BAM Rail bv
Maintenance Management at BAM Rail bvAd de BlaaijVice Director
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 2
Starting Position
Requirements created by the market
• Liberalisation of the markets through EU laws
• Increasing competition pressure as a result of the economic down turn
• Requirements adjusted by customers
• Restructuring of contracts with ProRail
Introduction of the maintenance management at BAM Rail bv
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 3
Starting PositionAdjusting to the requirements of the biggest customer
Fault-freeoperation
Increasein
quality
Comprehensive services
Cost-effectivesolutions
High networkavailability
The customer’s requirements determine the strategic objectives
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 4
Projects implemented to attain objectives
Optimisation of structures and processesImprovement of quality, productivity; reduction of costs; higheravailability
PRIO
Increasein
quality
Fault-free operation
Comprehensive of services
Cost-effectivesolutions
High network
availability Objectives PRIM
A
Pilo
t
proLean Management Consultancy Projects
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 5
Overall concept• Objective:
Job control of maintenance activities• Route:
Development of standard work methods and description in modules
Standardised findings documentationand problem solution with modules
Harmonisation of capacities
Activities carried out in inter-disciplinary teams
Development of an optimal job administration process
Development of the non-paperprocessing of jobs
PRIO/PRIMA Project
Ges
chäf
tsfe
ldlin
ie
Mod
ulnu
mm
er
M odul <= P
riorit
ät
Beschre ibung des Modulinha ltes Kal
kulie
rte Z
eit (
Fh)
Leis
tung
SO
LL-P
roze
ß
Mod
ulze
it/Ei
nhei
t (Fh
)
P rioritä t =>
I 1 MassivbauI 1.1 M auerw erk herste llen und instandsetzen
I 1.1.1 Naturs teinmauer hers tellen CM örtel hers tellen, auftragen; Naturs teine im Verband setzen, Zwischenräume schließen (einschließ lich Vor- und Nacharbeiten und Transport auf der Baustelle)
6 Fh/m³Quaders t. / 8 Fh/m³Bruchs t. ***
I 1.1.2 Naturs teinmauer ins tandsetzen B Ins tandsetzungsarbeiten, z . B. ersetzen ausgebrochener Steine, etc. 6-8 Fh/m ² *
I 1.1.3 Ziegelmauer hers tellen CM örtel hers tellen, auftragen; Ziegel im Verband setzen, Zwischenräume schließen (einschl. Vor- und Nacharbeiten) 5-6 Fh /m³ *
I 1.1.4 Ziegelmauer ins tandsetzen CM örtel hers tellen, auftragen; Ziegel im Verband setzen, Zwischenräume schließen (einschließ lich Vor- und Nacharbeiten und Transport auf der Baustelle) 7 Fh /m² *
I 1.1.5 M auerwerks fugen ausspitzen (Abbauhammer oder von Hand) C Fugen ausspitzen, Abbruchmaterial verladen inclus ive Transport auf der Baustelle 0,5 - 1,0 Fh/m² ***
I 1.1.6 M auerwerk verfugen (Naturstein, Ziegel) B Fugenmörtel herstel len, Fugen schließen 0,75- 2,50 Fh/m² ***
I 1.1.7 M auerwerk verputzen - Sanierputzen CUntergrund vorbereiten, Mörtel herstellen, aufbringen (einschließ lich Vor- und Nacharbeiten und Transport auf der Baustelle) baus tellenspez ifisch
I 1.2Herste llung Fertigbeton- und -stahlbetonbaute ilen (sta tionär)
I 1.2.1 Schalungsarbe iten (incl. ausschalen e tc.)
I1.2.1.1 B rettschalung C
Schalung hers tellen und montieren, ausschalen, reinigen, (inc lusive Riegel und Abstützung, B retter ungehobelt /gehobelt , mit Dreikantleis ten), inclus ive Transport auf 1,5-2,0 Fh/m² *
I1.2.1.2 Fertigschalung C
Z. B. Peri-Handset montieren, ausschalen, reinigen, Abs tützung hers tellen, inc lusive Transport auf der Baustelle 1,0-1,5 Fh/m² *
I 1.2.2 Bew ehrung
I1.2.2.1 Bewehrung herstel len (Bewehrungskorb) C Bügel und Längseisen verbinden, zwischenlagern 20-40 Fh/t (10-16er Baustahl) *
I1.2.2.2 Bewehrung einbauen C Bewehrungskorb einbauen, anpassen, inc lusive Abs tandhalter baus tellenspez ifisch *
I 1.2.3 Betonieren
I 1.2.3 Betonieren (inc l. abdecken, befeuchten) C Transportbeton mit Betonkübel (Kran) einbauen, verdichten,abz iehen etc . 2-3 Fh/m³ **
I 1.2.4 Nachbehandlung
I 1.2.4 Nachbehandlung (beschichten, hydrophobieren) C Beschichtung mit Pinsel/Rolle aufbringen (eine Lage) system abhängig
I 1.3Herste llung von Beton- und S tahlbetonbaute ilen (vor Ort)
Job
Job
Feedback
Findings sheet
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 6
Modules are the basis for improving the maintenance process
Modulmatrix
Summe d. Tätigkeitszeiten180170
3535
95
20
140
3045
9090
45
111
1212
45
020406080
100120140160180200
A B C D E F G H I K L M N O P Q
WertschöpfendNicht Wertschöpfend
Procedure: Modularisation
Modulnummer Modul Modulinhaltesmitgeltende Unterlagen / Vorschriften
Anzahl Mitarbeiter bzw. Maschinen,
Qualifikation
DIVAI u. W.-Fristen[Monat]
IWEAInspektion und Wartung Elektroenergieanlagen 50 HZ
Inspektion und Wartung Elektroenergieanlagen 50 HZ
01.01.01Netzers./ Akku Zellen, Batterie_Zellen, Elektrolytstan
Prüfe Elektrolytstand des Akkumulator ggf. nachfüllen; Besichtige Zelle
954.01954.0107UVV 2.10
00:02:00 / Zelle Efk 2
01.01.02 Gesamtladespannung Prüfe Gesamtladespannung
954.01954.0107UVV 2.10
DIN VDE 0510
00:02:00 / Akku Efk 2
01.01.03 Kraftstoffleitung
Prüfe Kraftstoffleitungen auf Dichtheit, Kraftstoffvorrat, Schmieröl u. Kühlwasser, Besichtige Zustand Zu-, Abluft- und Abgasführung
Betriebs- und Wartungs-anleitung des
Herstellers00:06:00 / Anlage Elektrotechnisch
unterwiesene Person2
01.01.04 Anlagenprobelauf;1 Std. Führe Probelauf durch, 1 Std. gemäß Herstellerangaben
Betriebs- und Wartungs-anleitung des
Herstellers00:30:00 / Anlage Elektrofachkraft;
unterwiesene Person2
01.01.06 Filter Reinige Filtereinsätze, ggf. wechselnBetriebs- und Wartungs-
anleitung des Herstellers
00:12:00 / Anlage unterwiesene Person 12
01.01.07 Schmierstellen Schmiere Schmierstellen abBetriebs- und Wartungs-
anleitung des Herstellers
00:05:00 / Anlage Elektrotechnisch unterwiesene Person
6
Entwässere Abgasanlage, Prüfe Zustand Keilriemen
01.01.09 USV-Raum Reinige Netzersatzraum954.01
954.0107UVV 2.10
00:03:00 / m2Elektrotechnisch
unterwiesene Person 12
01.01.10 Ueberwachung Prüfe Funktion Überwachungen954.01
954.0107UVV 2.10
00:20:00 / Anlage Efk 12
01.01.11 Kommutator
Prüfe Zustand des Kommutators bzw. Schleifringe u. der Kohlenbürsten; Kommutator bzw. Schleifringe reinigen, ggf Kohlebürsten erneuern
954.01954.0107UVV 2.10
00:30:00 / Anlage Efk 48
Elektrotechnisch unterwiesene Person 12
Modulzeit / Einheit in Fh /
Einheit (Format:hh:mm:ss)
01.01.08 Abgasanlage Betriebs- und Wartungs-anleitung des 00:10:00
Identify modules
Record modules, audit
Evaluate audits
Optimise modules
Create module matrix
Continuous improvement process
Introduce modules
PRIO Project
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 7
PRIO Project Findings and problem solving catalogue
• Definition of findings based on damage symptoms
Sleeper broken or decomposing• Agreement of the definitions among
group of experts• Setup of a coding system for sorting the
findingsG BN SP DWL ____ 205
• Acceptance of the coding system for the developed modules
H BN SP DWL DBHM010• Assignment of the individual modules to
the findings
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 8
PRIO ProjectExample of findings and problem solutions for broken or decomposingsleepers
Interpretation-free feedback of findings and solutions
Spoor Dwarsligger
G BN SP DWL ____ 205 Dwarsligger: gescheurd, gebroken, verrot H BN SP DWL HOHE 010 Steken 1x houten bewapende dwarsligger met de hand stuk 0034 H BN SP DWL DBHM 010 Steken 1x houten bewapende dubbelligger met de hand stuk 0035
H BN SP DWL HOHM 010 Steken meerdere houten bewapende dwarsliggers met de hand stuk 0036
H BN SP DWL MDVH 010 Steken houten bewapende dwarsliggers met een KROL's en een MDV bak stuk 0037
H BN SP DWL BEHM 010 Steken 1x een betonnen dwarsligger met de hand stuk 0038 H BN SP DWL BEMA 010 Steken 1x een betonnen dwarsligger met de KROL's stuk 0039
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 9
• Employee resource-specific layout of the schedules
• Inspections and repairs are carried out separately from one another
• Differrent start dates for schedules
• Inspections of various items at onelocation are carried out separately
• The maintenance strategy isindependent of the line standard
• Absence of capacity balancing121110987654321
100%
Months
Cap
aciti
es
Job congestion
LST:03/99
LST:05/99
LST:07/99Fb:10/99
50Hz:12/99
LST:09/99 50
Hz:11/99
LST:04/99
LST:08/99
Fb:09/99
Unneccessary complexity creates high expenses with regard to traveland communiting times and a low utilization of employee capacities
Schedule planning Starting positionPRIO Project
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 10
• Integration of employee resources at the items for
Inspection and maintenance
Immediate repair
• Capacity balancing
Harmonisation of the schedules
Equal distribution of the schedules
• Requirement-oriented capacity planning
• Line-oriented maintenance
Points :10/99
Signal 08/99
121110987654321
100%
MonthsCap
aciti
es
Capacity balancing Current situation
Inspection and servicing as fixed planable activities of the maintenance
PRIO Project
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 11
Setup of interdisciplinary teams: employee approach• Employee approach
1 Chief fitter, signal service1 Fitter, signal service1 Fitter, track
• Additional employees for safety(according to locality)
• Vehicle, tools, equipment, materials
VW LT 35Tools according to content of the inspection Points, signals and level crossingsEquipment
Impact wrench, grinding machine,measuring equipment etc.
PRIO Project
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 12
PRIO Project
Modules as basis of the planable maintenance
• Analysis capacity of the infrastructure statuswith standardised findings report
with standardised work assignments with modules
• Option of analysing the effect of the activity carried out
• Recording the environment of the immediate repair with modules
• Derivation of further maintenance measures from accumulation of findings
Inspection and servicing as basis of the maintenance
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 13
Inspection and servicing as basis of the maintenance
• Faults are actively taken into account as they occur
• Batch maintenance activities can be planned on a monthly basis and provide a balanced capacity utilization
• Repair work, projects, newconstruction, large section changeand use of large machinery can be planned on an annual basis
• Inspection, maintenance and smallrepairs can be planned as fixed
Isolation of fault clearance from inspection, repair and projects
PRIO/PRIMA Project C
apac
ity
100%
Time
Inspection + smaller repairs
Major repairs + projects
Batch activities
Fault clearances
80%
20%
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 14
PRIMA Project
Clear-cut planning of the inspection and maintenance
• Setting up dedicated inspection teamsTeam 1: Points, signals and level crossingsTeam 2: Visual control of the tracks and pointsTeam 3: Automatic train-stopping systems
• Creation of an automatic maintenance planning
• Positioning of all items to be examined
• Recording of measuring values and findings for the items
• Recording of fault reports
• Creation of follow-on jobs for repairing
Implementation of the modules and processes in an EDP system
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 15
PRIMA ProjectApproach
• Elaboration of the experienced current processes with all process participants
Team leaderPlanning engineerMaintenance engineerPlanner
• Clarification of the difference betweenPush principle of the job planningPull principle of the job planning
• Analysis of the current processWhat goes wrong?Why does it go wrong?How can it be improved?
• Improvement points as approach for the new process in the pull principle
1.
2.
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 16
New job administration process • Monthly job packages from the
system• Weekly job queue and staff
assignment by the team leader• Daily planning of fault clearance and
repairs • Carrying out activities in
interdisciplinary teams• Standardised recording of findings
and problem solving with modules• Daily feedback of the activities
carried out • Automatic creation of follow-on jobs
No activity without job
PRIMA Project
Ges
chäf
tsfe
ldlin
ie
Mod
ulnu
mm
er
M odu l <= P
riorit
ät
Be schre ibung de s M odu l inha l te s Kal
kulie
rte
Zeit
(Fh)
Leis
tung
SO
LL-P
roze
ß
Mod
ulze
it/Ei
nhei
t (Fh
)
P rio ri tä t = >
I 1 M ass iv ba uI 1.1 M a ue rw e rk he rste l le n und insta ndse tz e n
I 1.1 .1 N atu rs te inm auer hers te llen CM örte l he rs te llen, au ftragen; N aturs te ine im V erband s etzen , Zw isc henräum e sc h ließ en (e ins c hließ l ich V or- und N ac harbe iten und Trans port au f der B aus te lle )
6 Fh/m ³Q uaders t. / 8 Fh /m ³B ruc hs t . ***
I 1.1 .2 N atu rs te inm auer ins tands e tz en B Ins tands etz ungs arbei ten, z . B . e rs e tz en ausgebroc hener S teine , et c . 6 -8 Fh /m ² *
I 1.1 .3 Ziege lm auer hers te llen CM örte l he rs te llen, au ftragen; Ziege l im V erband se tzen , Zw isc henräum e sc h ließ en (e ins c hl. V or- und N ac harbe iten) 5 -6 Fh /m ³ *
I 1.1 .4 Ziege lm auer ins tands etzen CM örte l he rs te llen, au ftragen; Ziege l im V erband se tzen , Zw isc henräum e sc h ließ en (e ins c hließ l ich V or- und N ac harbe iten und Trans port au f der B aus te lle ) 7 Fh /m ² *
I 1.1 .5 M auerwerk s fugen aus sp it zen (A bbauham m er oder von Hand) C Fugen auss p itz en , A bbruchm aterial verladen inc lus ive Trans port au f der B aus telle 0,5 - 1,0 Fh /m ² ***
I 1.1 .6 M auerwerk verfugen (N aturs te in, Ziege l) B Fugenm örtel hers tel len , Fugen s ch ließ en 0,75- 2 ,50 Fh /m ² ***
I 1.1 .7 M auerwerk verpu tz en - S anie rpu tz en CU nterg rund vorbere iten , M örtel he rs tellen , au fb ringen (e ins c hließ lich V or- und N ac harbe iten und Trans port au f der B aus te lle ) baus te llens pez ifis c h
I 1.2H e rste l lung Fe rtigbe ton - und -sta h lbe tonba ute ile n (sta tionä r)
I 1.2 .1 S cha lungsa rbe i te n (incl . a usscha le n e tc .)
I1.2 .1 .1 B re tt s chalung C
S cha lung hers te llen und m ont ie ren, auss c ha len, rein igen, (inc lus ive Riege l und A bs tützung, B re tter ungehobelt /gehobelt , m it Dre ikan tle is ten), inc lus ive Trans port au f 1 ,5 -2 ,0 Fh /m ² *
I1.2 .1 .2 Fertigsc halung C
Z. B . P eri-Handse t m ont ie ren, auss c ha len, rein igen , A bs tü tz ung hers te llen, inc lus ive Transport auf der B aus te lle 1 ,0 -1 ,5 Fh /m ² *
I 1.2 .2 B e w e hrung
I1.2 .2 .1 B ew ehrung hers tel len (B ewehrungs korb ) C B üge l und Längs eisen verb inden, z wis c henlagern 20-40 Fh /t (10-16er B aus tah l) *
I1.2 .2 .2 B ew ehrung e inbauen C B ew ehrungs k orb e inbauen, anpas sen, inc lus ive A bs tandha lte r baus te llenspez ifis c h *
I 1.2 .3 B e ton ie re n
I 1.2 .3 B etonie ren (inc l. abdeck en, befeuch ten) C Transportbe ton m it B etonk übe l (K ran) e inbauen, ve rd ic h ten,abz iehen etc . 2 -3 Fh /m ³ **
I 1.2 .4 N a chbe ha nd lung
I 1.2 .4 N ac hbehandlung (besc h ich ten , hy drophobie ren) C B es c hic h tung m it P ins el/Ro lle aufbringen (e ine Lage) s y stem abhängig
I 1.3H e rste l lung von Be ton - und S ta h lbe tonba ute ile n (vor O rt)
Job
Job
Feedback
Findings sheet
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 17
PRIMA Project Job administration with MAXIMO mobile support
• Jobs are assigned by the team leader to a handheld
• The handheld is synchronised daily with the system
• The jobs are processed by the team Registering of measuring values for the item
Recording of findings at item levelAssigning of a solution to the
findings Creation of a new job from solution
and itemFollow-on jobs can also be carried
out immediatelyRecording of work times
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 18
PilotImplementation of a Pilot In Eindhoven/Boxtel
• Reasons for selection of the area The modules were developed hereThe job administration process was set up here The items are mapped out up to 95% in the EDP systemInterdisciplinary teams have already been in operation for a yearHarmonisation of capacities carried outIsolation of fault clearance and inspection carried outThe area is easily distinguished when compared with the old
organisation • Objectives
Introduction of the new job administration processIntroduction of processing of jobs with handheldReduction of costsReduction of faultsImprovement in quality and availability
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 19
PilotImplementation
• Planning of all activities in the MaximoEDP system
• Monitoring of capacities Number of hours of available personnelfor special functions
Work train driverGrinderWelder
• Planning of track possession according to scope of the work
Planning with modulesMinimum time and scope of the track
possession definedApplication for maximum track possession
time Remainder time filled in with other low
priority jobs
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 20
Pilot Results of the Pilot
• Reduction of costs by more than 30 %
• Reduction of influential faults by 10%
• Increase in employee productivity with job control: 15%
• Reduction in travel and commuting times with fine planning of the jobs
• Requirements catalogue for bordering processes
Logistics and warehousing
Maintenance management
Controlling
• Requirements catalogue for organisation
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 21
Projekt PRIMAResults
• Reduction of interfaces from 13 to 6
• Reduction of the involved process participants from 17 to 4
• Integrated process with one system
• Paperless handling of inspection orders
• Reduction of complexity in planning processes by 50%
• Reduction of administrative personnel by 50% (long dated)
• 80% less failings in the order processing
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 22
Fruther ProcedureFurther development at BAM Rail bv
• Adjustment of organisation for supporting the new process
• Roll out of the operating mode over all support points
EindhovenRotterdam
• Adjustment of bordering processes to the production process
Logistics and warehousingMaintenance managementControlling
<Wijzig de datum met beeld\kop en voettekst>
BAM Rail bv 23
Overview of further stepsFurther Procedure
Organisation-Development-Implementation
Roll out-Preparation-Area 1-Area 2
Roll out: other technology -Create modules-Add items
Other processes-Logistics-Maintenance management-Controlling
2003 2004 2005
Transfer to continuous
improvement process