Company Profile &
Capability
Copyright © Gulf Oil & Gas LLC (GOGAS). All rights reserved. No part of this publication may be re-used in any form or any means without prior permission of GOGAS. This document and the information contained in it, is strictly confidential and intended solely for the person or organization to which it is distributed. If you require copies of the document please contact the author. Any previous versions of the document should be destroyed. All trademarks are recognized and respected
Gulf Oil & Gas LLC (GOGAS)
Company Profile and Capability
June 2014
Company Profile &
Capability
Page 2 of 29
1 Introduction ....................................................................................................................... 4
1.1 Company Introduction ........................................................................................................ 4
1.2 Energy & Production ........................................................................................................... 4
1.3 Company Profile .................................................................................................................. 5
1.4 Offshore ................................................................................................................................ 6
1.5 Offshore Rigs ........................................................................................................................ 6
1.6 Onshore ................................................................................................................................. 7
1.7 Marine Division .................................................................................................................... 8
2 Operations .......................................................................................................................... 9
2.1 Organizational Chart ........................................................................................................... 9
2.2 Key Personnel ....................................................................................................................... 9
2.3 Corporate Operations ........................................................................................................ 10
2.4 GOGAS Mussafah Yard Operations................................................................................ 10
3 Capabilities and Resources ............................................................................................. 12
3.1 Fabrication.......................................................................................................................... 12
3.2 Marine ................................................................................................................................. 12
3.3 Manpower ........................................................................................................................... 13
3.4 Vessels ................................................................................................................................. 13
3.5 General Equipment ............................................................................................................ 14
4 Major Customers & Projects ........................................................................................... 15
4.1 Major Customers ............................................................................................................... 15
4.2 Project Experience ............................................................................................................. 17
5 Partners ............................................................................................................................ 26
6 HSE Philosophy ............................................................................................................... 27
Company Profile &
Capability
Page 3 of 29
7 Certification ..................................................................................................................... 28
7.1 ISO 14001:2004 & OHSAS 18001: 2007 .......................................................................... 28
7.2 ISO 9001: 2008 ................................................................................................................... 29
Company Profile &
Capability
Page 4 of 29
1 Introduction
1.1 Company Introduction
GOGAS Gulf Oil & Gas LLC was established in
1991 as an Electro – Mechanical Contracting
Company focusing quasi-exclusively on the Oil &
Gas sector in the UAE / GCC both in offshore and
onshore. Since then GOGAS has successfully
executed a number of projects primarily for the
ADNOC group companies (UAE). The company's
dominant operating policy has been to identify
customer’s needs and provide cost effective quality
services to meet the contractual requirements.
1.2 Energy & Production
GOGAS has in focus specifically on upstream and downstream
Projects in the GCC / Middle East. Historically GOGAS has been
working with consortium to cover wide span of activities upstream
and downstream.
Company Profile &
Capability
Page 5 of 29
1.3 Company Profile
GOGAS is dedicated to serve the Oil & Gas industry in
the fields of Electro Mechanical Projects and Marine
Services. With highly qualified management and staff,
GOGAS has the capability to offer a comprehensive
package to the clients through the Engineering,
Procurement, Construction and Commissioning of
turnkey projects to meet the total requirements of
customers.
Our Marine division with its fleet of barges, tug boats
and floating crane barge takes care of the logistics
requirements of our clients as well as supporting in-
house projects division in the offshore construction
works. We provide unique solutions with high levels of
customer satisfaction. GOGAS recognize customer’s
needs and develop quality, health, safety and
environmental protection plans, economical services and
products to satisfy those needs. With continuing
innovative marketing and excellent follow-through
construction, GOGAS maintain a strong market position
and remains poised for further growth in the future.
Company Profile &
Capability
Page 6 of 29
1.4 Offshore
GOGAS has been serving the Oil & Gas industry by
taking up specialized projects involving below water
and above water work related to modification and
maintenance of offshore Oil & Gas installations like
platforms, pipelines, jetties, loading facilities, etc.
1.5 Offshore Rigs
As member/leader of Consortium, case by case, we
supply, rent, provision of operations and maintenance
of onshore /offshore Rigs. Our Consortium Team has
vast experience and references can be furnished with all
information necessary to meet specific requirement
upon request.
We can offer specialist diving and underwater welding
services for maintenance and salvage operations. We
have our own floating barge crane, transport (dumb)
barges and tug boats which are deployed during
execution of our offshore projects and this gives us
greater control, flexibility and efficiency of operations
resulting in achieving tight project completion
schedules.
Company Profile &
Capability
Page 7 of 29
1.6 Onshore
In the onshore area GOGAS specializes in all types of
Piping (SS, NACE, CS, Cu-Ni, GRE, etc.), Mechanical
Equipment (static & rotary), Structural, Instrumentation,
Electrical and associated Civil works. Our sphere of
operations includes engineering, procurement, fabrication,
erection, testing and commissioning.
Another area of specialization is refurbishment and
modification of large size Tanks apart from building new
Tanks We also undertake dismantling of complete plants
including equipments / piping / instruments / tanks, etc. We
are uniquely experienced in undertaking plant modification
work in congested working plants and adopt stringent
safety measures as demanded by the hydrocarbon industry.
As member/leader of Consortium, case by case, we supply, rent, provision of operations and
maintenance of onshore /offshore Rigs. Our Consortium Team has vast experience and
references can be furnished with all information necessary to meet specific requirement upon
request
Company Profile &
Capability
Page 8 of 29
1.7 Marine Division
Our marine Division is responsible for
managing, operating and maintaining our
fleet of Transport Barges, Tug Boats and
Floating Barge Crane. This division provides
the vital offshore logistics support services to
our Project teams and also charter hires the
vessels, depending on planned usage.
Our Services Include:
Charter of DP-I and DP-II vessel, anchor handling tugs, supply vessel and other
offshore support vessel
Ship management, technical support and crewing
Provision of Manpower for deep water services like saturation diving, ROV services,
Remote System Engineering, NDT inspection and survey etc.,
Supply of ROV with under water cutting tools.
Marine Transportation of construction materials in and around UAE ports & Islands
Salvage Operations
Construction of costal protection like breakwater, marinas, jetty repair and Fender
Installation etc.,
Company Profile &
Capability
Page 9 of 29
2 Operations
2.1 Organizational Chart
2.2 Key Personnel
Nabil Atta - General Manager
Nizam Hassan - Assistant General Manager
Mike Chehata - Finance & Business Development Manager
Himadri Roy – AGM (Contracts and Proposals)
Siva Kumar– Project Manager
Faisal Zaman – Project Manager
Saravana Kumar – Project Manager
Mahalingam – Construction Manager
Company Profile &
Capability
Page 10 of 29
Arun Kumar – Yard Manager
Sreejit – Construction Manager
Mohd Sherif – Sr. Project Engineer
Arun V. R – Sr. Project Engineer
KMK Babu- QA/QC Manager
Prithviraj Prasad – Sr. HSE Engineer
2.3 Corporate Operations
GOGAS corporate office is located in Al Masood Tower at Hamdan Street, Abu Dhabi,
U.A.E., providing administration, personnel, accounting, information and management
support services to the Operations/Projects/Contracts located in Mussafah industrial area -
Abu Dhabi.
2.4 GOGAS Mussafah Yard Operations
With comprehensive capabilities to serve the upcoming industries in the area and with a
commitment towards these industries, GOGAS Mussafah Operations has been provided
adequate infrastructure & resources to meet increasing customer demands.
With comprehensive capabilities to serve the upcoming industries in the area and with a
commitment towards these industries, GOGAS Mussafah Operations has been provided
adequate infrastructure & resources to meet increasing customer demands.
The total area of the yard is 5247 sq. meters. A total 2860 sq. meters consists of fully enclosed
fabrication shop and 1770 square meters consists of open sheds for storage and offices.
GOGAS yard is capable to undertake all kinds of works in the following categories by highly
qualified and experienced crew in oil & gas sector:
Company Profile &
Capability
Page 11 of 29
Carbon Steel , Stainless Steel , Cu-Ni , Low Alloy and non ferrous fabrication up to
36”in heavy and light Steel Structures inside the shop floor.
For Heavy steel structure open yard available with 50 T Crane.
Pressure piping in the plants and installation.
Assembly of equipment skids and modifications.
Construction of Storage tanks.
Fabrication of Skids for special equipment, Installation, testing & commissioning.
Demolition of Steel Structures & Storage tanks.
GOGAS provides these services to Oil & Gas, and other industrial projects
Location of GOGAS Yard : Mussaffah M9, No:90
Mohamed Bader Al Rashid Building
Company Profile &
Capability
Page 12 of 29
3 Capabilities and Resources
GOGAS yard is capable to undertake all kinds of works in the following categories.
3.1 Fabrication
Carbon Steel and Stainless Steel fabrication in heavy and light Steel Structures
Pressure piping in the plants and installation.
Construction of Storage tanks.
Demolition of Steel Structures & Storage tanks.
Fabrication of Skids for special equipment, Installation, testing & commissioning
3.2 Marine
Marine equipment repairs
Overhauls of diesel & petrol engines , pumps etc.
Steel Structural refurbishment of ships and marine
vessels.
Company Profile &
Capability
Page 13 of 29
3.3 Manpower
We have a multinational construction team consists of welders, fabricators, riggers,
mechanics, technicians etc. lead by qualified and highly experienced supervisors and
engineers. Detailed break up is as follows.
Management 15
Administrative 20
Senior Engineering 25
Supervisory 15
Project Resources 300
Note: All the above mentioned personnel are our permanent staff. GOGAS always mobilizes
additional manpower, as per the requirements of the projects from our overseas contacts.
3.4 Vessels
Marine Vessels / Barges Qty Capacity
Barge GOGAS 250 01 5000 DWT
Barge GOGAS 252z 01 5000 DWT
Tug Boat (GOGAS 20) 01 2000 BHP
Tug Boat (GOGAS 10) 01 1000 BHP
Tug Boat (GOGAS 9) 01 940 BHP
Tug Boat (GOGAS 8) 01 800 BHP
Company Profile &
Capability
Page 14 of 29
3.5 General Equipment
The list of major equipment available in workshop is as below. This is indicative only and can
be augmented as per job requirement.
Description/ Manufacturer Qty Capacity
Diesel Engine Driven Welding m/c , Miller 23 400A & 600 A
Electric Driven Welding m/c, Miller 11 400 A
Electric Driven Welding m/c, Miller 02 200 A
Electric Driven Air Compressor 01 50 CFM /100 PSI
Diesel Engine Driven Air Compressor , Compare Holman 01 400 CFM/125 PSI
Crane 01 50T
Crane 01 25T
Fork lift , Nissan 01 5T
Pickup , Mitsubishi 01 3T
Pick up, Izuzu 04 1 T
Plasma Cutting m/c, Miller 03 12mm
Oxy Acetylene cutting set, Victor 15 Up to 1"
Pedestal drill M/c 01 Up to 25mm
Drill M/c, 04 Up to 16mm
Hilti Drill M/c 01 Up to 22 mm
Grinding M/c 6 7.5"
Grinding M/c 15 4.5"
Diesel Engine Driven Electric Power Generator, Caterpillar 01 27.5 KVA
Petrol Engine Driven Electric Power Generator, Yahamaha 01 5 KVA
Mini Bus, Nissan 03 14 Seater
Mini Bus, Mithsubishi 01 30 Seater
TATA BUS 01 50 Seater
H1 Vehicle 02 09 Seater
Company Profile &
Capability
Page 15 of 29
4 Major Customers & Projects
4.1 Major Customers
Abu Dhabi National Oil Company (ADNOC)
Abu Dhabi Gas Liquefaction Company
Limited (ADGAS)
ADMA-OPCO
Zakum Development Company (ZADCO)
Abu Dhabi Gas Industries Limited (GASCO)
Abu Dhabi Oil Refining Company
(TAKREER)
Abu Dhabi Water and Electricity Company
(ADWEA)
Company Profile &
Capability
Page 16 of 29
BOROUGE
Hitachi
Major EPC Contractors (TECHNIP, JGC,
SNAMPROGETTI)
Company Profile &
Capability
Page 17 of 29
4.2 Project Experience
GOGAS- GULF OIL& GAS L L C
ISO 9001:2008 Certified
LIST OF EXPERIENCE
Year
Project
Client
Location
Main or Sub
contractor
Brief Description/ Remark
2014
EPC Works For Borouge PO ISO Container Storage Yard Project
BOROUGE
RUWAIS
Main Contractor
EPC Works for the Container Storage Yard
2014
EPC SERVICES FOR FERTIL JETTY ETHYLENE VAPOUR RETURN ARM
BOROUGE
RUWAIS
Main Contractor
x
Design, Procurement ,Installation Of ETHYLENE VAPOUR RETURN ARM
2013
HABSHAN 0&1 HP Steam Modification (PC) Contract No. OHB. 13.067
GASCO
HABSHAN
Main Contractor
Contractor Scope Of Work Is In Habshan 1 And Habshan 0. Installation And Modification Of Existing Pipe Primary Supports. Replacement Of Spring Hanger Supports. Modification Of Steam Traps Construction Of Reinforced Foundations Including Material Supply For The Pipe Supports. Structural Steel Works For Pipe Supports. Installation Of Pipes.
2013
ADDITIONAL HANDLING FACILITIES FOR 10 PPM GAS OIL AT RUWAIS REFINERY. Agreement No-13RREDR10993.
TAKREER
RUWAIS
Main Contractor
EPC Contract For Design, Engineering. Procurement, Construction, Commisioning Of Multi Discipline Project For Additional Handling Facilities For 10 PPM Gas Oil At Takreer Ruwais Refinery.
2013
Labeling Of Pipelines In Process Units And Offsite Areas At Abu Dhabi Refinery. Agreement No- 13artsa11002
TAKREER Umm Al Nar Main Contractor
Engineering, Procurement, Installation Of Self Adhesive Maker Levels On All The Process Units And Offsite Area At Takreer-Abu Dhabi Refinery.
2013
CONSTRUCTION WORKS FOR PP POWDER TRIMMING PROJECT .Contract No-WC/13/TS/0023
BOROUGE
RUWAIS
Main Contractor
Procurement, Installation, Testing For The SS Piping Work Including E & I Work With MOV's And Feeder Valve/Equipment.
2013
Special Contract Of Supply Of Steel Piping, Fitting And Accessories For Mobile Polished Water Injection Skid To Carryout Water Injectiity Test At PW38-MRC5
HITACHI, Ltd Middle East
Branch
GOGAS YARD
Main Contractor
• Supply Of Piping And Electrical Materials • Transportation Of Free Issue Equipments, Skids, Instruments Etc. • Fabrication Of Piping Spools (CPVC, SS) With Piping Supports. • Installation Assembly Of Various Equipments, Skids, Tanks, With Piping And Electrical Cable Laying/Termination/ Glanding • Transportation And Unloading Of The Pre-Assembled Skids With Equipments
Company Profile &
Capability
Page 18 of 29
• Painting The Items Which Are Fabricated By GOGAS, Except CPVC Material. • Complete Installation Of Full Assembly Of The Equipments Including Marking On The Barge, Setting Equipment With Skid On The Barge, Leveling Of Equipment Using Liner, Shim Plate Etc.. Setting Of Generator And Fuel Tank, Setting Of Control Panel, Setting Of Container For Chemical Control Panel And Installation Of Sun Shade.
2013
Replacement Of Drinking Water Pipelines In Ruwais Refinery
TAKREER
RUWAIS
Main Contractor
Procurement, Supply, Pre-Fabrication/Fabrication, Erection, Installation, Testing, Pre-Commissioning And Commissioning Of New Above Ground/Under-Ground Piping Including Fittings, Valves, Expansion Loops, Supports, Anchors.
2013
REPLACEMENT OF 24" CORRODED FLARE LINE ITT NO. FTEFE1201, PROJECT NO. 8948
ZADCO
ZIRKU ISLAND
Main Contractor
REPLACEMENT OF 24" CORRODED FLARE LINE ITT NO. FTEFE1201,
2012
MANUFACTURING OF BLOCK BRANCHES
BOROUGE
RUWAIS
Main Contractor
MANUFACTURING OF BLOCK BRANCHES
2012
IMPLEMENTATION OF OPERATIONAL IMPROVEMENT TO PROCESS UNITS AT ABU DHABI REFINERY (TAKREER)
LITWIN
Abu Dhabi Refinery
Sub Contractor
IMPLEMENTATION OF OPERATIONAL IMPROVEMENT TO PROCESS UNITS AT ABU DHABI REFINERY (TAKREER)
2012
PROVISION OF TEMPORARY SITE EXECUTION SUPPORT FOR SHUT DOWNS & MAJOR SCHEMES (OFFSHORE) ON CALL-OFF BASIS ( CONTRACT NO. 156501)
ADMA-OPCO
OFFSHORE
Main Contractor
PROVISION OF TEMPORARY SITE EXECUTION SUPPORT FOR SHUT DOWNS & MAJOR SCHEMES (OFFSHORE) ON CALL-OFF BASIS
2012
CONSTRUCTION SERVICE FOR CONCRETE INSITU CASING OF BOROUGE 2 SEA WATER BASIN RUWAIS
BOROUGE
RUWAIS
Main Contractor
Upgrade Of Sea Water Basin With A Cast In - Situ Concrete Liner During Shut Down Period And Installation Of 72" Size GRE Header For Supplying Sea Water To Borouge 2 Facility.
2012
CONTRACT NO. 11RRMTR10816 INSPECTION AND MAINTENANCE OF SEAWATER INTAKES BOOM STRUCTURE IN GUP AT RUWAIS REFINERY
TAKREER
RUWAIS
Main Contractor
Inspect, Repair And Clean Of Sea Water Intake Booms, Buoys, Sliders Including Associated Auxilaries And Remove Sea Weeds, Floting Objects, Sands Stones And Other Debris Spread Out On Sea Water I.E Floating Or Settled In Nearby Sea Bed Of Sea Water Intake 1 And 2 Facility Of Ruwais Refinery Division.
2012
FOAM SYSTEM REPLACEMENT AT PLANT 27 AND JETTY. CONTRACT NO. CON-PAC-019-2011/LCO-2(MZ)
ADGAS
DAS ISLAND
Main Contractor
FOAM SYSTEM REPLACEMENT AT PLANT 27 AND JETTY
2012
REPLACEMENT OF COOLING WATER PIPING AT GG II - ZWSC
ADMA-OPCO
ZWSC
Main Contractor
Replacement Of 3" NS And Below Piping With GRE Pipe Work And Corroded Spools Of 4" NS And Above (Up To 24") Piping With Like To Like Material Of 90/10 Cu-Ni And In Addition Additional Isolation Valve Shall Be Provided.
2012
Contract No. 11xxzz10859 - The Modification Of Gas & Utilities Connections In Takreer Research Centre Laboratories & Pilot Plant Hall
TAKREER
Abu Dhabi Refinery
Main Contractor
THE MODIFICATION OF GAS & UTILITIES CONNECTIONS IN TAKREER RESEARCH CENTRE LABORATORIES & PILOT PLANT HALL
Company Profile &
Capability
Page 19 of 29
2012
UPGRADE/CONSTRUCTION OF CAB KITCHEN & RESTAURANT DAS ISLAND.
ADMA-OPCO
DAS ISLAND
Main Contractor
Carryout Civil HVAC Electrical Control Modification To The First Floor Of Central Aminities Building Das Island As Restaurant And To Extend The Kichen And Ground Floor By Converting Part Of Existing Al Shaheen Restaurant
2012
REPLACEMENT OF COOLING WATER LINE AT ZWSC-PGB. CONTRACT NO. 148150
ADMA-OPCO
ZWSC
Main Contractor
To Replace The Existing CS Cooling Water Lines With Cu-Ni Pipe Work From 03 Nos Cooling Water Lift Pumps Discharges To The Inlet Of Gas-Turbines. Procurement Of Materials. Fabrication Of Pipe Spools And Supports As Per Approved Drawings.
2012
SECTIONAL REPLCEMENT OF DRAIN GRE HEADERS AT ASAB RDS'S
ADCO
HABSHAN
Main Contractor
Remove The Existing Limit Stopper And Re-Construct At The New Location. New Manifold Flow Lines Anchor Bolts To Be Properly Secured With Vinyl Rubber Packing. Missing Horizontal Stopper Plates To Be Welded On Sleeper Supports. Clear And Excavate Sand
2012
FABRICATION OF HANDRAILS FOR NSP (PROJECT-8643) ITT NO. 912303/VAGEORGE
ZADCO
NSP
Main Contractor
Fabrication And Supply Of Handrails For NSP
2012
INSPECTION AND PAINTING OF HYDROGEN CYLINDERS AND NITOGEN CYLINDERS AT ABU DHABI REFINERY.
TAKREER
Abu Dhabi Refinery
Main Contractor
Dismantling , Removal From The Existing System, Inspection And Painting Of Hydrogen Cylinders And Nitrogen Cylinders And Related Piping Works At Site.
2011
EPC FOR PROVISION OF ACCOMMODATION IN AL JIMI CAMP FOR 2012 PLANT OVERHAUL AT DAS ISLAND. ADGAS NO. ENQ-PAC-059-2011/SCE#1(UD)
ADGAS
DAS ISLAND
Main Contractor
EPC FOR PROVISION OF ACCOMMODATION IN AL JIMI CAMP FOR 2012 PLANT OVERHAUL AT DAS ISLAND
2011
Construction Of Exercise Room Near Safety, Env. And Fire Dept.
TAKREER
Abu Dhabi Refinery
Main Contractor
Construction Of Exercise Room Near Safety, Env. And Fire Dept.
2011
SUPPLY, FABRICATION, PAINTING AND DLIVRY OF METAL SKIPS.
BOROUGE
Main Contractor
SUPPLY, FABRICATION, PAINTING AND DLIVRY OF METAL SKIPS.
2011
ACPT-2, BILGE AREA OPEN DRAIN PIPING REPLACEMENT. 909240/SREDDY
ZADCO
ACPT-2
Main Contractor
ACPT-2, BILGE AREA OPEN DRAIN PIPING REPLACEMENT.
2011 SUPPLY OF MATERIAL & CONSTRUCTION OF EMERGENCY FLUSHING LINE FOR SOUTH OIL TRUNK LINE (SOTL). NO. 812593/I BILAL
ZADCO Main Contractor SUPPLY OF MATERIAL & CONSTRUCTION OF EMERGENCY FLUSHING LINE FOR SOUTH OIL TRUNK LINE (SOTL).
2011 REROUTING/EXTENSION OF EXISTING WASTE WATER LINE OUTSIDE TAKREER MUSSAFAH TERMINAL
TAKREER MUSSAFAH TERMINAL
Main Contractor REROUTING/EXTENSION OF EXISTING WASTE WATER LINE OUTSIDE TAKREER MUSSAFAH TERMINAL
2011 Fabrication Of Boat Fenders For Whts US-4 To US-10, Project Ref. EU1087, Contract No. 144139
ADMA-OPCO US4-US-10 Main Contractor Procurement And Fabrication Of Fenders For Installation On Wellhead Towers US-4 To US-10.ADMA-OPCO Intend To Commission A Contractor For The Procurement & Fabrication Of The Fenders For Installation On WHT US-4 To US-10.
Company Profile &
Capability
Page 20 of 29
2011 Modification Required For Installation Of New Propain Compressor Motor With Self Contained Purgins System
ZADCO Main Contractor Modification Required For Installation Of New Propane Compressor Motor With Self Contained Purging System
2011 Manufacturing Of Long Term Storage And Shipping Containers. Agreement NO. 1613001
GASCO HABSHAN/BAB Main Contractor Manufacturing / Supply Long Term Storage And Shipping Containers For Insurance Spare Parts. Mainly Includes Design, Fabrication And Site Erection Of Containers.
2010 Replacement Of Marine Loading Arm & Other Accessories In Berth B At Ruwais Refinery. Agreement No. 09RRMTR10593
TAKREER Ruwais Refinery Main Contractor Design, Supply, Manufacturing, Installation, Testing & Commissioning Of 8 Nos Of Loading Arms In Berth B At Ruwais Refinery To Replace The Existing Ones.
2010 Repair, Renewal Of Flooring, Flase Ceiling Wall Lining Panel At ZWSC/ZCSC. Contract No. 134664
ADMA-OPCO ZWSC/ZCSC Main Contractor Engineering, Procurement, Demolition And Installation To Refurbish Damaged False Ceiling In Zakum West Super Complex And Zakum Central Super Complex. The Existing Electrical Light Fittings In Ceiling Of Mechanical Workshop, Electrical Pltf./ZCSC Shall Be Removed And Replaced With New Fittings.
2010 Improvement Of Al Jimi Village Accommodation. ADGAS Contract No. CON-PAC-034-2008/LCO-1 (UD)
ADGAS Das Island Main Contractor Refurbishment Of 6 Nos. Ablution Unit. Refurbishment Of 18 Nos. Dormitories 142 Nos. New Rooms - Civil/Electrical Etc. Roof Sheet Changing Of 154 Nos Caravans / Dormitories / Ablution Units. Demolition / Dismantling Of 56 Nos. Existing Caravans Including Structures And Transportation To Abu Dhabi. Installation Of 28 Nos. New Caravans (11M X 3M)
2010 Upgrade Of SWDP 20" Corroded Carbon Stell Dewatering Line With GRE, Contract No. 129789
ADMA-OPCO Das Island Main Contractor Engineering, Procurement, Fabrication And Laying Of 20" GRE Line And Related Civil Works At Das Island.
2010 Train-3 Main Cryogenic Heat Exchanger (MCHE) Replacement Project, Dismantling Of Mechanical, Insulation & E&I Items From Old MCHE. ADGAS Contract No. CON-PAC-034-2009/LCO-1 (UD)
ADGAS Das Island EPC Main Contractor Removal Of All Insulation & Cladding Including Removal Of Piperack, Structural Platforms, Electrical Cables And Instrument Items From Old Cryogenic Heat Exchanger In Train-3 At Das Island.
2010 Hiring Of Manpower For Six Months -Service Order No. 811875
ZADCO Central Complex (Offshore)
Main Contractor Hiring Of Manpower For House Keeping Of All Wellhead Platforms At Zakum Offshore Facilities.
2009 Supply, Installation, Testing And Commissioning Of A Completely New Marine Loading Arm (260-VLA-40) In Berth E At Ruwais Refinery TAKREER Agreement No.08RRMTR10492
TAKREER Ruwais Jetty Main Contractor Supply, Installation, Testing And Commissioning Of A Completely New Marine Loading Arm (260-VLA-40) In Berth E At Ruwais Refinery
2009 Inspection Of Ruwais Marine Terminal. TAKREER Agreement No. 08RRTSR10479
TAKREER Ruwais Jetty Main Contractor Inspection Of Rueais Marine Terminal Through Visual Examination & NDT Methods For Pipelines, Structures, Loading Arms, Loading Platforms, Handrails, Gratings, Bds, Mds, Etc. Above Water Inspection & Under Water Inspection. Which Includes CP Systems.
2008-10
Inspection Of TAKREER GUP Sea Water Intake And Maintenance Of Boom And Accessories Sand Trap Cleaning At Sea Water No. 1 & 2 In GUP TAKREER Refinery. Agreement NO. 07RRMTR10442
TAKREER Abu Dhabi Refinery
Main Contractor Inspection Of TAKREER GUP Sea Water Intake And Maintenance Of Boom And Accessories Sand Trap Cleaning At Sea Water No. 1 & 2 In GUP
2009 New Sulphur Rundown Line At Das Island ADGAS Contract No. CON-PAC-
ADGAS Das Island Main Contractor EPC Contract For Erector Of New Sulpure Rundown Line. Including Site Survey, Engineering, Procurement & Construction With Coordination
Company Profile &
Capability
Page 21 of 29
038-2007/LCO-2 With Tyco Thermals - UK
2008 Replacement Of Instrument Air Network At GTP & CSP In Central Copmplex, Project No. 8737, Contract No.CTEUZ071910
ZADCO Central Complex (Offshore)
Main Contractor To Carry Out Site Survey, Update Isometrics, Procure All Materials, Fabricate Transport To Offshore Site Except Multiphase Pump, Demolition And Extension Of Structural Platform, Installation Of New Skid, Piping, Electrical And Instrumentation Hook-Up Works.
2008 Modification Of 24" Coanda Relief Header - Contract No. 106523
ADMA-OPCO Das Island Main Contractor Engineering, Procurement Fabrication And Installation Of 20" CS Line, 24" Ball Valve And Related Civil Foundations
2008
Replacement Of Old Roof Sheets For Old BOG, VRU And Train 2 Plant 6MCR Compressor. Contract No. CON-PAC-0134-2008/SCE2
ADGAS
Das Island
Main Contractor
Engineering, Procurement, Manufacturing, Transportation To Site And Replacement Of Existing Roofing And Cladding FOR VARIOUS BUILDINGS AT Das Island.
2008
EPC Contract For Upgrade Of Corrossion Injection Skids In Das Island. Contract No. CON-MAC-037-2007
ADGAS
Das Island
Main Contractor To Carry Out Site Survey, Detail Engineering, Procure All Material Other Then Free Issued Skids, Demolition Of Existing Skids, Installation Of Pump,.
2008 Installation of MPP Package at WHPT -04 UAD. Contract No. CTEUA070110
ZADCO Offshore Platforms
Main Contractor To carry out Site Survey, Update Isometrics,Procure all material except multiphase pump,Demolition and Extension of Structural Platform, Instalaltion of new Skid, Piping, Electrical and Instrumentation Hook-up Works.
2008 Replacement of Fuel Gas Filter Seperator at UAD CPC on EPC basis Contract No. CTE UA06 3610
ZADCO Offshore Platforms
Main Contractor Design, Detailed Engineering Services, Procurement, Replacement of filter seperator package covering process including Piping, Instrumentation and Structural works.
2008 Helicopter Jet Fuel Daily Tank Jettison System Modification - Srvice Order No.SO0146283
ZADCO Offshore Platforms
Main Contractor To carry out modification of jettison tank, installation of rupture disks on the existing tanks, functioning decommissioning of of existing Jetison system, connection and Tie-inns of the existingg facilities, Piping, E&I and Structural works.
2008 Installation of Sodium Hypochlorite Dosing System at NSP. Project No.8184. Service Order No. SO102029
ZADCO Offshore Platforms
Main Contractor To carry out Site Survey, update Isometrics, procure all Materials including cu-nickel, PVC & GRE piping, fabricate , paint, transport, install offshore piping & instrumentation, test and commission the Hypochlorite Dosing System at North Satellite Platfo
2008 Inspection and Mintenanace of Oil Contaminent Boom Structure at Abu Dhabi Refinery Sea Water Outfall. Agreement No. 07ARMTA10363
TAKREER Abu Dhabi Refinery
Main Contractor To carryout the repair of Oil containment boom structure at Umm al Nar Sea water outfall, including periodic inspection & maintenanace of Boom Structure and on emergency call attendance during the contract period of 3 Years. The scope also include procure
2007-2008
Pre-fabrication of Pipe Spools for Inteligent Pigging at 19WHPT's
ZADCO Offshore Platforms
Main Contractor Site Survey, Engineering, Fabrication, testing, painting and delivery to ZADCO base in Musafah the piping spools for 19 Well Head Platforms for installation by ZADCO.
2007-2008
USSC - Installation of Atmospheric Vent for TA Glycol Generator
ADMA-OPCO Offshor Umm Shaif
Main Contractor Engineering, Procurement, Fabrication, Transportation to site, Installation, Hook-up, Tie-in and Commissioning of SS piping, supports, KOD and related instrumentation work
2007 Marine Barge Equipped with Crane Operator and Riging Team for Repair of 3 Nos.Marine Jetty Loading Arm at Ruwais Refinedry Jetty
TAKREER Ruwais Refinery Main Contractor Mobilize Crane Barge with operating crew and equipment for lifting of Marine Jetty Cranes for carrying out by TAKRER
Company Profile &
Capability
Page 22 of 29
2007-2008
New Portacabin for Offices at ACPT-1, 2 & CC. Contract No. CTOUZ0626
ZADCO Offshore Platforms
Main Contractor Design, Engineering, Procurement, Fabrication, Transportation to site, Installation, Hook-up, Tie-in and Commissioning of 8 Nos. Porto Cabin Offices at ACPT-1, 2 and Central Complex Offshore
2007 411-K-001 Cooling Water Piping Replacement at Satah Plant in Zirku Island. S.O. No. SO 101994
ZADCO Zirku Island Main Contractor Supply of all material, site survey, engineering, onshore fabrication, painting and testing of cu-ni. piping and delivery to ZADCO base in Mussafah.
2007- 2010
Replacement of Oily Water Sewer System at Abu Dhabi Refinery. Agreement No. 53.06.053
TAKREER Abu Dhabi Refinery
Main Contractor Replacement of existing GRE/CS coated pipes (6" to 32" sizes) layed underground, which are used for the oily water sewage system aongwith refurbishment/ replacement of Manholes. The GRE Pipes as wel as CS Pipes are 7.5 km each The number of Manholes are 3
2007 Quantification Works for Structural & Painting at Umm Al Dalkh WHP-03/07. Service Order No. SO132572
ZADCO Offshore Platforms
Main Contractor Carry out site survey of each platform and prepare EPC Scope of work for refurbishment of work, inluding budgetary cost for refurbishment work in order for ZADCO to invite RFQ's for the work
2007 Replacement of Flare Tip of 425H002B at Zirku Island
ZADCO Zirku Island Main Contractor Supply all manpower and equipment including the winch for lowering and lifting the tip and carryout the replacement of Flare Tip on Flare 425.H .002A at Zirku Island
2007 Chloride Guard Bed for Unit No. 13 in Ruwais Refinery. Agreement No. 52.05.046
TAKREER Ruwais Refinery Main Contractor Design, Engineering, Procurement, Fabrication, Transportation to site, Installation, Hook-up, Tie-in and Commissioning of 2 Nos. Chloride Guard Bed including related piping, supports, control valves and instrumentation
2007 Re-Roofing of Central Workshop at Das Island. Contract No. CON-MAC-049-2006
ADGAS Das Island Main Contractor Re-Roofing of Central Workshop in Das Island,including Engineering, Procurement, Manufacturing, Transportation to site and replacement of existing single skin and sandwitch panel Roofing and Clading.
2007 WIP-PGP Overboard Drain Lines Replacement. Contract No.CTOUZ0604
ZADCO Offshore Upper Zakum
Main Contractor Demolition of Existing CS Overboard Drain Lines and Installation of new GRE Lines including design, engineering, procurement, fabrication, offshore installation, testing and Commisioning of GRE Lines
2007 Repair of Damaged Boat Landing at Satah WHP-2. Contract No.CTE FE060810
ZADCO Offshore Satah Field
Main Contractor Carry out sikte survy, prepare fabrication drawings, procure shock cells, replace clamps asembly and shock cells on bumper fender at Leg B2 and remove boat landing on to barge, refurbish, replace all rub strips & ladder and reinstall boat landing on the W
2007 Installation of New Pig Traps on 8"Oil Production Flow Line between WHPTS PS-76 & PS-84
ZADCO Offshore WHPS Main Contractor Carry out site survey, prepare fabrication drawings, collect free issue material, supply balance material, fabricate new spools, remove the existing spools and install new Pig Traps and related piping including testing and touch up painting on offshore WH
2007 Replacement of Corroded Sea Water Drain Piping System (Water Injection) and Relocation of Carbon Steel Closed Drain Piping System. S.O No. SO131497
ZADCO Umm Al Dalkh Central Complex
Main Contractor Supply of all material, site survey, engineering, onshore fabrication, offshore scaffolding, offshore installatioin, painting and testing for replacemenmt of corroded cu-ni. Sea water drain piping system and relocation of carbon stel closed drain piping a
2007 6 Inch Bypass for Kerosene Feed Coalescer Outlet to Filter in Merox Unit at Abu Dhabi Refinery, Agrement No.53.05.073
TAKREER Abu Dhabi Refinery
Main Contractor Engineerig, Procurement and Construction of 6- inch kerosene bypass run pipe from outlet of 1701-F to ATK filter assmbly 1701-L and tie - in of new 6-inch bypass run pipes including installation of valves, associated pipe supports and related instrumentat
2006 Dismantling and Removal of Redundant Fixed Equipment, Piping and associated Accessories at Abu Dhabi
TAKREER Abu Dhabi Refinery
Main Contractor Dismantling, Removal and disposal of of various fixed Equipment, Piping and associated Accessories in the plant and Tanks with associated Foundations and Accessories in the Jetty area at
Company Profile &
Capability
Page 23 of 29
Refinery, Agreement No. 53.05.065
Abu Dhabi Refinery.
2006 Flare/ Fuel gas Metering Facilities Installation of Ultrasonic & Orifice type flow meters at CC & Satellites.
ZADCO Central Complex (Offshore)
Main Contractor Procure materials, install and commissioning of 12 nos. UT flowmeters and 8 nos. Orifice type flow meters, testing& commissioning
2006 Replacement of 7 nos. Pedestal crane at Takreer Marine Jetty Terminal.
Takreer Ruwais Main Contractor To carryout Engineering, Procure, Replace and Commission the 7 nos. Jetty pedestal cranes
2006 Tank Bottom Plate Replacement (Crude tank No.1)
ZADCO Zirku Island Main Contractor To Procure materials and carryout the refurbishment of 100m Dia. crude tank bottom plate
2005 Modification of Piping system for parallel operation at ZADCO CPC
ZADCO CPC, Umm Al Dalkh (Off Shore)
Main Contractor To carryout engineering, Procure materials, fabricate, install and commission to maximize the production capacity of the field. Also to carryout the debottlenecking study on existing UAD CPC Fuel Gas treatment and delivery system.
2005 Procurement, Install,Repair & Miscellaneous jobs at Ruwais marine jetty and Sulphur terminal jetty.Phase II
TAKREER Ruwais Main Contractor Procure berth fender systems, chains etc and install the same in oil tanker berth terminal. Also to repair the existing marine fender units and its painting. Replacement of various piping systems, Structural platforms, gangways etc.
2005 Debubbler tank 8" Vent lines modification and replacement of drain lines on chemical skid at CC WIP from SS to GRE
ZADCO Central Complex (Offshore)
Main Contractor
To carryout Engineering, Procurement, Prefabrication , Site installation and Commissioning of GRE Electrically conductive pipes and its accessories at ZADCO Central Complex
2004 Access platforms at various plant locations, protection sheds, Process lines protection and refurbishment of riser supports arrangement Contract No. CON-MAC-010-2004
ADGAS Das Island
Main Contractor
To carryout Engineering, Procurement, Prefabrication , Site installation and Commissioning of access platforms and pipelines protection and supports at ADGAS Das Island.
2004- 2007
Oil Spill Containment boom structure repair & maintenace at Takreer Umm Al Nar
TAKREER Umm Al Nar
Main Contractor
To procure materials and carryout the repair of Oil containment boom structure at Umm al Nar Sea water outfall, including periodic inspection & maintenance works and on call services during unforeseen failures
2004 Replacement of Flare Tip at Zirku Island
ZADCO Zirku Island
Main Contractor
To carryout the replacement of flare tip on flare 425.H .002A
2004 Reclamation of land in the sea and construction of Marine jetty in the reclaimed land for Private Department.
Private Dept, Abu Dhabi Government
Off shore
Main Contractor
Reclamation of land in the sea and construction of Marine jetty in the reclaimed land for Private Department.
2004 Al Geemi Camp additional accommodation
ADGAS Das Island
Main Contractor
To carryout the engineering, Procure material, Transport and install 30 nos. caravans at Das Island for enhancing the accommodation in Al Geemi camp.
2003 Replacement of Overboard Drain lines (20" &24" GRE lines) at Central Complex. SO No.101433
ZADCO Central Complex (Offshore) Main Contractor
Procure material, Fabricate, install and commissioning 20" &24" GRE Pipelines at siteat site.
2003 Demolition of Plant & machineries at GASCO, Habshan Project No.TS.55.02
GASCO Habshan
Main Contractor
Carry out the demolition of Plant and Equipment in units 45,55,61,64,73 and Thammama'F'
2003 Relocation of Warehouse (120m x36m) and Misc. Civil works in Umm Al Nar refinery. Project No. 53.00.016
TAKREER Umm Al Nar
Main Contractor
Carryout demolition of existing ware house and Construct new warehouse in refinery on EPC basis.
Company Profile &
Capability
Page 24 of 29
2003 Waste handling Facilities at Das Island
ADGAS Das Island
Main Contractor
Carryout Engineering, Procure materials and Construct waste handling facilities.
2003 Temporary Pentane Storage facilities and demolition of Tank 501 & 502 at Das Island. Project No CON- MAC-021-2002
ADGAS Das Island Main Contractor To carry out the Procurement, and Construction of various pipelines related to Pentane Pump relocation, Modification of existing Crude Tank(79m Dia x 19m H), Modification of Tank for change of product including partial replacement of bottom plates.
2002 Replacement of Fender at Production Platform in Bunduq Offshore Field
BUNDUQ Bunduq
Main Contractor
To carry out site survey, preparation of drawings, supply of all material, qualification of welders & welding procedures, fabrication of fender support structure, platform extensions & connecting flanges, mobilize marine vessel and install the Fender offs
2001 Al Geemi Camp additional accommodation (CON-MAC-020-01)
ADGAS Das Island
Main Contractor
To carryout the engineering, Procure material, Transport and install at Das Island for enhancing the accommodation in Al Geemi camp. Total 100 caravans installed.
2001 Renew Platform gratings in Train 1 & train 2
ADGAS Das Island
Main Contractor
To carry out the fabrication and installation of Steel gratings at Train 1 & 2 as per ADGAS instructions.
2001-3
Hire of Manpower & Equipment ADGAS Das Island
Main Contractor
Hire of Welders and fabricators to ADGAS
2002 Refurbishment of berthing Dolphins no.1 &5 at ADGAS Marine Jetty
ADGAS Das Island
Main Contractor
To remove the damaged fender units and install new units in berthing dolphins 1 & 5.
2001 Procurement, Install,Repair & Painting jobs at Ruwais marine jetty and Sulphur terminal jetty.
TAKREER Ruwais
Main Contractor
Procure berth fender systems, chains etc and install the same in oil tanker berth terminal. Also to repair the existing marine fender units and its painting.
2001 Inspection of Marine Terminal and Sulpher Jetties. Contract no. 52.00.055
TAKREER Ruwais
Sub Contractor to INW
To carryout the inspection of above water steel structures, vessels and pipelines including corrossion mapping of pipelines. Main contractor (INW) will carryout the under water inspection part of the job.(Total contract value is 2.25 Million)
2001 Fabricate & Install Air supply Manifolds at WHP's
ZADCO Satah Field (Off shore) Main Contractor
Procure material, pre-fabricate, NDT, Blast & paint, Installation, electrical & instrumentation at site and commissioning of Pressure Pipelines.
2001 Utilization of Satah Facilities. Test Separator Piping and Commissioning at WHP 8
ZADCO Satah Field (Off shore) Main Contractor
Procure material, pre-fabricate, NDT, Blast & paint, Installation, electrical & instrumentation at site and commissioning of High Pressure Pipelines.
2001 Utilization of Satah Facilities. Test Separator Piping and Commissioning at WHP 2,3,&6 (S.O. no.785018001)
ZADCO Satah Field (Off shore)
Main Contractor Procure material, pre-fabricate, NDT, Blast & paint, Installation, electrical & instrumentation at site and commissioning of High Pressure Pipelines.
2000 Installation of 3rd manifold ( S.O.No: 720008006)
ZADCO Umm Al Dhalak (Offshore)
Main Contractor Procurematerial, pre-fabricate, NDT, Blast & paint, Installation at site including instrumentation and commissioning of High Pressure Pipelines.
2000 Salvage of Sunken Ship from Umm Al Nar Channel
TARGET/ ADWEA
Umm Al Nar (Offshore)
Main Contractor Salvage of Sunken Ship from Sea bed.
2000 Dismantling /Removal Of FD Fan Houses for Boilers in Train 1 &2. CON-MAC-029-99
ADGAS Das Island Main Contractor Dismantling & Removal of existing 4 nos. Portal Steel FD fan houses and installing Steel structures for the fan intakes.
1999 Supply, Fabricate, Errect, Test & Commission all piping related to DCS Project. 0277/006/C
GASCO Ruwais (Plant Piping)
Sub Contractor to Technip Geo Production & UTS Kent.
Procure material, pre-fabricate, NDT, Blast & paint, Installation at site and commissioning of High & Low Pressure Pipelines.
Company Profile &
Capability
Page 25 of 29
1999 Provide WPS,PQR and carryout Welding of 2 nos C.S. Split Tee for Hot Tapping related to installation of Fuel & vent Gas pipeline at ADCO, ASAB Contract no: 1267)
ADCO/GASCO Asab (On shore field)
Sub Contractor to Toledo & Kvaerner
Welding of Split Tees.
1998 Installation of Residue gas line for fire training ground ( Contract no:446/001/C)
GASCO Buhassa (Onshore)
Main Contractor Procure material, Pre-fabricate, NDT, Blast& Paint , Installation and commissioning of pipe line including Hot tapping operation .
1998 Replacement Of 30" leaking Tee . Shut down Work Contract no: 0446/002/C
GASCO Buhassa (Plant Piping)
Main Contractor Installation of Tee & Related shut down jobs.
1998 Debottlenecking of MP Fuel Gas line at GP & P Division Contract no: 333.98.30
ADNOC Habshan (Plant Piping)
Main Contractor Procure material, Pre-fabricate, NDT, Blast& Paint , Installation and commissioning of pipe line including Hot tapping operation .
1998 Inspection of Sulpher Loading Platform by Abseling.
ADGAS Das Island Sub Contractor to INW
Survey and inspection of steel structures & pipe lines
1997
Construction of Break water H.E. Mohammed Al Habroosh
Mechaseb Island Main Contractor Supply material, marine transportaion, and construction of break water .
1996
Construction of Marine Jetty H.E. Shk.Ahmed Bin Hamed
Hanoura Island Main Contractor Supply material, marine transportaion, and construction of marine jetty.
1995
Construction of Break water Mohammed Bin Masood
Fataer Island Main Contractor Supply material, marine transportaion, and construction of break water .
1993 Demolition of sahil A restaurant Building and supporting Marine services
ADMA-OPCO Das Island Main Contractor Demolition of existing structure and its transportation to Abu Dhabi.
1992
Power supply to Radar building UAE Armed Forces
Al Dafra Air Base
Main Contractor Suppy Material, errection& commissioning of lighting, LV,MV panel system, Underground cabling etc.
1992 Structural inspection & Maintenance of Ruwais jetty
ADNOC Ruwais Sub Contractor to INW
Structural inspection and repair of damaged structures .
1992
Demolition of Storage Tanks ADMA-OPCO Das Island Main Contractor Demolition of existing structure and its marine transportation to Abu Dhabi.
1992 Demolition of Plant & Storage Tanks
ADGAS Das Island Main Contractor Demolition of existing structure and its marine transportation to Abu Dhabi.
1991 Demolition of LPG/LNG storage Tanks
ADGAS Das Island Sub Contractor to NPCC
Demolition of existing structure and its marine transportation to Abu Dhabi.
Company Profile &
Capability
Page 26 of 29
5 Partners
1. Off-shore Subsea Works and under Water Projects
2. Refinery Maintenance and Operations
3. Dismantling and Heavy Lift Operations
4. Trading Partners
5. Investment Partners in Oil and Gas & Marine Off-shore Projects
6. Being Gulf based company we can establish a branch in GCC region.
Working with our International Partners in the area of Maintenance and Operations
1. For the Maintenance and Operations of Refineries.
2. For the Maintenance and Operations of several subsea Projects
3. On-shore and Offshore Rig Maintenance and Operations with Consortium Partners
4. Pipeline Partners
Company Profile &
Capability
Page 27 of 29
6 HSE Philosophy
GOGAS is an ISO , OHSAS & EMS certified company: ISO 9001:2008,ISO 14001:2004 &
OHSAS 18001:2007).
The ultimate goal of GOGAS Project Management Team are:
Timely completion of Project with full compliance to HSE Requirements;
No harm to people,
No damage to company’s or client’s property;
No adverse impact on environment
Safety (QSMS): We are committed to maintaining the highest levels of Quality and Safety in
our systems and operations, in line with requirements set forth by the operator companies in
the region. We are proud to have a very achieved a very high level of safe operations records
for the past five years. No accidents or incidents were reported during the past five years,
which shows our commitment to provide a safe work environment for our crew.
GOGAS Considers HSE as Line Responsibility and believes “No project is so important that
it cannot be performed / completed safely ”
Company Profile &
Capability
Page 28 of 29
7 Certification
7.1 ISO 14001:2004 & OHSAS 18001: 2007
Company Profile &
Capability
Page 29 of 29
7.2 ISO 9001: 2008
Safety (QSMS): We are committed to maintaining the highest levels of Quality and Safety in
our systems and operations, in line with requirements et forth by the operator companies in
the region. We are proud to have a very achieved a very high level of safe operations records
for the past five years. No accidents or incidents were reported during the past five years,
which shows our commitment to provide a safe work environment for our crew.