HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING ASAOTI-PATLI-ASAUDAH-RATHDHANA STATIONS
FEASIBILITY STUDY REPORT
I
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING ASAOTI-PATLI-ASAUDAH-RATHDHANA STATIONS
FEASIBILITY STUDY REPORT
Table of Contents 1 EXECUTIVE SUMMARY ................................................................................................... 1
1.1 Introduction ............................................................................................................ 1
1.2 Traffic Demand Forecast ......................................................................................... 1
1.3 Civil Engineering ...................................................................................................... 2
1.4 Salient Features ...................................................................................................... 2
1.5 Power Supply and System of Traction ..................................................................... 3
1.6 Signalling and Telecommunication .......................................................................... 4
1.7 Cost Estimate .......................................................................................................... 4
1.8 Proposed Financial Structuring ................................................................................ 4
1.9 CONCLUSION & RECOMMENDATIONS .................................................................... 5
2 OBJECTIVE AND DESIGN METHODOLOGY ...................................................................... 6
2.1 Project Objective – Haryana Orbital Rail Corridor .................................................... 6
2.1.1 Major Development near project location ....................................................... 6
2.1.2 Conceptualisation of the Alignment. ................................................................ 7
2.2 Project Location ...................................................................................................... 8
2.2.1 Key Map of Project location ............................................................................. 8
2.2.2 Serving Station: ................................................................................................ 9
2.2.3 Major Locations & Districts .............................................................................. 9
2.3 Concept of Study ................................................................................................... 10
2.3.1 Feasibility Study ............................................................................................. 10
2.4 Stakeholder outreach on Haryana Orbital Rail Corridor Project ............................. 10
2.5 Fixed Points ........................................................................................................... 12
2.5.1 Asaoti to Harsana Kalan ................................................................................. 12
2.5.2 Y-Connectivity towards Rewari Station........................................................... 12
2.5.3 Y-Connectivity towards Garhi-Harsaru Jn Station ........................................... 12
2.5.4 Y-Connectivity towards Rohtak Station .......................................................... 12
2.6 Standard of Construction ...................................................................................... 12
2.6.1 Category of Line ............................................................................................. 12
2.6.2 Gradient ......................................................................................................... 13
2.6.3 Grade Compensation ..................................................................................... 13
2.6.4 Gauge ............................................................................................................ 13
2.6.5 Rails ............................................................................................................... 13
2.6.6 Ballast ............................................................................................................ 13
II
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING ASAOTI-PATLI-ASAUDAH-RATHDHANA STATIONS
FEASIBILITY STUDY REPORT
2.6.7 Sleeper ........................................................................................................... 13
2.6.8 Track Structure .............................................................................................. 13
2.6.9 Welding ......................................................................................................... 13
2.6.10 Points & Crossings .......................................................................................... 13
2.6.11 Switches & SEJ ............................................................................................... 14
2.6.12 Track Tolerances ............................................................................................ 14
2.6.13 Catch Water Drains and Longitudinal side Drains ........................................... 14
2.6.14 Speed potential .............................................................................................. 14
2.6.15 Length of Infrastructure ................................................................................. 14
2.6.16 Traction ......................................................................................................... 14
2.6.17 Horizontal and Vertical Alignment .................................................................. 14
2.6.18 Formation ...................................................................................................... 15
2.6.19 Bridges ........................................................................................................... 15
2.6.20 Fixed Structure Clearance .............................................................................. 15
2.6.21 Road Crossing ................................................................................................ 15
2.6.22 Protective Works ........................................................................................... 15
2.6.23 Fixed Structure Clearances ............................................................................. 16
2.6.24 Land requirement .......................................................................................... 16
2.7 Miscellaneous works ............................................................................................. 16
3 Cost Estimation ........................................................................................................... 17
3.1 Abstract Estimates ................................................................................................ 17
3.2 Methodology ........................................................................................................ 17
4 Financial & Implementation Aspects of the Proposal ................................................... 18
4.1 Estimation of Traffic Revenues .............................................................................. 18
4.2 Passenger Earnings ............................................................................................... 18
4.3 Freight Earnings .................................................................................................... 18
4.4 O&M Costs ............................................................................................................ 19
4.5 Financial Appraisal ................................................................................................ 19
4.5.1 Net Present Value Method (NPV) ................................................................... 20
4.5.2 Internal Rate of Return (IRR) .......................................................................... 20
4.5.3 Discount Rate ................................................................................................. 21
4.5.4 Capital Asset Pricing Model (CAPM) ............................................................... 21
4.6 Haryana Orbital Rail Corridor Proposal –Project Executed by JV ............................ 22
4.7 Economic Appraisal ............................................................................................... 23
4.8 Assessment of Economic Cost ............................................................................... 24
III
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING ASAOTI-PATLI-ASAUDAH-RATHDHANA STATIONS
FEASIBILITY STUDY REPORT
4.9 Assessment of Economic Benefit ........................................................................... 24
4.10 Implementation through SPV as per JV Model ................................................... 25
5 Proposed Financial Structuring .................................................................................... 29
IV
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING ASAOTI-PATLI-ASAUDAH-RATHDHANA STATIONS
FEASIBILITY STUDY REPORT
List of Tables
Table 13 : Revenue Projections till Horizon Year 2049 ........................................................ 19
V
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING ASAOTI-PATLI-ASAUDAH-RATHDHANA STATIONS
FEASIBILITY STUDY REPORT
List of Figures
Figure 2.3 Proposed Alignment crosses DFCC ........................................................................ 7
Figure 2.4 Key Plan of Proposed Rail Corridor ........................................................................ 9
1
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
1 EXECUTIVE SUMMARY
1.1 Introduction
Haryana Rail Infrastructure Development Corporation Limited (HRIDC) was incorporated on
22nd August 2017 as a Joint Venture with Government of Haryana and Ministry of Railways
with equity participation of 51% and 49% respectively. The Company has a mandate of
selecting bankable railway projects for development, study, arranging finance, execution of
Projects and to boost the Rail infrastructure projects in the state of Haryana on the
principle of cooperative federalism
The Company intends to develop many common user rail corridors to open unserved areas
of the State of Haryana, thereby, for easing out the Delhi region from the freight traffic
movement passing through and by allowing shifting from radial and inner ring rail network.
The Regional Orbital Rail Corridor was conceived by NCR as a Ring Railway around Delhi at
about 200KM radius.
There was proposal to connect Palwal- Manesar- Patli- Farukhnagar- Jhajjar to make a
Western Peripheral Rail Corridor to connect Palwal to Panipat bypassing Delhi.
After Implementation of KMP Expressway and the planning of Panchgram Urban centres,
the project alignment from Palwal to Sonipat has been conceived on Techno-Economic
consideration.
The proposed Rail corridor will facilitate the diversion of Freight traffic not meant for Delhi
and will help in developing Multi Modal Hubs in NCR region of Haryana.
This study pertains to new electrified Double BG rail line project from Pawal to Sonipat
bypassing Delhi region and will provide direct rail connectivity (by-passing Delhi) from
Palwal to Sonipat by linking Asaoti (on Delhi-Mathura Route)-Patli (on Delhi Rewari Route)-
Asaudha(on Delhi-Rohtak Route) and Harsana Kalan (on Delhi-Ambala Route) by new
Broad Gauge rail line and also with DFC network at Pirthala.
1.2 Traffic Demand Forecast
The potential Assessed traffic that can be diverted through the proposed corridor is
40.5 GMT
The new traffic generation points along the corridor are IMT Faridabad, Sohna,
Manaesar, Rothak and SEZ at Farukhnagar.
Traffic from Maruti Suzuki is 600 Rakes per year
2
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
CONCOR and all other ICD’s proposed 5 GMT in 2023
Anticipated passenger traffic is 24000 per day for starting year
2024 2026 2031 2036 2041 2046
Freight GMT 45.65 52.85 67.45 86.08 86.08 86.08
Rakes 41 47 61 77 77 77
Passenger 24000 29000 35000 42000 50000 60000
Trains 20 24 29 35 42 50
Total 61 71 90 112 119 127
1.3 Civil Engineering
The proposed route is having following sections.
Asaoti to Harsana Kalan – 130 Km
Y-Connectivity at Patli station towards Rewari
Y-Connectivity at Sultanpur station towards Garhi Harsaru
Y-Connectivity at Asaudah station towards Rohtak
The minimum and maximum inter distance between the proposed crossing stations
are 7.880 Km and 15.520 Km
There are 3Y-Connectivity lines proposed for connecting the Radial lines coming
from Delhi i.e on Delhi-Rewari, Delhi-Rohtak and GarhiHarsaru-Farukhnagar
sections
Total 50 curves are proposed in the enroute. The maximum degree of curvature
considered as 5.0 degree.
Land required for construction is 654.26 Hectares inclusive of doubling, of which 70
Hectares of land is under HSIIDC
All the bridges on the proposed new BG line will be of 25 T Axle loading and
provided with ballasted deck as per extent guidelines of Railway Board.
Track structure is proposed with 60 Kg. 110 UTS Rails on PSC sleepers 1660 Nos per
KM and 350 mm ballast cushion.
1.4 Salient Features
Total Route Length – 130 Kms (excluding Y-Connectivities)
Ruling Gradient - 1 in 200 Compensated
Maximum Length of Ruling Gradient - 2635 m
3
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Bridges:
Description No.s
Water way Bridges
Major 14
Minor 68
Road Crossing
RUB 128
ROB 8
Rail Crossing
RFO 3
Crossing Stations- 14 Nos. crossing stations have been proposed in the corridor
between Asaoti to Harsana Kalan. These are including 3 nos. Existing stations viz.
Asaoti, Pirthala yard and Harsana Kalan. The average inter distance between
stations is 11.70 Kms. The station locations are identified with a prime importance
of village centric.
All the crossing stations have been proposed with minimum two common loops.
1.5 Power Supply and System of Traction
The proposed corridor between Asaoti to Harsana Kalan having a total of about 130
Route KM & Over Head Conductor Track Km of 320 TKM. The section is proposed to
be electrified section.
The corridor is proposed to be electrified with 25 KV, single phase, 50 Hz.
TSS - Traction Substations with 2x21.6 MVA transformers have been proposed at
the following locations for power supply to the sections.
S.No. Station Rating Capacity
1 Dhulawat 132/27.5 kV 2x21.6 MVA
2 Mandothi 132/27.5 kV 2x21.6 MVA
Over Head Equipment’s (OHE) and Supervisory Control and Data Acquisition System
(SCADA) have been proposed.
Necessary modifications to the power line crossings of 11/33Kv line have been
considered.
4
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Electric power supply system including 220, 132 KV D/C transmission line from SEB
Grid substation to TSS & modification in Grid Substation also considered.
1.6 Signalling and Telecommunication
All stations shall be class-B type with standard –II-R interlocking having Electronic
Interlocking, multi aspect LED based color light signaling, electrically operated point
machine and DC track circuiting for detection of track section.
For block working, it is proposed to provide a pair of single line block instrument
along with UFSBI as per latest RDSO specification. The block instrument will be
connected with 6 quad copper cables laid all along the system.
In order to improve system reliability, the provision of integrated power supply
system has been considered. This will have an added advantage of ensuring
uninterrupted power supply round the clock, preventing signal going blank.
Provision of optical fiber based communication system has been planned for
complete section.
1.7 Cost Estimate
The Cost Estimate of all components of works envisaged to be taken up for
implementation has been prepared.
The overall capital cost for Haryana Orbital Rail Corridor including land cost works
out to Rs. 4086.08 Crores.
1.8 Proposed Financial Structuring
As per the JV model as per Government of India Ministry of Railways (Railway
Board) Letter No. 2011/Infra/12/32 dated 10.12.2018, “Participative models for
rail-connectivity and capacity augmentation projects.
The project may be implemented as a SPV by HRIDC with Debt-Equity ratio of 70:30
considering the total cost of project is 4086.08Cr including land, the financial results
like Equity IRR is computed to 13.44% with Equity NPV of 1015.48Cr. (Ref: Para 13.6
of this report)
The total project cost including private land that need to be acquired is 3786.08cr
(Ref: Chapter-3 of this report) of which 70% debt i.e 2650.25 Cr and 30% overall
equity i.e 1135.82 Cr is considered.
Out of the total equity, proposed share of various stakeholders in equity is
mentioned below:
5
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Overall Equity 1135.82 Crores
Equity share of Various Stakeholders
Stakeholder % Equity Share Amount (in Crores)
HRIDC 30% 340.746
Private Sectors 40% 454.328
Other PSU's 30% 340.746
1.9 CONCLUSION & RECOMMENDATIONS
The project may be implemented as a SPV by HRIDC with Debt-Equity ratio
of 70:30 considering the total cost of project is 4086.08 Cr including land,
the financial results are looking promising with Equity IRR is computed to
13.44% with Equity NPV of 1015.48Cr making the project financially viable.
Further EIRR of 18.00% makes the project viable on Socio-Economic
consideration also.
6
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
2 OBJECTIVE AND DESIGN METHODOLOGY
2.1 Project Objective – Haryana Orbital Rail Corridor
The objective of this study is to facilitate and develop an orbital rail corridor connecting
Palwal and Sonipat with suitable Rail corridor by easing out the Delhi region from the
freight traffic movement by allowing shifting from radial and inner ring rail network to the
proposed corridor.
Delhi NCR being centre acts as a Hub connecting the spokes in nearby states
Direct connectivity for Gurugram, Faridabad, Ballabhgarh, Palwal, Manesar
&Farukhnagar etc. with all the districts of Haryana
Peripheral rail link will help in industrial growth of cities around Delhi (Sohna,
Manesar, Gurugram, Jhajjar, Rohtak)
Connectivity to Dedicated Freight Corridor (DFC) at Pirthala
It will help in easing pressure from transport network of Delhi as traffic movements
in radial will shift to peripheral
Freight traffic not meant for Delhi will get diverted and will help in developing Multi
Modal Hubs in NCR region of Haryana
Connectivity to Maruti Suzuki and Logistic Hubs in the region.
The aim of this study is to prepare Feasibility Report along with estimates, drawings, of
Civil works, GADs and drawings for Signalling arrangements, Electrification of yards,
stations and other buildings in connection with construction of a new electrified BG rail line
corridor between Palwal and Sonipat
2.1.1 Major Development near project location
2.1.1.1 Panchgram Yojana
The Haryana government will develop five new cities in the two km area on either side of
the Kundli-Manesar-Palwal expressway and the area will be named as Panchagram.The
Haryana Govt. approved the concept of the Panchagram Region and developing five
cities on the Kundli-Manesar-Palwal (KMP) expressway on 50,000 hectares each side of
the expressway which would cover eight districts of the State namely Sonipat, Rohtak,
Jhajjar, Gurugram, Rewari, Mewat, Faridabad and Palwal.
The Industrial and Commercial Townships were being set up on 3,300 acres area in
Kharkhoda, Sonipat. Similarly, Industrial Model Township has been developed on 1,400
acres in Sohna of Gururgram.
7
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
The Proposed Alignment is going parallel to Kundli-Manesar-Palwal expressway of about
95 Km so that will boost to industrial Sector in the State.
2.1.1.2 Dedicated Freight Corridor
The Indian Railways quadrilateral linking the four metropolitan cities of Delhi, Mumbai,
Chennai and Howrah, commonly known as the Golden Quadrilateral; and its two diagonals
(Delhi-Chennai and Mumbai-Howrah), adding up to a total route length of 10,122 km
carries more than 55% of revenue earning freight traffic of IR.
Western Corridor comprising of 1483 km of a double line diesel track from JNPT to Dadri
via Vadodara-Ahmedabad-Palanpur-Phulera-Rewari. In addition, a single line connection of
32km long from proposed Pirthala Junction Station (near Asaoti) to Tughlakabad is also
proposed to be provided.
The Proposed rail corridor is going parallel to the Western DFCC alignment for as stretch of
15.6 Kms and crosses the Western DFCC at Proposed Pirthala Station which is showing in
Figure 1.5 below.
Figure 2.1 Proposed Alignment crosses DFCC
2.1.2 Conceptualisation of the Alignment.
Study on Palwal - Panipat connectivity via Jhajjar
8
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Study has been conducted on Palwal- Panipat connectivity via Jhajjar taking off from DFCC
yard at Pirthala
The alignment was proposed to run along the DFC alignment from Pirthala Yard up to
Sohna.
From Sohna the alignment will then run parallel to Kundli-Manesar-Palwal (KMP)
Expressway in Sohna- Manesar-Sultanpur stretch.
It will cross Delhi- Rewari Railway line near Patli Station through Rail Fly Over (RFO) and
connects to existing Patli station with a surface connection.
Near GarhiHarsaru- Farukhnagar Line, the alignment shall be diverted towards Jhajjar
connecting to the Farukhnagar station and terminates at Jhajjar station on Rewari-Rohtak
corridor of Northern Railway
Rewari-Rohtak line is a Single Non-electrified line. Therefore, to cater the movement of
anticipated traffic through this corridor necessitate doubling of the existing track complete
up to Panipat. This being a brown field project, running parallel to already existing
alignment shall be difficult. Because of the urbanization, development for new industrial
hubs and sidings shall be a constraint.
Only 50% of Reserved Orbital rail corridor can be used and balance 50% need to be
acquired parallel to existing alignment which is of mostly Built-up area.
After Implementation of KMP Expressway and the planning of Panchgram Urban centres,
the project alignment from Palwal to Sonipat has been conceived on Techno-Economic
consideration.
2.2 Project Location
2.2.1 Key Map of Project location
Haryana proposed Orbital Rail Corridor from Palwal to Sonipat by linking Asaoti – Patli –
Harsana Kalan by new BG line. Total Route length of project is 130 Km (excluding Y-
Connectivities). The Proposed rail corridor is bypassing Delhi which is shown in Fig. 1.3
below:
9
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Figure 2.2 Key Plan of Proposed Rail Corridor
2.2.2 Serving Station:
The serving stations for the connectivity shall be
Pirthala station on the Rewari-Dadri section of Dedicated Freight Corridor
having connectivity to both Asaoti and Palwal with Y-connectivity’s.
Patli Station on Delhi-Rewari section of Northern Railways
Sultanpur and Farukhnagar Stations on Garhi Harsaru- Farukhnagar section
Asaudah Station on Delhi -Rohtak section of Northern Railways
2.2.3 Major Locations & Districts
The proposed alignment of 130Km (excluding Y-Connectivities) route length passes
through 11 no. of proposed station locations and connecting to 3 no. of existing station
10
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
locations. The Proposed line runs parallel to Kundli-Manesar-Palwal (KMP) Expressway
near Sohana-Manesar-Harsana Kalan Stretch and about 95 Km alignment runs parallel to
KMP.
Apart from that proposed alignment passes through 5 Districts i.e. Palwal, Nuh, Gurugram,
Jhajjar and Sonipat in the state of Haryana and that will help in growth of industrial
development as alignment directly connects to cities near Delhi.
2.3 Concept of Study
Our scope of work formulated as below:
2.3.1 Feasibility Study
a) Field Reconnaissance and assessment of existing yard facilities at serving station
using hand held GPS.
b) Desk study on Google imagery and Topo sheets for assessment of alignment.
c) Foot by foot survey for identification of major constraints and features
d) Finalization of route based on Reconnaissance Survey.
e) Proposed rail connectivity route has been formulated with due consideration to the
following aspects.
▪ Topographical and Geographical features of route.
▪ Existing National as well as State Highways and Indian Railway lines.
▪ Existing rivers, streams, canals and forest lands.
▪ Rail corridor by means of curves and gradients.
▪ Proximity of crossing stations to human settlements for future development
as passenger corridor.
▪ Proximity to have connectivity to Industrial Model Townships along the
corridor.
2.4 Stakeholder outreach on Haryana Orbital Rail Corridor Project
Haryana Rail Infrastructure Development Corporation Limited (HRIDC) has hosted an
outreach event to the stakeholders on 13-02-2019 at Gurgaon to deliberate on the
“Haryana Orbital rail Corridor Project from Palwal to Sonipat” with a key objective of
providing boost to Rail Infrastructure projects in the Haryana state on the principle of
cooperative federalism and emphasizing on opportunities for investors and stakeholders
The event was a great success with great number of stakeholders and investors turned up
and showed their interest to invest in the project. The list of all participant for the event
was placed in the Annexure-X
11
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
The Brief description on the proceedings of the event are mentioned below:
Sh. Alok Nigam, IAS, Addl. Chief Secretary, Govt. of Haryana inaugurated the
Stakeholders Meet and presided over the function.
30 delegates from the Govt. of Haryana & Ministry of Railways, 10 from the
Financial Institutions and 24 delegates from the Industry participated in the
discussion.
MD/ HRIDC briefed the gathering about the activities of the company and about the
Haryana Orbital Rail Corridor specifically.
Sh. Alok Nigam, ACS (PW) addressed the gathering highlighting the need for the
project. Running of Shatabdi from Gurugram to serve the unserved areas was
emphasized.
ED/ MTP/RB: Praised the efforts by HRIDC to develop this project. Explained the
idea behind formation of JV companies with the participation of state Govt. & their
working.
Sh. Subodh Jain Principal Advisor (Former Member Engineering, Railway Board)
made detailed presentation on the proposed Haryana Orbital Rail corridor project
and clarified the doubts of the participants.
Representatives from Reliance, All-Cargo, Maruti participated enthusiastically in the
question & answer session.
Hon’ble Chief Minister Haryana, Sh. Manohar Lal also attended the Stakeholders
meet and appreciated the project & the enthusiasm shown by the participants in
the meet.
Major highlights of the event
M/s Maruti Udhyog Ltd have confirmed participation in the project SPV as Equity
partner.
M/s AllCargo has also shown keen interest to participate in this project and they
will revert shortly after due deliberations in their BOD.
This event has generated a lot of interest among various stakeholders and
Investors.
Railway Board & Northern Railway officials have also commended the idea of the
proposed Haryana Orbital Rail Corridor.
12
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
2.5 Fixed Points
2.5.1 Pirthala to Sonipat
Alignment for Haryana Orbital rail Corridor is proposed by taking-off from Ch. 2210.91 m
F/CSB for up line and from Ch. 2200.46 m F/CSB for down line of Pirthala Yard. For
computing the route length of proposed alignment, the CSB of Pirthala Yard is assumed as
0.00m. Subsequently the chainage towards Sonipat has been considered as positive.
2.5.2 Y-Connectivity towards Rewari Station
Y-connectivity towards Rewari Station has been proposed from proposed Manesar railway
station to existing Patli railway station in order to connect proposed Haryana Orbital rail
Corridor alignment with Delhi – Rewari route. For computing the route length of Y-
connectivity, the CSB of proposed Manesar railway station is assumed as 0.00m.
Subsequently the chainage towards Patli has been considered as positive.
2.5.3 Y-Connectivity towards Garhi-Harsaru Jn Station
Y-connectivity towards Garhi-Harsaru Jn station has been proposed from proposed Badsa
railway station to existing Sultanpur Halt station converting to block station in order to
connect proposed Haryana Orbital rail Corridor alignment with Farukhnagar – Garhi-
Harsaru Jn route. For computing the route length of Y-connectivity, the CSB of proposed
Badsa Railway station is assumed as 0.00m. Subsequently the chainage towards Sultanpur
has been considered as positive.
2.5.4 Y-Connectivity towards Rohtak Station
Y-connectivity towards Rohtak Station has been proposed from proposed Mandothi
railway station to existing Asaudah station in order to connect proposed Haryana Orbital
rail Corridor alignment with Delhi – Rohtak route. For computing the route length of Y-
connectivity, the CSB of proposed Mandothi railway station is assumed as 0.00m.
2.6 Standard of Construction
Minimum Standards of construction for new railway lines under JV model participative
policy of Indian railway vide Railway Board circular no. 2016/Infra/12/1, dt. 06.04.2018
shall be followed for the proposed railway infrastructure of Haryana Orbital Rail Corridor.
2.6.1 Category of Line
The proposed passenger line between Palwal to Sonipat 130Km (excluding Y-
Connectivities) will be constructed to Group ‘A’ standard with maximum speed potential of
160 kmph.
13
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
2.6.2 Gradient
Ruling Gradient
1 in 200 compensated grade is considered as ruling gradient of the section
Station Yard
A gradient of 1 in 1200 is generally adopted in exceptional cases 1 in 400 has been adopted
in all station yards. High level Passenger platforms and low-level loading platforms have
been proposed at station locations with necessary loop lines and sidings.
2.6.3 Grade Compensation
Grade compensation at the rate 0.04% per degree of curvature has been provided on
curves as per requirement of BG rail lines.
2.6.4 Gauge
The gauge adopted for the proposed alignment is 1676 mm to suit the existing gauge of
Indian Railways.
2.6.5 Rails
60 Kg (T-12) - Prime quality is envisaged for connectivity and 52 Kg second hand rails to be
used as check rails for curves and as guard rails for major bridges.
2.6.6 Ballast
Track Ballast as per IRS:GE-1 with 350 mm minimum cushion for mainline and 250mm for
loop line have been envisaged for the project.
2.6.7 Sleeper
60 Kg PSC sleepers with 1660 nos. per Km for entire stretch/ alignment shall be used.
2.6.8 Track Structure
Normal ballasted LWR track all along the alignment with the provision of blanket material
(granular fill as per RDSO Specs).
2.6.9 Welding
Flash butt welding for LWR track and Alumino Thermic welding/SKV welding for SWR track
have been envisaged.
2.6.10 Points & Crossings
All the crossovers in the proposed crossing stations connecting the main lines and loop
lines shall have P&C of 1 in 12 with 60 Kg rails, CMS crossing on PSC fan shaped PSC sleeper
14
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
layouts. Turnouts provided for over shoot lines are proposed with 1 in 12 with 60 kg rails,
CMS crossing and Fan shaped PSC sleeper layouts conforming to RDSO standards.
2.6.11 Switches & SEJ
For running lines, Thick web switches shall be used. Improved SEJ will be in used in LWR
track section.
2.6.12 Track Tolerances
Track tolerances specified under IRPWM by the Railway Board for new lines shall be
maintained.
2.6.13 Catch Water Drains and Longitudinal side Drains
Catch Water Drain or Longitudinal Side Drains are proposed wherever the depth of cutting
is more than 3 m.
2.6.14 Speed potential
Maximum permissible speed on proposed corridor shall be 160 kmph. On turnouts speed
shall not cross 30 kmph.
2.6.15 Length of Infrastructure
The total route length of the proposed alignment from Asaoti to Harsana Kalan is 130 km
(excluding Y-Connectivities).
2.6.16 Traction
Railway line from proposed Asaoti to Harsana Kalan as Electrified.
2.6.17 Horizontal and Vertical Alignment
Design parameters for Railway Infrastructure are detailed below:
S.No. Description Specification
Horizontal Alignment Design Criteria
1 Main line Curve Radius in m
a Preferred 1750
b Absolute Minimum 1350
2 Minimum loop curve radius (in crossing stations) in m
a Preferred 875
15
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
2.6.18 Formation
The top width of the formation in bank is proposed as 7.85m for Single line and 13.85m for
double line. The bottom width proposed in cutting shall be 10.85m for single line and
16.85m for double line including side drains. The formation in the embankment is
proposed with side slopes of 2H to 1V in banking and 1H to 1V in cutting. Granular
blanketing layer as per GE G:14 is proposed over the earth fill for the formation in banking.
An extra width of 150mm is considered for formation width on curved track. The drawing
showing Typical cross sections of Embankment and cutting are Annexed as Annexure-III(A1
& A2).
2.6.19 Bridges
All the bridges are proposed for 25T loading as per IRS bridge rules-2008. The super
structure of all major bridges is proposed either as Steel open web girders/plate girders or
PSC slabs. RDSO type Composite Girders are proposed for ROBs. However, a different
design of superstructure during detailed design stage is not ruled out.
2.6.20 Fixed Structure Clearance
Clearance of fixed structures is proposed to be adopted as per railway schedule of
dimension for BG line.
2.6.21 Road Crossing
All proposed road crossings are provided with either RUB or ROB as per the importance of
road. Level crossings are avoided as per Railway Board’s letter No. 2013/W-I/Genl./0/30
pt.-II, of not proposing any Level crossings on new lines.
2.6.22 Protective Works
Side slopes of banks shall be protected by providing turfing to prevent rain water flowing
down and eroding the side-slopes. It is proposed to provide pitching to the slopes of the
bank at platform locations to avoid erosion of slopes. The bridge quadrants will be
provided with pitching to avoid erosion. Toe wall with pitching of slopes may be provided
where available land width is less.
b Absolute Minimum (in crossing station) Straight
Vertical Alignment Design Criteria
1 Ruling Gradient 1 in 200 (Compensated)
16
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
2.6.23 Fixed Structure Clearances
All fixed structures to be provided on the corridor shall have clearances conforming to
recommended schedule of dimensions of Indian Railways.
2.6.24 Land requirement
Proposed alignment runs through Western DFCC ROW between Pirthala – Sohna, Reserved
land corridor of 50mtr along the KMP expressway, Government land, private land, forest
land etc. Necessary arrangement will be made by HRIDC to acquire the required land for
development of Rail corridor. Entire land has been proposed to acquire for double line.
2.7 Miscellaneous works
Features like sign boards, Fouling marks, surface drains, embankment side slope
protection, river training works etc shall be provided as per existing railway specifications
and RDSO guidelines. Road diversions have been proposed for minor/earthen roads at
certain locations based on importance to reduce the number of bridge openings.
17
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
3 Cost Estimation
3.1 Abstract Estimates
The total capital cost of the proposed Haryana Orbital Rail Corridor has been computed
based on the Latest awarded rates of the Northern Railways and summary of estimate is
placed below
SUMMARY OF COST ESTIMATES
Sl.No Description Cost (in Crores)
1 Civil Engineering 2255.28
2 Signalling and Telecommunication 135.29
3 Over Head Electrification and General Electrical 307.51
Total Construction cost 2698.08
4 Land Cost including Rehabilitation and resettlement 1088.00
Total Cost including Land 3786.08
5 HSIIDC Land cost (Considered as Sub-ordinate Debt) 300.00
Total Cost (In Crores) 4086.08
3.2 Methodology
The project is divided into the following structures for preparation of civil engineering
construction cost estimate.
Formation for Track
Rail Track
Bridges
Tunnels
Station Buildings
Workshops
Office Buildings
Staff Quarters
18
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
4 Financial & Implementation Aspects of the Proposal
4.1 Estimation of Traffic Revenues
Theyearofcommissioningofthe Project isassumedto be endof 2024. Accordingly,
revenuecalculationshavebeen done basedontrafficprojectsfromtheyear 2025.
4.2 Passenger Earnings
AccordingtotheRailwayBoardletter No. 2011/Infra/12/32 onParticipativemodelsfor rail-
connectivity and capacityaugmentationprojects, dated 10.12.2018, no apportionmentof
Passenger revenueswill be made in therevenuemodelforthe Project development JV. JV
shallprovide free Access to IR Passenger Trains. Hence, Passenger revenuecalculations are
notpresented in thisreport.
4.3 Freight Earnings
Freightrevenueshavebeencalculatedseparatelyforallcommoditiesoffrieghtanticipated,
basedontrafficprojectsmadeforincoming and outgoingtraffic.
Shortest Route as per http://rbs.indianrail.gov.in/ShortPath/ShortPathServlet have
been taken for finding shortest route up to nearest stations present
Revenue calculations and apportioning for project route has been made by using
following formula
𝑅𝑒𝑣𝑒𝑛𝑢𝑒 = (𝐹𝑟𝑒𝑖𝑔ℎ𝑡𝑅𝑎𝑡𝑒 − 𝑇𝑒𝑟𝑚𝑖𝑛𝑎𝑙𝐶ℎ𝑎𝑟𝑔𝑒𝑠) ∗ (𝑇𝑟𝑎𝑓𝑓𝑖𝑐) ∗ (𝑃𝑟𝑜𝑗𝑒𝑐𝑡𝑅𝑜𝑢𝑡𝑒𝐿𝑒𝑛𝑔𝑡ℎ
𝑇𝑜𝑡𝑎𝑙𝑅𝑜𝑢𝑡𝑒𝐿𝑒𝑛𝑔𝑡ℎ)
The freight rate per tonne as given in the Indian Railway Conference Association’s
“Goods Tariff No. 48 Part I (Vol. II) & Part II”, applicable from 1st April 2015 has
been taken for calculating freight revenues.
Additional surcharges are collected on the Base freight rate Vide Railway Board
Letter No.TCR/1078/2015/14 DATED 20.07.2015. They are Busy season charge 15%
from 1st April to 30th June & 1st Oct to 31st March on all commodities except
Container traffic and Automobile traffic. In addition Development surcharge is
charged on all Goods Traffic throughout year.
Revenue to SPV is taken as 50% of revenue of the project route length as per model
JV agreement and Participative models for rail-connectivity and capacity
augmentation projects- JV model.
19
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Theestimated total revenues (in LakhRs.) fromfreighttraffic as applicabletothe Project line
(Palwal to Sonipat), and SPV are shown in the table below:
Table 1 :Revenue Projections till Horizon Year 2049
2020 2025 2030 2035 2040 2045 2049 Revenues 1 6 11 16 21 26 30
Operating Revenues to SPV (Lakhs)
0 449.88 574.17 732.81 935.27 1193.66 1450.91
10% Increased Revenue with non-fare box cost
0.00 494.87 631.5904 806.0871 1028.794 1313.031 1595.997
4.4 O&M Costs
In terms of extant policy of Railway Board, train operations shall be managed by Northern
Railway. Further, manpower required for stations, commercial operations, fuel / energy
cost and operation, maintenance & replacement of all rolling stock shall be on Railway’s
account. The Concessionaire is expected to take care of maintenance of fixed assets,
security, renewals and replacements, insurance, accident repairs etc. at its own cost. The
Concessionaire shall have an O&M Agreement with Northern Railway to take care of these
issues.
Year 2025 2030 2035 2040 2045 2049
Maintenance Cost - For SPV (In Crores)
0.00 37.06 47.30 60.37 77.05 98.34 119.53
4.5 Financial Appraisal
Financial Appraisal is a method used to evaluate the viability of a project by assessing the
value of net cash flows that result from its implementation. Financial Analysis looks at the
impact of the project on the finances of the Sponsoring Agency.
A financial appraisal is concerned with the financial impact of the project on the finances of
the Sponsoring Agency. Financial analysis focuses on cash flows as opposed to economic
flows and, in particular, considers sustainability and profitability. Some of the general
objectives associated with this type of analysis are:
Identifying and estimatingfinancial cash flows;
Assessingfinancialsuitability – sustainabilityoccursifthe net
flowofcumulatedgenerated cash flowis positive forallyearsconsidered;
Calculating performance indicators (e.g. Net PresentValue, InternalRateofReturn);
and
Assessingfundingsourcesfortheproject
20
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
4.5.1 Net Present Value Method (NPV)
The Net Present Value (NPV) is the sum of the discounted cash flows over the period. This
criterion is simply based on whether the sum of discounted benefits exceeds the sum of
discounted costs.
4.5.2 Internal Rate of Return (IRR)
The internal rate of return is the maximum rate of interest that a project can afford to pay
for the resources used which allows the project to cover the initial capital outlay and on-
going costs and still break even. It can also be described as the discount rate that equates
the present value of benefits and costs. The IRR is generally compared to a hurdle rate of
return (normally the test discount rate for public investment appraisal) which corresponds
to the opportunity cost of funds.
Discounted cash flow (DCF) appraisal or valuation views the intrinsic value of an asset or a
project as the present value of its expected future cash flows. When applied to dividends,
the DCF model is the discounted dividend approach or dividend discount model (DDM).
This reading extends DCF analysis to value a company and its equity securities by valuing
free cash flow to the firm (FCFF) and free cash flow to equity (FCFE). Whereas dividends
are the cash flows actually paid to stockholders, free cash flows are the cash flows
available for distribution to shareholders.
In corporate finance or project appraisal, free cash flow to firm (FCFF) is a way of looking at
a project's cash flow to see what is available for distribution among all the securities
holders of the project entity. This may be useful to parties such as equity holders, debt
holders, preferred stock holders, and convertible security holders when they want to see
how much cash can be extracted from a company without causing issues to its operations.
Unlike dividends, FCFF and FCFE are not readily available data. Analysts need to compute
these quantities from available financial information, which requires a clear understanding
of free cash flows and the ability to interpret and use the information correctly.
Forecasting future free cash flows is also a rich and demanding exercise.
Free cash flow can be calculated in various ways, depending on audience and available
data. A common measure is to take the earnings before interest and taxes multiplied by (1
− tax rate), add depreciation and amortization, and then subtract changes in working
capital and capital expenditure. Depending on the audience, a number of refinements and
adjustments may also be made to try to eliminate distortions.
21
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
4.5.3 Discount Rate
The WACC is probably the single most important factor beside the return on invested
capital (ROIC), when estimating a project’s financial feasibility – the basis for most strategy
and performance evaluation methods. It is also the discount rate (time value of money)
used to convert expected future cash flow into present value for all investors. To be
consistent with the Free Cash Flow or Economic Profit approach, the estimated cost of
capital must comprise a weighted average of the marginal cost of all sources of capital -
debt, equity etc that involves cash payment, now or in the future - excluding non-interest-
bearing liabilities (in simple form):
𝑊𝐴𝐶𝐶 = 𝐶𝑑 × (1 − 𝑡) × 𝐷
𝑉+
𝐶𝑒 × 𝐸
𝑉
Where,
Cd = Pre-taxdebt nominal interestrate,
Ce = Opportunitycostofequity capital,
T = Corporate marginal taxrate,
D = MarketValueofinterest-bearingdebt,
E = MarketValueofequity,
V = MarketValueofentity (V=D+E)
Discount rate reflects the amount of risk associated with a particular investment. In
another way, it is the rate of return an investor would require for choosing a particular
investment and not any other alternative opportunities. Two broad approaches, namely
the Ibbotson Build-Up Method and the Capital Asset Pricing Method are available to value
an equity interest.
4.5.4 Capital Asset Pricing Model (CAPM)
As per Capital Asset Pricing Model,
𝐶𝑜𝑠𝑡 𝑜𝑓 𝐸𝑞𝑢𝑖𝑡𝑦 (𝐾𝑠) = 𝑅𝑓 + 𝛽 (𝐸𝑅𝑃) + 𝑆𝐶𝑅
Where,
Ks = CostofEquity,
Rf = Risk Free RateofReturn
β = Beta
ERP = Risk Premium
22
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
SCR = Project SpecificRisk Premium
As can be observed, the CAPM model requires beta for which the market and comparable
companies are selected and analyzed for their performances with regard to the market. In
our analysis, the lack of comparable public companies prevented us from relying on CAPM
model.
4.6 Haryana Orbital Rail Corridor Proposal –Project Executed by JV
Thisscenarioisbasedonthe Following assumptions
The Discounting rate has been8.5%
30% Equity and 70% Debt model has been considered.
Revenues are shared between SPV and MOR with 50% share of each as per model JV agreement.
Costs to be incurred by SPV includes Project’s capital cost, O&M cost (Fixed + Manpower)
Profit and Loss Statement for SPV as per JV model agreement -
Year 2020 2025 2030 2035 2040 2045 2049
Project Revenue - 494.87 631.59 806.09 1028.79 1313.03 1596.00
Project O&M cost - 37.06 47.30 60.37 77.05 98.34 119.53
EBITDA - 457.81 584.29 745.72 951.75 1214.69 1476.47
D&A - 84.50 84.50 84.50 84.50 84.50 84.50
EBIT - 373.31 499.79 661.22 867.25 1130.19 1391.97
Interest - 416.28 371.28 221.20 73.44 6.68 0.00
PBT - -42.97 128.51 440.02 793.81 1123.52 1391.97
Accumulated losses - -42.97 190.28 440.02 793.81 1123.52 1391.97
Taxable income - 0.00 190.28 440.02 793.81 1123.52 1391.97
Income Tax - 0.00 47.57 110.00 198.45 280.88 347.99
PAT - -42.97 80.94 330.01 595.35 842.64 1043.98
FIRR Calculation for SPV -
Year 2020 2021 2022 2023 2024
PAT 0.00 0.00 0.00 0.00 0.00
Add: D&A 0.00 0.00 0.00 0.00 0.00
Add: Interest Tax shield 0.00 0.00 0.00 0.00 0.00
Less: Capex 1598.00 547.50 547.50 547.50 547.50
Less: Investment in Working Capital 0.00 0.00 0.00 0.00 0.00
Add: Debt raised 1118.60 383.25 383.25 383.25 383.25
Less: Debt repaid 0.00 0.00 0.00 0.00 0.00
Free Cash Flow to Equity -169.98 -182.48 -182.48 -182.48 -182.48
23
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Year 2025 2030 2035 2040 2045 2049
PAT 28.18 41.90 374.93 620.47 844.92 1043.98
Add: D&A 84.50 84.50 84.50 84.50 84.50 84.50
Add: Interest Tax shield 83.93 72.12 40.33 9.99 0.91 0.00
Less: Capex 0.00 0.00 0.00 0.00 0.00 -1088.00
Less: Investment in Working Capital 0.00 0.00 0.00 0.00 0.00 0.00
Add: Debt raised 0.00 0.00 0.00 0.00 0.00 0.00
Less: Debt repaid 0.00 198.93 275.39 76.46 76.46 0.00
Free Cash Flow to Equity 196.61 -0.40 224.37 638.50 853.87 2216.48
Equity IRR 13.44%
Equity NPV 1015.48
4.7 Economic Appraisal
Substantial investment has been made at national level in rail transport infrastructure over
the past 50 years and is likely to continue in the future. The need to appraise transport
projects in economic and social terms has developed alongside this in both scope and
complexity. The state-of-the-art in the economic appraisal of transport projects is
reviewed, progress is assessed, and future challenges are identified. The review addresses
the general framework, treatment of major impacts, presentation of outputs and issues
such as uncertainty. It draws on national practice in India, and other countries, which
varies substantially reflecting a range of cultural and economic differences. Some points of
commonality exist, and the principle of monetizing direct transport impacts is generally
accepted. Progress has been made towards the measurement of environmental impacts,
but the assessment of the wider impacts remains under-developed. Increased
sophistication and complexity have brought increasing data and presentation
requirements, where computerized decision support methods have potential. Many
challenges exist for the future of appraisal and the review is concluded with a discussion of
some key issues. At the heart of these is the continuing debate over the relative roles of
national and European government in decision-making and resource allocation.
Economic appraisal is a type of decision method applied to a project, programme or policy
that takes into account a wide range of costs and benefits, denominated in monetary
terms or for which a monetary equivalent can be estimated. Economic appraisal is a key
tool for achieving value for money and satisfying requirements for decision accountability.
It is a systematic process for examining alternative uses of resources, focusing on
assessment of needs, objectives, options, costs, benefits, risks, funding, affordability and
other factors relevant to decisions.
24
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
Economic appraisal is most effective when it becomes a routine part of capital works
planning, incorporated from the early stages of project development. An iterative process
may then follow, as data are updated; for example, as a result of revised more detailed
construction cost estimates, or changes to the project as a consequence of the
environmental assessment process. The appraisal is reassessed to ensure that the
preferred option provides the best value for money outcome to meet the service objective.
An economic appraisal's methodology is such that certain concepts contained in
conventional financial analysis, such as depreciation, interest, and inflation and sunk or
historical costs are accounted for by different means or are not relevant to the evaluation
of project options.
While economic appraisal is required for capital works proposals, it does not remove the
need or desirability for financial analysis which will show cash flow demands on the State's
finances, and the financial rate of return from the project for Sponsoring authorities.
Sponsoring authorities may also wish to separately show economic appraisal results from
the agency's viewpoint, as well as from the overall community perspective, for
comparative purposes.
4.8 Assessment of Economic Cost
Thecostcomponentofthe Project are
Capital Cost of the Project – which are computed on the basis of depreciation and
amortization charges of the Project, which reflect the annual capital cost for the
Project
Operating Cost of the Project – which are the operations and maintenance costs
derived from our analysis and survey.
4.9 Assessment of Economic Benefit
Reduction in Pollution - The setting up of the project will trigger a modal shift in
transportation of goods from road to rail. This would reduce the number of trucks plying
on road and consequently the pollution (in the form of vehicular emission) caused by the
trucks would fall.
The benefits due to reduction in pollution have been calculated by considering the
emissions caused by heavy commercial vehicles per km (0.0169 kg/km), and damage cost
due to these emissions (lNR 38.4 per kg of emission).
Land Freement - As major freight traffic will by-pass Delhi area, some of the yards & goods
sheds will get closed, releasing huge area of prime real estate. Taking a conservative
25
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
estimate of only 50 acres during the project lifetime, @ 20 crores/acre total value
computed to 1000 cr
Benefits due to Increased Employment and Household spending - The investment will
lead to employment creation (both direct and indirect) An employment multiplier of 0.21
Jobs/INR Crore of investment as well as other appropriate multipliers (eg. indirect
employment multiplier of 1.5) have been taken to quantify the benefits on account of
employment generation. The quantified benefits using the above employment multipliers
and using the average per capita income of Rs. 1,00,000 per annum has been computed.
Economic Internal Rate of Return
Based on the above net economic cash flows are computed, which are then adjusted for
the initial investment required for the project and then, the economic internal rate of
return is computed using the principles of discounting.
The EIRR of the project is therefore the implied rate of return for the society and other
stakeholders at large and reflects a holistic assessment of the project.
2020 2021 2022 2023 2024
Economic Benefits 736.31 322.68 322.68 322.68 215.58
Land Freement
Asset value to Govt.
Net Economic benefit 736.31 322.68 322.68 322.68 215.58
Capex (-1,870.00) (-819.50) (-819.50) (-819.50) (-547.50)
Economic Cash Flows (-1,133.69) (-496.82) (-496.82) (-496.82) (-331.92)
4.10 I
mpl
em
ent
atio
n
thr
oug
h SPV as per JV Model
2028 2033 2038 2043 2048 2053
Economic Benefits 422.38 680.25 1,095.55 1,764.40 2,841.58 4,160.36
Land Freement 40.00 40.00 40.00 40.00 40.00 40.00
Asset value to Govt. 4,616.32
Net Economic benefit 462.38 720.25 1,135.55 1,804.40 2,881.58 8,816.68
Capex - - - - - -
Economic Cash Flows 462.38 720.25 1,135.55 1,804.40 2,881.58 8,816.68
EIRR 18.0%
26
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
The project may be implemented as a JV model as per Government of India Ministry of
Railways (Railway Board) Letter No. 2011/Infra/12/32 dated 10.12.2018, “Participative
models for rail-connectivity and capacity augmentation projects. Brief features of JV model
as per Railway Board letter is detailed below-
Applicability
It is generally applicable for bankable new line and gauge conversion projects either
sanctioned or proposed to be sanctioned having clearly identifiable stakeholder either as
user of the line or utilities such as ports, mines, exporters, plants and state governments.
Bankability of the projects, if required, can be enhanced through innovative financial
structuring such as sub-ordinate debt, grants etc.
Project Development and Project Structuring, Land Acquisition
Project development will be done by HRIDC through consulting Firms to establish
project cost, land requirement, project design and other project component
requirements, and project bankability.
IR will do financial structuring of the project to make it bankable including
identification of risk and mitigation measures.
Land acquisition will be done either by Indian Railways at the JV’s cost or by the JV
itself as mutually decided. Ownership of the land will vest with Railways. Land will
be given to the JV on annual token lease of 1 Rs. For the entire concession period.
Cost of acquisition of land will be treated as long term non-interest-bearing
advance and will be refunded to the JV on expiry/ termination of concession. For
such cases the land acquisition cost will be certified by an independent agency.
Selection of Equity Partners, Funding, Revenue Model
It envisages participation of the stakeholder and beneficiaries besides national level
infrastructure funding institutions in the development and creation of rail
infrastructure through appropriate concession.
Financial participation will be through equity participation in the JV. The JV will be a
joint venture with railways as a partner with IR or HRIDC holding a minimum of 26%
equity shares. Other partners will be selected from the stakeholders such as users
of the line like ports, mines, other Industries etc.
Selection of partners will be done through transparent expression of interest
process, with clearly laid down technical qualification based on parameters like net
worth, minimum threshold of equity participation etc. However, participation by
27
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
state governments and PSUs and other government entities will be through
nomination basis.
Projects will be assigned to JV by Ministry of Railways on nomination basis.
Debt will be raised through project finance route without any guarantee by the
government of India.
Revenue from the operation on the project line will be collected by IR though its
commercial staff. Revenue stream of the JV shall be established through revenue
apportionment from freight operation for the project line as per inter-railway
financial adjustment as stipulated in the IR code volume 1. No apportionment of
the passenger revenues will be made. JV will provide free access to IR Passenger
trains.
Normal IR tariff/ freight rates will be applicable, inflated tariff to improve
bankability could be approved by railway board in specific cases.
Commercial utilization of railway land, commercial publicity rights as permissible
under the law and public policy.
Construction
Project construction will be done by the JV. Th JV must ensure transparency in
project procurement in line with the extant guideline of government for public
procurement. The JV may, however, choose to entrust construction to IR or its
agencies by entering into a construction agreement. Certification will be done by IR
as per the extant rules/policy.
Maintenance
Maintenance of the project line could be done either by the JV or by IR through an
O&M agreement. In case the maintenance is undertaken by the JV, supervision/
certification shall be done by IR on payment of supervision/ certification charges by
the JV.
Operations
Operations will be done by IR.
Recovery of O&M Cost
IR will recover O&M cost or cost of operations as applicable as per the agreement.
The JV shall compensate IR for the fixed cost that is the cost of essential operational
and maintenance staff and other maintenance expenditure (if maintenance is to be
28
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
done by IR), or the cost of supervision/certification. The variable cost of operation
i.e. the cost of rolling stock usage, fuel, crew etc. shall be recovered from the
apportioned revenue. IR will pay to the JV apportioned revenue net of such cost as
applicable, as per a predefined formula to be specified in the O&M or operations
agreement.
Concession Period
Concession period will be normally 30 years including the construction period. The
concession period shall be subject to both upward and downward revision
depending on shortfall/excess of traffic materialization vis-à-vis the specified
threshold traffic (80% of the total traffic to be carried during the concession period
expressed in terms of million tonne Kms.) On the target date (25 years after signing
of the agreement) threshold traffic shall be determined on the basis of the
feasibility report. For every shortfall of 4%, the concession shall be extended by 1
year and a reverse principle shall apply if actual exceed the threshold traffic.
However, the concession period shall not be less than 25 Years and more than 35
years of operation.
Cost of land acquisition paid by the JV shall not be factored in for the purpose of
such equity return. No termination payment shall be admissible in case of natural
expiry of concession period.
Risk Mitigation
Traffic guarantee and rolling stock availability agreement will be signed wherever
such guarantees are considered necessary to mitigate demand risk. Traffic
guarantee shall be in form of a “Take or Pay” agreement on the part of strategic
partners (users) for the minimum volume of traffic to be moved. Strategic partners
will be required to enter into an agreement with IR on minimum commitment of
traffic volumes to be moved on the line. IR shall assure provision of rolling stock for
loading and transportation in respect thereof. In case of failure by either the
strategic partners (users) or IR, penalties stipulated in the agreement shall be
payable to JV.
General Features
JV shall operate “common carrier” principle of public transportation of goods and
passengers. For Rail users, IR would be the interface.
29
HARYANA ORBITAL RAIL CORRIDOR CONNECTING PALWAL TO SONIPAT BY LINKING PATLI- SULTANPUR- ASAUDAH STATIONS
FEASIBILITY STUDY REPORT
5 Proposed Financial Structuring
As per the JV model, Government of India Ministry of Railways (Railway Board)
Letter No. 2011/Infra/12/32 dated 10.12.2018, “Participative models for rail-
connectivity and capacity augmentation projects.
The project may be implemented as a SPV by HRIDC with Debt-Equity ratio of 70:30
considering the total cost of project is 4086.08Cr including land, the financial results
like Equity IRR is computed to 13.44% with Equity NPV of 1015.48Cr. (Ref: Para 4.6
of this report)
The total project cost including private land that need to acquired is 3786.08cr (Ref:
Chapter-03 of this report)of which 70% debt i.e 2650.25 Cr and 30% overall equity
i.e 1135.82 Cr is considered.
Out of the total equity, various stakeholder equity share is mentioned below
Overall Equity 1135.82 Crores
Equity share of Various Stakeholders
Stakeholder % Equity Share Amount (in Crores)
HRIDC 30% 340.746
Private Sectors 40% 454.328
Other PSU's 30% 340.746
The proposed alignment passes through the HSIIDC land near IMT Sohna, Manesar
and Kharkhoda of about 70 Hectares. This land costing approximately Rs. 300 crores
is proposed to be taken under subordinate debt.