STRUCTURE
• In-situ re-inforced Concrete structure
• Regular column spacing
• Hotel use required cellular floor plan
• Change of use= reduced floor loading
• Basement with retaining walls on 3 sides
• Approx 6000 Tonnes of concrete
Structure
Embodied Energy
Existing Frame
Cast concrete= 1.3MJ/kg
6000 tonnes= 7,800,000 MJ
7,800,000 MJ= 2,166 Mwh
Existing + Replacement Frame= say 4,300 Mwh
Estimated heating requirement for new building: 68 Mwh per annum
Energy saved by retaining existing frame would heat the building for 63 years
8 Tonne Skip
750 Skips
1500 Trips to Landfill