling probe connects to the machine via the quick hitch and the machine pushes into the ground about 2m. A permit system as above must be in place when using the pile probe as it can damage services.
If any obstructions are encountered with the probe the area will be excavated locally, and the obstruction removed.
The piling mat will be constructed as per temporary works design and will be inspected and signed off by the Temporary Works supervisor and a permit to load issued for the areas.
After completion of a sizeable area, an appropriate compaction roller will be used to consolidate the area.
Only qualified and competent operatives are to drive the compaction roller. Rollers shall only be used perpendicular to the edge of the pile mat.
All soft spots are to be excavated, filled and levelled off and compacted with the site-crushed concrete or as otherwise specified. This area will then be inspected by GCL Site Management and thereafter a layer of Terram -1000 (or similar) will be placed.
The piling mat will then be constructed in prescribed layers, using the above onsite material and maximum increments of 225mm are to be placed at a time, on top of the piling mat with a layer of Geo-Grid between layers if required
The piling mat will be checked daily and the inspection will be recorded on site and inspection records filed in the project office.
An additional 150mm sacrificial layer of crush will be laid on top of the piling mat as well as another layer of Geo grid. This will act as a “tell-tale” indicator that the mat has been reduced too low below its’ design depth and therefore needs to be topped up.
During this operation, all plant movements are to be controlled by competent banksman who will also control any interface with site traffic, site operatives and the other trades on nearby phases of the development.
The material is to be spread evenly throughout and all levels will be achieved with the use of a laser level.
The Site Engineer must ensure that the mat is installed in the correct layers and the compaction of these layers is as per specification.
The mat will be consolidated using an appropriate compaction roller with the prescribed number of passes after which the area will then be inspected by GCL Site Manager and then fenced off until piling commences.
The piling mat then be handed over to St George once installed as per design.
![Page 16: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/16.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 16 of 45
St George Ltd, Grand Union, Phase 2 00
Excavation Support
Excavations will be battered/ stepped in accordance with the relevant and approved Temporary Works design.
This design will take into account the existing ground condition, SI report and loadings in the nearby area.
Exclusion zones will be enforced around the top of all excavations, and these will be defined by physical barriers and signage.
Site logistics will be planned and coordinated with St George, and this will be briefed to other contractors.
Sheet piles, ground anchors, trench boxes or precast L shaped walls can be used where required and specified in the appropriate TW design.
It is envisaged that temporary support will be required in the 2no corners of the pile mat across the site. See below extract of these locations.
The above detail will be required to protect the existing canal wall by limiting the surcharge load imposed on the wall by the existing water beyond. This detail will be required at the southwest corner of both the E1 & E2 pile mat area and the F1 & F2 pile mat area.
Where any of these methods are required, the method of installation and design will be covered by a separate approved Method Statement and TW design.
Excavations will be inspected at the start of every shift or after inclement weather which may affect the stability of the excavation. All open excavations, the inspection will be recorded in the excavation register.
It is the responsibility of the Construction Manager to ensure that these excavation inspections are completed and recorded by the TW Supervisor prior to any operative entering the excavation.
The proprietary access, whether that be excavation steps or Layher staircase, will also be inspected by a qualified and competent scaffolder and the tags must be kept up to date.
Where a scaffold access staircase is required, this must be erected by a qualified scaffolder and then inspected as mentioned above.
All access staircase inspections must be recorded and filed in the project office.
![Page 17: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/17.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 17 of 45
St George Ltd, Grand Union, Phase 2 00
6.0 Programme As per agreed programme 7.0 Quality
See approved Quality Plan for more detail. Inspection of the areas by GCL & St George.
8.0 Safety 8.1 Personal Protective Equipment (Standard PPE)
All site personnel at all times on site
Hard Hat
High Visibility Vests
Safety Footwear
Gloves
FFP3 Dust masks/ Force 8 half mask respirators (when cutting/ drilling concrete based products)
Face Coverings where required by task specific risk assessments
Site personnel involved in using angle grinder & stihl saws
Hard Hat (EN 397)
High Visual Vest/ Coat (EN 471)
Safety Footwear (with midsole protection), (EN 345)
Gloves (EN 420)
Goggles (to BS EN166 – B-rated)
Suitable hearing protection (EN 352)
8.2.1 Risk Assessments (See Appendix A)
8.3 COSHH Assessments (See Appendix B)
8.4 Fire
A trained fire marshal will be on site at all times.
Fire points will be installed throughout the site, extinguishers to hand at point of hot works.
Operatives will be briefed on the Fire Plan at the time of induction.
All operatives will receive a toolbox talk if there has been a change to the Fire Plan.
An integrated firm alarm system will be on site and tested weekly by the PC. (GCL)
The fire plans will be displayed at all fire points & maintained by the PC. (GCL)
Daily permits to work will be issued GCL for all hot works.
8.5 Documentation
All plant and equipment will be inspected before use, inspections will be recorded on the relevant inspection register.
All lifting accessories will have a thorough examination every six months with a certificate produced. Lifting equipment will be inspected before each use and recorded on the weekly inspection register.
Relevant permits will be issued before work commences. 9.1 Temporary Works
The Temporary Works File will contain an up to date TW Register, signed off EDB’s (Engineering Design Brief) for all temporary works on site and the latest revision of the TW drawings/ calculations.
The TW Co-ordinator & TW Supervisor will ensure the file is up to date and works on site is constructed as per design approved. They will also ensure all permits and inspections are carried out as required.
Please refer to GCL’s Temporary Works Procedures for more detail
![Page 18: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/18.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 18 of 45
St George Ltd, Grand Union, Phase 2 00
10.0 Environment
Nuisance: Noise – Works are to be carried out within agreed working hours for the main site, these will be planned with St George where required exclusion zones with barriers and signage will be set up, GCL is aware of the nearby residential properties and will not start works before 08:00 and finish by 18:00, any other times or days will be agreed with St George in advance. Vibration: - Operatives using the grinder will be exposed to vibration emitted from the tool. To reduce the risk of Hand Arm Vibration syndrome a HAVS assessment was carried out on the grinder. Operatives will be briefed on this trigger times. Operating times will be recorded to ensure the operatives do not exceed the allowable trigger times. Dust: - Water will be used to supress any dust that may arise. water attachment on the petrol saws, wet vac to be used to clear slurry from the saw process, FFP3 mask to be worn when cutting concrete or silica-based products, all will be faced fitted and clean shaven when using press to Check masks
Prevention of water pollution: - Nearby drains to be protected from slurry produced from slurry, spill kits to be on site, double bunded fuel bowsers, nappies to static plant / generators, funnels to be used when re-fuelling. Fuel – If is to be kept to a minimum, petrol in 5l plastic containers with screw cap kept in a locked flam-box/ COSHH store when not required. Diesel will be stored in 2000l bunded lockable containers (minimum 110% bunded). Fire extinguisher to hand at storage area.
11.0 Traffic Management
Access on to site is via the Main Gate located on Wycombe Road, off Beresford Avenue. St George will have a full-time gate team in place to accept deliveries and collections to/ from site. Deliveries will be booked in in advance with St George. All delivery drivers will have the Logistics Manager’s contact number; they will call him/ her before coming to site to ensure their slot is available. A small number of vehicles will be allowed to park in a holding area prior to being able to enter the project, and this holding area will be controlled by the Traffic Marshalls for St George. A site speed limit of 5mph must be obeyed when on site and vehicles will be banked along the site haul road by GCL’s traffic marshals to the point of unloading. All vehicle routes will be highlighted on the project logistics plan, and this will be communicated in the induction and reviewed daily within the daily activity briefing.
![Page 19: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/19.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 19 of 45
St George Ltd, Grand Union, Phase 2 00
RISK ASSESSMENTS
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Ground Workers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
1
2.
Excavations
Cutting
steel/rebar/scaf
fold tubes
Collapse of
excavation/Fall from
Height
Fire
4
4
5
5
20
20
Where possible access into the excavation will be via a
tammet steps or stepped walkways with handrails.
All access routes will be kept clear of materials and tools
to ensure access and egress is not impeded.
The excavation will be inspected by the GCL Site
Manager at the start of each shift or after inclement
weather. Inspection will be recorded in the excavation register.
Open excavations will be fenced of and signage will be
displayed.
No spoil will be stored at the edge of open excavations.
The basement and pile cap excavations will be battered
To a safe angle of repose as per TW design.
No cutting of steel unless there is a daily hot works
permit in place for that particular task
Suitable fire extinguishers are in the immediate vicinity
of the works
Rebar only to be cut in a designated area.
Petrol is stored away from works area.
All cutting to cease one hour before work finishes, to
ensure all hot surfaces have cooled sufficiently before the
site is closed.
4
4
2
2
8
8
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
Site Manager
Site Foremen.
![Page 20: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/20.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 20 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating: Review 3mts
Occupations involved in Activity (Specify): General & Plant Operatives
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
3 4
Moving plant. Unloading Lorries
Struck by moving plant. Falls from height
4
5
20
All mobile plant will have visual and or audible warning devices. A competent attendant will direct all plant movements. Mirrors and or CCTV will be fitted,
Segregated walkways to be in place marked & well maintained. Crossing points are to be identified using red hoop gates.
Keys to be removed from plant when not in use key fobs to be worn
If working/moving outside the site boundary plant will be controlled by a banksman at all times.
All reversing of vehicles will be carried out under the control of banksman.
At the site access gate cones will be set up along the slip road leading to the site entrance, concertina barriers will be used to prevent pedestrians crossing when vehicles enter/leave the site.
Spoil and debris will be stockpiled inside the site hoarding. Only at agreed locations.
Vehicles to remain on designated vehicle routes
Pedestrians to use walkways, do not walk on vehicle routes
Vehicle access gate will be under the control of BH gate men
Gate and public roads to be managed by berkeley Homes logistic team
Delivery lorries also to be self- off load (Hiab) where possible.
No access to the rear of a trailer without edge protection in place and trailer access platform positioned to the rear of the trailer.
Banksman to be in place, unload in a safe area away from others.
Fall protection system to be worn to protect against falls from height if handrails cannot be installed
Trailers to be loaded correctly, do not over load trailer
Pre-slung loads where possible
4 4
2 2
8 8
Site Manager / Site Forman / Operatives Site Manager / Site Forman / Operatives
Site Manager Site Foremen. Site Manager/ Site Foremen.
![Page 21: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/21.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 21 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Ground Workers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
5
6.
Collision of
operatives/
public with
moving plant.
Plant
movement
Struck by moving plant.
Interface with the public/
dust/noise
4
4
5
4
20
16
All mobile plant will have visual and or audible
warning devices. A competent Banksman will direct
all large plant movements.
Banksman will be in view of the drivers at all times
When working outside the site boundary plant will be
controlled by a banksman at all times.
All reversing of vehicles will be carried out under the
control of banksman.
Vehicles and pedestrians will be segregated.
Where pedestrians must cross a vehicular route a cross
over point will be in place
Banksmen will be in attendance & in view of the
drivers at all times to ensure the interface with the public is controlled.
Spoil and debris will be stockpiled in a segregated area
inside the site hoarding.
Water will be used to suppress any dust that may arise
during the use of breakers. Additional PPE will be
worn b-rated goggles, RPE (FFP3 FILTERS, HEAR
DEFENDERS 30SNR)
Operatives required to wear dust masks will be face fit
tested and clean shaven.
Jet wash will be used to clean the vehicles before they
leave the site.
4
4
2
2
8
8
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
Site Manager
Site Foremen.
![Page 22: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/22.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 22 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Ground workers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Harrow Rd 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
7.
8
Piling Mat
construction/R
eduction
reduce dig
Loading
lorries/
dumpers from
stockpile
Slip, trips and fall
Overturned excavator
4
4
5
5
20
20
Work area to be checked and cleared of any hazards
prior to commencement of work
Housekeeping breaks will be carried out during the
course of each shift.
A single excavator will be used for the spoil heap
removal.
The excavator will work from a platform cut into the
spoil heap; it will be compacted down with the back of
the bucket to form a secure and stable working area.
Platform will be a maximum of 2m high.
The working platform must extend the length of the
spoil heap
When tracking the excavator the operator will always
face the direction of travel.
Loading area will be restricted area with no pedestrians
allowed into this area. Excavator min of 1m from the
stockpile edges at all times
4
4
2
2
8
8
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
Site Manager
Site Foremen.
![Page 23: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/23.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 23 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Ground Worker, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
9.
13.
Excavations
Enabling
works/piling
mat
construction
Striking of live services
Manual Handling
4
3
5
4
20
12
Copy of a permit to dig and reference will be made to
the latest service drawing (issued by St George) will
be in place before any ground penetrations take place.
The area will be scanned throughout the dig.
The route and location of the detected services will be
physically marked on the ground using spray-line
paint.
No mechanical digging or power tools will be used
within 500mm of a known or detected service.
Tools used for hand-digging will be insulated.
Operatives will dig to the side of the cable not directly
above it. Final exposure of the service by horizontal
digging
.
Mechanical means will be used where possible to
reduce manual handling where possible.
Rebar will be lifted individually and will be a two man
lift
4
3
2
1
8
3
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
Site Manager
Site Foremen
![Page 24: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/24.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 24 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Ground woker, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
14.
15.
Enabling
works/piling
mat
construction
Enabling
works/piling
mat
construction
Weils Disease
Use of 110v power
tools/saws
4
4
4
5
16
20
Cover all cuts and abrasions with waterproof plasters
Always wear gloves to avoid cuts to your hands – cut
5.
Operatives to receive a toolbox talk regularly
Correct use of PPE provided
Wash hands prior to eating and drinking.
Ensure that cuts are cleaned and covered
Inform medical staff that you may have been in contact
with polluted water if you are suffering an unexplained
illness
All 110v tools will be portable appliance tested and have
pat testing labels displayed.
All electrical equipment will be PAT tested every 3
months.
All saws will be inspected before first use; the inspection
will be recorded weekly in the plant register.
Operatives changing the blades on the circular saws
will be trained in abrasive wheels.
4
4
2
2
8
8
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
Site Manager
Site Foremen
![Page 25: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/25.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 25 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Ground workers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
16
17
Concrete works
Cutting
plywood/timber
Pouring concrete
Exposure to wood dust
that may cause lung
cancers
4
5 20
All operatives will be wearing correct. Overalls,
waterproof gloves & wellingtons as well as standard
PPE.
Any concrete will be poured using the bucket on the
excavator/column skip
Banksman will be in attendance
Any formwork will be signed off prior to concrete
being poured
GCL have carried out personal dust monitoring with
operatives cutting plywood/ timber on a typical GCL site.
Results show operatives exposure to wood dust is well
below the daily exposure limit.
Hoovers are fitted to all saws cutting timber/ plywood.
Regular housekeeping breaks are mandatory.
4
2
8
Site Manager /
Site Foreman/
Operatives
Site Manager
Site Foremen.
.
![Page 26: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/26.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 26 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Groundworkers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
18
19
Cutting Plywood
Erecting
Handrails
Splinter formation
Bucket striking operative
3
4
4
5
12
20
Ensure the sheet of ply is secured to the bench before
cutting begins (using nails, G clamps etc.)
Ensure the blade is sharp and the saw is running at full
speed before commencing the cut.
Feed the saw at a slow and steady pace.
Select a blade with a high number of teeth.
Adjust the depth of the blade; have no more than half
the teeth falling below the bottom of the plywood.
When cutting against the grain place a strip of masking
tape over the cutting line.
The operator will shake and rattle the bucket as a safety
check to ensure the bucket is attached correctly to the
hitch.
When standing the post the operative will stand to one
side of the upright post.
The CPCS trained excavator driver will apply minimal
pressure to the post.
Before the post is pushed into the ground all operatives
will stand clear of the operation.
3
4
1
2
3
8
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
.
Site Manager
Site Foremen.
![Page 27: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/27.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 27 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Groundworkers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
20
Enabling works
(Piling mat
installation/sheet
piles/trench
boxes)
Failure of TW 3
4
12
All Temporary works to be installed as per approved
designs & recorded on the TW register
Excavations as per TW design & inspections carried
out by TWS
GCL TWC/TWS on site
Applicable permits in place & signed off by TWC &
TWS where required
3
4
1
2
3
8
Site Manager /
Site Forman/
Operatives
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
.
Site Manager
Site Foremen.
![Page 28: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/28.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 28 of 45
St George Ltd, Grand Union, Phase 2 00
Category Of Persons At Risk And Means Of Briefing RA SCS Other
S = Severity Rating
L = Likelihood of Occurrence
RR = Risk Rating
Occupations involved in Activity (Specify): Plant operator, Slinger signaler, Groundworkers, Labourer
Y 1. Negligible 1. Improbable
Severi
ty
5 5 10 15 20 25 R Unacceptable risk, plan out or add further controls
Others Persons at Work (Specify): Foreman, Y 2. Minor Injury 2. Remote 1 – 10%
4 4 8 12 16 20 O Acceptable only if no other method
viable and with high level controls in place
Public or Other Parties (Specify): n/a Y 3 .Major Injury (RIDDOR)
3. Possible 10 – 50%
3 3 6 9 12 15 Y Acceptable with suitable controls
Site: Beaufort Park MS-01 4. Fatality 4. Probable 50 – 90%
2 2 4 6 8 10 G Acceptable, no further action required
5. Multiple Fatality
5. Almost certain 90%+
1 1 2 3 4 5
1 2 3 4 5
Item Activity Hazards/Risks Identified Risk Rating Control Measures Residual Risk Responsibility Monitoring Responsibility S L RR S L RR
21
Pressure Washer
works
Direct water jet injuries/
Electric shock from using
damaged equipment or
spraying water onto live
electrics
Risk of being hit by
ejected material
General health
considerations
Slips & trips from wet
surfaces
Risk of injury from
kickback during startup
Noise risks
3
4
12
Complete regular checks for signs of damage before use. do
not use faulty pressure washers. report any faults to site
manager
If the engine does not start after two pulls, squeeze trigger of
gun to relieve pump pressure. Pull starter cord slowly until
resistance is felt. Then pull cord rapidly to avoid kickback
and prevent hand arm injury
Use of PPE – goggles, gloves & clothing, safety
wellington/boots, and ear defenders when necessary i.e. noise
levels 85db and above.
Do not use the following substances in the cleaner - acids,
petrol, diesel or any other flammable materials, chlorine,
bleach or any other corrosive compound
Do not stand in front of the cleaning jet. Hands must not be
placed directly in front of the nozzle. Spray will be always
directed from self and others. Consider neighbouring
properties and windblown spray
During Operation, only touch the control surfaces e.g.
Trigger & insulated areas provided on the Lance. Grip
gun/wand firmly with both hands. The operator must not hold
onto the hose or fittings.
When not in use, relieve the system pressure by shutting off
the engine or electricity supply; turning off water supply, and
pulling the trigger until the water stops flowing.
Unplug the pressure washer before attempting to clean it.
Wand/Lance or hose fittings will not be attached or removed
while the system is pressurised. Never leave a pressurised
unit unattended
Good housekeeping is required at all times. Keep hoses tidy
& away from walkways.
3
1
3
Site Manager /
Site Forman/
Operatives
Site Manager
Site Foremen.
.
![Page 29: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/29.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 29 of 45
St George Ltd, Grand Union, Phase 2 00
36. COSHH ASSESSMENTS
Product Name (s): Ready Mixed Concrete (RMC).
Site All GCL Sites
Description of substance & quantity :
A combination of a course aggregate sand, cement,
admixtures mixed together at the batching plant
which is usually a greyish colour and primarily
used for casting into shape prior to hardening e.g.
wall/floor columns, floor slab construction.
Assessed by:
Tara Quinn
Workplace
Exposure Limits: N/A.
Date: 04.10.21
Task/Activity: How applied
Various methods of application.
Risk Phrase
Contact with wet cement,
mortar or screed may
cause irritation,
dermatitis or burns
Suppliers Name & Address:
Various.
Safety Phrase
Avoid eye and skin
contact by wearing
suitable eye protection,
clothing and gloves
Suppliers Telephone / e-mail
Various. MSDS Attached
Yes No
Substance Properties –
Acute Toxicity Corrosive Flammable Explosive Compressed Health Aquatic Oxidising Respiratory Gas Hazard Hazard Hazard
Form: Tick all applicable
Dust Silica Dust Fume Smoke Mist Gases Vapour Liquid Biological i.e. pigeon droppings etc State :
Health Surveillance Required : YES NO If YES attach details of what / how / who / frequency etc
Route of Exposure: Tick all applicable
Skin Ingestion Eyes Inhalation Cuts/Abrasions Inhalation Injection
Persons at Risk: Users of Products Other workers Visitors Members of the Public
PPE Requirements: Insert BS / EN Grade in Type
Gloves Dust mask Overalls Eye Protection Face Shield Respirator
Type: Type: Type: Type: Type: Type: BS EN374 BS EN166
![Page 30: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/30.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 30 of 45
St George Ltd, Grand Union, Phase 2 00
Environmental Risks i.e. is this material harmful to the environment and / or eco-toxic: Harmful to water (surface / ground) Harmful to air Harmful to land
General Precautions:
Ensure that the above specific PPE is worn and that all staff are informed of the risks, control measures and precautions required when working with the substance. Where RPE stipulated ensure evidence of face fit testing as appropriate. Ensure all users’ sign off this risk assessment to confirm they have received information and understand the controls applicable to works involving this substance / carrying out this task. Ensure that adequate supervision is provided at all times. If health surveillance required appoint a person to monitor the surveillance process.
First Aid / Hygiene Arrangements – insert specific to this site & susbtance not general requirements: Eye Contact: wash with clean, fresh running water for 15 minutes and seek medical attention Ingestion: If RMC enters the mouth, avoid swallowing, immediately rinse with clean fresh water and seek medical advice. Skin Contact: wash the affected with soap and clean water. If clothes become contaminated by concrete, they must be changed and washed prior to using again. If irritation persists, seek medical advice.
Fire Precautions - insert specific to this site & susbtance not general requirements This presents no fire risk.
LEV / Ventilation Requirements – in many cases working outside will suffice consideration required for working
indoors / covered areas and confined spaces.
N/A.
Storage Requirements insert specific to this site & susbtance not general requirements N/A
Transport Arrangements If hazardous materials to be carried in vehicles additional regulations apply contact HS&E.
Mixed at batching plant and delivered by vehicle to site.
Monitoring Regime Supervision required, background or personnel air monitoring etc
N/A.
Spillage Procedures: insert specific to this site & susbtance not general requirements Contain into a designated area. Allow harden and dispose as general builders waste. Concrete must not be allowed to enter water courses/drains etc.
Disposal Requirements for substances and contaminated containers insert specific to this site &
susbtance not general requirements
Hazardous Waste Return to Depot Return to Supplier Other If other please state:
Allow harden and dispose as general builders waste.
![Page 31: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/31.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 31 of 45
St George Ltd, Grand Union, Phase 2 00
Product Name (s): Febstrike (Mould Oil, concrete release agent). Part No:
F450535 Site All GCL Sites
Description of
substance & quantity :
An amber/brown coloured substance which acts as a
chemical release agent suitable for mould and shutter
faces (timber, steel, plastic) prior to casting concrete to
achieve a clean release after the removal of the
formwork.
Assessed by:
Tara Quinn
Workplace Exposure
Limits:
Exposure of this oil may induce dermatitis, drowsiness,
nausea and ultimately unconsciousness. Date: 04.01.18
Task/Activity:
How applied
It can be applied by spraying, brush or roller.
Risk Phrase
R51/53: Toxic to aquatic
organisms, may cause
long term adverse effects
in the aquatic
environment.
Suppliers Name &
Address:
BASF Construction Chemicals, Albany House, Swinton
Hall Road, Swinton, Manchester, M27 4DT Safety
Phrase
S-36/37: Wear suitable
protective clothing and
gloves.
Suppliers Telephone /
Tel: +44(0) 161 485 6222 MSDS
Attached
Yes No
Substance Properties –
Acute Toxicity Corrosive Flammable Explosive Compressed Health Aquatic Oxidising Respiratory Gas Hazard Hazard Hazard
x x x
Form: Tick all applicable
Dust Silica Dust Fume Smoke Mist Gases Vapour Liquid Biological i.e. pigeon droppings etc State : Health Surveillance Required : YES NO If YES attach details of what / how / who / frequency etc
Route of Exposure: Tick all applicable
Skin Ingestion Eyes Inhalation Cuts/Abrasions Inhalation Injection
X x x x Persons at Risk: Users of Products Other workers Visitors Members of the Public
PPE Requirements: Insert BS / EN Grade in Type
Gloves Dust Overalls Eye Protection Face Shield Respirator
Mask Type: Type: Type: Type: Type: Type: BS EN374 Type 5 disposable overalls BS EN166
![Page 32: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/32.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 32 of 45
St George Ltd, Grand Union, Phase 2 00
Environmental Risks i.e. is this material harmful to the environment and / or eco-toxic: Harmful to water (surface / ground) Harmful to air Harmful to land
X
General Precautions:
Ensure that the above specific PPE is worn and that all staff are informed of the risks, control measures and precautions required when working with the substance. Where RPE stipulated ensure evidence of face fit testing as appropriate. Ensure all users’ sign off this risk assessment to confirm they have received information and understand the controls applicable to works involving this substance / carrying out this task. Ensure that adequate supervision is provided at all times. If health surveillance required appoint a person to monitor the surveillance process.
First Aid / Hygiene Arrangements – insert specific to this site & susbtance not general requirements: Eye Contact: Wash eye(s) thoroughly with copious amounts of clean fresh water for at least 15 minutes Seek medical advice if any pain or redness develops or persists Ingestion: Wash thoroughly with fresh water and seek medical advice Inhalation: In case of breathing difficulties, remove to fresh air and seek medical attention Skin Contact: Wash skin thoroughly with soap and water. Remove contaminated clothing and wash underlying skin Wash clothing prior to wearing again. If irritation/redness occurs, seek medical advice
Fire Precautions - insert specific to this site & susbtance not general requirements In case of a fire only use Foam, Dry Powder, CO2 extinguishers and sand. Cool containers exposed to flames with water until extinguished
LEV / Ventilation Requirements – in many cases working outside will suffice consideration required for working
indoors / covered areas and confined spaces.
Store in well-ventilated areas. Apply to surface in well-ventilated areas.
Storage Requirements insert specific to this site & susbtance not general requirements Store in well-ventilated areas and away from heat sources of ignition and not in direct sunlight. Avoid skin and eye contact.
Transport Arrangements If hazardous materials to be carried in vehicles additional regulations apply contact HS&E.
Delivered to site in 45-gallon drums or in 5 litre containers.
Monitoring Regime Supervision required, background or personnel air monitoring etc
N/A
Spillage Procedures: insert specific to this site & susbtance not general requirements Contain and recover spilled material by using sand or other suitable inert absorbent material. Do not discharge substance into water courses, drains, sewers etc.
Disposal Requirements for substances and contaminated containers insert specific to this site &
susbtance not general requirements
Hazardous Waste x Return to Depot Return to Supplier Other If other please state:
![Page 33: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/33.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 33 of 45
St George Ltd, Grand Union, Phase 2 00
Product Name (s): Chemcure S
Site All GCL Sites
Description of substance & quantity :
An aqueous solution of metallic silicates which when applied to fresh concrete forms a micro crystalline seal in the pores, reducing the evaporation of moisture from the mix thus assisting in the efficient curing of the concrete.
Assessed by:
Tara Quinn
Workplace
Exposure Limits:
Not highlighted within material safety data sheet Date:
04.01.18
Task/Activity: How applied
Poured directly. Risk Phrase
R38: Irritating to skin.
Suppliers Name & Address:
Universal Sealants (UK) Limited, Kingston House, 3 Walton Road, Pattinson North, Washington, Tyne & Wear, NE38 8QA
Safety Phrase
S37/39: Wear suitable gloves and eye/face protection.
Suppliers Telephone / e-mail
[email protected], Tel: +44 (0) 191 416 1530 MSDS Attached
Yes No
Substance Properties –
Acute Toxicity Corrosive Flammable Explosive Compressed Health Aquatic Oxidising Respiratory Gas Hazard Hazard Hazard
x
Form: Tick all applicable
Dust Silica Dust Fume Smoke Mist Gases Vapour Liquid x Biological i.e. pigeon droppings etc State :
Health Surveillance Required : YES NO x If YES attach details of what / how / who / frequency etc
Route of Exposure: Tick all applicable
Skin Ingestion Eyes Inhalation Cuts/Abrasions Inhalation Injection
x x x x Persons at Risk: Users of Products Other workers Visitors Members of the Public X
PPE Requirements: Insert BS / EN Grade in Type
Gloves Dust Mask Overalls Eye Protection Face Shield Respirator
Type: Type: Type: Type: Type: Type:
BS EN374 BS EN166 BS EN149 FFP3 filters
![Page 34: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/34.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 34 of 45
St George Ltd, Grand Union, Phase 2 00
Environmental Risks i.e. is this material harmful to the environment and / or eco-toxic: Harmful to water (surface / ground) Harmful to air Harmful to land
General Precautions:
Ensure that the above specific PPE is worn and that all staff are informed of the risks, control measures and precautions required when working with the substance. Where RPE stipulated ensure evidence of face fit testing as appropriate. Ensure all users’ sign off this risk assessment to confirm they have received information and understand the controls applicable to works involving this substance / carrying out this task. Ensure that adequate supervision is provided at all times. If health surveillance required appoint a person to monitor the surveillance process.
First Aid / Hygiene Arrangements – insert specific to this site & susbtance not general requirements: Eye Contact: Flush with copious amounts of clean water for at least 20 minutes, with the eyelids held open. This prolonged irrigation is of extreme importance and must be done at once otherwise permanent damage will result. Continue irrigation until medical attention can be obtained. Seek medical advice if any pain or redness develops or persists Ingestion: Do not induce vomiting. Inhalation: In case of drowsiness or sickness remove to fresh air, keep patient warm and at rest. If unconscious, turn to the recovery position. Seek medical assistance. If any symptoms continue, seek medical advice Skin Contact: Promptly remove contaminated clothing and wash the affected area with plenty of soap and water to ensure all traces of product are removed, then rinse thoroughly. Any contaminated clothing must be thoroughly cleaned before re-using. Seek medical advice if irritation persists. Emergency CPPL: 01248 490855 Telephone numbers: GCL Safety Manager: 07903 576982
Fire Precautions - insert specific to this site & susbtance not general requirements The product is not combustible, however if it is involved in a fire, use water spray, foam, dry powder, carbon dioxide or sand. May give off toxic fumes if heated or involved in a fire.
LEV / Ventilation Requirements – in many cases working outside will suffice consideration required for working
indoors / covered areas and confined spaces.
Use adequate ventilation to keep concentrations of this product below occupational exposure limits particularly in confined spaces.
Storage Requirements insert specific to this site & susbtance not general requirements Store in an ambient and well-ventilated area, away from children and do not allow to freeze.
Transport Arrangements If hazardous materials to be carried in vehicles additional regulations apply contact HS&E.
Supplied in 20 and 210 liter containers.
Monitoring Regime Supervision required, background or personnel air monitoring etc
N/
Spillage Procedures: insert specific to this site & susbtance not general requirements Spillages to be cleaned up with an approved absorbent granule. Disposal of spilled material at an approved site. Disposal Requirements for substances and contaminated containers insert specific to this site &
susbtance not general requirements
Hazardous Waste Return to Depot x Return to Supplier Other If other please state:
![Page 35: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/35.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 35 of 45
St George Ltd, Grand Union, Phase 2 00
Product Name (s): CONCRETE SURFACE RETARDER.
Site All GCL Sites
Description of substance & quantity :
Top face retarder, water based retarder designed to expose aggregate on horizontal surfaces.
Assessed by:
Tara Quinn
Workplace
Exposure Limits:
Titanium Dioxide / Calcium Carbonate:8 Hour TWA 10mg/m3 (total inhalable), 4mg/m3 (respirable) OES .Ammonia: 8 Hour TWA 25ppm, 15 min STEL 35ppm OES.
Date:
04.01.18
Task/Activity: How applied
During decanting, use a hand pump or position drum on a flat surface with a tap connected. Use a funnel.
Risk Phrase
R10,R66
Suppliers Name & Address:
Various. Safety Phrase
Not shown in msds
Suppliers Telephone / e-mail
Various. MSDS Attached
Yes No
Substance Properties –
Acute Toxicity Corrosive Flammable Explosive Compressed Health Aquatic Oxidising Respiratory Gas Hazard Hazard Hazard
x x x
Form: Tick all applicable
Dust Silica Dust Fume Smoke Mist Gases Vapour Liquid x Biological i.e. pigeon droppings etc State :
Health Surveillance Required : YES NO x If YES attach details of what / how / who / frequency etc
Route of Exposure: Tick all applicable
Skin Ingestion Eyes Inhalation Cuts/Abrasions Inhalation Injection
X x x x Persons at Risk: Users of Products Other workers Visitors Members of the Public x
PPE Requirements: Insert BS / EN Grade in Type
Gloves Dust Overalls Eye Protection Face Shield Respirator
Mask
Type: BS EN374 Type: BS149 Type: Type: BS EN166 Type: Type: Environmental Risks i.e. is this material harmful to the environment and / or eco-toxic: Harmful to water (surface / ground) Harmful to air Harmful to land
X
![Page 36: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/36.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 36 of 45
St George Ltd, Grand Union, Phase 2 00
General Precautions:
Ensure that the above specific PPE is worn and that all staff are informed of the risks, control measures and precautions required when working with the substance. Where RPE stipulated ensure evidence of face fit testing as appropriate. Ensure all users’ sign off this risk assessment to confirm they have received information and understand the controls applicable to works involving this substance / carrying out this task. Ensure that adequate supervision is provided at all times. If health surveillance required appoint a person to monitor the surveillance process.
First Aid / Hygiene Arrangements – insert specific to this site & susbtance not general requirements: Inhalation: In case of drowsiness or sickness remove to fresh air, keep patient warm and at rest. If unconscious, turn to the recovery position. Seek medical assistance. Skin Contact: Promptly remove contaminated clothing and wash the affected area with plenty of soap and water to ensure all traces of product are removed, then rinse thoroughly. Any contaminated clothing must be thoroughly cleaned before re-using. Seek medical advice if irritation persists. Eye Contact: Flush with copious amounts of clean water for at least 15 minutes, with the eyelids held open. Seek medical attention. Ingestion: Wash out mouth with water. Keep patient at rest and obtain medical attention. DO NOT INDUCE VOMITING.
Fire Precautions - insert specific to this site & susbtance not general requirements The product is not combustible, however if it is involved in a fire, use water spray, foam, dry powder, carbon dioxide or sand.
LEV / Ventilation Requirements – in many cases working outside will suffice consideration required for working
indoors / covered areas and confined spaces.
Do not use in confined or poorly ventilated areas.
Storage Requirements insert specific to this site & susbtance not general requirements Store in an ambient and well-ventilated area.
Transport Arrangements If hazardous materials to be carried in vehicles additional regulations apply contact HS&E.
No special precautions are necessary. When handling unopened containers follow any relevant manual handling guidance.
Monitoring Regime Supervision required, background or personnel air monitoring etc
N/A
Spillage Procedures: insert specific to this site & susbtance not general requirements Contain and recover spilled material by using sand or other suitable inert absorbent material. Avoid substance entering water courses/drains etc.
Disposal Requirements for substances and contaminated containers insert specific to this site &
susbtance not general requirements
Hazardous Waste Return to Depot x Return to Supplier Other If other please state:
![Page 37: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/37.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 37 of 45
St George Ltd, Grand Union, Phase 2 00
Product Name (s): Petrol(gasoline) Site All sites
Description of substance & quantity :
A liquid fuel used for compression ignition for petrol engines.
Assessed by:
Tara Quinn
Workplace
Exposure Limits: 300ppm TWA
Date: 04/01/18
Task/Activity: How applied
used as a fuels source for the operation of machinery. Machines usually refuelled using various sized container.
Risk Phrase
R65 may cause lung damage if swallowed
Suppliers Name & Address:
Various Safety Phrase
S45 if you feel unwell seek medical advice
Suppliers Telephone / e-mail
www.bp.com MSDS Attached
Yes
Substance Properties –
Acute Toxicity Corrosive H Flammable Explosive Compressed Health Aquatic Oxidising Respiratory Gas Hazard Hazard Hazard
x x x
Form: Tick all applicable
Dust Silica Dust Fume Smoke Mist Gases Vapour Liquid X X Biological i.e. pigeon droppings etc State :
Health Surveillance Required : YES NO If YES attach details of what / how / who / frequency etc
Route of Exposure: Tick all applicable
Skin Ingestion Eyes Inhalation Cuts/Abrasions Injection
x x x X Persons at Risk: Users of Products Other workers Visitors Members of the Public X X
PPE Requirements: Insert BS / EN Grade in Type
Gloves Dust Overalls Eye Protection Face Shield Respirator
Mask
Type: Type: Type: Type: Type: Type: BS EN374 EN 166 Environmental Risks i.e. is this material harmful to the environment and / or eco-toxic: Harmful to water (surface / ground) Harmful to air Harmful to land
x
![Page 38: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/38.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 38 of 45
St George Ltd, Grand Union, Phase 2 00
General Precautions:
Ensure that the above specific PPE is worn and that all staff are informed of the risks, control measures and precautions required when working with the substance. Where RPE stipulated ensure evidence of face fit testing as appropriate. Ensure all users’ sign off this risk assessment to confirm they have received information and understand the controls applicable to works involving this substance / carrying out this task. Ensure that adequate supervision is provided at all times. If health surveillance required appoint a person to monitor the surveillance process.
First Aid / Hygiene Arrangements – insert specific to this site & susbtance not general requirements: Eye Contact: Wash eye(s) thoroughly with copious amounts of clean fresh water, keeping the eyelids open.
Seek medical advice if any pain or redness develops or persists.
Ingestion: Wash thoroughly with fresh water and seek medical advice.
Skin Contact: Wash skin thoroughly with soap and water. Remove contaminated clothing and wash underlying
skin. Wash clothing prior to wearing again. If irritation/redness occurs, seek medical advice.
Fire Precautions - insert specific to this site & susbtance not general requirements In case of a fire only use Foam, Dry Powder, CO2 extinguishers, Never Use Water
LEV / Ventilation Requirements – in many cases working outside will suffice consideration required for working
indoors / covered areas and confined spaces.
Use adequate ventilation to keep vapour concentrations of this product below occupational exposure and flammability limits, particularly in confined spaces.
Storage Requirements insert specific to this site & susbtance not general requirements Stored in 45 gallon storage tanks and large double bunded fuel tanks. Store in well-ventilated areas and away
from heat and sources of ignition.
Transport Arrangements If hazardous materials to be carried in vehicles additional regulations apply contact HS&E.
Delivered to site in various sizes cylinders Where possible use mechanical aids to move cylinders around.
Monitoring Regime Supervision required, background or personnel air monitoring etc
N/A.
Spillage Procedures: insert specific to this site & susbtance not general requirements Contain and recover spilled material by using sand or other suitable inert absorbent material. Avoid substance
entering water courses/drains etc.
Disposal Requirements for substances and contaminated containers insert specific to this site &
susbtance not general requirements
Hazardous Waste x Return to Depot Return to Supplier Other If other please state:
![Page 39: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/39.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 39 of 45
St George Ltd, Grand Union, Phase 2 00
Product Name (s): CRYSTALLINE SILICA DUST
Site All GCL Sites
Description of substance & quantity :
By-product from concrete cutting/ breaking operations
Assessed by:
Tara Quinn
Workplace
Exposure Limits: Long-term exposure level (8hrTWA): Respirable Crystaline Silica 0.1mg- m3
Date: 04.01.18
Task/Activity:
Cutting/ breaking concrete based products
Risk Phrase
R49 Do not breath dust. R23 toxic by inhalation
Suppliers Name & Address:
N/A – Substance is generated as a by-product of quarrying activities
Safety Phrase
S22 Do not breath dust
Suppliers Telephone / e-mail
MSDS Attached
Yes No
X
Substance Properties –
Acute Toxicity Corrosive Flammable Explosive Compressed Health Aquatic Oxidising Respiratory Gas Hazard Hazard Hazard
x x
Form: Tick all applicable
Dust Silica Dust Fume Smoke Mist Gases Vapour Liquid x x Biological i.e. pigeon droppings etc State :
Health Surveillance Required : YES X NO If YES attach details of what / how / who / frequency etc – daily supervisor to ensure operatives involved in the operation are wearing the correct PPE.
Route of Exposure: Tick all applicable
Skin Ingestion Eyes Inhalation Cuts/Abrasions Inhalation Injection
x Persons at Risk: Users of Products Other workers Visitors Members of the Public X X X X
PPE Requirements: Insert BS / EN Grade in Type
Gloves Dust Overalls Eye Protection Face Shield Respirator
Mask
Type: Type: Type: Type: Type: Type: BS EN374 FPP3 BS EN166
Environmental Risks i.e. is this material harmful to the environment and / or eco-toxic:
![Page 40: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/40.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 40 of 45
St George Ltd, Grand Union, Phase 2 00
Harmful to water (surface / ground) Harmful to air Harmful to land
General Precautions:
Ensure that the above specific PPE is worn and that all staff are informed of the risks, control measures and precautions required when working with the substance. Ensure all users’ sign off this risk assessment to confirm they have received information and understand the controls applicable to works involving this substance / carrying out this task. Ensure that adequate supervision is provided at all times. If health surveillance required appoint a person to monitor the surveillance process.
First Aid / Hygiene Arrangements – insert specific to this site & susbtance not general requirements: Eye Contact: Wash eye(s) thoroughly with copious amounts of clean fresh water for at least 15 minutes Seek medical advice if any pain or redness develops or persists Ingestion: Swallowing small amounts of dust is unlikely to cause significant reaction. Do not induce vomiting. Wash thoroughly with fresh water and seek medical advice Inhalation: Remove to fresh air. If any symptoms continue, seek medical advice Skin Contact: Remove contaminated clothing and wash skin thoroughly with soap and water If irritation/redness occurs, seek medical advice.
Fire Precautions - insert specific to this site & susbtance not general requirements N/A
LEV / Ventilation Requirements – in many cases working outside will suffice consideration required for working
indoors / covered areas and confined spaces.
Area must be dampened down using water, if required LEV may be required in enclosed area’s.
Storage Requirements insert specific to this site & susbtance not general requirements N/A
Transport Arrangements If hazardous materials to be carried in vehicles additional regulations apply contact HS&E.
N/A.
Monitoring Regime Supervision required, background or personnel air monitoring etc
Daily supervision by the supervisor to ensure operatives involved in the operation are wearing the correct PPE and water is used to reduce dust creation.
Spillage Procedures: insert specific to this site & susbtance not general requirements N/A
Disposal Requirements for substances and contaminated containers insert specific to this site &
susbtance not general requirements
Hazardous Waste Return to Depot Return to Supplier Other x If other please state:
![Page 41: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/41.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 41 of 45
St George Ltd, Grand Union, Phase 2 00
COSHH ASSESSMENT: Refuelling of plant
HAZARD IDENTIFICATION
Inhalation: Fumes or vapour may cause irritation to eyes and mucous membranes, and drowsiness leading to
loss of consciousness.
Skin: Unlikely to cause irritation on single contact. Prolonged or repeated contact may cause
dermatitis which could eventually lead to irreversible skin disorders
Eyes: May cause irritation with short-term redness and stinging
Ingestion: The swallowing of small amounts is unlikely to have adverse effects; larger amounts may cause
irritation with diarrhoea and vomiting
EXPOSURE CONTROLS/PERSONAL PROTECTION
Gloves: Wear impervious gloves to BS EN374
Eye Protection: Eye protection approved to BS EN 166 if likely to splash
Skin protection: Avoid skin contact. Use protective clothing when required. Overalls and
Wellington boots.
Respiratory Protection: Unlikely to be required in normal use but ensure good ventilation – not
Flash Point 60ºC min.
FIRST AID MEASURES
Inhalation: If inhalation of vapour causes irritation or drowsiness remove to fresh air. Get medical advice if
the symptoms continue.
Skin: Wash skin as soon as possible with soap and water. Change contaminated clothing and launder
before reuse. Get medical advice if irritation persists. Eyes: Wash out thoroughly with large amounts of water. If redness and/or irritation continues get
medical advice. Ingestion: Wash mouth out with water and give water to drink. If a large amount has been swallowed
get medical advice. Do not induce vomiting because of the danger of aspiration (inhaling
diesel into the windpipe or lungs).
FIRE PREVENTION AND FIRE FIGHTING MEASURES
Conditions to avoid: No Smoking permitted - avoid naked flames, hot surfaces, other high
temperature/ignition sources.
Extinguishing media: Extinguish with Dry Powder or Foam, for small fires use Carbon Dioxide.
ENVIRONMENTAL CONSIDERATIONS
Do not allow to enter controlled waters (drainage system, surface or groundwater). Use drip
trays when in use.
Dispose of as hazardous waste.
![Page 42: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/42.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 42 of 45
St George Ltd, Grand Union, Phase 2 00
37. Noise Assessments Example
![Page 43: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/43.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 43 of 45
St George Ltd, Grand Union, Phase 2 00
![Page 44: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/44.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 44 of 45
St George Ltd, Grand Union, Phase 2 00
38. OPERATIVES SIGNATURES BELOW
I have read and understood this method statement, or it has been explained to me and will adhere to it at all
times:
Print Name Signature Date
![Page 45: Method Statement and Risk Assessments](https://reader035.vdocuments.us/reader035/viewer/2022062222/62a46272b1c803442610269a/html5/thumbnails/45.jpg)
DOCUMENT Ref MS 01 Enabling works & installation of piling mat ISSUE Page 45 of 45
St George Ltd, Grand Union, Phase 2 00
38. OPERATIVES SIGNATURES BELOW
I have read and understood this method statement, or it has been explained to me and will adhere to it at all
times:
Print Name Signature Date