HTM Guide 3 Chapter 1-2
Anna WormFor Engineering World Health
March 20
![Page 2: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/2.jpg)
2
HTM for session 5
• We will cover Guides 3 and 6.
• Guide 3: How Procure and Commission: How to Manage Vol 3, Lenel et. al., (Ziken International: 2005).
Guide 6: How to Manage Finances: How to Manage Vol 6 Lenel et. al., (Ziken International: 2005).
![Page 3: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/3.jpg)
3
What will we cover with Guide 3?
• Procurement and commissioning of new (and used) equipment.– Activities before purchasing– Steps to take when purchasing– How to prepare for, and receive, store and distribute
goods– Receiving, installing, commissioning and accepting
goods– How to monitor and evaluate (and improve) your
activities
![Page 4: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/4.jpg)
4
definitions
• Procurement =The acquisition of goods and services through purchase,
donation or rental.
• Commissioning= the process of assuring that all systems and components are designed, installed, tested, operated and maintained according to the operational requirements of the owner
![Page 5: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/5.jpg)
5
Why are we covering Guide 3?
![Page 6: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/6.jpg)
6
HTM cycle p24
![Page 7: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/7.jpg)
7
What is your role in the procurement process?
• Does the hospitals write requirements? Are you involved?
• Do you check the equipment when it is delivered? Do you write or sign documents after checking it?
• Do you install new equipment? Do you sign documents?
• etc
![Page 8: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/8.jpg)
8
Teams for procurement and commissioning p15
• Procurement unit• Procurement/tender committee• Specification writing group• Commissioning team• Training sub-group• Project sub group (external funders)
![Page 9: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/9.jpg)
9
Important pages from the book
• H1: – p9-10– p14-19
• H2:– p24 Figure 4– p39 box– p42
![Page 10: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/10.jpg)
HTM Guide 3 Chapter 3How to decide when and what to procure
Anna WormMarch 20
![Page 11: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/11.jpg)
11
content
3.1 why you need to procure3.2 issues to consider when choosing
equipment3.3 a review of the different ways to get
equipment3.4 new or second hand items?
![Page 12: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/12.jpg)
12
3.1 Why you need to procure
• First planning and budgeting as covered in Guide 2 (p45):– Up to date inventory– Vision for health services delivery– Policies– Model equipment lists
![Page 13: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/13.jpg)
13
Procurement policies p.45,46,47
1. equipment requires replacement2. Regular supplies of equipment-related items
are required3. Additional equipment is necessary for
providing a basic standard level of care4. additional equipment is required to improve
services and go beyond a basic level of care5. Additional equipment is required that is
outside the health facility’s own plansONLY POSSIBLE IF FUNDING COMES AVAILABLE
![Page 14: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/14.jpg)
14
3.2 issues to consider when choosing equipment
• Purchasing and donation policies should help you by specifying ‘good selection criteria’, which should also help you to decline gift if not appropriate for your healthcare system
• Al equipment should:– Be appropriate to your setting– Be of assured quality and safety– Be affordable and cost effective– Be easily used and maintained– Conform to your exsisting policies, plans and guidelines
![Page 15: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/15.jpg)
15
example
• EWH offers your district hospital a brand new MRI, what do you do?– Be appropriate to your setting NO– Be of assured quality and safety Probably– Be affordable and cost effective NO– Be easily used and maintained NO– Conform to your existing policies, plans and
guidelinesNO
![Page 16: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/16.jpg)
16
Be appropriate to your setting, p51Factors Issues
You have the skills Equipment can be operated and (preferably) maintained by your staff, with or without additional training.
It suits your climate and conditions
It has been designed or adapted to cope with the location where it will be used. For example:
◆ In humid climates: ◆ In high ambient temperatures: With unreliable power supplies: ◆ ◆ With unreliable water supplies: ◆ In dusty environments:
It is simple to use The equipment should have a limited number of settings and modes of operation (unless you are buying extremely specialized equipment to suit extremely specialized personnel). Experience shows that equipment with more than three settings requires a specialist.
It fits into your health facility
The equipment: ◆ is compatible with existing equipment and knowledge in the organization (if
possible) ◆ is suited to the power source and power quality available ◆ does not require unavailable or unreliable service supply installations
(utilities) ◆ does not require more space than you have.
![Page 17: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/17.jpg)
17
• Performance• Sources• Materials & Design• Safety• Standards• Labeling and Packaging
Be of assured quality and safety, p52
![Page 18: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/18.jpg)
18
Be affordable and cost effective, p54
![Page 19: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/19.jpg)
19
Be easily used and maintained p59
Many of the cost we discussed relate to the (availability of the) following• Skills & training MANUALS!• Maintenance & support services SERVICE
ENGINEER in country?• Guarantees and warranties • Consumables, Accessories and spare parts
![Page 20: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/20.jpg)
20
Conform to your existing policies, plans and guidelines
• Purchasing and donation policies;– In line with equipment development plan
• Standardization policy– Limit the variety of equipment, limit your purchases to a
few trusted suppliers• Model equipment lists and generic specifications– National standard
• Literature & knowledge available– Prepare well before deciding. Do proper market
research
![Page 21: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/21.jpg)
21
![Page 22: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/22.jpg)
22
3.3 ways to get equipment, p64
• Purchase/donate/lease, rent or hire
3.3.1 purchase with national funds3.3.2 purchase using external support
agencies3.3.3 donations3.3.4 leasing3.3.5 research & demonstration models
![Page 23: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/23.jpg)
23
3.3.1 purchase with national funds
• Government funds- find out which bodies and which sections are responsible for purchasing different types of equipment
• Own independent funds
![Page 24: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/24.jpg)
24
3.3.2 purchase using external support agencies
• Loans (repayable with interest) & grants (non- repayable)• Donors might have different regulations and procedures that
conflict with yours. Potential conflict areas:– Your standardization policy– Your budgets, external partner responsible for the ‘hippo’– Your aims and whishes. You should be able to make choices
THE ART OF GETTING THE RIGHT EQUIPMENT IS CHOOSING THE RIGHT EXTERNAL SUPPORT AGENCY TO SUPPORT IT! TO DO SO YOU NEED YOUR EQUIPMENT DEVELOPMENT PLAN TO BUILD A STRONG AND CLEAR BUSINESS CASE
![Page 25: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/25.jpg)
25
3.3.3 donations
Keep in mind:• What will it cost?• Is it appropriate?• Do you have the skills?• Is it sustainable?• Why am I being offered it?
![Page 26: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/26.jpg)
26
3.3.4 leasing p76
• Equipment can sometimes be hired, meaning it remains under ownership of the other party, they are responsible for maintenance and repair. Lease contract
• Lease type arrangement: a way of buying with spread costs
![Page 27: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/27.jpg)
27
(dis)advantages leasing etc, p77Advantages Disadvantages
◆ Provides certainty as costs are known in advance.
◆ Reduces the need to tie up capital funds in fixed assets.
◆ Enables the suitability of equipment to be assessed over a pre-determined trial period.
◆ Sometimes enables you to obtain equipment or material that is hard to purchase.
◆ A fixed obligation is created to pay rental from your recurrent funds.
◆ The flexibility to dispose of obsolete equipment before the end of the lease may be reduced.
◆ Doesn’t provide ownership. ◆ Agreements are one-sided. When leasing, if
something goes wrong most risks are transferred to the lessee (for example, loaned items must be replaced if damaged). Under leasing type arrangements, although most of the risk remains with the owner of the equipment this has to be paid for in the rental price, and additional costs will be incurred, depending on the contract terms, if a leased item is misused or otherwise damaged.
![Page 28: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/28.jpg)
28
3.3.4 obtain new or second hand equipment
Advantages Disadvantages
◆ Often reduces the cost substantially (on average between 40 and 80 per cent of new equipment costs). ◆ May be more readily available. ◆ When reconditioned or rebuilt, may have a long life and be protected by guarantees or warranties. ◆ May be economical to buy when it would not pay to acquire new. ◆ May be compatible with others already in use, thus reducing the cost of holding stocks of spare parts and consumables.
◆ Can have problems linked to age and lack of spare parts, consumables, manuals, or servicing support. Although some organizations repair second-hand goods to improve their lifespans, many do not. ◆ Risks are bigger and you may have less protection if anything goes wrong. Used goods are sold as they are, meaning they are not always perfect. The supplier takes no responsibility if the faults are obvious when you make your purchase and you cannot expect a refund or compensation. You can only ask for your money back if the equipment does not do the job you bought it to do. ◆ May be less reliable, last for a shorter period of time, and require more maintenance than new equipment.
![Page 29: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/29.jpg)
29
3.3.5 research and demonstration models
• Research models are still under development• Demo models are second hand with full documentation• Only accept when:
– Officially tested and approved – Conforms to standards– Equipment remains property of supplier– Supplier responsible for running cost– Supplier responsible for claims from patients– You are not responsible for loss or damage– You ask permission of patients (or relatives) before using the
equipment on the patient
![Page 30: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/30.jpg)
30
![Page 31: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/31.jpg)
31
Important pages from the book
• H3 all– P 45-82– Annex 3 p305-308
![Page 32: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/32.jpg)
HTM Guide 3 Chapter 4
Anna WormMarch 27
![Page 33: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/33.jpg)
33
Chapter 4 How to decide on the way to purchase
4.1 determining the model for procurement4.2 choosing your purchasing method4.3 different types of suppliers4.4 Identifying suitable suppliers
![Page 34: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/34.jpg)
34
4.1 models for procurement
• Centralized procurement– E.g. through MoH or ACM– Often big tenders, high value
• Group procurement– E.g. procure equipment for all PiH hospitals– More negotiating power
• Decentralized procurement– Direct procurement by your hospital– Often small orders, low value, with local suppliers
![Page 35: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/35.jpg)
35
4.1 models for procurement
• Mixed procurement– Combination of centralized and decentralized – E.g. the big orders through MoH and the small
ones through the hospital• Using procurement agents– E.g. when orders are large and/or complicated. – Often for development projects, e.g. a new
hospital
![Page 36: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/36.jpg)
36
4.2 choosing your purchasing method
• Direct order; contact supplier, ask for price and order
• Tendering; procedure with bidders . Open and restricted tenders
• Quotation; you ask for a price, and have some time to decide. Normally you ask quotations from several suppliers
![Page 37: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/37.jpg)
37
Why do you choose Direct order, tender or quotation?
• What are you purchasing?• The model of procurement• Who is paying• Transparancy required• Procurement guidelines (e.g. grant requires tender)• The market place• The size of the order• Level of authorization needed; e.g. I am allowed to by a
$5 stapler without advanced approval• How soon the equipment is needed
![Page 38: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/38.jpg)
38
4.2.2 Tenders
• Open tenders– Open for any supplier to bid– You receive many respsonses– Takes at least 6 months up to 1 year
• Restricted tenders– Smaller number of bidders (e.g. only national)– 4 to 6 months
Disadvantage of tenders: price only thing that counts, what about quality?
![Page 39: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/39.jpg)
39
4.2.3. Quotation-based methods
• Request for quotes: buyer asks minimum of 3 suppliers for a quote. Buyer evaluates and decides
• National competitive bids: advertised nationally, many bids accepted, evaluate, compare and decide
• Competitive negotiation: several suppliers are asked for a price, the buyer shares all offers with all suppliers to get even better offers
![Page 40: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/40.jpg)
40
4.2.4. Direct ordering
• You know what you want, model, brand etc
• You know which supplier to approach
• You contact supplier directly communicate personally with them and negotiate terms
![Page 41: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/41.jpg)
41
4.3 different types of suppliers
• International manufacturers– And their representatives. E.g GE
• national manufacturers and suppliers– E.g supplier of imported goods, service company
• Whole salers and retailers– Range of products from different suppliers
• International supply organizations– E.g procurement agents
• International turnkey organizations– Also do design, work with engineers etc
![Page 42: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/42.jpg)
42
(dis)advantages local/international
• discussion
![Page 43: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/43.jpg)
43
4.4 identifying suitable suppliers
• Pre qualification– Screen potential suppliers before bids or quotes
• Post qualification– Suppliers are screened after bids or quotes
• Monitoring– Keep track of suppliers
• Disqualification– You need a system to disqualify suppliers who do
not perform well or don’t keep their word
![Page 44: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/44.jpg)
HTM Guide 3 Chapter 5
Anna WormMarch 27
![Page 45: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/45.jpg)
45
Chapter 5 How to Prepare for procurement
5.1 determining quantities needed5.2 Deciding whether to use lots5.3 Finalizing how to procure5.4 Timetabling 5.5 Preparing paperwork
![Page 46: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/46.jpg)
46
5.1 determining quantities
Available plans; look at your Equipment Development plan!
Decide what you need, how much and what quality
Capital budget recurrent budget
![Page 47: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/47.jpg)
47
Capital budget
• To buy euqipment• Big amounts• Hippo model, not only purchasing costs
![Page 48: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/48.jpg)
48
Recurrent budget
• Also called operational budget • Smaller amounts• Supplies, accessories, contracts
![Page 49: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/49.jpg)
49
5.2 using lots
• Combining similar or related equipment into lots to make purchasing easier – Stronger position for negotiation– Reducing time scale of procurement and delivery– Attracting a large number of bidders– Examples:• Imaging equipment• Laboratory equipment
![Page 50: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/50.jpg)
50
5.4 time table for procurement
• Plan your purchases!• Example Ultrasound:– Once purchase– Lifetime– Accessories
Annual/scheduled/perpetual/single project p133
![Page 51: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/51.jpg)
51
5.5 paperwork
• Remember Costica’s example last week
• Please read this to review Costica’s lesson last week
![Page 52: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/52.jpg)
HTM Guide 3 Chapter 6
Anna WormMarch 29
![Page 53: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/53.jpg)
53
6. How to manage the purchasing process
6.1 Asking for bids/quotes and issuing documents6.2 receiving and opening the bids/quotes6.3 evaluation and comparison process6.4 award of contract and placing the order
6.5 local direct purchasing and ordering
![Page 54: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/54.jpg)
54
6.1 Asking for bids/quotes and issuing documents
• First write detailed purchase document• Request tender bids or (at least 3) quotations– Open tenders or national competitive bids: invitation to bid
is advertised in a number of locations
– Restricted tenders/competitive negotiation/request for quotes: purchase document directly issued to preselected suppliers
– Direct order: the purchase document is issued directly to a single prequalified or selected supplier
![Page 55: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/55.jpg)
55
6.2 receiving and opening tender bids/quotations
• For direct orders, competitive negotiation, request for quote of low value can be informal. E.g. You can set a date for receiving quotes
• For all other methods you’ll need a more formal procedure
![Page 56: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/56.jpg)
56
Opening tender bids/high value quotations
• Opening; Procurement Mngr opens sealed bids (or quotations) at the indicated time and place and in public
• Registering; bidders (or reps) should be present and sign a register, quotation opening should be recorded
• Processing; open, content checked, signature checked. Bid/quote admitted for further comparison
• Late arrivals: should not be openened, but stamped with date and time and unopened returned to sender
![Page 57: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/57.jpg)
57
6.3 Evaluation and Comparison process
1. Checking for compliance; compare the bid with the tender document
2. Preparing the evaluation information; put all information next to each other
3. Carrying out the technical evaluation; does the product offered fit the requirements?
4. Carrying out the financial evaluation; lowest purchase price or most economically advantageous offer
See sample quotation comparison form! p175
![Page 58: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/58.jpg)
58
5. Making recommendations: use scoring and weighting
6. Consultations: talk to users and technicians7. Evaluating the suppliers8. Final decision: does the offer fit the budget?
![Page 59: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/59.jpg)
59
6.4 award of contract and placing the order
Nice table on p 183• Prepare the notification of award• Inform supplier• Discuss contract terms• Issue purchase order• Supplier’s response• Issue the contract• Inform all bidders• Organize the funds• Make a record of the purchase
![Page 60: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/60.jpg)
60
documents
• Purchase order: numbered printed form used by the buyer to place an order with an supplier. For accountants the purchase order number will be used to dedicate the funds from the relevant budget account
• Proforma invoice: breakdown of suppliers quote and terms of payment
• Contract: binding document for a specified period of time
• Notification of award: for winning bidder, signed by authorities, including unit and total price awarded
![Page 61: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/61.jpg)
HTM Guide 3 Chapter 7
Anna WormMarch 29
![Page 62: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/62.jpg)
62
7. How to receive goods and distribute them to site
7.1 preparing to receive equipment and supplies7.2 safe shipment, custom clearance, and transport to distribution centers7.3 storage at distribution centers and dispatch7.4 Delivery to final destination site
![Page 63: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/63.jpg)
63
7.1 preparing to receive equipment and supplies
• Monitoring progress using a Gantt Chart p196• Pre-installation work– Site preparation chart p 201– Organizing lifting equipment– Organizing warehouse space– Installation and commissioning details– Training details
• Preparing for customs clearing
![Page 64: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/64.jpg)
64
7.2 safe shipment, custom clearance, and transport to distribution centers
• Is the equipment always delivered in the hospital? Who’s taking care of the safe shipment and clearance?
• Supplier or buyer should contract clearing agent
• Insurance• Customs to initial destination, who’s in charge:
supplier or buyer?
![Page 65: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/65.jpg)
65
7.3 storage at distribution centers and dispatch
• Your aim should be to put equipment into service directly, and don’t use storage. Of course for things in bulk, you store (like accessories or disposables)
• Distribution centers, central or zonal
![Page 66: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/66.jpg)
66
7.4 Delivery to final destination site
• Do you use own transportation or do you contract a company?
• Direct delivery by freight forwarder• Collection from airport using your own
vehicle, hired vehicle or a clearing agent• You may organise onward delivery from the
distriv=ution centers yourself
![Page 67: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/67.jpg)
67
Important abbreviations, p328
• EXW= Ex Works. All cost for buyer• FOB= Free On Board. Supplier pays till port of departure• CIF=Cost Insurance and Freight. Supplier pays till port of
destination, incl insurance• CIP= Carriage and Insurance Paid. Supplier pays insurance and
transport till final destination (avec DDU)• DDU= Delivered Duty Unpaid. Buyer pays import taxes.• DDP= Delivered Duty Paid. Supplier pays all taxes.
LEARN BY HEART!
![Page 68: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/68.jpg)
HTM Guide 3 Chapter 8
Anna WormApril 2
![Page 69: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/69.jpg)
69
Chapter 8: how to receive commission and store goods on site
8.1 an overview of the acceptance process8.2 receipt and checking of goods8.3 assembly, installation, commissioning and initial training8.4 registration and hand over8.5 when and how to make payments8.6 damage or unsatisfactory supply
![Page 70: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/70.jpg)
70
8.1 an overview of the acceptance process
• Acceptance Procedure:– Delivery/receipt of the equipment on site– Unpacking and checking for damage and for
completeness– Assembly & Installation– Commissioning and safety testing– Official acceptance– Initial training– Registration; entering stocks into stores and records– handover
![Page 71: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/71.jpg)
71
Who’s responsible?
The HTM working group (ideally the commissioning team)
It’s normal for a manufacturer to send technical personnel (such as engineers) to do the installation and commissioning, and a different person to do the user training
![Page 72: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/72.jpg)
72
Documents required for acceptance
• Copies of purchase order• Shipping documents• Packing list• Blank copies of Acceptance test Logsheet• New Equipment files
• Service and user manuals
![Page 73: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/73.jpg)
73
Materials required for acceptance
• Hand trolley, fork lift, people?• Tools to open the box• Tools for assembly and installation• Insulation testing instruments to test
insulation and earth connections• Safety analyzer• Any other relevant test equipment
![Page 74: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/74.jpg)
74
Space required
• Room fo unpacking• Room for assembly• Room for training
![Page 75: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/75.jpg)
75
8.2 receipt and checking of goods
• Receiving and unpacking– Clean environment– Easy access for crates– Easy access to department
![Page 76: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/76.jpg)
76
8.3 Assembly, installation, commissioning and training
• Preparation• Assembly: steps to put equipment together if it was
dismantled for transport• Installation: fixing equipment into place• Commissioning: series of tests and adjustments
performed to check whether new equipment is functioning well, and that any adjustments are made before equipment is used
• Training: VERY important. Before users start using new equipment they need to be trained
![Page 77: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/77.jpg)
77
8.4 registration and handover
• Entering new orders into health facility records; equipment inventory, PPM plan, etc
• Storing manuals; original copies in a safe place, make photocopies
• Upload digital copies to your CMMS• Storage and stock control of recurrent orders of
equipment related supplies• Handover: formal presentation of the equipment
to he user department after acceptance
![Page 78: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/78.jpg)
78
8.6 damage to goods or unsatisfactory supply of goods or services
• goods are damaged• order incomplete• Wrong product• Product doesn’t fit specifications• Doesn’t fulfill function• No service as agreed (e.g. training)
Compare your original purchase contract with what you received. The person contacting the supplier should be senior and have enough clinical and technical knowledge
![Page 79: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/79.jpg)
79
• Call supplier, contact insurance company• Do NOT sign acceptance Test logsheet, but
write Fault Report to the procurement manager describing the problems. Make pictures!!
![Page 80: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/80.jpg)
HTM Guide 3 Chapter 9
Anna WormApril 3
![Page 81: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/81.jpg)
81
Chapter 9; action planning and monitoring of progress
• Planning and reviewing to evaluate your performance and the performance of the system
= Quality Managementfor client satisfactionfor cost efficiencyfor compliance with laws
![Page 82: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/82.jpg)
82
9.1 setting goals
• Important to monitor performance and progress with regard to procurement and commissioning
• Annual Action Plan; clear specific goals for the coming year. An opportunity for team members to agree the range of activities they want to implement
![Page 83: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/83.jpg)
83
NOT in AAP
• Need for major investments in equipment (that’s part of the EDP)
• Shortage of staff or money
WHAT DO WE PUT in AAP?• Improvements that staff can execute
them selves, with the existing staff, equipment, facilities and other resources
![Page 84: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/84.jpg)
84
For all aspects of your work
• Find info on new products• Improve procurement skills• Implementing effective equipment acceptance
procedures• Improving stock control of supplies• More successful installation and
commissioning• Improved training
![Page 85: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/85.jpg)
85
AAP
• Plan should be clear and straight forward• Goals understood by all• If staff is involved in creating the AAP they will
be more motivated to make it happen
• The book suggests an Action Planning Seminar once a year
![Page 86: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/86.jpg)
86
Ultimate goal of an AAP
• Be able to plan in advance and to look back and compare the results with the plan. So in January 2012 you compare the AAP 2011 with the results of 2011 and you create AAP2012.
• Discuss problems and seek solutions!
![Page 87: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/87.jpg)
87
Setting goals
1. Targets2. Recommendations3. Longer term objectives
![Page 88: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/88.jpg)
88
targets
• Targets guide the work of all groups involved in procurement and commissioning during the following year
• Targets should be SMART– Specific what and who– Measurable easy to measure– Achievable possible with existing resources– Relevant solve a priority– Time-bound when should it be completed
![Page 89: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/89.jpg)
89
P 259target By whom How to
measureHow to achieve
Time table
Actions agreed in order of priority
Name(s) of responsible persons
How progress will be measured
Resources required
Time fram, start and completion
![Page 90: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/90.jpg)
90
recommendations
• Sometimes you can’t achieve something without extra money, extra staff, or extra supplies. Make a recommendation
• Specifically addressed to someone• Reasonable keep it
realistic• Essential no
easier alternative
![Page 91: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/91.jpg)
91
Longer term objectives
• Some things can not be solved in one year.
• Try to chop it up in smaller pieces and monitor the progress over several years
![Page 92: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/92.jpg)
92
How to measure goals
• You need indicators to measure and you need baseline data
• Table p 261
![Page 93: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/93.jpg)
93
9.2 monitoring progress with procurement and commissioning
• After planning we do monitoring
• Monitor progress against annual goals• Monitoring progress in general• Audit process for development projects
![Page 94: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/94.jpg)
94
Antivirus & back up
• Comodo• Sophos• Norton• McAfee
• External hard drive• Burn CD• Print hard copy
![Page 95: HTM Guide 3 Chapter 1-2 Anna Worm For Engineering World Health March 20](https://reader035.vdocuments.us/reader035/viewer/2022070414/5697c0011a28abf838cc22e1/html5/thumbnails/95.jpg)
95
Citations:• How to Organize: How to Manage Vol 1, Lenel et. al., (Ziken International: 2005). Retrived from:
http://library.ewh.org/greenstone/collect/BMETDigitalLibrary/index/assoc/HASH019f.dir/guide%201%20How%20to%20Organize.pdf
• How to Plan and Budget How to Manage Vol 2, Lenel et. al., (Ziken International: 2005). Retrived from: http://library.ewh.org/greenstone/collect/BMETDigitalLibrary/index/assoc/HASH3e7a.dir/guide%202%20How%20to%20Plan%20and%20Budget.pdf
• How Procure and Commission: How to Manage Vol 3, Lenel et. al., (Ziken International: 2005). Retrieved from: http://library.ewh.org/greenstone/collect/BMETDigitalLibrary/index/assoc/HASH01c1/0c3e7249.dir/guide%203%20How%20to%20Procure%20and%20Commission.pdf
• How to Manage Finances: How to Manage Vol 6 Lenel et. al., (Ziken International: 2005). Retrieved from: http://library.ewh.org/greenstone/collect/BMETDigitalLibrary/index/assoc/HASH01ad.dir/guide%206%20How%20to%20Manage%20Finances.pdf