LOI – Next Steps?
John Thomason
ISIS Schedule
Possible Workplan (1)
Experiments in R5.4 to showfull operation of system with integration of ISIS LPRF, cure for oscillations in IA, etc.
ISIS staff complete break-out box and cabling tosynchrotron and prepare LOI HPD and water manifold for move to synchrotron SP6
First experiments with beam in synchrotron
January experiments go well 4 x ISIS 2RF systems fully commissioned ISIS management approval to operate so close to first real TS-2 beam
Assumes:
May/June 2008
Possible Workplan (2)
Experiments in R5.4 to showfull operation of system with integration of ISIS LPRF, cure for oscillations in IA, etc.
ISIS staff complete break-out box and cabling tosynchrotron and prepare LOI HPD and water manifold for move to synchrotron SP6
First experiments with beam in synchrotron
January experiments go well 4 x ISIS 2RF systems not fully commissioned No ISIS management approval to operate so close to first real TS-2 beam
Assumes:
August/September 2008
Possible Workplan (3)
More experiments in R5.4 needed 4 x ISIS 2RF systems fully commissioned ISIS management approval to operate so close to first real TS-2 beam
Assumes:
Experiments in R5.4 to showfull operation of system with integration of ISIS LPRF, cure for oscillations in IA, etc.
ISIS staff complete break-out box and cabling toSynchrotron SP6
First experiments with beam in synchrotron (to be decided after June experiments)
Further experiments in R5.4