Town of Bowling Green – Public Works and Utilities Council Monthly Report/Project Update For July 2018

Prepared By: Billy Deavers Date: July 30, 2018 Additional and/or Support Materials Attached: Yes X No

Ongoing: Wastewater Operations:

● Began monthly in-house Wastewater training with Operators ● Received draft of new permit from DEQ, and am reviewing for any changes or discrepancies Water Operations:

● Continuing to flush waterline on Crystal Court every other Friday Public Works:

• Grass cutting in normal locations

Completed: Wastewater Operations:

• Used sewer camera on sewer line at 121 Maury Avenue • Had control module replaced on UV lights • Pump capacitor replaced on Pump #2 at Lacey Lane pump station

Water Operations:

• Two water leaks were repaired. Elm St and Chase St • Monthly water samples were collected

Public Works: • Filled pothole on Trewalla Ln. Also filled a hole in the sidewalk on S. Main St • Painted the exterior of buildings at Well #1 • Cut back trees on Milford St and Dorsey Lane • Cleaned out the shop on Cedar Lane and hauled off scrap

Heads up:

●. The light pole on Main Street was replaced