![Page 1: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/1.jpg)
© Copyright NorthConnect KS - All rights reserved.
1 24.08.2018 RFU – Re-issued for Use FIH ECB,GMC,JOA RIB
0 06.08.2018 IFU- Issued for Use FIH ECB,GMC,JOA RIB
A 04.07.2018 IFR- Issued for Review FIH ECB,GMC,JOA RIB
Revision Issue Date Reason for Issue / Change Author Reviewer Approver
HVDC Cable Infrastructure –
UK Construction Method Statement
Document Originator Project Name: NorthConnect
Total Pages
NorthConnect KS
NCT Document Number
Originator Logo NCGEN-NCT-X-RA-0002
30
![Page 2: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/2.jpg)
NORTHCONNECT PROJECT
Page : 2 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
REVISION RECORD
Rev. No.
Date Section(s) Page(s) Change
A 04.07.18 All All Initial Draft
0 06.08.18 All All Updated with reviewer comments
1 24.08.18 4.4 18 Clarification that Remedial Rock Placement in STW will be 5-10%
![Page 3: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/3.jpg)
NORTHCONNECT PROJECT
Page : 3 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
TABLE OF CONTENTS 1. ABBREVIATIONS ............................................................................................................................................... 4 2. PROJECT DESCRIPTION ..................................................................................................................................... 5 3. PURPOSE OF THIS DOCUMENT ......................................................................................................................... 6 4. CABLE INFRASTUCTURE DESCRIPTION .............................................................................................................. 6
4.1 HVDC Onshore Cables .............................................................................................................................. 6 4.2 Landfall Horizontal Directional Drill (HDD) ............................................................................................... 8 4.3 HVDC Offshore Cables .............................................................................................................................. 8
4.3.1 Cable Protection ................................................................................................................................ 8 4.3.2 Crossings .......................................................................................................................................... 11 4.3.3 Cable Installation Techniques .......................................................................................................... 18
4.4 Rock Placement...................................................................................................................................... 18
5. CONSTRUCTION ACTIVITIES ............................................................................................................................ 20
5.1 Onshore Enabling Works ........................................................................................................................ 20 5.1.1 Fencing ............................................................................................................................................ 20 5.1.2 Landfall HDD Preparations .............................................................................................................. 20 5.1.3 Cable Duct Installation ..................................................................................................................... 20
5.2 Onshore Cable Installation ..................................................................................................................... 21 5.2.1 Trench Digging ................................................................................................................................. 21 5.2.2 Joint Pit Formation .......................................................................................................................... 21 5.2.3 Road Crossing HDD .......................................................................................................................... 21 5.2.4 Cable Laying/Pulling ........................................................................................................................ 22 5.2.5 Trench Infilling ................................................................................................................................. 22
5.3 Landfall HDD .......................................................................................................................................... 22 5.3.1 Site Set-Up ....................................................................................................................................... 22 5.3.2 Pilot Hole Drilling ............................................................................................................................. 23 5.3.3 Casing .............................................................................................................................................. 23 5.3.4 Drilling Fluid ..................................................................................................................................... 23 5.3.5 Reaming ........................................................................................................................................... 24 5.3.6 Pilot Hole Exit .................................................................................................................................. 24 5.3.7 Duct Installation .............................................................................................................................. 24
5.4 Offshore Preparations ............................................................................................................................ 25 5.4.1 Pre-Lay Survey ................................................................................................................................. 25 5.4.2 Sea Trials .......................................................................................................................................... 26 5.4.3 Seabed Preparation ......................................................................................................................... 26 5.4.4 Pre-Trenching .................................................................................................................................. 26 5.4.5 Crossing Rock Placement ................................................................................................................. 27
5.5 Marine Cable Pull ................................................................................................................................... 27 5.5.1 Seabed Preparations........................................................................................................................ 27 5.5.2 Cable Pull ......................................................................................................................................... 27
5.6 Onshore Demobilisation and Reinstatement ......................................................................................... 28
5.7 Offshore Cable Installation ..................................................................................................................... 28 5.7.1 Cable Laying ..................................................................................................................................... 29 5.7.2 Cable Installation Survey/ As-laid Survey ........................................................................................ 29 5.7.3 Post Cable Trenching ....................................................................................................................... 29 5.7.4 Trenching Survey ............................................................................................................................. 29 5.7.5 Cable Joints ...................................................................................................................................... 29 5.7.6 Rock Placement ............................................................................................................................... 29 5.7.7 Rock Placement Survey ................................................................................................................... 30 5.7.8 Post Installation Survey/As-Built Survey ......................................................................................... 30
5.8 Reporting ............................................................................................................................................... 30
6. REFERENCES ................................................................................................................................................... 30
![Page 4: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/4.jpg)
NORTHCONNECT PROJECT
Page : 4 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
1. ABBREVIATIONS
CBRA Cable Burial Risk Assessment CPAR Cable Protection Analysis Report DOL Depth of Lowering DOB Depth of Burial EIAR Environmental Impact Assessment Report HDD Horizontal Directional Drill HVDC High Voltage Direct Current JV Joint Venture KP Kilometer Point MBES Multi-beam Echo Sounder MI Mass Impregnated MW Mega Watt OOS Out of Service OSL Original Sea Level ROV Remote Operated Vehicles SBP Sub-bottom Profiler SSS Side Scan Sonar STW Scottish Territorial Waters TW Trench Width UKEEZ United Kingdom Exclusive Economic Zone UXO Unexploded Ordinance
![Page 5: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/5.jpg)
NORTHCONNECT PROJECT
Page : 5 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
2. PROJECT DESCRIPTION NorthConnect is a project set up to develop, consent, build and operate an HVDC electrical interconnector between Peterhead in Scotland and Simadalen in Norway. The 665km long, 1400MW interconnector will provide an electricity transmission link allowing the two nations to exchange power and increase use of renewable energy. The intention is for the HVDC interconnector to be operational by 2023. NorthConnect is a Joint Venture (JV) project company owned by four community and state-owned partners from Norway and Sweden: Agder Energi AS, E-CO Energi AS, Lyse Produksjon AS, and Vattenfall AB. The partnership was established on 1st February 2011. Figure 2.1 details the main elements of the project, however this document focuses on the HVDC cabling and associated infrastructure from the UK Converter Station Building to the limits of the UK Exclusive Economic Zone (UKEEZ).
Figure 2.1: Main Project Elements
The Scottish Converter Station is located at a site called Fourfields, which is approximately 2.6km south of the outskirts of Peterhead, 4.5km south of Peterhead town centre, and 1km southwest of the village of Boddam. The Fourfields site is located to the south of Lendrum Terrace and Highfield, east of the Den of Boddam, Sandfordhill and Denhead and west of the Hill of Boddam and Stirling Hill Quarry. The cable landfall site is at Long Haven Bay, to the south of the village of Boddam and east of the village of Longhaven. The onshore cable corridor links the landfall site to the Converter Station at Fourfields. The marine cable consenting corridor heads north-easterly for approximately 7nautical miles (NM) then in an east-north-east direction across the North Sea towards the Norwegian Coast. The corridor has been specifically selected taking account of:
• Existing infrastructure including pipelines, cables, and offshore installations;
• Bathymetry;
• Seabed geology and sediment characteristics;
• Commercial fisheries, shipping and navigation;
• Cultural heritage and marine archaeology;
• Benthic ecology and habitat types; and
• Designated sites and protected habitats. As such the consenting corridor is not a straight route and although the majority of it is 500m wide, the width varies to avoid features such as wrecks and to provide additional options for routing in challenging areas such as areas of large sand-waves.
![Page 6: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/6.jpg)
NORTHCONNECT PROJECT
Page : 6 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
3. PURPOSE OF THIS DOCUMENT
This document sets out the Construction Method Statement for the installation of the HVDC and Fibre Optic Cables from the Converter Station Building to the limits of the UKEEZ. The purpose of the document is to provide a sufficient understanding of construction methods for regulators and stakeholders, to inform their consideration of the planning consent and marine license applications.
4. CABLE INFRASTUCTURE DESCRIPTION
There will be two HVDC cables connecting the Converter Stations in Fourfields and Simadalen. To provide process controls there will also be a fibre optic cable connection, which will follow the same route as the HVDC cables from Fourfields to the entrance of the Norwegian Fjord network. The fibre optic cable will not have any repeaters within the marine environment, and is landed at the Norwegian coastline, where it will connect into the wider Norwegian fibre optic network. The landing point at Long Haven Bay is a cliff and, as such, the Horizontal Directional Drill (HDD) will be required to allow the cables to be pulled under the cliff onto shore, this is known as the Landfall HDD. Similarly, HDD will be utilised to pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ will be installed within the confines of the NorthConnect Consenting Corridor, as shown in the following drawings:
• NCFFS-NCT-X-XG-0001-01;
• NCOFF-NCT-X-XG-0001-01;
• NCOFF-NCT-X-XG-0001-02;
• NCOFF-NCT-X-XG-0001-03; and
• NCOFF-NCT-X-XG-0001-04. Further information with regard to the UK Onshore Cables and the Marine Cables is provided in this section.
4.1 HVDC Onshore Cables
There will be two HVDC cables, and one ducted fibre optic cable. The exact cable details will depend on which specialist cable manufacturer is involved, but the HVDC cables used will be Mass Impregnated (MI) in design. There are several different options for cabling, but the indicative cable parameters are shown in Table , using values assessed in similar HVDC projects and from cable manufacturers.
Table 4.1 Indicative HVDC Cable Parameters
Cable Parameter Quantity
HVDC export system 2 x 700 MW HVDC cables
Nominal voltage (kV) ±525
HVDC onshore cable route length (km) 2
Cable linear weight (kg/m) 52 (approximately)
Cable outer diameter (mm) 130 (approximately)
Cable minimum bending radius (m) 5
Cable duct outer diameter (mm) 400
Cable maximum pulling tension (kN) 315
Fibre optic linear weight (kg/m) 1.6
Fibre optic cable outer diameter (mm) 24-30
Fibre optic minimum bending radius (m) <1
Fibre optic duct outer diameter (mm) 90
Cable trench depth onshore (m) 1.6
![Page 7: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/7.jpg)
NORTHCONNECT PROJECT
Page : 7 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Further detail on the HVDC Cable is provided in Chapter 2 of the HVDC Cable Infrastructure Environmental Impact Assessment Report (EIAR) (NorthConnect, 2018a). The fibre optic cable is likely to be armoured with layers of steel wire and sheathed with either a polypropylene or polyethylene material for outer protection. The onshore cable consenting corridor is wider than the actual onshore cable construction corridor required to allow for micro routing during detailed design. The actual construction corridor will include space for access along the route for excavation of cable and drainage trenches, storage of topsoil and soil from the trenches, delivery of materials and transport of personnel, excavation and cable installation plant and equipment. An overview of the onshore consenting corridor and indicative cable routes is provided in Drawing NCGEN-NCT-Z-XE-0002-01, with additional indicative detail provided in Drawings NCGEN-NCT-Z-XD-0001-01 to -04. From Joint Pit 1 to the converter station it is assumed that the onshore HVDC cables will be laid within one trench. The width of the cable construction corridor for this section is likely to be around 20m (10m access road, 10m trench plus soil storage). From the Landfall HDD entrance to the Joint Pit 1 it is assumed the HVDC cables will be laid in two separate trenches. For this section, the construction corridor would be 30m (10m access road and 2 x 10m trenches plus soil storage). The onshore cables trench will be approximately 1.3m deep and 4.5m wide, with an approximate distance of 1m between the two HVDC cables if both cables are within a single trench (Drawing NCGEN-NCT-Z-XE-0003-01). For a two-trench design there will be a separation of approximately 3m between the two trenches and 7m between the two cables (Figure 4.1). The depth of the cables are such that arable farming techniques can be employed in the reinstated fields without risk of interaction with the cables.
Figure 4.1: Onshore Cable Trench Cross-section a Two-Trench Design
Onshore HVDC Cables have a different armour protection composition to offshore cables, so there will be a joint pit (Jointing Pit 1) approximately 450m from the landing point to the south of the disused railway, where the transition between the two cable types will be located. Limitations on the maximum length of onshore HVDC cable that can be delivered means the maximum deliverable cable lengths are likely to be in the range of 850m – 1000m. As the proposed route is approximately 2km, a second onshore HVDC cable joint pit will be required to join the sections of onshore HVDC cables. Jointing Pit 2 will be located just to the south of Fourfields (Drawings NCGEN-NCT-Z-XD-0001-02 and NCGEN-NCT-Z-XD-0001-03).
Both jointing pits are expected to be approximately 25m long by 6m wide. Each cable will be under a precast concrete slab located at least 1 m below surface level (Drawing NCGEN-NCT-Z-XE-0003-01). The ground over a joint pit will be re-instated following the completion of the joints, such that farming activities can be resumed. In event of access to the joint be being required, the ground would be dug out to allow the concrete slab to be removed and access to the cable gained. To avoid disruption to users of the A90 trunk road and to avoid disturbing the disused railway line, HDD will be utilised. The entry point will be on the southeast of the A90 next to Joint Pit 1 as shown in Drawing NCGEN-NCT-Z-XD-0001-02.
![Page 8: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/8.jpg)
NORTHCONNECT PROJECT
Page : 8 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
The HVDC cables pass under the landscape bunds around the converter station into the converter station site. The actual location will be determined by the final converter station design; however, it is likely that the cables will need to come into the site below the converter station platform. Depending on where the cables enter this may be 8 to 17m below the existing ground level, and 20m or greater below the final ground level when landscape bunds are installed. An indicative layout is provided in Drawing NCGEN-NCT-Z-XE-0004-01.
4.2 Landfall Horizontal Directional Drill (HDD)
The marine cables will be pulled ashore through ducts which will be installed into holes drilled from a point 100-120m inland from the cliffs, and under the cliffs with a marine exit point approximately 190m offshore from the cliffs. There will be 3 boreholes drilled: one for each of the HVDC cables; and one for the fibre optic cable. However, all three holes will be drilled to a diameter suitable for an HVDC cable. This is to provide redundancy such that, if there is an issue with one of the HVDC ducts preventing the cable pull, there is a backup route available. In this instance the fibre optic would be bundled with an HVDC cable for pulling. Further detail is shown in Drawing NCGEN-NCT-Z-XD-0001-01.
4.3 HVDC Offshore Cables
4.3.1 Cable Protection
The HDD marine exit point is located in water depths of approximately 26m. The fibre optic cable will be routed towards one of the marine HVDC cables and bundled with it for the remainder of the route. It is assumed that the two HVDC cables will be installed separately, there is however a potential that they could be bundled together and laid in the same trench. To protect the cable from damage the cable will be buried or protected by rock placement for the entire cable route. To identify the level of protection required, taking into account the various threats to the cable a Cable Burial Risk Assessment (CBRA) has been completed and provided as Appendix 1 to this document. The CBRA took into account the understanding of the seabed conditions gained by the completion of the subsea survey, primary hazards including: shipping, anchorages, fishing, on-bottom stability, dredging /spoil dumping; and with particular regard to the Norwegian waters and fjords: fish farming, rockfall and submarine slopes and slide escarpments. The secondary hazard of mobile sediments was also considered. The assessment considers sections of the corridor split by sediment types based on the survey results from the centre line of the survey corridor. The CBRA was utilised to inform the protection level required by the NorthConnect project to reduce risk of cable damage to a sufficient level. The protection levels were split into four categories A to D. Cables can be protected in four main ways:
1. They can be laid on the seabed then post-lay trenched into place, the depth the cable ends up lower than the original seabed level (OSL) is called the Depth of Lowering (DOL). The seabed material will naturally infill, the extent of which will be determined by the seabed composition, as shown in Figure 4.2.
2. The cable can be laid directly onto the seabed and rock placed on to the cable to provide protection as shown in Figure 4.3.
3. Rock can also be utilised in conjunction with trenching, where trenching has not provided a sufficient DOL as shown in Figure 4.4.
4. Pre-lay trenching can be utilised where post-lay trenching is unlikely to provide sufficient DOL to minimise the need for above OSL rock placement. However, in seabed types where this is likely to be the case, natural backfill may be slow and as such forced backfill may be required. To prevent damage to the cable from backfill ploughing, then backfill rock placement is the preferred means, to bury the cable up to OSL. The use of backfill augers or inverted plough to provide forced backfill may be considered by NorthConnect, only if the installation contractor can demonstrate relevant experience records and/or sea trials show that the cable is not jeopardised by the technique.
For the purpose of marine licencing it has been assumed that where pre-lay trenching is utilised backfill rock placement will be required to protect the cable, but that this will not be above OSL. Material removed from the trench by pre-lay trenching may form berms either side of the trench, but these will naturally disperse with time.
![Page 9: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/9.jpg)
NORTHCONNECT PROJECT
Page : 9 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 4.2: Typical Post Lay Trench Cross Profile
Where: DOL: Depth of Lowering: Distance from the top of the cable to original seabed. DOB: Depth of Burial: Distance from top of cable to the lowest point on any forced or natural backfill. TW: Trench Width: Width of trench on top of trench. Top of trench is measured at mean undisturbed seabed
level. Any trench side beads shall not be accounted for.
Figure 4.3: Typical Cross Profile of Protection by Rock Placement Only.
Where: DOB: Depth of Burial: Distance from top of the berm to top of the cable.
Figure 4.4: Remedial Rock Placement where Trenching is Insufficient
Where: DOB: The sum of the backfill of seabed material and additional protection provided by rock placement.
The preference is to lower the cable as far as practicable, the minimum DOL that the cable lay contractors will be expected to achieve for each of the categories A to D identified in the CBPA is detailed in Table 4.2.
![Page 10: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/10.jpg)
NORTHCONNECT PROJECT
Page : 10 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Table 4.2: Definition of Acceptance DOLs for Protection Levels A-D.
Protection Level
ACCEPTANCE CRITERIA
Trenching
Soft seabed Hard seabed
A DOL = 0m DOL = 0m
B DOL≥0.5m DOL≥0.4m
C DOL ≥1.0m DOL ≥0.8m
D DOL ≥1.5m DOL ≥1.3m
However, it is recognised that there may be localised features of the seabed which affect the ability to lower the cable, therefore if the target DOL is not achieved, the following will apply:
• There have been three attempts to trench the cable with: o Correct trencher settings during all 3 attempts, and o All trencher functions in order.
• The maximum length of each section is no more than 20m.
• The maximum accumulated length of sections is no more than 100m/km. Then the DOL may be reduced to those identified in Table 4.3. Table 4.3: Relaxed Acceptance DOLs for Protection Levels A-D.
Protection Level
ACCEPTANCE CRITERIA
Trenching
Soft seabed Soft seabed
A n/a n/a
B DOL≥0.3 DOL≥0.2
C DOL>0.5 DOL ≥0.4
D DOL ≥1.0 DOL ≥0.8
Where the DOL detailed in Table 4.2 and 4.3 are not achieved there will be a need for above OSL rock placement as shown in Figure 4.4. Where the seabed is rock, and hence the cable cannot be lowered, then rock placement will have to be utilised as shown in Figure 4.3. To protect the cables whether they are lowered or not they will need to be buried to provide the appropriate protection. The DOB may be achieved by: natural infill of the trench; backfill rock placement to OSL where DOL has been achieved but natural infill will not provide sufficient DOB; or where DOL has not be achieved rock placement including some above OSL. The DOB required for each of the protection levels are detailed in Table 4.3.
![Page 11: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/11.jpg)
NORTHCONNECT PROJECT
Page : 11 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Table 4.3: Definition of Burial Levels
Protection Level
ACCEPTANCE CRITERIA
DOB
Normal (Note 1 & 2)
Relaxed Lowering Levels (Note 1)
A DOB = 0m
B DOB ≥0.4 m DOB ≥0.2
C DOB ≥0.8m DOB ≥0.4
D DOB ≥1.3m DOB ≥0.8
Note: DOB = natural back fill + backfill rock /rock placement. If DOL is as defined in Table 4.2 and the Trench Width > 1.2 x DOL, then DOB ≥ 0.5xDOL is acceptable.
Protection Level C is required for all cables within STW and UKEEZ other that than the initial 750m section from the HDD marine exit point where protection level D is required. This is not due to an increase risk to the cable, but due to a desire to increase the distance between the cable and vessels to reduce the effects of compass deviation in shallow waters to acceptable levels. As such, the lowest DOL below the seabed in STW and UKEEZ is 0.4m and this is should occur for no more an 10% of the cables length. The majority of the route ≥90% of the route will be lowered and/or buried by at least 0.8m. The only area of bedrock within the STW/UKEEZ consenting corridor is very close to shore and the cable will be pulled under this through the HDD ducts. It is not anticipated that any sections of the cables within the UK consenting corridor; not associated with crossings; will be laid directly on the seabed and protected solely by rock placement, as per Figure 4.3.
4.3.2 Crossings
There are 20 items of infrastructure within the cable corridor which will need to be negotiated in STW/UKEEZ:
• 1 x power cable crossing;
• 10 x in-service pipeline crossings;
• 2 x in-service umbilical crossings;
• 2 x Out of Service (OOS) telecom cable crossings;
• 1 x OOS umbilical crossing; and
• 4 x OOS service pipelines.
Sections of out of service telecommunications cables will be removed, and as such there will be 18 crossings required. Figure 4.5 shows the locations of the 20 existing subsea assets that are crossed by the consenting corridor, while Drawing NCOFF-NCT-X-XG-0008-01 shows the locations of the asset crossing which will require above OSL rock protection.
![Page 12: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/12.jpg)
NORTHCONNECT PROJECT
Page : 12 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 4.5: Crossing Locations
The crossing designs and methodology will be in accordance with crossing agreements with the respective crossed asset owner. The descriptions below must therefore be regarded as indicative only. The crossings shall be treated individually during detailed design considering aspects such as regional constraints, requirements from the crossed infrastructure owner, practicalities regarding trenching near the crossing, volume of rock ramps, stability, and top cover. The angle between the NorthConnect HVDC cables and the crossed utility shall be as close to 90 degrees as practicable and not be less than 45 degrees for a distance of minimum 200 m from the crossed asset. NorthConnect has defined 4 standard types of crossings which form the basis for the planning of further work unless other designs are required by the crossed infrastructure owner. Relevant typical crossings are illustrated in the drawings shown in Figures 4.6-4.10:
• Crossing Design A - Crossing Untrenched Pipeline
• Crossing Design B - Crossing Trenched Pipeline
• Crossing Design C - Crossing Untrenched Umbilical or Cable
• Crossing Design D - Crossing Trenched Umbilical or Cable Some small diameter pipelines, such as glycol lines, may best be crossed according to design C or D. At crossing of trenched or un-trenched umbilicals or cables a separation is maintained by means of adding a protection sleeve of type Uraduct, or similar onto the NorthConnect cables. The sleeve will have a length of minimum 20 m and be fitted to the NorthConnect cables during lay. Protection sleeves may be required also on pipeline crossings pending agreement with the crossed pipeline owner. If the crossed infrastructure has such high temperature that it might result in a thermal bottle neck in the NorthConnect cables, the separation must be increased. This will be carried out either by means of additional rock placement or,
![Page 13: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/13.jpg)
NORTHCONNECT PROJECT
Page : 13 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
alternatively, by other means such as mattresses. The rock protection on the top will be according to the general requirements to protection in the area. Trenching near the crossing will be carried out according to agreement with crossed asset owner.
Figure 4.6: Crossings Design A - Crossing Untrenched Pipeline
![Page 14: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/14.jpg)
NORTHCONNECT PROJECT
Page : 14 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 4.7: Crossings Design B - Crossing Trenched Pipeline
![Page 15: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/15.jpg)
NORTHCONNECT PROJECT
Page : 15 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 4.8: Crossing Design C1 – Crossing Untrenched Cable – Protection Sleeve for Separation
![Page 16: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/16.jpg)
NORTHCONNECT PROJECT
Page : 16 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 4.9: Crossing Design C2 – Crossing Untrenched Cable – Rock Ramp for Separation
![Page 17: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/17.jpg)
NORTHCONNECT PROJECT
Page : 17 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 4.10: Crossing Design D – Crossing Trenched Cable – Using Protection Sleeve only
To ensure that the asset being crossed is not damaged during the HVDC Cable installation, trenching will not be carried out within the vicinity of the crossing. The distance from the asset to be crossed to the point the trenching will cease is based on the risk posed by the technique employed for:
• A trencher towed by a surface vessel: there shall be no trenching closer than 250 m from the crossing point
• Self-tracked mechanical cutting devices: there shall be no trenching closer than 50 m from the crossing location.
• A self-propelled trencher that use water jetting to excavate the trench and is designed such that there are negligible or no risk for damaging the crossed cable by interaction: there shall be no trenching closer than 15 m from the crossing location.
The distances above may vary to meet requirements of the owner of the crossed infrastructure.
![Page 18: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/18.jpg)
NORTHCONNECT PROJECT
Page : 18 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
4.3.3 Cable Installation Techniques
The CBRA and associated protection levels have then been utilised in the Cable Protection Analysis Report (CPAR) (Appendix 2) which considers the techniques that could be employed to provide the desired protection levels along the cable route. The five tools considered for cable installation are:
• Jet trencher
• Chain Cutter
• Combined Jet/Chain Cutting tool
• Pre-lay Plough
• Cable Burial Plough Section 4.2 and Appendix D1.2 of the CBRA provide information about each of the installation tools. The effectiveness of each of the tools with regard to meeting the cable protection areas along the cable corridor is graded as ‘A to C’ in APPENDIX B. ‘A’ denotes that the tool should achieve the required depths across the section and ‘C’ denotes that the tool is inappropriate for the expected soil conditions (See Section 4.4.2 of the CPAR for full definitions). Drawings NCOFF-NCT-X-XG-0006-01, NCOFF-NCT-X-XG-0007-01, and NCOFF-NCT-X-XG-0008-01 show the grading of each of the tools within the different sections of the consenting corridor. It is anticipated that for the majority of the cable route (~97%), jet trenching will be suitable and enable the target protection levels to be achieved. However, in areas of dense boulders (and potentially dense subsurface boulders), tills and coarse surficial sediments, pre-lay ploughing may offer a lower risk solution with greater potential for achieving the necessary target trench depths. In STW/UKEEZ the main area where jet trenching may not be suitable is between 213564E, 6378161N and 228191E and 6389279N. This is the majority of the route within STW. NorthConnect wish to keep the range of permitted cable installation tools as wide as possible to facilitate competition from potential cable contractors, however the contractors will be required to meet the protection levels outlined in Section 4.3.1. Cable contractors will be required to carry out sea trials, to demonstrate that they can achieve the required levels of protection in the more challenging substrates, prior to their methodology being accepted by the project.
4.4 Rock Placement
Rock placement is required for crossings as discussed in Section 4.3.2. It will also be required to protect cables by increasing the DOB. The amount of rock required will be determined by the cable installation method utilised. The two options utilised to calculate the rock volumes required were:
• Option 1: Jet Trenching for the full route, which will potentially require remedial rock placement; and
• Option 2: Jet Trenching in combination with Pre-lay Ploughing for the initial section in STW until the seabed conditions makes jet trenching more acceptable. It has been assumed that pre-lay ploughing will require backfill rock placement and a small amount of remedial rock placement.
Drawings NCT-X-XG-0006-01 and NCT-X-XG-0007-01 show the location of potential rock placement for each of the options considered within STW. The two options are the same outwith STW as it is unlikely the Pre-lay Ploughing would be required beyond STW, and the rock placement locations are shown in Drawing NCT-X-XG-0008-01. The main difference between the two options is that the majority of rock utilised for Option 2 is backfill and, as such, will be below OSL, with an estimate of 5 to 10% of the cable lengths within STW requiring remedial rock placement. Whereas the majority of the rock required for Option 1 will be above OSL, with almost 100% of the route within STW requiring remedial rock placement above OSL. In the UKEEZ it is estimated that less than 1% of the route will require remedial rock placement (<2km). The full rock estimate calculations can be found in the CPAR (Appendix F) and these are summarised in Table 4.4. Option 2 requires only 4% more rock volume (3800m3) than Option 1. On the basis that the total rock volumes involved are similar for the two options, and that there is a preference not to change the seabed profile to minimise effects on fishing, either Option 2, or techniques that can achieve a DOL such that remedial rock is not required for the majority of the route, are preferred. Hence, the remedial rock placement above OSL is between 5 and 10% of the route in STW and 1% of the route from 12nm to the limit of the UK EEZ.
![Page 19: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/19.jpg)
NORTHCONNECT PROJECT
Page : 19 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Table 4.4: Rock Volume Estimates
Assessed Length
Remedial rock
placement estimate
(m3)
Backfill estimate
(m3)
Subtotal (m3)
Crossings estimate
(m3)
Theoretical Total (m3)
Total including 40%
contingency factor (m3)
Full Route: Option 1 - Jetting
67600 0 67600 54200 121800 170600
Full Route: Option 2 - Jetting with Pre-lay ploughing KP0.823 - 17.891
21800 48600 70400 54200 124600 174400
KP0 to 12NM limit: Option 1 - Jetting
50400 0 50400 1800 52000 72800
KP0 to 12NM limit: Option 2 - Jetting with pre-lay ploughing KP 0.823 - 17.891
4400 48600 53000 1800 54800 76600
KP0 to UK EEZ limit: Option 1 - Jetting
52400 0 52400 13800 66200 92600
KP0 to UK EEZ limit: Option 2 - Jetting with pre-lay ploughing KP0.823 - 17.891
6600 48600 55200 13800 68800 96400
The anticipated rock grading to be used is 1”-5” (CP45/125mm), with D10 45mm, D50 80mm, D90 125mm, with an installed bulk density of 1.5 – 1.7 tons/ m3. Hence the total rock requirement assuming Option 2 in STW/UKEEZ is 163,880 tonnes.
![Page 20: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/20.jpg)
NORTHCONNECT PROJECT
Page : 20 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
5. CONSTRUCTION ACTIVITIES
The following main construction activities are required to facilitate the installation of the cables:
• Onshore Enabling Works;
• Onshore Cable Installation;
• Landfall HDD;
• Offshore Preparations;
• Marine Cable Pull;
• Onshore Demobilisation and Reinstatement;
• Offshore Cable Installation; and
• Reporting. Further details on each are discussed below. It should be noted that multiple site activities may be ongoing concurrently and that the order of tasks will not be exactly as the activities are laid out below. Details will be determined by the cable contractors’ schedules and logistics but taking account of any schedule constraints.
5.1 Onshore Enabling Works
5.1.1 Fencing
To prevent livestock and members of the public accessing construction areas, security/livestock fencing will be installed around work areas. The intent is not to fence the full onshore consenting corridor for the duration of the works, but rather to fence areas prior to specific access being required. Once works have been completed in an area they will be reinstated to allow fencing to be removed and access to be restored at the earliest convenience.
5.1.2 Landfall HDD Preparations
The HDD landfall area is situated in a field to the south east of the A90, the existing access track to the fields is not of a sufficient standard to be utilised for the HDD and cable installation works. A new access road is proposed to the south of the existing access as detailed within the Transport Statement (Allen and Gordon, 2018). The road will be installed as part of enabling works, most likely through the summer months, such that the ground conditions are favourable for the works and that it is in place to allow HDD activities to be completed through the winter. The road installation will involve the removal of topsoil and subsoil to a suitable depth, which will be retained for reinstatement purposes. The route will be levelled, with geotextile and compacted stone laid to provide appropriate stability. The initial section from the A90 will be tarmacked (at least 50m), with the later sections being finished with crushed stone placed within geogrid to enhance its load bearing capacity. Rumble strips shall be installed on the access road at least 45m before the exit onto the A90 to assist in the removal of mud from wheels. The landfall HDD compound will also need to be prepared and a hardstanding constructed required. The topsoil and subsoil removed from the area will be utilised to form bunds to the north and south of the compound to provide some screening of the worksite in terms of noise and shelter from the winds. The east and westerly sides will need to be kept open to allow the cables to be laid inland to the west, and the HDD works out to the east. A water supply will be required for the HDD works, so a connection will be made from the water main which runs parallel to the A90 on the seaward (south east) side. The temporary water supply will be laid adjacent to the access road.
5.1.3 Cable Duct Installation
The cables will need to be routed such that they enter the Fourfields converter site and building at appropriate locations. The earthworks will be completed prior to the cable installation, as part of the earthworks, ducts will be installed for the cables. This will involve trench excavation the required depths of which will be dependent on the location that the cables are required to enter the converter station building.
![Page 21: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/21.jpg)
NORTHCONNECT PROJECT
Page : 21 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
The onshore HVDC cables have to cross a core path which runs along the south side of the Fourfields site. Hence it is proposed that before the other parallel path (which bisects the Fourfields site) is closed off from public access, cable ducts will be installed under the core path. This will allow the path users to be rerouted during the duct installation via the existing path, and then the core path will be reinstated before the other is closed. The onshore HVDC cables can then be pulled after the construction of the Convertor building with minimal disturbance to the core path users. The duct installation will be a simple excavation of material to allow the ducts to be installed and reinstatement utilising the materials removed as far as practicable, and then appropriate surfacing installed. A water supply is to be provided to the Fourfields site from the south. This pipeline will be installed in advance of the Convertor station construction and cable installation and, as far as practicable, at the same time as the cable ducts under the core path to minimise disruption.
5.2 Onshore Cable Installation
5.2.1 Trench Digging
Topsoil and subsoil will be excavated from the cable trench, these soils will be stockpiled separately within the construction corridor. If rock is incurred prior to the trench depths being achieved it will be broken out. Gaps will be left between the stockpiles so as not to impede the flow of surface water and, where practicable, the stockpiles will be located on the higher ground within the construction corridor, to minimise surface water running over them. The trench depth will be around 1.3m. The cable trench bottom will also have sand protection above the formation level and will need to be cleared of any rocks and boulders which could cause damage to the cables. Where required, the Contractor may need to use appropriate measures to prevent the trench collapsing whilst still open. Concrete water stops will be installed approximately every 100m, to prevent water running through the cable trench. Drainage will be provided within the trench where required and this may include the digging of sumps to allow dewatering pumps to be utilised. If pumping of water is required, it will be pumped to an appropriate location to allow any sediments present to be settled out prior to discharge. Means of escape from the trench in the form of ramps will be provided for mammals to avoid entrapment. As detailed in Chapter 10: Onshore Water Quality of the EIAR (NorthConnect, 2018a) there will be 4 watercourse crossings along the route. The watercourses are all relatively minor. They will be dammed above and below the crossing point, to allow the crossing point to dry out. The water will be pumped from upstream of the crossing point to downstream of the crossing point, such that flows up and downstream of the crossing point are maintained throughout. The cable trench shall be dug, ducts inserted, or cables laid directly in the ground, then the stream bed reinstated, and the dams removed to allow the stream to return to its previous condition.
5.2.2 Joint Pit Formation
The joint pits will be dug as part of the trench digging works discussed in Section 5.2.1. If necessary, the excavated pit will be dewatered. Sand will be utilised to form the cable bed. The cable protection slabs will be pre-cast offsite ready for installation after the cable has been laid.
5.2.3 Road Crossing HDD
5.2.3.1 Site Set-Up
The road crossing HDD will be relatively shallow though still within rock and it may be completed by a smaller HDD Rig than the Landfall HDD, but this will be determined by the cable Contractor. The Road Crossing HDD area will be on the southeast side of the A90 within the consenting corridor. An appropriate hardstanding area will be required, and this will take the form of an engineered hardstanding or, alternatively, construction mats maybe utilised. With either method, the site will be prepared in such a way as to allow the area to be reinstated to original levels once works are complete.
![Page 22: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/22.jpg)
NORTHCONNECT PROJECT
Page : 22 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
5.2.3.2 Pilot Hole Drilling
Prior to drilling, an entry pit will be excavated and generally, this is several metres squared and 1.5m to 2m depth. A pump in the pit transfers any drilling fluid returns to a mud recycling unit. More information on drilling fluid is provided in Section 5.3.4. The pilot holes will be drilled, and downhole positional surveys taken at the end of each drilled rod.
5.2.3.3 Reaming
On completion of the pilot holes, the drill bit, downward motor and steering equipment are removed. The holes are then enlarged using forward reaming. The HDD may require several reaming passes with progressively larger diameter reamers until the final hole size is reached.
5.2.3.4 Duct Installation
Ducts will be pulled through the reamed holes from the north west side of the A90 towards Jointing Pit 1 on the south east side of the A90.
5.2.4 Cable Laying/Pulling
Cables can be laid directly into the open trenches. Where the cables need to cross the A90 and the disused railway line, the cables will be pulled under the A90 and disused railway to Jointing Pit 1 through the ducts installed by the HDD. Similarly, the cable will be pulled through the ducts installed under the core path and in the Fourfields site, this may be done from either end. The sequencing of the cable lay will be determined by the availability of cable and the readiness of the converter station to accept the cable connection. As the offshore cables will be landed at different times as discussed in Section 5.7, then Joint Pit 1 may need to be accessed to allow the marine cables to be joined to the onshore cables at different times. Joint Pit 1 will be made safe in the periods between access being required. This will either be by reinstating the ground above the pit to allow access for agricultural activities, or temporary fencing installed to prevent access. The means will be determined by the programme and hence timescales between access requirements and the landowner’s preferences.
5.2.5 Trench Infilling
It is likely the cable will require a stabilising material, such as sand or cement bound sand (CBS), which will be placed directly over the laid cables. Protective slabs will also be placed over the cables for added protection. The subsoil and topsoil will then be used for backfilling the cable trench, as per the indicative designs shown in Drawing NCGEN-NCT-Z-XE-003-01. Any excess soil will be removed from site and disposed of appropriately. The corridor will be restored back to its original level and condition, and security/livestock fencing removed.
5.3 Landfall HDD
The majority of the landfall HDD drilling works will be carried out through the winter months, avoiding the bird breeding season to minimise effects associated with disturbance.
5.3.1 Site Set-Up
As discussed in Section 5.1, prior to the arrival of the HDD equipment, the vehicle access, drilling pad and working area, and the water supply to the entry site will be prepared. The equipment and welfare facilities will be delivered to the site on appropriate HGV’s or low loaders in line with an agreed traffic management plan. A crane will be utilised to unload equipment from the transport vehicles and place them into position. An indicative site layout is shown in Figure 5.1. The site layout shown has been specifically designed to place the noisiest equipment furthest away from the cliffs. Although the specific equipment utilised will be determined by the cable contractor the approach of locating equipment to minimise noise impacts will be followed.
![Page 23: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/23.jpg)
NORTHCONNECT PROJECT
Page : 23 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 5.1: Indicative Site Set-up for the Landfall HDD
5.3.2 Pilot Hole Drilling
Prior to drilling an entry pit is excavated, generally, this is several metres squared and 1.5m to 2m depth. A pump in the pit transfers any drilling fluid returns to the mud recycling unit. The hole is drilled and downhole positional surveys taken at the end of each drilled rod.
5.3.3 Casing
Surface casing is utilised at the entry points of HDD’s where the material is likely to be more weathered to prevent collapse of the hole. Surface casing may not be required at this site but, if it is, it is likely to only be 10-15m in length and will either be washed over the pilot drill or trenched in prior to pilot drilling. Ideally, the casing will be of a larger diameter than the final reamed hole size.
5.3.4 Drilling Fluid
The primary purpose is to create a thick gel to suspend soil and rock cuttings and carry them out of the hole. In addition, the fluid hydraulically excavates soil in soft ground, powers the downhole motor in hard ground, cools the drilling equipment, clears debris from the drilling bit, seals the perimeter of the borehole in porous ground and lubricates the borehole to reduce friction on the drilling equipment. The drilling fluid, once used, is pumped into a mud recycling unit, Figure 5.2, shows an example drilling fluid recycling unit with hydrocyclones and shaker screens on the upper level and active mud tank underneath. Cleaned drilling fluid is transferred to the active tank ready for circulating back into the hole.
![Page 24: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/24.jpg)
NORTHCONNECT PROJECT
Page : 24 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 5.2: Example Drilling Fluid Recycling Unit
5.3.5 Reaming
On completion of the pilot hole, the drill bit, downward motor and steering equipment are removed. The hole is then enlarged using forward reaming. The HDD will require several reaming passes with progressively larger diameter reamers until the final hole size is reached.
5.3.6 Pilot Hole Exit
Once all reaming is complete the pilot hole is then extended to the exit point. This is a key point to ensure minimal drilling fluid from the hydrostatic head is lost into the sea, as such excess drilling fluid will be pumped out prior to breakout to the marine environment, leaving only the volume of fluid required to complete the pilot hole exit. The remainder of the pilot hole is then opened up to the final diameter.
5.3.7 Duct Installation
A duct will be installed using a pushed installation, as this means there will be a reduction in the number of days required for the offshore works. The ducts are pushed from land to the sea and the cables can then be pulled in through the ducts. At the offshore exit point there will be temporary concrete mattressing placed over the end of the HDD until the offshore cable installation is ready to take place (Figure 5.3). The bulk of the HDD equipment will be removed from the HDD area at that point, leaving only equipment required for the cable pull activities.
![Page 25: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/25.jpg)
NORTHCONNECT PROJECT
Page : 25 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 5.3: Cable Duct Protected by Concrete Mattress
5.4 Offshore Preparations
5.4.1 Pre-Lay Survey
The cable contractor shall review all existing survey data to plan their cable routing through the consenting corridor. Prior to cable installation, a survey will be completed to confirm the routing. The pre-lay survey shall be performed as close as practically possible to the start of cable installation and shall document the seabed; and relevant sub-seabed; conditions along the planned cable route(s). The detailed survey shall be performed by a low flying ROV equipped to collect Multi-beam Echo Sounder (MBES), Side Scan Sonar (SSS) and Sub-bottom Profiler (SBP) data simultaneously. The ROV shall also be equipped with a video system for benthic habitat confirmation and possible inspection tasks on the same dive. The data shall be used for approval of the final routing with regards to obstructions, or areas where pre-lay trenching, dredging, rock placement or other forms of seabed intervention may be required. The route may be revised within the consenting corridor based on the pre-survey findings to avoid obstacles or previously unmapped sensitive habitats. The survey will also cover the asset crossings. Crossing surveys were completed as part of the original seabed surveys, but additional surveys will be required to identify possible changes in the existing infrastructures status. Magnetic data will be acquired for the proposed cable route, to identify potential Unexploded Ordinance (UXO). Several magnetometers shall be mounted in an array to form a gradiometer and towed behind the vessel (if water depths allow) or mounted on an ROV. The maximum distance between the survey lines to achieve full coverage to detect possible UXO will depend on the gradiometer unit, mass of the possible UXO items and the towing height of the gradiometer. The magnetic data shall be used to map metallic objects and also evaluate the origin of the object to estimate the chance of it being an UXO. This will require full coverage of the defined cable route/corridor width in areas, which from the UXO Desk Top Study are identified as possible UXO areas. This is to ensure identification of such objects and avoid any HSE issues. Where possible potential UXO contacts are identified during the survey, they will be avoided by an appropriate safety buffer during the final route engineering process. If avoidance is not possible, the items of UXO will be disposed of by an appropriately licenced explosives ordnance disposal contractor, or by the Royal Navy.
![Page 26: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/26.jpg)
NORTHCONNECT PROJECT
Page : 26 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
5.4.2 Sea Trials
The purpose of sea trials is to prove that vessels, equipment, procedures and personnel are suitable for an efficient installation of the Submarine HVDC and fibre optic Communication Cables, maintaining the cable integrity and in accordance with principles for Health Safety Environment and Quality during all phases of the Work. Sea trials will be carried out if the cable contractor cannot:
• Provide track records of successful use of equipment under the conditions it is intended for the work;
• Demonstrate that he has successfully applied the proposed procedures on earlier comparable projects; or
• Demonstrate that the cable safety is maintained during all phases of the work. The following typical operations would potentially require a sea trial:
• Pre-lay trenching and cable lay within the trench;
• Post-lay jet trenching in UK nearshore and other areas of competent soil conditions; and
• Post-lay mechanical trenching in UK nearshore and other areas of competent soil conditions. The sea trials shall be carried out in the consenting corridor close to the locations where the actual Work will take place. Upon completion of the sea trials, the seabed shall be cleared of all temporary equipment deployed for the purposes of the trial. Trials may need to be completed until:
• It is evident what alterations/adjustments must be made; and
• The spread and procedures prove to function according to the requirements for the work intended. The methods deployed are equivalent to those utilised in the actual works described below, but on a smaller scale. The trials will be over a length of 200-500m.
5.4.3 Seabed Preparation
An initial sweep of the seabed shall be carried out to remove any debris, boulders or obstacles, such as abandoned nets and wires, on the surface. This may involve a grapnel (hooked) device being dragged along the exact cable route. Alternatively, ROVs or grabs may be used to remove obstacles (Figure 5.4).
Figure 5.4: Example machinery for boulder clearance pre-cable lay.
5.4.4 Pre-Trenching
As discussed in Section 4.3, there is a potential to pre-trench parts of the cable route to help with gaining the DOL required to protect the cable. The pre-trenching plough would cut a trench in the seafloor by means of the ploughing tool being pulled along the seabed floor with great force by a vessel.
![Page 27: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/27.jpg)
NORTHCONNECT PROJECT
Page : 27 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
The performance of the plough and the trench depth being achieved will be closely monitored during trenching, to allow appropriate adjustments to be made and ensure that the appropriate trench depths are being achieved, as far as practicable. As discussed in Section 4.3.1, up to 3 passes will be made to reach the desired trench depth to ensure appropriate DOL can be achieved. Pre-trenching will be conducted as soon a practically possible before cable laying, in order to minimise the risk of natural backfilling reducing the DOL before the cable is installed.
5.4.5 Crossing Rock Placement
As discussed in Section 4.3.2 there will be a need to place rocks to protect existing infrastructure prior to cables being laid over them. The rock will be placed from a specialist fall pipe vessel prior to the cable being laid.
5.5 Marine Cable Pull
5.5.1 Seabed Preparations
To allow the cables to be pulled from the offshore environment, the protective mattressing installed to protect the HDD marine exit hole will be removed. An area around the duct (pull in pipe) will be excavated and a clamp with mounting flanges installed, as shown in Figure 5.5. Preparations will be completed immediately prior to each cable being pulled. Seabed preparation works may include ROVs and Divers.
Figure 5.5: Seabed Preparations for the Marine Cable Pull.
5.5.2 Cable Pull
The marine HVDC cables will be delivered in 150 km long sections, hence assuming that the HVDC cables are laid separately, the two marine HVDC cable pulls will be carried out at different times. The fibre optic cable will be pulled during one of the HVDC cable pull campaigns, as it will be bundled with it for the remainder of the route. When the cable lay vessel arrives at site, the bell mouth will be installed to guide the cable into the duct (Figure 5.6). The cable will be pulled from land utilising a set-up similar to that shown in Figure 5.7. Once the cable is in place, a cap will be installed to isolate the duct from the sea. Bentonite will then be pumped into the duct to fix the cable in the duct (Figure 5.6). The marine cable on the seabed will then be protected by placing rock over the HDD marine exit point along the cable route (Figure: 5.6) until the cable is suitably protected by other means (see Section 5.7).
![Page 28: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/28.jpg)
NORTHCONNECT PROJECT
Page : 28 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Figure 5.6: Cable Pulling Steps
Figure 5.7: Indicative Set up for the Marine Cable Pull.
5.6 Onshore Demobilisation and Reinstatement
Once all the marine cables have been pulled onto land and jointed with the onshore cables, the onshore areas can be fully demobilised. Equipment will be removed from site, the temporary water supply removed, hardstanding materials lifted, and the field reinstated for agricultural use to its existing ground levels. The access track will be mainly removed, with only a small area of tarmac (approx. 1m wide) remaining adjacent to the A90, this is to minimise the need to control traffic on the A90 during demobilisation works. The access road route will be reinstated to original levels suitable for agricultural use.
5.7 Offshore Cable Installation
The HVDC cables will be delivered in sections approximately 150km long. Four sections of cable will be required for the STW/UKEEZ. The first cable will be pulled ashore (as discussed in Section 5.5) and installed as discussed below. The cable end will be marked with a buoy and guard vessel utilised to protect it. Information with regard to the role of guard vessels is provided in the Fisheries Liaison and Mitigation Action Plan (FLMAP) (NorthConnect, 2018c). The second cable section will either be pulled ashore and laid, or attached to the end of the first section, this will depend on the timing of the delivery in relation to the bird breeding season. The third section will be attached to the first section or pulled ashore, depending on the placement of the second section. The fourth section will be attached to the end of the second cable installed from the UK landfall. If the HVDC cables were to be bundled, all Landfall cable pulls would be completed in one campaign, the cables would be approximately half the length (75km) and hence joins will be every 75km, with each section being joined to the end of the previous section. In parallel, cable installation will commence at Simadalen in Norway, working eastward to join with the cables laid from the UK to the middle of the North Sea. The exact location will be determined by cable section lengths, but it is likely to be outwith the UKEEZ.
![Page 29: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/29.jpg)
NORTHCONNECT PROJECT
Page : 29 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
5.7.1 Cable Laying
The cable will be laid on the seabed by the cable lay vessel, along the pre-identified cable route within the consenting corridor. Where pre-trenching is utilised, the cable will be laid directly into the trench. Guard vessels will be deployed as detailed in the FLMAP (NorthConnect, 2018c) to ensure that the cable is not damaged, and prevent hazards to other legitimate users of the sea including commercial fishing vessels, while the cable is unprotected on the seabed.
5.7.2 Cable Installation Survey/ As-laid Survey
Survey operations will be carried out during the cable installation to monitor the cable and the positioning of the cable touch down point. This is likely to be carried out by an ROV, either deployed from the cable lay vessel or an additional survey vessel. Particular attention shall be given to areas of importance like obstructions (e.g. boulders), areas with limited flexibility due to exposed bedrock, possible pre-trenched sections, infrastructure crossings, etc. The survey will cover a minimum of 25m each side of the cable and utilise at least SSS and MBES.
5.7.3 Post Cable Trenching
The cable will then be trenched into the seabed utilising an appropriate trenching device as discussed in Section 4.3.3.
5.7.4 Trenching Survey
The post trenching survey is expected to consist of two phases:
• Trenching performance monitoring; and • As trenched survey to document results of the trenching.
There is a potential that intermediate surveys may be required when multiple trench passes are executed. The minimum survey coverage on each side of the cable shall be 25m (SSS and MBES), i.e. both “high fly survey” and “low fly survey” shall be performed to ensure MBES/SSS coverage and video coverage/cable tracking ability, respectively. SBP and cable tracking devices may also be employed to verify DOL/DOB.
In order to achieve optimised trenching performance, the trencher operators shall actively use data from the survey to optimise trencher setup, such as sword depth, trenching speed, buoyancy, water pressure, nozzle configuration, etc. The as-trenched survey is partly the measurements used to control/monitor the trenching operations and partly necessary to check/document survey results where the quality of the trenching for some reason is doubtful. In challenging areas, the as-trenched surveys are normally performed in limited trenching sections and, if appropriate, performed in several passes to document the results of additional trenching passes.
5.7.5 Cable Joints
To join cable sections, the installed cable will be lifted from the seabed to the cable lay vessel, where the joint will be made prior to relaying the cable on the seabed and installation of the cables being completed (trenched/rock placed).
5.7.6 Rock Placement
Rock will be placed in the following circumstances: • To provide cable protection at crossings; • To backfill trenches which have not naturally infilled sufficiently, or where natural infilling is not expected
to achieve the required DOB; or • Remedial rock placement to provide the appropriate protection levels where DOL has not been achieved.
![Page 30: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/30.jpg)
NORTHCONNECT PROJECT
Page : 30 of 30
Date : 24.08.2018
NCON Doc. No. Rev. No.
: :
NCGEN-NCT-X-RA-0002 1
HVDC CABLE INFRASTRUCTURE – UK CONSTRUCTION METHOD STATEMENT
© Copyright NorthConnect KS - All rights reserved.
Rock will be placed from a specialist fall pipe vessel at the required locations, to provide the appropriate protection levels. The rock will be appropriately sloped at gradients between approximately 1:3 to 1:2.5 to ensure stability, and to allow for demersal trawl fishing to be carried out safely over the rock berms.
5.7.7 Rock Placement Survey
A rock placement survey shall be performed immediately after rock placement or, if necessary, at an intermediate stage during rock placement by the rock placement vessel with the fall-pipe ROV. The rock placement survey shall cover 25m on each side of the cable (SSS and MBES), i.e. both “high fly survey” and “low fly survey” shall be performed to ensure MBES/SSS coverage and video coverage/cable tracking ability, respectively. SBP and cable tracking devices may also be employed to verify DOL/DOB. The rock placement survey shall be conducted either to monitor the performance of an on-going rock placement operation, or in order to form the basis for the as-built documentation/as-installed survey planning. Remedial works will be conducted where: rock berms do not provide an adequate level of protection as defined in Section 4.3.1, do not meet the specifications detailed in Section 5.7.6, or where a snagging rick is identified,
5.7.8 Post Installation Survey/As-Built Survey
An as-built survey shall document the final conditions of the cable and the nearby corridor after the cable has been completely installed, including protection and possible sediment settlement. This survey shall cover a minimum corridor width of 50m centred over each cable and the results shall form the reference for future inspection surveys. The as-built survey shall be performed as a low-fly survey using the basic ROV spread, including MBES, SSS, SBP, video cameras, and an appropriate cable tracker, along all installed cables. The main objectives of the as-built survey shall be to:
• Map the horizontal and vertical curvature of the cable;
• Identify cable separation;
• Identify any free spans and rectified if found (none are expected in STW/UKEEZ);
• Map the protection depth (top of cable) in trench/rock berm and compare with depth specification;
• Map the detailed topography of the trench and corridor to investigate, e.g.: o Width of trench; o Depth of trench (and thus depth of cover); o Cross profiles of rock berms; o Potential debris/obstructions within the corridor; and o Moving sediments
5.8 Reporting
The as-built survey results will provide the exact routes the cables have taken. This information will be shared with the appropriate bodies as detailed in the Communications Strategy (NorthConnect, 2018b).
6. REFERENCES
Allen and Gordon. (2018). HVDC Cable Infrastructure - Transport Statement. NorthConnect. (2018a). HVDC Cable Infrastructure - UK Environmental Impact Assessment Report. 2 - Main
Report(NCGEN-NCT-X-RA-0004). NorthConnect. (2018b). HVDC Cable Infrastructure - Communication Strategy. NorthConnect. (2018c). HVDC Cable Infrastructure - Fisheries Liaison Mitigation Action Plan.
![Page 31: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/31.jpg)
-.
-/
--
,
-
.
/
0
,1
,0
,/
,.
1
3
2
4
,+
,,,-
,2
,4
-+
,3
-,
-0
-1
-2
.
,.3
, -
-1
-2
'*%$,&*)!+'$)
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
.74#@=94#?4@>=<@81898AE#=5#A78@#>B19820A8=<#984@#D8A7#A74#0BA7=?&#.74#)B?=>40<#/<8=<#8@#<=A#?4@>=<@8194#5=?#0<E#B@4#A70A#;0E#14#;034#=5#A74#8<5=?;0A8=<#2=<A08<43#A74?48<&
9H6M?D=!FHE9K8;H!9E8)!DE)*H;L
9H6M?D=!J?JB;
FHE@;8J
9H6M?D=!DE
I>;;J H;L?I?ED <EHC6J I86B;
=;E9;J?8
H;<;H;D8;
IOIJ;C
9H6M?D=!FHE9K8;H!9E8)!J6=!DE)
H;L!DE ?IIK;!H;6IED 96J; FH;F6H;9 8>;8A;9 6FFHEL;9
$#
./3(2
,()(.'
H;9!B?D;!7EKD96HO
DEHJ>8EDD;8J
KA!>L98!H;9!B?D;!7EKD96HO!%EDI>EH;&!FB6D
D8<<I(D8J(N(N=(+++,(+,
++, ,5-0++
7E996C
F;J;H>;69
&/!/1'+.$3(2!3$%,(
0/+.3 ($23+.) ./13*+.)
, /,,23- 3/,+14
- /,,32, 3/+2.3
. /,,2/+ 3/+133
/ /,,2.2 3/+101
0 /,,3/- 3/+,0.
1 /,-+,. 3/++0,
2 /,-+23 3/++.1
3 /,--0/ 3.4424
4 /,-.+3 3.441,
,+ /,--34 3.44+2
,, /,--03 3.4344
,- /,---- 3.44,1
,. /,-+,0 3.443.
,/ /,,22+ 3/+,-3
,0 /,,1+. 3/+,1-
,1 /,,02, 3/+,40
,2 /,,2./ 3/+.00
,3 /,,2+/ 3/+/43
,4 /,,2,/ 3/+0++
-+ /,,124 3/+110
-, /,,1,4 3/+1/0
-- /,,10+ 3/,,+3
-. /,,142)4 3/,/1,
-/ /,,2,+ 3/,0,+
-0 /,-+4+ 3/,/3/
-1 /,-,-4 3/,+3.
-2 /,-+20 3/+432
+ ?<K!(!?IIK;9!<EH!KI; -/*+2*,3 @6C @E6 IJC
k 8b_g^ S_`ibYWXd Q^T TQdQRQcU bYWXdc -+,3 EI ,+++0.,/.
![Page 32: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/32.jpg)
D96 6E
5C2H;@8 E;E>6
5C2H;@8 @A&
BCA<64E
C6G ;D;A@ 7AC?2E D42 >6
C6G @A ;DD F6 C62DA@ 52E6 BC6B2C65 4964=65 2BBCAG65
5C2H;@ 8 BC A 5 F46 C 5 A4& @ A&
5C2H;@ 8 BC A 5 F46 C 5 A4& C 6G &
5C2H;@ 8 BC A 5 F46 C >A8A
""
""
""
""
""
"
"
""
""
2²1(1#Y2²21(1#Y2²31(1#Y2²41(1#Y2²51(1#Y2²61(1#Y
68
²56
(1#P
68
²51
(1#P
68
²46
(1#P
68
²41
(1#P
68
²36
(1#P
68
²31
(1#P
321111 331111 341111 351111 361111 371111
74
81
11
17
49
11
11
74;
11
11
75
11
11
17
52
11
11�
( * , . 0 )()
UW
"
"
"
"
6\[S$ 96C6$ 8K[WSX$ d AZOXD][OO]?KZ
MYX][SL^]Y[\$ KXN ]RO 8;D ^\O[ MYWW^XS]b
PEQHH.PEV.Z.ZI.1112.12
@AE EA 36 FD65 7AC @2G;82E;A@
d 4[Y`X 4YZb[SQR] KXN'Y[ NK]KLK\O [SQR]\&
COZ[YN^MON Lb ZO[WS\\SYX YP ]RO 4YX][YVVO[ YP 9O[ ?KTO\]be\ D]K]SYXO[b APP SMO KXN ]RO F= 9bN[YQ[KZRSM APPSMO "```&8AG&^U'F=9A#& >SMOXMO )1-(+&
PQTVJEQPPGEV
WM!JXFE!Tgf!Nkpg!Dqwpfct{
)Octkpg*!Rncp!2
)*-$((( 6ECD )101 FE? JYXO +)@
E=)++(%()
(()(
( 2*
ERS\ NYM^WOX] MYX ]KSX \ MYXPS NOX]S KV SXPY [WK] SYX& @Y] ] Y LO MYZSON ]Y ]RS[N Z K[ ]SO\ `S] RY^] `[S] ]OX K^]RY[ScK]SYX& d 4YZb[SQR] @Y[ ]R4YXXOM] =D % 2VV [SQR]\ [O\O[_ON&
ERO \Y VO [O\ZYX\ SL SVS] b YP ]RS\ Z^LVSMK] SYX VSO\ `S]R ]RO K^ ]RY[& ERO 6^[YZOKX FXSYX S\ XY ] [O\Z YX\S LVO PY[ KXb ̂ \O ]RK] WKb LO WKNO YP ]RO SXPY[WK]SYX M YX]KSXON ]RO[OSX&
86A56E;4 C67&
DI DE6?
Ngigpf
F= CON >SXO 3Y^XNK[b
@Y[`OQSKX 4YX\OX]SXQ 4Y[[SNY[
F= 6aMV^\S_O 6MYXYWSM JYXO
" " F= )*@? EO[[S]Y[SKV HK]O[\
2 CO_SO` *1'(+'*()0 3B9 <A2$643
;\\^ON PY[ \̂O( *,'(/'*()0 52?
B6<
B6<<A2$643
![Page 33: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/33.jpg)
D96 6E
5C2H;@8 E;E>6
5C2H;@8 @A&
BCA<64E
C6G ;D;A@ 7AC?2E D42 >6
C6G @A ;DD F6 C62DA@ 52E6 BC6B2C65 4964=65 2BBCAG65
5C2H;@ 8 BC A 5 F46 C 5 A4& @ A&
5C2H;@ 8 BC A 5 F46 C 5 A4& C 6G &
5C2H;@ 8 BC A 5 F46 C >A8A
1²21(1#Y1²31(1#Y1²41(1#Y1²51(1#Y1²61(1#Y2²1(1#Y
69
²1(1
#P68
²66
(1#P
68
²61
(1#P
68
²56
(1#P
68
²51
(1#P
371111 381111 391111 3;1111 411111 421111
74
;1
11
17
51
11
11
75
21
11
175
31
11
17
54
11
11
755
11
11
�
( * , . 0 )()
UW
"
"
"
"
6\[S$ 96C6$ 8K[WSX$ d AZOXD][OO]?KZ
MYX][SL^]Y[\$ KXN ]RO 8;D ^\O[ MYWW^XS]b
PEQHH.PEV.Z.ZI.1112.13
@AE EA 36 FD65 7AC @2G;82E;A@
d 4[Y`X 4YZb[SQR] KXN'Y[ NK]KLK\O [SQR]\&
COZ[YN^MON Lb ZO[WS\\SYX YP ]RO 4YX][YVVO[ YP 9O[ ?KTO\]be\ D]K]SYXO[b APP SMO KXN ]RO F= 9bN[YQ[KZRSM APPSMO "```&8AG&^U'F=9A#& >SMOXMO )1-(+&
PQTVJEQPPGEV
WM!JXFE!Tgf!Nkpg!Dqwpfct{
)Octkpg*!Rncp!3
)*-$((( 6ECD )101 FE? JYXO +)@
E=)++(%(*
((*(
( 2*
ERS\ NYM^WOX] MYX ]KSX \ MYXPS NOX]S KV SXPY [WK] SYX& @Y] ] Y LO MYZSON ]Y ]RS[N Z K[ ]SO\ `S] RY^] `[S] ]OX K^]RY[ScK]SYX& d 4YZb[SQR] @Y[ ]R4YXXOM] =D % 2VV [SQR]\ [O\O[_ON&
ERO \Y VO [O\ZYX\ SL SVS] b YP ]RS\ Z^LVSMK] SYX VSO\ `S]R ]RO K^ ]RY[& ERO 6^[YZOKX FXSYX S\ XY ] [O\Z YX\S LVO PY[ KXb ̂ \O ]RK] WKb LO WKNO YP ]RO SXPY[WK]SYX M YX]KSXON ]RO[OSX&
86A56E;4 C67&
DI DE6?
Ngigpf
F= CON >SXO 3Y^XNK[b
@Y[`OQSKX 4YX\OX]SXQ 4Y[[SNY[
F= 6aMV^\S_O 6MYXYWSM JYXO
" " F= )*@? EO[[S]Y[SKV HK]O[\
2 CO_SO` *1'(+'*()0 3B9 <A2$643
;\\^ON PY[ \̂O( *,'(/'*()0 52?
B6<
B6<<A2$643
![Page 34: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/34.jpg)
D96 6E
5C2H;@8 E;E>6
5C2H;@8 @A&
BCA<64E
C6G ;D;A@ 7AC?2E D42 >6
C6G @A ;DD F6 C62DA@ 52E6 BC6B2C65 4964=65 2BBCAG65
5C2H;@ 8 BC A 5 F46 C 5 A4& @ A&
5C2H;@ 8 BC A 5 F46 C 5 A4& C 6G &
5C2H;@ 8 BC A 5 F46 C >A8A
1²51(1#G1²41(1#G1²31(1#G1²21(1#G1²1(1#1²21(1#Y
69
²26
(1#P
69
²21
(1#P
69
²6(1
#P69
²1(1
#P68
²66
(1#P
421111 431111 441111 451111 461111 471111
75
31
111
754
11
11
75
51
11
17
56
11
11
75
711
11
�
( * , . 0 )()
UW
"
"
"
"
6\[S$ 96C6$ 8K[WSX$ d AZOXD][OO]?KZ
MYX][SL^]Y[\$ KXN ]RO 8;D ^\O[ MYWW^XS]b
PEQHH.PEV.Z.ZI.1112.14
@AE EA 36 FD65 7AC @2G;82E;A@
d 4[Y`X 4YZb[SQR] KXN'Y[ NK]KLK\O [SQR]\&
COZ[YN^MON Lb ZO[WS\\SYX YP ]RO 4YX][YVVO[ YP 9O[ ?KTO\]be\ D]K]SYXO[b APP SMO KXN ]RO F= 9bN[YQ[KZRSM APPSMO "```&8AG&^U'F=9A#& >SMOXMO )1-(+&
PQTVJEQPPGEV
WM!JXFE!Tgf!Nkpg!Dqwpfct{
)Octkpg*!Rncp!4
)*-$((( 6ECD )101 FE? JYXO +)@
E=)++(%(+
((+(
( 2*
ERS\ NYM^WOX] MYX ]KSX \ MYXPS NOX]S KV SXPY [WK] SYX& @Y] ] Y LO MYZSON ]Y ]RS[N Z K[ ]SO\ `S] RY^] `[S] ]OX K^]RY[ScK]SYX& d 4YZb[SQR] @Y[ ]R4YXXOM] =D % 2VV [SQR]\ [O\O[_ON&
ERO \Y VO [O\ZYX\ SL SVS] b YP ]RS\ Z^LVSMK] SYX VSO\ `S]R ]RO K^ ]RY[& ERO 6^[YZOKX FXSYX S\ XY ] [O\Z YX\S LVO PY[ KXb ̂ \O ]RK] WKb LO WKNO YP ]RO SXPY[WK]SYX M YX]KSXON ]RO[OSX&
86A56E;4 C67&
DI DE6?
Ngigpf
F= CON >SXO 3Y^XNK[b
@Y[`OQSKX 4YX\OX]SXQ 4Y[[SNY[
F= 6aMV^\S_O 6MYXYWSM JYXO
" " F= )*@? EO[[S]Y[SKV HK]O[\
2 CO_SO` *1'(+'*()0 3B9 <A2$643
;\\^ON PY[ \̂O( *,'(/'*()0 52?
B6<
B6<<A2$643
![Page 35: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/35.jpg)
D96 6E
5C2H;@8 E;E>6
5C2H;@8 @A&
BCA<64E
C6G ;D;A@ 7AC?2E D42 >6
C6G @A ;DD F6 C62DA@ 52E6 BC6B2C65 4964=65 2BBCAG65
5C2H;@ 8 BC A 5 F46 C 5 A4& @ A&
5C2H;@ 8 BC A 5 F46 C 5 A4& C 6G &
5C2H;@ 8 BC A 5 F46 C >A8A
2²41(1#G2²31(1#G2²21(1#G2²1(1#G1²61(1#G1²51(1#G
69
²41
(1#P
69
²36
(1#P
69
²31
(1#P
69
²26
(1#P
69
²21
(1#P
481111 491111 4;1111 511111 521111
75
611
11
75
71
11
17
58
11
11
759
11
11
75
;1
11
1
�
( * , . 0 )()
UW
"
"
"
"
6\[S$ 96C6$ 8K[WSX$ d AZOXD][OO]?KZ
MYX][SL^]Y[\$ KXN ]RO 8;D ^\O[ MYWW^XS]b
PEQHH.PEV.Z.ZI.1112.15
@AE EA 36 FD65 7AC @2G;82E;A@
d 4[Y`X 4YZb[SQR] KXN'Y[ NK]KLK\O [SQR]\&
COZ[YN^MON Lb ZO[WS\\SYX YP ]RO 4YX][YVVO[ YP 9O[ ?KTO\]be\ D]K]SYXO[b APP SMO KXN ]RO F= 9bN[YQ[KZRSM APPSMO "```&8AG&^U'F=9A#& >SMOXMO )1-(+&
PQTVJEQPPGEV
WM!JXFE!Tgf!Nkpg!Dqwpfct{
)Octkpg*!Rncp!5
)*-$((( 6ECD )101 FE? JYXO +)@
E=)++(%(,
((,(
( 2*
ERS\ NYM^WOX] MYX ]KSX \ MYXPS NOX]S KV SXPY [WK] SYX& @Y] ] Y LO MYZSON ]Y ]RS[N Z K[ ]SO\ `S] RY^] `[S] ]OX K^]RY[ScK]SYX& d 4YZb[SQR] @Y[ ]R4YXXOM] =D % 2VV [SQR]\ [O\O[_ON&
ERO \Y VO [O\ZYX\ SL SVS] b YP ]RS\ Z^LVSMK] SYX VSO\ `S]R ]RO K^ ]RY[& ERO 6^[YZOKX FXSYX S\ XY ] [O\Z YX\S LVO PY[ KXb ̂ \O ]RK] WKb LO WKNO YP ]RO SXPY[WK]SYX M YX]KSXON ]RO[OSX&
86A56E;4 C67&
DI DE6?
Ngigpf
F= CON >SXO 3Y^XNK[b
@Y[`OQSKX 4YX\OX]SXQ 4Y[[SNY[
F= 6aMV^\S_O 6MYXYWSM JYXO
" " F= )*@? EO[[S]Y[SKV HK]O[\
2 CO_SO` *1'(+'*()0 3B9 <A2$643
;\\^ON PY[ \̂O( *,'(/'*()0 52?
B6<
B6<<A2$643
![Page 36: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/36.jpg)
867B;!B6D9<6BB!I?J;
8EDL;HJ;H!IJ6J?ED!I?J;
+++,(+.
+++,(+,
+++,(+-
+++,(+/
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
.74#@=94#?4@>=<@81898AE#=5#A78@#>B19820A8=<#984@#D8A7#A74#0BA7=?&#.74#)B?=>40<#/<8=<#8@#<=A#?4@>=<@8194#5=?#0<E#B@4#A70A#;0E#14#;034#=5#A74#8<5=?;0A8=<#2=<A08<43#A74?48<&
9H6M?D=!FHE9K8;H!9E8)!DE)*H;L
9H6M?D=!J?JB;
FHE@;8J
9H6M?D=!DE
I>;;J H;L?I?ED <EHC6J I86B;
=;E9;J?8
H;<;H;D8;
IOIJ;C
9H6M?D=!FHE9K8;H!9E8)!J6=!DE)
H;L!DE ?IIK;!H;6IED 96J; FH;F6H;9 8>;8A;9 6FFHEL;9
&$
>L98!EDI>EH;!867B;!HEKJ;
C6IJ;HFB6D
D8=;D(D8J(P(N;(+++-(+,
DEHJ>!8EDD;8J
B;=;D9
FHEFEI;9!M6J;H!C6?D
?D9?86J?L;!>L98!867B;
HEKJ;%I&
H;9B?D;!7EKD96HO
FH;L?EKIBO!8EDI;DJ;9
H;9!B?D;!7EKD96HO
%H;<5!6FF*-+,0*,,-,&
EKJB?D;!E<!FHEFEI;9
8EDL;HJ;H!7K?B9?D=
;NJ;DJ!E<!B6D9I86F?D=
7KD9I
)*,'+
JE!7;!H;69!?D!8ED@KD8J?ED!M?J>!9H6M?D=
D_b)!+++,(+,'!+++,(+-'!+++,(+.!#!+++,(+/
#%#""""#
+ ?<K!(!?IIK;9!<EH!KI; ,+*+2*-+,3 ;> =@9 =@9
"#
, ?<K!(!?IIK;9!<EH!KI; -.*+2*-+,3 @6C IJC =C8
![Page 37: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/37.jpg)
,-S
8G43!312=5
3@CC94@C
5IE5?E!@6!D@FE85C?
1=97?>5?E!D9E5
5DE12=9D8>5?E
DE1CE!@6!844!C@14
3C@DD9?7
@?D8@C5!844
5?EC1?35
=@31E9@?D
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
.74#@=94#?4@>=<@81898AE#=5#A78@#>B19820A8=<#984@#D8A7#A74#0BA7=?&#.74#)B?=>40<#/<8=<#8@#<=A#?4@>=<@8194#5=?#0<E#B@4#A70A#;0E#14#;034#=5#A74#8<5=?;0A8=<#2=<A08<43#A74?48<&
4C1H9?7!AC@4F35C!4@3&!?@&'C5G
4C1H9?7!E9E=5
AC@;53E
4C1H9?7!?@
D855E C5G9D9@? 6@C>1E D31=5
75@45E93
C565C5?35
DJDE5>
4C1H9?7!AC@4F35C!4@3&!E17!?@&
C5G!?@ 9DDF5!C51D@? 41E5 AC5A1C54 3853<54 1AAC@G54
'%
8G43!@?D8@C5!312=5
75?5C1=!1CC1?75>5?E
!D855E!)!@6!,
?375?%?3E%K%I4%((()%()
?@CE8!3@??53E
=575?4
AC@A@D54!=1?461==!844
1=97?>5?E
9?4931E9G5!312=5!C@FE5
C54!=9?5!2@F?41CJ
?@E5D
)& 51CE89?7!C5BF9C5>5?ED!1=@?7
312=5!C@FE5!E@!25!3@?69C>54
#&$"""#
E@!25!C514!9?!3@?;F?3E9@?!H9E8!4C1H9?7
?OQ&!(((*%()$!((()%(*$!((()%(+!#!((()%(,
( 96F!%!9DDF54!6@C!FD5 )('(/'*()0 58 7;4 7;4
"#
) 96F!%!9DDF54!6@C!FD5 *+'(/'*()0 ;1> DE> 7>3
![Page 38: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/38.jpg)
9H54!423>6
4ADD;5AD
21(!FDG@=!DA25
A@E9AD6!FD2@E;F;A@
<A;@F!B;F!)
955!E64F;A@
G@56D!21(
IAD=;@8!2D62!7AD
DA25!4DAEE;@8
IAD=;@8!2D62!7AD
955!DA25!4DAEE;@8
BDABAE65
F6?BAD2DK
2446EE!A77!21(
6@5!A7!955!DA25
4DAEE;@8
EF2DF!A7!955!DA25
4DAEE;@8
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
.74#@=94#?4@>=<@81898AE#=5#A78@#>B19820A8=<#984@#D8A7#A74#0BA7=?&#.74#)B?=>40<#/<8=<#8@#<=A#?4@>=<@8194#5=?#0<E#B@4#A70A#;0E#14#;034#=5#A74#8<5=?;0A8=<#2=<A08<43#A74?48<&
5D2I;@8!BDA5G46D!5A4&!@A&'D6H
5D2I;@8!F;F>6
BDA<64F
5D2I;@8!@A
E966F D6H;E;A@ 7AD?2F E42>6
86A56F;4
D676D6@46
EKEF6?
5D2I;@8!BDA5G46D!5A4&!F28!@A&
D6H!@A ;EEG6!D62EA@ 52F6 BD6B2D65 4964=65 2BBDAH65
'%
9H54!A@E9AD6!423>6!DAGF6
86@6D2>!2DD2@86?6@F
!E966F!*
@486@%@4F%L%J5%((()%(*
@ADF9!4A@@64F
>686@5
;@5;42F;H6!423>6!DAGF6
D65!>;@6!3AG@52DK
IAD=;@8!2D62!955!DA25
4DAEE;@8
@AF6E
)& 62DF9;@8!D6CG;D6?6@FE!2>A@8
423>6!DAGF6!FA!36!4A@7;D?65
#&$"""#
FA!36!D625!;@!4A@<G@4F;A@!I;F9!5D2I;@8
@SU&!(((*%()$!((()%()$!((()%(+!#!((()%(,
( ;7G!%!;EEG65!7AD!GE6 )('(/'*()0 69 8<5 8<5
"$
) ;7G!%!;EEG65!7AD!GE6 *+'(/'*()0 <2? EF? 8?4
![Page 39: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/39.jpg)
=K87!756A9
7DGG>8DG
?D>CI!E>I!,
756A9H!ID!69!8J7I98!JC89G
9M>HI>C<!E5I=!$8J7IH!>CHI5AA98
8JG>C<!9C56A>C<!LDG@H%
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
.74#@=94#?4@>=<@81898AE#=5#A78@#>B19820A8=<#984@#D8A7#A74#0BA7=?&#.74#)B?=>40<#/<8=<#8@#<=A#?4@>=<@8194#5=?#0<E#B@4#A70A#;0E#14#;034#=5#A74#8<5=?;0A8=<#2=<A08<43#A74?48<&
8G5L>C<!EGD8J79G!8D7(!CD()G9K
8G5L>C<!I>IA9
EGD?97I
8G5L>C<!CD
H=99I G9K>H>DC ;DGB5I H75A9
<9D89I>7
G9;9G9C79
HNHI9B
8G5L>C<!EGD8J79G!8D7(!I5<!CD(
G9K!CD >HHJ9!G95HDC 85I9 EG9E5G98 7=97@98 5EEGDK98
'%
=K87!DCH=DG9!756A9!GDJI9
<9C9G5A!5GG5C<9B9CI
!H=99I!-
C7<9C'C7I'O'M8'***+'*-
CDGI=!7DCC97I
A9<9C8
EGDEDH98!L5I9G!B5>C
>C8>75I>K9!756A9!GDJI9
G98!A>C9!6DJC85GN
9M>HI>C<!L5I9G!B5>C
EG9K>DJHAN!7DCH9CI98
G98!A>C9!6DJC85GN
$G9;4!5EE),*+/)++,+%
CDI9H
+( 95GI=>C<!G9FJ>G9B9CIH!5ADC<
756A9!GDJI9!ID!69!7DC;>GB98
#&$"""#
ID!69!G958!>C!7DC?JC7I>DC!L>I=!8G5L>C<
CUW(!***,'*+&!***+'*+&!***+'*,!#!***+'*.
* >;J!'!>HHJ98!;DG!JH9 +*)*1),*+2 9= <?8 <?8
"%
+ >;J!'!>HHJ98!;DG!JH9 ,-)*1),*+2 ?5B HIB <B7
![Page 40: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/40.jpg)
?D>CI!E>I!,
DJIA>C9!D;!5EEGDK98
7DCK9GI9G!6J>A8>C<
5EEGDM>B5I9!9MI9CI
D;!A5C8H75E>C<!6JC8H
756A9H!ID!69!8J7I98!JC89G
9M>HI>C<!E5I=!$8J7IH!>CHI5AA98
8JG>C<!9C56A>C<!LDG@H%
5G7=59DAD<>75A!;95IJG9!ID
69!EGDI97I98!8JG>C<!LDG@H
756A9!5A><CB9CI!5
ED>CI!5
EGDEDH98!0-TT
E9!E9GB5C9CI
L5I9G!B5>C
EG9K>DJHAN
7DCH9CI98!!G98
A>C9!!6DJC85GN
5EE),*+/)++,+
ED>CI!6
756A9!5A><CB9CI!6
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
.74#@=94#?4@>=<@81898AE#=5#A78@#>B19820A8=<#984@#D8A7#A74#0BA7=?&#.74#)B?=>40<#/<8=<#8@#<=A#?4@>=<@8194#5=?#0<E#B@4#A70A#;0E#14#;034#=5#A74#8<5=?;0A8=<#2=<A08<43#A74?48<&
8G5L>C<!EGD8J79G!8D7(!CD()G9K
8G5L>C<!I>IA9
EGD?97I
8G5L>C<!CD
H=99I G9K>H>DC ;DGB5I H75A9
<9D89I>7
G9;9G9C79
HNHI9B
8G5L>C<!EGD8J79G!8D7(!I5<!CD(
G9K!CD >HHJ9!G95HDC 85I9 EG9E5G98 7=97@98 5EEGDK98
(%
=K87!DCH=DG9!756A9!GDJI9
<9C9G5A!5GG5C<9B9CI
!H=99I!.
C7<9C'C7I'O'M8'***+'*.
CDGI=!7DCC97I
CDI9H
+( I=9!=K87!756A9!L>AA!69!GDJI98!>CID
5C!5EEGDEG>5I9!AD75I>DC!>C!I=9
7DCK9GI9G!HI5I>DC&!A>C9H!H=DLC
=9G9!5G9!>C8>75I>K9!DCAN(
,( H99!8G<!CD(!+')(+#+',#.#-(#$$$&#$%
;DG!89I5>AH!D;!756A9!8J7IH!JC89G
A5C8H75E>C<!6JC8H(
-( 95GI=>C<!G9FJ>G9B9CIH!5ADC<!756A9
GDJI9!ID!69!7DC;>GB98(
A9<9C8
EGDEDH98!E9GB5C9CI
L5I9G!B5>C
>C8>75I>K9!756A9
GDJI9!5
>C8>75I>K9!756A9
GDJI9!6
G98A>C9!6DJC85GN
DJIA>C9!D;!EGDEDH98
7DCK9GI9G!6J>A8>C<
EG9K>DJHAN!7DCH9CI98
G98!A>C9!6DJC85GN
$G9;4!5EE),*+/)++,+%
9MI9CI!D;!A5C8H75E>C<
6JC8H
#'$"""#
ID!69!G958!>C!7DC?JC7I>DC!L>I=!8G5L>C<
CVY(!***,'*+&!***+'*+&!***+'*,!#!***+'*-
* >;J!'!>HHJ98!;DG!JH9 +*)*1),*+2 9= <?8 <?8
"&
+ >;J!'!>HHJ98!;DG!JH9 ,-)*1),*+2 ?5B HIB <B7
![Page 41: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/41.jpg)
*)))'))))
E7C3D3F<BA
47FI77A534?7E
D7<AEF3F7@7AF
$A3F<H7 FBCEB<? E7F 3E<67 3A6 D7C?3576%
FKC<53? E75F<BA F;DBG9; 534?7 FD7A5;
$CBEF & 5BAEFDG5F<BA%E53?7 *2+.
E7?75F76 7J53H3F76 @3F7D<3?
E3A6 EGDDBGA6 FB 534?7E
E3A6 4766<A9 FB 534?7E
*.))'))))*.))')))) *.))'))))
CDBF75F<BA E?34E
BH7D 534?7E
3C
CD
BJ
' *
,)
)')
)))
3C
CD
BJ
'
*)
))
'))
))
5B
H7
D
FB
53
4?
7E
*)))'))))E7C3D3F<BA
47FI77A
534?7E
EG997EF76 I3F7DEFBC 67F3<?E53?7 *2+.
-))) P *))) P -.) F;<5> 9D367 97A, @3EE
5BA5D7F7 I3F7DEFBC $FB 47 CDBH<676 3F *))N
57AFD7E BD 3E 6<5F3F76 4K E<F7 5BA6<F<BAE%
E3A6 4766<A9 FB 534?7E
*.))'))))*.))')))) *.))'))))
3C
CD
BJ
' *
,)
)')
)))
3C
CD
BJ
'
*)
))
'))
))
5B
H7
D F
B
53
4?
7E
534?7E FB 47 <AEF3??76 <A EC?<F 6G5FE F;DBG9; 5BA5D7F7 I3F7DEFBC
$6G5FE FB 47 E73?76 CD<BD FB 435>8<??<A9%
F7?75B@@GA<53F<BA 6G5F
$5BAH7DF7D EF3F<BA FB 5BAH7DF7D EF3F<BA%F7?75B@@GA<53F<BA 6G5F
$5BAH7DF7D EF3F<BA FB 5BAH7DF7D EF3F<BA%
*)))'))))E7C3D3F<BA
47FI77A 534?7E
FKC<53? E75F<BA F;DBG9; 534?7 5BDD<6BD
$6GD<A9 5BAEFDG5F<BA%E53?7 *2+.
*.))'))))*.))')))) *.))'))))
3C
CD
BJ
' *,
))
')))
)
FBCEB<? EFB5>C<?7
-.))'))))
45;,'
-04(2 ;8(*1 *549;8<*;054 +,;(029 ;5 ), *54-083,+#
;,3658(8? +8(04(., 3(? ), 8,7<08,+ >0;/04 ;/, -089; 2(?,8
5- -022 ;5 68,=,4; 654+04. 54 90;,#
F7@CBD3DK 3557EE FD35> C3D3??7? FB FD7A5; $,'.N I<67%
97BF7JF<?7 ?3<6 6<D75F?K BA A3F<H7 9DBGA6
<@CBDF76 I7??&5B@C35F76 9D3AG?3D @3F7D<3?
@3J<@G@ -.) H7DF<53? 57AFD7E 47FI77A 97B9D<6E
EG4EB<? EFB5>C<?7
F7?75B@@GA<53F<BA 6G5F
$5BAH7DF7D EF3F<BA FB 5BAH7DF7D EF3F<BA%
*)))'))))
E7C3D3F<BA47FI77A
534?7E
D7<AEF3F7@7AF$A3F<H7 FBCEB<? E7F 3E<67 3A6 D7C?3576%
=B<AF<A9 C<F & E75F<BA F;DBG9; 534?7 FD7A5; $CBEF & 5BAEFDG5F<BA%E53?7 *2+.
E7?75F76 7J53H3F76 @3F7D<3?
E3A6 EGDDBGA6 FB 534?7E
E3A6 4766<A9 FB 534?7E
/)))'))))*.))')))) *.))'))))
CDBF75F<BA E?34E BH7D 534?7E
3C
CD
BJ
' *,
))
')))
)
3C
CD
BJ
'
*)
))')
))
)
5B
H7
D
FB
53
4?
7E
F7?75B@@GA<53F<BA 6G5F$5BAH7DF7D EF3F<BA FB 5BAH7DF7D EF3F<BA%
+.)))
/))
)
EF
3A
63
D6
FD
7A
5;
EF
3A
63
D6
FD
7A
5;
3C
CD
BJ
'
*-)
)
3C
CD
BJ
'*-
))
@<A
.N
D3
6<G
E
=B<AF<A9 C<F C?3AE53?7 *2.)
@<A
.N
D3
6<G
E
)23; .7-=5/6< -76<+36; -7603./6<3+4 360795+<376B '7< <7 ,/ -783/. <7 <239. 8+9<3/; ?3<27=< ?93<</6 +=<2793A+<376B E #78@9312< '79<2#766/-< %( C "44 9312<; 9/;/9>/.B
)2/ ;74/ 9/;876;3,343<@ 70 <23; 8=,43-+<376 43/; ?3<2 <2/ +=<279B )2/ $=978/+6 *6376 3; 67< 9/;876;3,4/ 079 +6@ =;/ <2+< 5+@ ,/ 5+./ 70 <2/ 360795+<376 -76<+36/. <2/9/36B
6D3I<A9 CDB6G57D 6B5' AB'(D7H
6D3I<A9 F<F?7
CDB=75F
6D3I<A9 AB
E;77F D7H<E<BA 8BD@3F E53?7
97B67F<5
D787D7A57
EKEF7@
6D3I<A9 CDB6G57D 6B5' F39 AB'
D7H AB <EEG7 D73EBA 63F7 CD7C3D76 5;75>76 3CCDBH76
(%
;H65 BAE;BD7 534?7 DBGF7 67F3<?E
A597A&A5F&L&J7&))),&)*
ABDF; 5BAA75F
(E EACFB&
) <8G & <EEG76 8BD GE7 *)()0(+)*1 7; 9=6 9=6
$%
*D8G & F7?75B@@GA<53F<BAE 6G5F 36676 FB
534?7 FD7A5; # ABF7 36676 $<A6<53F<H7 BA?K%+.()0(+)*1 =@
+ D8G & <A6<53F<H7 BA?K ABF7 D7@BH76 +-()1(+)*1 =@ EF@ EF@
![Page 42: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/42.jpg)
"/
"/
&U'*#%"@&U(%#%"@&U(*#%"@&U)%#%"@&U)*#%"@&U*%#%"@
*,
U(*
#%"8
*,
U(%
#%"8
*,
U'*
#%"8
'&%%%% '&*%%% ''%%%% ''*%%% '(%%%% '(*%%%
+(
,*
%%
%+
(-
%%
%%
+(
-*
%%
%+
(.
%%
%%
+(
.*
%%
%
�
) * + , - .)'.
VX
ABF FB 47 GE76 8BD A3H<93F<BA
d 5\ZaY 5Z[b\TRS^ LYO(Z\ OL^LML]P \TRS^]' DP[\ZO_NPO Mb [P\XT]]TZY ZQ ^SP 5ZY^\ZWWP\ ZQ ;P\ @LUP]^be] E^L^TZYP\b BQQTNP
LYO ^SP G> ;bO\ZR\L[STN BQQTNP #aaa'9BH'_V(G>;B$' ?TNPYNP *1.),'
7EGEMD
>TWZXP^P\ CZ]^
FP\\T^Z\TLW IL^P\]
DPOWTYP 4Z_YOL\b
0PNQQIMGQ <NCJ ;KBCELEMR
"/ 5LMWP
"/ CT[PWTYP
1QRILBRED <ELEDIBK <NCJ ;KBCELEMR <EOSIPELEMRQ
;EPCEMRBGE NF =ECRINM 7EMGRH
)"
) & +"
+ & 0"
0 & *+"
*))"
3 <]]_PO QZ\ DP T̀Pa ).()/(+)*0 63@ =B3% 754 C7=
80922$80>$A$A3$%%%+$%&
89<>4098810>
;PEDICRED <ELEDIBK <NCJ ;KBCELEMR/5ERRIMG 9MKT V ?6>@
*))%))) 7FDE *101 GF@ KZYP ,*A
F>*,+,&)*
))) )) 3,
FST] OZN_XPY^ NZY^LTY] NZYQTOPY^TLW TYQZ\XL^TZY' AZ^ ^Z MP NZ[TPO ^Z ^ST\O [L\^TP] aT^SZ_^ a\T^^PY L_^SZ\TcL^TZY' d 5Z[b\TRS^ AZ\^S5ZYYPN^ >E & 3WW \TRS^] \P]P\`PO'
FSP ]ZWP \P][ZY]TMTWT^b ZQ ^ST] [_MWTNL^TZY WTP] aT^S ^SP L_^SZ\' FSP 7_\Z[PLY GYTZY T] YZ^ \P][ZY]TMWP QZ\ LYb _]P ^SL^ XLb MP XLOP ZQ ^SP TYQZ\XL^TZY NZY^LTYPO ^SP\PTY'
97B67F<5 D78'
EJEF7@E;77F
6D3I<A9 F<F?7
6D3I<A9 AB'
CDB=75F
D7H<E<BA 8BD@3F E53?7
6D3I<A9 CDB6G57D 6B5' AB'
6D3I<A9 CDB6G57D 6B5' D7H'
6D3I<A9 CDB6G57D ?B9B
EP\`TNP ?LbP\ 5\POT^]2 7]\T% ;7D7%
9L\XTY% d B[PYE^\PP^@L[ NZY^\TM_^Z\]%
LYO ^SP 9<E _]P\ NZXX_YT^b
) <]]_PO QZ\ G]P )1()/(+)*0 63@ =B3% 754 C7=
D7H AB <EEG7 D73EBA 63F7 CD7C3D76 5;75>76 3CCDBH76
![Page 43: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/43.jpg)
"/
"/
'W(+#&"B'W)&#&"B'W)+#&"B'W*&#&"B'W*+#&"B'W+&#&"B
+-
W)+
#&";
+-
W)&
#&";
+-
W(+
#&";
('&&&& ('+&&& ((&&&& ((+&&& ()&&&& ()+&&&
,)
-+
&&
&,
).
&&
&&
,)
.+
&&
&,
)/
&&
&&
,)
/+
&&
&
�
) * + , - .)'.
VX
ABF FB 47 GE76 8BD A3H<93F<BA
d 5\ZaY 5Z[b\TRS^ LYO(Z\ OL^LML]P \TRS^]' DP[\ZO_NPO Mb [P\XT]]TZY ZQ ^SP 5ZY^\ZWWP\ ZQ ;P\ @LUP]^be] E^L^TZYP\b BQQTNP
LYO ^SP G> ;bO\ZR\L[STN BQQTNP #aaa'9BH'_V(G>;B$' ?TNPYNP *1.),'
9GIGOF
>TWZXP^P\ CZ]^
FP\\T^Z\TLW IL^P\]
DPOWTYP 4Z_YOL\b
2RPSSKOIS >PEL =MDEGNGOT
"/ 5LMWP
"/ CT[PWTYP
3STKNDTGF >GNGFKDM >PEL =MDEGNGOT >GQUKRGNGOTS
=GREGOTDIG PH ?GETKPO 9GOITJ
)"
) & +"
+ & 0"
0 & *+"
*))"
C\PWLb CWZ_RS 4LNVQTWW DZNV CWLNPXPY^
3 <]]_PO QZ\ DP T̀Pa ).()/(+)*0 63@ =B3% 754 C7=
;2<44%;2@%C%C5%&&&-%&'
;<>@62<;;32@
=RGFKETGF >GNGFKDM DOF 1DELHKMM >PEL =MDEGNGOT0
7GTTKOI $ =RGMDV =MPUIJ X A8@B
*))%))) 7FDE *101 GF@ KZYP ,*A
F>*,+,&)*
))) )) 3,
FST] OZN_XPY^ NZY^LTY] NZYQTOPY^TLW TYQZ\XL^TZY' AZ^ ^Z MP NZ[TPO ^Z ^ST\O [L\^TP] aT^SZ_^ a\T^^PY L_^SZ\TcL^TZY' d 5Z[b\TRS^ AZ\^S5ZYYPN^ >E & 3WW \TRS^] \P]P\`PO'
FSP ]ZWP \P][ZY]TMTWT^b ZQ ^ST] [_MWTNL^TZY WTP] aT^S ^SP L_^SZ\' FSP 7_\Z[PLY GYTZY T] YZ^ \P][ZY]TMWP QZ\ LYb _]P ^SL^ XLb MP XLOP ZQ ^SP TYQZ\XL^TZY NZY^LTYPO ^SP\PTY'
97B67F<5 D78'
EJEF7@E;77F
6D3I<A9 F<F?7
6D3I<A9 AB'
CDB=75F
D7H<E<BA 8BD@3F E53?7
6D3I<A9 CDB6G57D 6B5' AB'
6D3I<A9 CDB6G57D 6B5' D7H'
6D3I<A9 CDB6G57D ?B9B
EP\`TNP ?LbP\ 5\POT^]2 7]\T% ;7D7%
9L\XTY% d B[PYE^\PP^@L[ NZY^\TM_^Z\]%
LYO ^SP 9<E _]P\ NZXX_YT^b
) <]]_PO QZ\ G]P )1()/(+)*0 63@ =B3% 754 C7=
D7H AB <EEG7 D73EBA 63F7 CD7C3D76 5;75>76 3CCDBH76
![Page 44: HVDC Cable Infrastructure Construction Method Statement · pass the cables below the A90 and disused railway, the Road Crossing HDD. All HVDC Cable Infrastructure within the UK EEZ](https://reader033.vdocuments.us/reader033/viewer/2022042915/5f533e3f342ea752c068f9b7/html5/thumbnails/44.jpg)
"/
"/
"/
"/
"/
"/
"/
"/
"/
"/"/"/"/"/
"/"/"/
'X&#&"3&X&#&"'X&#&"B(X&#&"B
+.
X)&
#&";
+.
X&#&
";
+-
X)&
#&";
(&&&&& (+&&&& )&&&&& )+&&&& *&&&&&
,)
+&
&&
&,
*&
&&
&&
,*
+&
&&
&,
+&
&&
&&
,+
+&
&&
&
�
) *) +) ,) -) .).
VX
ABF FB 47 GE76 8BD A3H<93F<BA
e 5\ZaY 5Z[c\TRS^ LYO(Z\ OL^LML]P \TRS^]' DP[\ZO_NPO Mc [P\XT]]TZY ZQ ^SP 5ZY^\ZWWP\ ZQ ;P\ @LUP]^cf] E^L^TZYP\c BQQTNP
LYO ^SP G> ;cO\ZR\L[STN BQQTNP #aaa'9BH'_V(G>;B$' ?TNPYNP *1.),'
9HJHPG
>TWZXP^P\ CZ]^
7bNW_]T`P 7NZYZXTN KZYP
FP\\T^Z\TLW IL^P\]
DPOWTYP 4Z_YOL\c
2SQTTLPJT >QFM =NEFHOHPU
"/ 5LMWP
"/ CT[PWTYP
3TULOEUHG >HOHGLEN >QFM =NEFHOHPU >HRVLSHOHPUT
=HSFHPUEJH QI ?HFULQP 9HPJUK
)"
) & +"
+ & 0"
0 & *+"
*))"
C\PWLc CWZ_RS 4LNVQTWW DZNV CWLNPXPY^
3 <]]_PO QZ\ DP T̀Pa ).()/(+)*0 63@ =B3% 754 C7=
;2<44%;2@%C%C5%&&&.%&'
;<>@62<;;32@
=SHGLFUHG >HOHGLEN EPG 1EFMILNN >QFM =NEFHOHPU0
7HUULPJ $ =SHNEW =NQVJK Y A833D
/.)%))) 7FDE *101 GF@ KZYP ,*A))) )) 3,
FST] OZN_XPY^ NZY^LTY] NZYQTOPY^TLW TYQZ\XL^TZY' AZ^ ^Z MP NZ[TPO ^Z ^ST\O [L\^TP] aT^SZ_^ a\T^^PY L_^SZ\TdL^TZY' e 5Z[c\TRS^ AZ\^S5ZYYPN^ >E & 3WW \TRS^] \P]P\`PO'
FSP ]ZWP \P][ZY]TMTWT^c ZQ ^ST] [_MWTNL^TZY WTP] aT^S ^SP L_^SZ\' FSP 7_\Z[PLY GYTZY T] YZ^ \P][ZY]TMWP QZ\ LYc _]P ^SL^ XLc MP XLOP ZQ ^SP TYQZ\XL^TZY NZY^LTYPO ^SP\PTY'
97B67F<5 D78'
EJEF7@E;77F
6D3I<A9 F<F?7
6D3I<A9 AB'
CDB=75F
D7H<E<BA 8BD@3F E53?7
6D3I<A9 CDB6G57D 6B5' AB'
6D3I<A9 CDB6G57D 6B5' D7H'
6D3I<A9 CDB6G57D ?B9B
EP\`TNP ?LcP\ 5\POT^]2 7]\T% ;7D7%
9L\XTY% e B[PYE^\PP^@L[ NZY^\TM_^Z\]%
LYO ^SP 9<E _]P\ NZXX_YT^c
) <]]_PO QZ\ G]P )1()/(+)*0 63@ =B3% 754 C7=
D7H AB <EEG7 D73EBA 63F7 CD7C3D76 5;75>76 3CCDBH76
F>*,+,&)*