Download - LCLS Undulator System Status and Schedule
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
LCLS Undulator System Status and Schedule
Geoff Pile
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Safety Minute
Two really important statements –
1. Never Underestimate the Power of Co-incidence (There could be more safety issues less obvious than the one you are trying to negate)
2. ISM – Do what you say you do!
Define the scopeAnalyze (ALL) hazardsDevelop/implement controlsPerform the work within controlsFeedback & improvement
Even though you wear your PPE you’re not always as safe as you might think. This guy is wearing his face mask while arc welding. In this case, it’s almost as useful as an ashtray on a motorbike.
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
All Argonne girder components are planned to be available at least 1 month before the P3 “Early Start” of Girder Assembly
Schedule Considerations
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Controls Status and Schedule
Controls -1.4.2 – Work Remaining
Undulator In-tunnel Rack (UIR)
Intra Undulator Cables
Electronic Interface Assembly (EIA)
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
1.4.2 - Controls
Ongoing Work
Completed
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Undulator In-tunnel Rack (UIR)
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Undulator In-tunnel Rack (UIR)
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Electronic Interface Assembly (EIA)
~1800 Intra Undulator Cables(pre-made/pre-
tested)
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Undulator Magnets and Supports 1.4.3
Undulators (39 @ SLAC 7/2007)
Support & Motion System - girder, cam movers & fixed supports (37@SLAC 3/2008)
X translation issue
Quads and Correctors (36 @SLAC 4/2008)
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
1.4.3 - Magnets and Supports
Ongoing Work
Completed
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
All 40 undulators were completed by July 2007
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Girder Manufacture at Metalex Critical
Engineering and QA Oversight by Argonne
Girders Assembled and Packed at Hi-Tech
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
X Translation Stage, Limit Switches, and Adjustable Switch Actuator
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Obtaining X Translation Limits & Stops
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
1.4.3.5 - Quads and Correctors37 magnets and 2 sets of
spare coils completed 4/08
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Vacuum Systems 1.4.4
46 Vacuum Chambers produced Manufacture started September 2007 & ended May 2008
33 required
7 spares
1 LTT
5 sacrificed for surface finish measurements
Monumental task, huge effort, successful ending.
Interest has already been expressed in this technology by other projects around the world.
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Inspection and correction of the LCLS VC end flange
perpendicularity
Inspection of the total Inspection of the total length of the LCLS length of the LCLS Vacuum ChamberVacuum Chamber
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Surface Finish Data of 46 Chambers…33 required (7 spare – 5 sacrificed – 1 LTT)
Desirable
Acceptable
Not Desirable
Should Avoid
Slope Criteria from H-D Nuhn adjusted for the oval shape
Longitudinal:
Transverse:
The transverse rms slope tolerance is 60 mrad
Extrusion # h (mm) rms transverse slope (mrad) rms longitudinal slope (mrad)1 353.57 45.45 17.362 216.02 20.03 7.983 248.52 27.78 8.534 236.10 23.69 12.295 261.25 23.03 9.476 271.06 37.19 13.528 302.81 32.23 14.069 251.17 31.14 19.1211 230.72 25.14 9.82
12 294.41 27.43 15.5713 308.75 26.59 12.6414 350.85 38.58 19.3715 306.37 34.49 15.0417 324.34 26.67 16.2018 341.19 50.46 20.5019 246.35 24.78 11.6220 244.29 18.58 8.0821 331.53 34.12 15.4822 268.19 36.40 14.2623 275.33 40.43 18.5624 229.15 23.36 10.8325 258.43 28.51 10.1426 325.92 46.87 18.4627 327.66 53.97 23.1029 327.50 38.76 20.3630 317.95 45.59 18.9131 334.76 47.89 19.9632 230.19 25.44 12.6533 230.15 21.74 10.2734 294.70 44.42 16.3236 245.60 23.85 8.9337 198.97 17.83 6.8538 345.21 48.72 22.8639 311.58 51.02 18.6240 311.04 35.81 15.3341 341.13 49.27 15.5842 233.57 22.24 10.9943 342.60 56.25 21.7444 321.34 52.82 18.6745 332.56 52.82 19.0446 254.38 29.50 10.34 Totals (rms) 36.94 15.52
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Diagnostic Systems 1.4.5
BPM – 1.4.5.5
BFW – 1.4.5.6
BLM – 1.4.5.8
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Beam Position MonitorLarge effort- solved serious production problems
Many brazing issues
(differential thermal expansion)
Window QA problems
Multi-step Process now
understood
8 now delivered to SLAC
-remainder on track
Promising World Class Diagnostic
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
1.4.5 - Diagnostics – BFW & BLM
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Beam Finder Wire
All production problems are resolved at this point, but we were somewhat delayed due to issues with repeatability, chamber coating, and electronic modules.
Two units that should have shipped last week are on the way to SLAC at this time.
Details in Dean Walters’ talk
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Beam Loss Monitor
Five production BLMs will be used to protect the undulators by inhibiting beam bunches following an “above-threshold” radiation event.A joint R&D effort is aimed at enhancing these 5 units to enable LCLS to track each undulator’s accumulated radiation dose.
Undulator protection is the highest priority. The BLM will be integrated into the Machine Protection System (MPS) and requires only limited dynamic range from the detectors.Dose tracking will enable long-term magnet damage to be characterized, but requires a radiation detector with large dynamic range (order of 106) and sophisticated diagnostics hardware and software.
30 production BLMs may be built in FY09 if R&D is successful
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
BLM in Inserted Position(Can be easily made to track out
with Undulator)Interface Module
Beam Loss Monitor
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Status and Schedule
Undulator System Management and IntegrationCPR & Costs to go –
Generally in good shape. Some unplanned effort has been required in the last two months to solve problems and meet production schedules. Most spares costs were moved to OPC. Final spares costs will be recalculated using actuals and any required adjustments will be made.
Green Sheet SystemA Web-based, almost real time, method of managing Argonne-APS cross- matrixed effort – (up to 60 staff 18FTE’s/year)
ASK SystemA Web-based method of managing deliveries and technical documentation. A dictionary/index style look-up system.
Geoff Pile
FAC Review - Undulator System [email protected]
17 June 2008
Summary
Almost all deliveries complete by July 2008!Production BLMs? TBD (2009)
Argonne Construction team rolls off the project in JulyArgonne Management team drops to half-time in mid-July, and rolls off the project in September.FY09 – a small budget is included for installation and commissioning support