ID Task Mode Task Name Duration Start Finish
1 PASS Project 84 days? Mon 5/4/15 Thu 8/27/15
2 Initialize 2 days Mon 5/4/15 Tue 5/5/15
3 Business case 2 days Mon 5/4/15 Tue 5/5/15
4 Milestone: Business Case Approved 0 days Tue 5/5/15 Tue 5/5/15
5 Planning 3 days? Wed 5/6/15 Fri 5/8/15
6 Project charter 1 day? Wed 5/6/15 Wed 5/6/15
7 Project plan 2 days Thu 5/7/15 Fri 5/8/15
8 Milestone: Planning Complete 0 days Fri 5/8/15 Fri 5/8/15
9 Analyze 10 days Mon 5/11/15 Fri 5/22/15
10 User requirements report 10 days Mon 5/11/15 Fri 5/22/15
11 Interview users 5 days Mon 5/11/15 Fri 5/15/15
12 Document requirements 5 days Mon 5/18/15 Fri 5/22/15
13 Milestone: Users sign off on requirements
0 days Fri 5/22/15 Fri 5/22/15
14 Milestone: Analysis complete 0 days Fri 5/22/15 Fri 5/22/15
15 Design 14 days Mon 5/25/15 Thu 6/11/15
16 Logical Design 5 days Mon 5/25/15 Fri 5/29/15
17 Data flow diagrams 5 days Mon 5/25/15 Fri 5/29/15
18 Physical Design 9 days Mon 6/1/15 Thu 6/11/15
19 Interface design 9 days Mon 6/1/15 Thu 6/11/15
20 Database design 8 days Mon 6/1/15 Wed 6/10/15
21 Milestone: Design Complete 0 days Thu 6/11/15 Thu 6/11/15
22 Construction 26 days Fri 6/12/15 Fri 7/17/15
23 Create database 10 days Fri 6/12/15 Thu 6/25/15
24 Create user interface 11 days Fri 6/12/15 Fri 6/26/15
Matthew Watson
5/5
Rei Jimenez
Jimmy Huver
5/8
Kris Velazquez
Sophie Patterson
S S M T W T F S S M
Apr 26, '15 May 3, '15 May 10, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Deliverable 7
Date: Thu 3/19/15
ID Task Mode Task Name Duration Start Finish
25 Program system functions 15 days Mon 6/29/15 Fri 7/17/15
26 Milestone: System Constructed 0 days Fri 7/17/15 Fri 7/17/15
27 Testing 13 days Mon 7/20/15 Wed 8/5/15
28 Test Plan 10 days Mon 7/20/15 Fri 7/31/15
29 Create test plan 4 days Mon 7/20/15 Thu 7/23/15
30 Approve test plan 2 days Fri 7/24/15 Mon 7/27/15
31 Test system 4 days Tue 7/28/15 Fri 7/31/15
32 Milestone: System Functioning 0 days Fri 7/31/15 Fri 7/31/15
33 Analyze Test 3 days Mon 8/3/15 Wed 8/5/15
34 Evaluate test results 2 days Mon 8/3/15 Tue 8/4/15
35 Approve results 1 day Wed 8/5/15 Wed 8/5/15
36 Milestone: Test Approved 0 days Wed 8/5/15 Wed 8/5/15
37 Milestone: Testing Complete 0 days Wed 8/5/15 Wed 8/5/15
38 Implementation 10 days Thu 8/6/15 Wed 8/19/15
39 Training 10 days Thu 8/6/15 Wed 8/19/15
40 Plan training classes 3 days Thu 8/6/15 Mon 8/10/15
41 Hold training classes 7 days Tue 8/11/15 Wed 8/19/15
42 Conversion Plan 4 days Tue 8/11/15 Fri 8/14/15
43 Install system 4 days Tue 8/11/15 Fri 8/14/15
44 Milestone: System Installed 0 days Fri 8/14/15 Fri 8/14/15
45 Close Project 8 days Mon 8/17/15 Wed 8/26/15
46 Contract closure 1 day Mon 8/17/15 Mon 8/17/15
47 Administrative closure 3 days Tue 8/18/15 Thu 8/20/15
48 Documentation 2 days Tue 8/18/15 Wed 8/19/15
S S M T W T F S S M
Apr 26, '15 May 3, '15 May 10, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Deliverable 7
Date: Thu 3/19/15
ID Task Mode Task Name Duration Start Finish
49 Archiving 1 day Thu 8/20/15 Thu 8/20/15
50 Final acceptance 1 day Fri 8/21/15 Fri 8/21/15
51 Project Evaluation 3 days Mon 8/24/15 Wed 8/26/15
52 Evaluate project team 1 day Mon 8/24/15 Mon 8/24/15
53 Lessons learned 1 day Tue 8/25/15 Tue 8/25/15
54 Best practices 1 day Wed 8/26/15 Wed 8/26/15
55 Milestone: Project Closure 1 day? Thu 8/27/15 Thu 8/27/15
56 Milestone: Close Project Team 0 days Thu 8/27/15 Thu 8/27/15
57 Milestone: Project Completed 0 days Thu 8/27/15 Thu 8/27/15
S S M T W T F S S M
Apr 26, '15 May 3, '15 May 10, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Deliverable 7
Date: Thu 3/19/15
Matthew Watson
5/5
Rei Jimenez
Jimmy Huver
5/8
Kris Velazquez
Sophie Patterson
5/22
5/22
Yan Lang
Kris Velazquez
Yan Lang
6/11
Matthew Watson,Jimmy Huver
Kris Velazquez
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
May 10, '15 May 17, '15 May 24, '15 May 31, '15 Jun 7, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 4
Project: Deliverable 7
Date: Thu 3/19/15
Jimmy HuverM T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
May 10, '15 May 17, '15 May 24, '15 May 31, '15 Jun 7, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 5
Project: Deliverable 7
Date: Thu 3/19/15
M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
May 10, '15 May 17, '15 May 24, '15 May 31, '15 Jun 7, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 6
Project: Deliverable 7
Date: Thu 3/19/15
Kris Velazquez
Sophie Patterson
5/22
5/22
Yan Lang
Kris Velazquez
Yan Lang
6/11
Matthew Watson,Jimmy Huver
Kris Velazquez
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 7
Project: Deliverable 7
Date: Thu 3/19/15
Jimmy Huver
7/17
Sophie Patterson
Matthew Watson
Sophie Patterson,Yan Lang
7/31
Rei Jimenez
Matthew Watson
8/5
8/5
Sophie Patterson
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 8
Project: Deliverable 7
Date: Thu 3/19/15
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
Jun 7, '15 Jun 14, '15 Jun 21, '15 Jun 28, '15 Jul 5, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 9
Project: Deliverable 7
Date: Thu 3/19/15
Kris Velazquez
Yan Lang
6/11
Matthew Watson,Jimmy Huver
Kris Velazquez
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 10
Project: Deliverable 7
Date: Thu 3/19/15
Jimmy Huver
7/17
Sophie Patterson
Matthew Watson
Sophie Patterson,Yan Lang
7/31
Rei Jimenez
Matthew Watson
8/5
8/5
Sophie Patterson
Matthew Watson,Sophie Patterson
Yan Lang
8/14
Rei Jimenez
Jimmy Huver
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 11
Project: Deliverable 7
Date: Thu 3/19/15
Sophie Patterson
Matthew Watson
Matthew Watson
Jimmy Huver,Kris Velazquez,Rei Jimenez
Jimmy Huver,Kris Velazquez,Rei Jimenez
8/27
8/27
W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T
Jul 5, '15 Jul 12, '15 Jul 19, '15 Jul 26, '15 Aug 2, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 12
Project: Deliverable 7
Date: Thu 3/19/15
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 13
Project: Deliverable 7
Date: Thu 3/19/15
Jimmy Huver
7/17
Sophie Patterson
Matthew Watson
Sophie Patterson,Yan Lang
7/31
Rei Jimenez
Matthew Watson
8/5
8/5
Sophie Patterson
Matthew Watson,Sophie Patterson
Yan Lang
8/14
Rei Jimenez
Jimmy Huver
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 14
Project: Deliverable 7
Date: Thu 3/19/15
Sophie Patterson
Matthew Watson
Matthew Watson
Jimmy Huver,Kris Velazquez,Rei Jimenez
Jimmy Huver,Kris Velazquez,Rei Jimenez
8/27
8/27
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F
Aug 2, '15 Aug 9, '15 Aug 16, '15 Aug 23, '15 Aug 30, '15
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 15
Project: Deliverable 7
Date: Thu 3/19/15