How long does SCADA implementation take?
![Page 2: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/2.jpg)
Depends on environment, subcontractors, and system complexity.
But…
![Page 3: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/3.jpg)
Let’s try to narrow it down to a specific timeframe.
![Page 4: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/4.jpg)
First, let’s review the 3 main
phases to SCADA integration.
![Page 5: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/5.jpg)
Phase 1 is when all equipment ordering takes
place.
IN HOUSE CONFIGURATION
SCADA architecture is
then meticulously planned for seamless
integration with existing systems.
![Page 6: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/6.jpg)
The part that takes time in
Phase 2 is waiting for
schedules to coordinate for
onsite configuration.
ONSITE CONFIGURATION
…either waiting for a good
maintenance window or
planning around other
subcontractors.
![Page 7: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/7.jpg)
After onsite integration, it’s
time to thoroughly test
the system.
ONSITE TESTING
A single generator can take an entire day, while a
battery system may only take a
few hours.
![Page 8: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/8.jpg)
So what does that actually look like, in terms of timing?
![Page 9: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/9.jpg)
Total turnaround time: 5-6 weeks
commissioninghardware ship
drawings submittal
integration
shippingto site
in-houseintegrationsoftware setup
Example: Small 5-Piece System w/ 20 Monitoring Points
![Page 10: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/10.jpg)
Total turnaround time: 3-4 months
commissioning
hardware ship
submittal
integration
shippingto site
in-houseintegration
software setupExample: Large 50-Piece System
![Page 11: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/11.jpg)
How to shorten the SCADA project
timeframe
![Page 12: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/12.jpg)
Hire a flexible integrator with in-house project
managers dedicated to
getting projects completed on time.
![Page 13: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/13.jpg)
Allow your integrator to participate in scheduling
conversations. You’ll avoid important
information getting miscommunicated
down the line.
![Page 14: How Long Does SCADA Implementation Take](https://reader035.vdocuments.us/reader035/viewer/2022062903/58e51fcc1a28ab624e8b5ab1/html5/thumbnails/14.jpg)
Set a realistic deadline. Those that manage your projects should dig into everything that could possibly impact
the schedule (holidays, subcontractors, extended timelines).