+Introduction
Indonesia has submitted the ER-PIN prior to 11th CF Meeting
and obtained provisional inclusion in the pipeline
Targeted to submit a revised ER-PIN by 13th CF Meeting, but
due to institutional reforms the revising process need to wait
until the unification of MoE and MoFor completed
Now CF-based ER Program development is decided to be
led by FORDIA, Ministry of Environment and Forestry
The remaining time is very limited difficult to achieve the
target
+Recommendations from CF 11 Meeting
di Washington (1)
The revised ER-PIN shall address the following issues:
Geographic consolidation of program and accounting areas;
Explanation of how:
one consolidated reference level will be developed
emissions from peat will be fully included
consistency with the national reference level approach and MRV
system will be ensured;
Explanation of how all relevant sources of potential leakage
resulting from the ER Program will be addressed;
+Recommendations from CF 11 Meeting
di Washington (2)
Explanation of how the ER Program will contribute to
Indonesia’s pledge to reduce national GHG-emissions by
26% by 2020 (with own efforts) and by 41 % (with
international support);
Description of how relevant components of the national MRV
system, including institutions, are used for the ER Program,
and are not unnecessarily duplicated at sub-national level;
Additional information on the relevant stakeholders, drivers,
tenure, and the proposed actions at the level of intervention
(e.g. the district level).
+Previously Proposed CF Program
Locations: 7 Districts – 4 Provinces
• Merangin (311,293 ha)
• Bungo (96,519 ha) Kapuas (814,000 ha)
• Donggala (302,897 ha)
• Toli-toli (202,480 ha)
• Kutai Barat (903,556 ha)
• Berau (1,513,170 ha)
+A New Consolidated Location
EAST KALIMANTAN
PROVINCE
14.7 million ha of
forest cover (incl.
newly-established
North Kalimantan
Province) 0.4
million ha of peat land
+Why A Province?
Clear Jurisdiction
In line with the new Law of Regional Government (Law No.
23/2014):
Forestry, Mining and Fisheries are under provincial government
authority
Significant size of forest area
Significant size of carbon emission reduction
+Why East Kalimantan Province?
Has been involved in the preparation of CF ER Program
through Berau and West Kutai Districts
Political Will:
Kaltim Green Low emission development initiative
incorporated into provincial development plan Governor
Regulation No 54 of 2012
Provincial Action Plan on the Reduction of GHG Emissions
Provincial Strategies for REDD+ Implementation
+Why East Kalimantan Province?
Institutional Arrangements:
Have established Provincial Council for Climate CHange
An active member of Governors' Climate & Forests Task Force
Support from NGOs and International Agencies: TNC, WWF,
GGGI, etc
Strong Leadership on Climate Change Issue
+Drivers of Deforestation in East
Kalimantan Province
Forest Zone
Over-exploitation of
timber
Illegal logging
Encroachment
Infrastructure
development
Forest Fires
Agricultural Land
Food estate development
Slash and burn
agriculture
Expansion of plantation
estate
Mining
Expansion of mining
areas
+Reference Emission Level and
Expected Emission Reduction
Average Annual Emissions:
Based on Provincial REDD+ Strategies (2006 – 2011): 49.43 MtCO2e
Based on INCAS (2001 – 2012): 48.35 MtCO2e
+The emissions of East Kalimantan are
about 10% of the national emissions
+Institutional Arrangement
Ministry of Environment and Forestry:
Forestry and Environmental R&D and Innovation Agency
(FORDIA)
Directorat General of Climate Change
East Kalimantan Province:
East Kalimantan Provincial Council for Climate Change
GCF Secretariat
GGGI
TNC in Berau District
WWF in West Kutai District
+Political Will
Provincial Action Plan for Reducing GHG Emissions
Provincial Strategies to Implement REDD+
Development Strategies for A Sustainable and Environmentally Friendly East Kalimantan (KaltimGreen)
East Kalimantan Safeguards for REDD+
Prioritised Program:
One map one data
Permit Moratorium
+Focused Programs: Addressing the drivers of
deforestation and forest degradation
Improving forest licensing system
Improving the clarity of forest tenure FMU, CBFM
Providing community-based agricultural map and ensuring itssustainability based-on district spatial plan
Enhancing the productivity of small-scale plantations
Revising local regulation on mining activity zone and ensuringFPIC prior to the operation
Preserving essential ecosystems:
Heart of Borneo
Governor Regulation No. 67 of 2012 on the Protection of SangkulirangMangkalihat Karst Ecosystem 1.8 million ha
+MRV System
Will be developed based on:
Indonesian National Carbon Accounting System (INCAS)
National Inventory System of Greenhouse Gases (SIGN SMART)
The East Kalimantan MRV System will cover 5 sub-systems:
Deforestation monitoring sub-system
Land cover change monitoring sub-system
Emission factor sub-system
Terrestrial and spatial database sub-system
Safeguard information sub-system
+Benefit Sharing Mechanism
The availability of local regulations to back up the benefit
sharing mechanisms
Stakeholders to be involved:
Provincial government
District government
Village government
Forest Management Unit (KPH)
Community-based forest management
Companies
+What’s Next?
Establishing a task force for developing CF-based ER Program by the 3rd week of October
Revising the ER-PIN and produced an Indonesian version of ER-PIN 2nd week of November
Public Consultation to comment on the revised ER-PIN 5 districts that have been excluded will also be invited 3rd week of November
Revised ER-PIN are ready to be translated 30 November
The English version of ER-PIN is reviewed first week of December
17 December: Submission date
+A Proposed Time Line of Indonesian
Carbon Fund
20162015 20182017 2019 2020
MRV and
ER
Payment
Dec
2021
Emissions
Reduction
Program
Document
(ER-PD)
Submitted
Mar 2017
Emissions
Reduction
Payment
Agreement
(ERPA)
Signed
Dec 2017
ERPA ImplementationERPA SubmissionER-PIN
Submission
ER-PD Development
Readiness Investment
REVISED
ER-PIN
Submitted
December
2015
Letter
of Intent
Signed
Feb 2016R-Package
Submitted
Mar 2016
2021
+
Thank You
Terima