INTRODUCTION ABOUT INDUSTRY
![Page 3: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/3.jpg)
Jaipur, RajasthanCapacity36,000 MTs per annum of lattice towers
BRANCHES IN INDIA
Nagpur, MaharashtraCapacity55,000 MTs per annum of lattice towers
Jabalpur, Madhya PradeshCapacity60,000 MTs per annum of lattice towers
![Page 4: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/4.jpg)
KEC PRODUCTES:-
TRANSMISSION
CABLES
RAILWAYS
DISTRIBUTION
TELECOM
WATER TREATMENT
![Page 5: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/5.jpg)
SIMPLE STRCTURE OF TRANSMISSION TOWER
Arm
Foundation
Damper
Peak of transmission tower
The portion above the top cross arm is called peak of transmission tower. Generally earth shield wire connected to the tip of this peak.Cross Arm of transmission towerCross arms of transmission tower hold the transmission conductor.
Cage of transmission tower
The portion between tower body and peak is known as cage of transmission tower. This portion of the tower holds the cross arms
![Page 6: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/6.jpg)
Department in kecPRE PRODUCTION
RAW FINISH YARD
GALVINISING SHOP
FABRICATION SHOP1 & 2 DEPT
PLANNING
TOWER TESTING DEPT.
QUALITY ASSURANCE DEPT.
![Page 7: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/7.jpg)
Pre Production Department
1. Understanding the drawings made in Mumbai Design Department of KEC. 2. Making 2d drawings of each particular part in
Auto-Cad with full dimension. 3. Teaching labors about the drawings.
4. After making one sample model comparing that model with given design. 5. Than calculating the errors and making again an error free drawing. 6. Then again helping the labors in understanding the new Drawing and making the final model..
![Page 8: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/8.jpg)
PRODUCTION PROCESSES
1. Straightening2. Bending3. Punching4. Cutting5. Stamping6. Notching7. Drilling8. Galvanizing
![Page 9: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/9.jpg)
Production Procedure
• Straightening
When angles are imported they are not fully straight according to requirement . For that purpose roller
straightening machine is used.
![Page 10: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/10.jpg)
Bending Bending is a manufacturing process that produces a V-shape,
U-shape, or channel shape along a straight axis in ductile materials
KEC use Hot Bending Machine, which bend the angles by heat treatment process.
Here angles are heated for 30 to 35 minutes and than hydraulic pressure is applied to bend
![Page 11: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/11.jpg)
Punching, cutting & stamping
• Punching :- The main function of punching is to holes on angles at
various distance which have thickness up to 12mm.This m/c is based on hydraulic pressure principle.
• Cutting :- Cutting is the separation of a physical object, or a
portion of a physical object, into two portions, through the application of an acutely directed force.
![Page 12: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/12.jpg)
• Stamping:-A stamp is a distinctive mark or impression made
upon an object, a device used to make it, or a distinctive sticker applied to an object
CNC machines are used to complete all these processes
![Page 13: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/13.jpg)
Notching• Notching is a metal-cutting process, small cuts are
made on the flanges of angle at any angle.
![Page 14: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/14.jpg)
Drilling
The angles which have their thickness above 12mm are drilled. For this purpose there are six radial arm drilling machines. These machines are rounded at 360’. The machine is operated manually.
![Page 15: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/15.jpg)
Galvanization• Galvanization is the process of applying a protective zinc coating to
metal, in order to prevent rusting and corrosion. • Mainly there are two methods of Galvanizing : 1. Dry galvanizing 2. Wet galvanizingThe life time of wet galvanizing more then dry galvanizing so KEC uses
wet galvanizing.
• Procedure of galvanizing :- Galvanizing is completed in different steps. The process is following in different tanks.
![Page 16: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/16.jpg)
Prepration for galvanizing
![Page 17: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/17.jpg)
Degreasing Tank:- Caustic solution presents in this tank for removing oil, grease, dust etc. on the material. Material is dipped about half an hour at 30-35’c temp.
![Page 18: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/18.jpg)
Acid Pickling Tank:- The material is dipped into HCL tank for removing rust, oxides, dust, oil etc. This process takes time about 40-45 min.
![Page 19: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/19.jpg)
• Rinsing Tank:- The material is cleaned and cooled by dipping it in
water tank because HCL acid sticks on it.
![Page 20: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/20.jpg)
• Pre-Fluxing tank:- A light coating of ZINC-CHLORIDE &
AMMONIUM-CHLORID is made on material. There are 60:40 ratio of zinc & ammonium chloride. It is used for preventing spotting during coating of ZINC in Zinc bath
![Page 21: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/21.jpg)
• ZINK BATH:- There is mainly ZN in this bath at 460’c
temperature. AL & Lead also present these for surface finishing of material. The material is dipped into it and after certain time it is raised from it. Thus the Zn coating is made.
![Page 22: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/22.jpg)
• RINSING TANK:- This tank consists water. The material is dipped
into it for cooling , cleaning after Zn coating.
![Page 23: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/23.jpg)
Galvanizing procedure:-
![Page 24: Kamani Engg. Cor. INTERNATIONAL LTD. JHOTWARA,JAIPUR](https://reader036.vdocuments.us/reader036/viewer/2022062313/557c5b60d8b42a0b4b8b4d03/html5/thumbnails/24.jpg)
After galvanizing and all production procedure, the product was sent either to
Quality department – In case of when angles are made first time for customer requirement ,
than sampling is necessary. So the quality department assembles the
manufactured tower if it founds any error it reports to preproduction department.
Or to
Loading Department In case when quality department is ok with angles, they directly go for
loading, than they dispatched to their desired location.