![Page 1: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/1.jpg)
Market Simulation – Spring and Independent 2017
Releases
Trang Deluca
Sr. Change and Release Planner
Spring and Independent 2017 Releases Market Simulation
April 20, 2017
![Page 2: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/2.jpg)
Agenda
• Spring and Independent 2017 MAP Stage Availability
• Spring and Independent 2017 Market Simulation Initiatives and
Timelines
• Initiatives
• LMPM Enhancements
• PIRP System Decommissioning
• MRI-S ACL Groups and CPG Enhancements
• Known Issues
• Next Steps
• Reference Slides
Page 2
![Page 3: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/3.jpg)
MAP Stage Scheduled Maintenance –
Upcoming maintenance –
MRI-S GUI only offline, available May 1, 2017
Integration Layer Maintenance 4/24
MAP Stage Daily Maintenance Window - Tuesday, Wednesday, Thursday and
Friday 16:00 – 20:00
MAP Stage Weekly Maintenance Window - Monday 08:00 – Tuesday 09:00
Please refer to the MAP Stage portal at https://portalmap.caiso.com for specific
application availability information.
Page 3
Spring and Independent 2017 Releases MAP
Stage Availability
![Page 4: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/4.jpg)
Spring and Independent 2017 Releases Market
Simulation Initiatives and Timelines
Page 4
Market Simulation Plan -
http://www.caiso.com/Documents/MarketSimulationPlan_Spring_Independent2017R
eleases.pdf
Spring and Independent 2017 Releases Initiatives
Start Date Start Date (Trade Date)
End Date Structured Simulation Start (Trade
Date)
Expected Participation
Spring 2017 Release Market Simulation
RTD LMPM2/6/17 2/7/17 2/24/17 N/A
EIM Entities and ISO MPs
PIRP System Decommissioning4/4/17 N/A 4/18/17 N/A ISO MPs
Independent 2017 Release Market Simulation
MRI-S ACL Groups and CPG Enhancements 3/13/17 N/A 5/26/17 N/A
EIM Entities and ISO MPs
![Page 5: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/5.jpg)
Local Market Power Mitigation (LMPM) Enhancements
SimulationLMPM Enhancements Market Simulation timeline - Complete
CMRI Tech Spec –
http://www.caiso.com/Documents/CMRI-
InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf
OASIS Tech Spec –
http://www.caiso.com/Documents/OASIS-
InterfaceSpecification_v4_3_5Clean_Spring2017Release.pdf
OASIS LMPM Enhancements reports deployed to MAP Stage March 15, 2017 –
1. 1. PRC_MPM_RTM_NOMOGRAM_CMP RTD - now has data for TD 3/23 Intervals 8-12.
This report will only have data when the nomogram is binding, thus will be intermittent.
2. PRC_MPM_CNSTR_CMP - RTD - this report has data TD 3/22 starting HE12
3. PRC_MPM_RTM_REF_BUS - RTD - this report has data TD 3/22 starting HE12
Page 5
![Page 6: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/6.jpg)
PIRP System Decommissioning Simulation
PIRP System Decommissioning Market Simulation timeline –
• PIRP System Decommissioning Simulation - April 4, 2017 – April 18, 2017
CMRI Tech Spec –
• http://www.caiso.com/Documents/CMRI-
InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf
Page 6
![Page 7: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/7.jpg)
MRI-S ACL Groups and CPG Enhancements
Simulation
MRI-S ACL Groups and CPG Enhancements Market Simulation timeline –
• MRI-S ACL Groups and CPG Enhancements Simulation - March 13, 2017 – May 26, 2017
Unstructured
MRI-S Tech Spec –
• http://www.caiso.com/Documents/OMAROnlineReplacementTechnicalSpecificationCleanV1
_10.pdf
AIM ACL Training –
• http://www.caiso.com/Documents/Access_IdentityManagementAccessControlListTraining-
Jan_2017.pdf
AIM User Guide –
• http://www.caiso.com/Pages/documentsbygroup.aspx?GroupID=EBFDD87D-9926-4BFE-
8DBD-09AA3D1E5CC5
Page 7
![Page 8: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/8.jpg)
Known Issues
Page 8
# System Summary Status Estimated Fix Date
1 MRI-S Implementation of the requirement stated in MRIS-BRQ085 for allowing users within the same organization to view the batch submission status is being delayed in market simulation pending further security validations.
Open 5/1/2017
2 MRI-S The error description for error code 1028 incorrectly has X and Y instead of the actual meter value and PMAX, respectively.
Open 5/1/2017
3 MRI-S Intermittent issues with Export function in the UI not returning expected results.
Open 5/1/2017
4 MRI-S UpdateSinceDateTime does not allow time input Open 5/1/2017
5 MRI-S IntervalEndTime for 3/12/2017 (DST Date) is not displaying correctly
Open 5/1/2017
6 MRI-S Error generated when data is submitted for a resource that is valid till the end of the day in GMT
New 5/1/2017
![Page 9: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/9.jpg)
Next Steps
• The next teleconference will take place @ 14:00 PPT on
Monday, April 24, 2017
Page 9
![Page 10: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/10.jpg)
Page 10
Reference Slides
![Page 11: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/11.jpg)
Page 11
Transmission B2B Service Changes
• Production activation, April 5, 2017
• Transmission B2B Service Changes
– V1 supported, V2 to be added
– NoW Enumerations: RIMS_OUTAGE, RIMS_TESTING,
– New Equipment Type – SYNCHRONOUS_MACHINE and Multiple instances of
Adjusted Operational Limit per Equipment
Nature of WorkSwitch
Modeling
EquipmentD
erate
Overlaps
Allowed
Exclusive
Nature of
Work
RIMS Outage A A Yes Yes
RIMS Testing A A Yes Yes
Out of service R A Yes Yes
Energized Work Yes Yes
Relay work A Yes Yes
Special Setup A A Yes Yes
Test Program A A Yes Yes
Equipment Derate R Yes Yes
Equipment Abnormal A A Yes Yes
Path Limitation A A Yes Yes
Communications Yes Yes
Out of Service with Special Setup A A Yes Yes
![Page 12: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/12.jpg)
Settlements Calendar for Settlements Production
Release (sample statement)
Page 12
Calendar Day
CMRI
T+1B
Publish Initial Statement
T+4B04-Mar-17
05-Mar-17
06-Mar-17
07-Mar-17
08-Mar-17
09-Mar-17 8-Mar
10-Mar-17
11-Mar-17
12-Mar-17
13-Mar-17
14-Mar-17 8-Mar
15-Mar-17
16-Mar-17
17-Mar-17
Draft Configuration Output File has been posted under “Settlements technical documentation” at: http://www.caiso.com/market/Pages/Settlements/Default.aspx
![Page 13: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/13.jpg)
Settlements Calendar for Spring Release 2017
Page 13
Calendar DayCMRIT+1B
Publish Initial
Statement T+4B
13-Feb-17
14-Feb-17
15-Feb-17
16-Feb-17 15-Feb
17-Feb-17
18-Feb-17
19-Feb-17
20-Feb-17 ISO Holiday
21-Feb-17
22-Feb-17 15-Feb
23-Feb-17
24-Feb-17
25-Feb-17
26-Feb-17
February 15, 2017 TD statement was published on time.
![Page 14: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/14.jpg)
FMM and RTD Market Execution Reports
Link -
http://www.caiso.com/Pages/documentsbygroup.aspx?Gro
upID=DB357A9C-87C9-4BDF-8020-29C5E40A7A82
Page 14
![Page 15: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/15.jpg)
Mitigation Status
Page 15
![Page 16: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/16.jpg)
MPM Not Competitive constraints on Oasis
Page 16
![Page 17: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/17.jpg)
Not competitive constraints for 02/15/2017 HE13HE Interval Not competitive Interface Type of constraint
13 17755 SOL5_NG Nomogram
13 1
PATH26_BG
TCOR
13 1PACW EIM XFER
13 1PSEI EIM XFER
13 225406_J.HINDS _230_24806_MIRAGE _230_BR_1 _1 LINE
13 2NEVP EIM XFER
13 2AZPS EIM XFER
13 2PSEI EIM XFER
13 2PACE EIM XFER
13 2PACW EIM XFER
13 325406_J.HINDS _230_24806_MIRAGE _230_BR_1 _1 LINE
13 3
PATH26_BG
TCOR
13 3SUMMIT_BG TCOR
13 3NEVP EIM XFER
13 3PSEI EIM XFER
13 3PACE EIM XFER
13 3PACW EIM XFER
13 425406_J.HINDS _230_24806_MIRAGE _230_BR_1 _1 LINE
13 4SUMMIT_BG TCOR
13 4NEVP EIM XFER
13 4AZPS EIM XFER
13 4PSEI EIM XFER
13 4PACE EIM XFER
13 4PACW EIM XFER
13 47755 SOL5_NG Nomogram
Page 17
![Page 18: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/18.jpg)
Not competitive constraints for 02/15/2017 HE13
13 5 25406_J.HINDS _230_24806_MIRAGE _230_BR_1 _1 LINE
13 5 NEVP EIM XFER
13 5 AZPS EIM XFER
13 5 PSEI EIM XFER
13 5 PACE EIM XFER
13 5 PACW EIM XFER
13 6 25406_J.HINDS _230_24806_MIRAGE _230_BR_1 _1 LINE
13 6 NEVP EIM XFER
13 6 AZPS EIM XFER
13 6 PSEI EIM XFER
13 6 PACE EIM XFER
13 6 PACW EIM XFER
13 7 25406_J.HINDS _230_24806_MIRAGE _230_BR_1 _1 LINE
13 7 NEVP EIM XFER
13 7 AZPS EIM XFER
13 7 PSEI EIM XFER
13 7 PACE EIM XFER
13 7 PACW EIM XFER
13 12 NEVP EIM XFER
13 12 AZPS EIM XFER
13 12 PSEI EIM XFER
13 12 PACE EIM XFER
13 12 PACW EIM XFER
Page 18
![Page 19: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/19.jpg)
Key points
• Input bid from corresponding RTPD is used in RTD
LMPM. It can be market bid, or mitigated in RTPD bid.
• RTPD mitigated bid can be mitigated farther in RTD.
• RTD LMPM evaluates second interval. If bids are
mitigated, they will be used for binding interval of next
RTD.
• Mitigated bids will be used within quarter of the hour (15
min interval corresponding to RTPD interval).
Corresponding RTPD input bids used at the beginning of
every quarter.
• EIM bids will be mitigated if EIM MCP is higher than
CAISO MCP.
Page 19
![Page 20: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/20.jpg)
ISO System Access Documentation
• http://www.caiso.com/Documents/SystemAccessInformat
ion_MarketParticipants.pdf
Page 20
![Page 21: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/21.jpg)
ISO Market Simulation Support
• Hours - 09:00 - 18:00, PPT (Monday through Friday)
• ISO’s 24X7 Help Desk - (916) 351-2309 (Connectivity - GUI or API)
• Email - [email protected]
Page 21
![Page 22: Market Simulation Presentation - California ISO · 2018. 2. 10. · Sr. Change and Release Planner Spring and Independent 2017 Releases Market Simulation April 20, 2017. ... InterfaceSpecification_v3_5_4Clean_Fall2016Release.pdf](https://reader035.vdocuments.us/reader035/viewer/2022071404/60f8be1911693d3881401fca/html5/thumbnails/22.jpg)
Market Simulation Issue Management
• Submit all issues to the ISO CIDI case management system
• CIDI tickets will need to have
– ‘Functional Environment’ = “Market Simulation Spring 2017”
– Or ‘Functional Environment’ = “Independent Market Simulation
2017”
to be reviewed by ISO SME’s
Page 22