Transcript
Page 1: Interconnection Issues at Higher Penetrations

Interconnection Issues at Higher Penetrations

Sky C. Stanfield

1

Page 2: Interconnection Issues at Higher Penetrations

2

Installed Grid-Connected Solar Capacity (MW)

0  

500  

1,000  

1,500  

2,000  

2,500  

3,000  

3,500  

Capa

city  (M

W-­‐dc)  

U)lity  

Non-­‐Residen)al  

Residen)al  

1800  MW  

3340  MW  

Page 3: Interconnection Issues at Higher Penetrations

3

Number of Annual Grid-Connected Installations

65,000  

0

10,000

20,000

30,000

40,000

50,000

60,000

70,000

80,000

90,000

100,000

U)lity  

Non-­‐Residen)al  

Residen)al  

95,000  

Page 4: Interconnection Issues at Higher Penetrations

Most Interconnection Procedures Were Designed for a Different Era

•  FERC adopted SGIP in 2005, subsequently many states adopted procedures modeled on SGIP or the original California Rule 21 –  In 2005 the US installed 79 MW of grid connected

PV –  In 2012 the US installed 3,300 MW of grid

connected PV •  Until last year, few states had updated their

procedures to reflect this changing reality 4

Page 5: Interconnection Issues at Higher Penetrations

Key Reasons for Updating Interconnection Procedures

•  High volume of interconnection applications •  Increased penetration on distribution circuits •  Backlogged study queues •  Unclear review requirements •  Lack of transparency regarding system

conditions •  Better procedures = lower costs for solar

customers and utilities/rate payers 5

Page 6: Interconnection Issues at Higher Penetrations

Interconnection Rules Are Changing

•  Both state and federally regulated procedures in California have been updated

•  Hawaii, Massachusetts, Ohio and others have recently adopted or are considering changes

•  FERC is currently considering significant updates to SGIP

6

Page 7: Interconnection Issues at Higher Penetrations

A Few Principles for Efficient Interconnection

•  Filter projects before applications are filed •  Enable developers to select low-cost sites •  Apply the appropriate amount of study to

each project •  Ensure timelines are clear and complied

with •  Allow opportunities for cost sharing

7

Page 8: Interconnection Issues at Higher Penetrations

New and Noteworthy Approaches to Interconnection

•  Pre-Application Reports and other tools •  Fast Track size limits •  Improved Supplemental Review •  Differentiated Study Processes •  Group/Cluster Studies •  Up Next: Integrated Distribution Planning?

8

Page 9: Interconnection Issues at Higher Penetrations

Pre-Application Report

•  Report on system conditions at a particular point of interconnection

•  Reduces number of speculative projects •  Help developers strategically locate projects •  Maximizes utilization of existing infrastructure •  Can help manage expectations •  Minimizes study queues, conserves utility

staff time

9

Page 10: Interconnection Issues at Higher Penetrations

Fast Track Size Limits •  Most common Fast Track limit is 2 MW •  May result in studies being required where

not needed to protect safety and reliability •  Goal should be to filter projects that are

unlikely to pass the Fast Track screens •  Size is a key factor, but location on the circuit

is also a key determining factor •  Couple of options on the table at FERC

10

Page 11: Interconnection Issues at Higher Penetrations

Fast Track Eligibility Proposals

11

Line Capacity Fast Track Eligibility-regardless of location

Fast Track Eligibility- on > 600 amp line and < 2.5 miles from substation

< 4kV < 1MW < 2 MW 5kV – 14 kV < 2MW < 3 MW

15 kV – 30 kV < 3MW < 4 MW 31 kV – 60 kV < 4MW < 5 MW

Line Voltage Fast Track Eligibility Regardless of Location

Fast Track Eligibility on a Mainline* and <2.5 Miles**

from Substation < 5 kilovolt (kV) < 500 kW < 500 kW

≥ 5 kV and < 15 kV < 2 MW < 3 MW ≥ 15 kV and < 30 kV < 3 MW < 4 MW ≥ 30 kV and 69 kV < 4 MW < 5 MW

* For purposes of this table, a mainline will typically constitute lines with wire sizes of 4/0 AWG, 336.5 kcmil, 397.5 kcmil, 477 kcmil and 795 kcmil ** Electrical Line Miles *** An Interconnection Customer can determine this information in advanced by requesting a pre-application report pursuant to section 1.2.

Page 12: Interconnection Issues at Higher Penetrations

Defined Supplemental Review •  Retains the 10 existing initial review screens

– if any are failed options are: 1.  Approve anyway with “minor modifications” 2.  Offer to perform supplemental review, or 3.  Get agreement to study

•  Three supplemental review screens: 1.  100% of minimum load, daytime for PV; 2.  Power quality and voltage, and 3.  Safety and reliability

12

Page 13: Interconnection Issues at Higher Penetrations

Differentiated Study Processes

•  Pre-Application (± 10 days) •  Fast Track (± 30 days) •  Supplemental Review (± 60 days) •  Independent Study (± 6 months) •  Distribution Group Study (± one year) •  Transmission Cluster Study (± two years)

13

Page 14: Interconnection Issues at Higher Penetrations

Group/Cluster Studies

•  Can be necessary to avoid serial-study queue clogging

•  Have advantages in cost sharing for study fees as well as upgrades

•  Longer study time per-project, but overall shorter wait time to be studied

•  Still in the experiment stage in California

14

Page 15: Interconnection Issues at Higher Penetrations

Integrated Distribution Planning

•  Proactive instead of Reactive •  Advanced determination of hosting capacity •  Can shorten project specific study time •  Could even result in upgrades not done on a

project-by-project basis •  For more see 3iForum talks on IDP

15

Page 16: Interconnection Issues at Higher Penetrations

Questions?

Sky Stanfield Keyes, Fox & Wiedman LLP

(510) 314-8204 [email protected]

16

Page 17: Interconnection Issues at Higher Penetrations

What is FERC Doing with SGIP?

•  Issued a NOPR in January 2013 post SEIA petition

•  Workshops were held, Comments filed in June •  Considering a rule similar to Rule 21 •  Why does it matter?

–  Model for state procedures –  Could help facilitate greater penetration of DG at lower

cost to developers •  Watch for decision later this year or early next

17

Page 18: Interconnection Issues at Higher Penetrations

THANKS to our generous sponsors for the 2013 3iForum and 3iAwards


Top Related