Transcript
Page 1: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Getting the Booster to 2010

Eric PrebysDecember 20, 2002

• Outine

• Longevity Issues

• Non-radiation related

• Radiation related

• Personnel

• Performance Issues

• Limiting Factors

• Plan

Page 2: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Longevity Issues (non-radiation)

• GMPS (upgraded, OK)• Transformers (serviced, OK)• Vacuum system (being update, finished 2003)• Kicker PS charging cables

– Run three times over spec– Fail at the rate of about 1/month – AFTER A CERTAIN NUMBER OF

PULSES.– Seven spare coils– Evaluating improved design (better cable, LCW-filled heliac, etc)

• Low voltage power supplies, in particular Power 10 Series:– Unreliable, some no longer serviced.– Starting search for new supplier and evaluate system to minimize number

of different types.– Probably a few $100K to upgrade system.

Page 3: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Longevity Issues (non-radiation, cont’d)

• RF Hardware– (original) Copper tuner cooling lines are beginning to spring leaks.

Difficult to repair because they’re hot.

• High Level RF– More or less original.– Our highest maintenance item.– Will probably last, BUT expensive to maintain.– John Reid and Ralph Pasquinelli feel a new solid state system would pay

for itself ($5.5M) in about four years.

• Low Level RF– Many old modules, some without spares, some without drawings.– An upgrade plan in place.– Not expensive, but NEED people.

Page 4: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Longevity Issues (radiation related)

• We’ve seen failures in ion pump HV lines -> planning to replace.

• Hoses on beam valves will be replaced with copper of stainless.

• Looking at other miscellaneous cabling and hoses.• Magnet insulation:

– Biggest worry– We have no idea how close we are– During January shutdown

• Will remove some existing dosimetry and evaluate• Will put in widely distributed new dosimetry.• Take these numbers to the people who know.

Page 5: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Longevity Issues: Personnel

• Several key people will likely retire before 2010.• We need at least one new hire at the Engineer or

Engineering Physicist level to insure continuity.

Page 6: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Some Cold Hard Facts about the Proton Future

• Running as we are now, the Booster can deliver a little over 1E20 protons per year – this is about a factor of four over typical stacking operations, and gives MiniBooNE about 20% of their baseline.

• NuMI will come on line in 2005, initially wanting about half of MiniBooNE’s rate, but hoping to increase their capacity – through Main Injector Improvements – until it is equal to MiniBooNE.

• Whatever the lab’s official policy, there will be great pressure (and good physics arguments) for running MiniBooNE and NuMI at the same time.

• -> By 2006 or so, the Proton Source will be called upon to deliver 10 times what it is delivering now.

• At the moment, there is NO PLAN for achieving this, short of a complete replacement!

Page 7: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Limitations to Total Booster Flux

• Total protons per batch: 4E12 with decent beam loss, 5E12 max.

• Average rep rate of the machine:– Injection bump magnets (7.5Hz)– RF cavities (7.5Hz, maybe 15 w/cooling)– Kickers (15 Hz)– Extraction septa (now 4Hz, 7.5 after Jan. shutdown)

• Beam loss– Above ground:

• Shielding• Occupancy class of Booster towers

– Tunnel losses• Component damage• Activiation of high maintenance items (particularly RF cavities)

Of particular interest to NUMI

Our biggest concern

Page 8: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Proton Timelines

• Everything measured in 15 Hz “clicks”• Minimum Main Injector Ramp = 22 clicks = 1.4 s• MiniBoone batches “sneak in” while the MI is ramping.• Cycle times of interest

– Min. Stack cycle: 1 inj + 22 MI ramp = 23 clicks = 1.5 s– Min. NuMI cycle: 6 inj + 22 MI ramp = 28 clicks = 1.9 s– Full “Slipstack” cycle (total 11 batches):

6 inject+ 2 capture (6 -> 3)+ 2 inject+ 2 capture (2 -> 1)+ 2 inject+ 2 capture (2 -> 1)+ 1 inject+ 22 M.I. Ramp----------------------39 clicks = 2.6 s

Page 9: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Summary of Proton Ecomomics

 

Batches Protons delivered ( x E12 pps)* Total Scenario Cycle (clicks)

prepulse Stack MB NuMI

Rep rate (ave. Hz) Stack MB NuMI E12 /RunII

Stack 23 2 1 2.0 3.3 0. 0. 3.3 1.

Stack/MB 23 2 1 8 7.2 3.3 26.1 0. 29.3 9.0

Stack/NuMI 28 2 1 5 4.3 2.7 0. 13.4 16.1 4.9

Stack/NuMI/MB 28 2 1 10 5 9.6 2.7 28.8 13.4 42.9 13.1

Slipstack/NuMI 39 2 2 9 5.0 3.8 0. 17.3 21.2 6.5

Slipstack/NuMI/MB 39 2 2 13 9 10.0 3.8 25.0 17.3 46.2 14.2

Booster Hardware Issues Radiation Issues

MiniBooNE baseline 5E20 p/year

*assuming 5E12 protons per batch

NUMI “baseline” = 13.4E12 pps x 2E7 s/year 2.7E20 p/year

Right now we’re at roughly 1/5 of the MiniBooNE baseline

Page 10: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Typical Booster Cycle

Various Injected Intensities

Transition

Intensity (E12)

Energy Lost (KJ)

Time (s)

Page 11: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Booster Losses (Normalized to Trip Point)

BRF11: 200 mR/hr @ 1ft

BRF15: 300 mR/hr @ 1ft

Page 12: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Booster Tunnel Radiation Levels

Activation in Booster Tunnel (6 hour cooldown)

0

500

1000

1500

2000

2500

L20

L21_

RF9_ds

S21

L22_

RF12_us

L23_

RF13_us

L23_

RF14_ds

L24_

RF15_ds S24 S1 L3 S3 L5 S6 L8 L9 L1

0S11 S12 L1

3S13

L14_

RF2_us

L15_

RF3_us

L15_

RF4_ds

L16_

RF5_ds

S16

L17_

RF8_us

L18

L19_

RF17_ds S19

Standard Locations (some contact, some 1ft)

mR

/hr 28-Aug-02

17-Dec-02

• On the last access

• The people doing the radiation survey got about 20 mR.

• Two technicians received 30 mR doing a minor HV cable repair.

• We’re at (or past??) the absolute limit on our overall activation

Page 13: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Hardware Improvements to Booster

• Shielding and reclassification of Booster towers: complete 2001• New extraction septum (MP02) power supply: complete 11/02• New extraction septum: magnet complete. To be installed 1/03• Collimation system: complete, but cannot be used until…• Collimation system shielding: 75 tons of steel to be stacked 1/03• Time line improvements (very important for MiniBooNE

operation): more or less complete.• More cables for extraction septum (will allow 15 Hz

operation): ??• New injection bump magnets: ??• New RF cavities: ??

Page 14: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Plan

• All near term hardware improvements will be complete by early to mid 2003. At the point the Booster will physically be able to run a 7.5 Hz.

• Proceed with tuning improvements (C. Ankenbrandt coor.):– IPM calibration (Tomlin, Spentzouris, Lackey).– Orbit correctors: complete, working out operational issues

(Prebys, Coney).– Precision lattice measurement: (Lackey, Coney, new grad.

Student).– Transition studies (gamma-t jump??): (Jackson et al.)– Damping improvements: Pellico + ??

Page 15: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

New RF System

• The existing RF cavities form the primary aperture restriction (2 ¼” vs. 3 ¼”).

• They are high maintenance, so their activation is a worry.• There is a plan for a new RF system with 5” cavities:

– Powered prototype built– Vacuum prototype ready for summer installation– Second prototype to be built by university machine shops?

• Total cost: $5.5M cavities + $5.5M power supplies (maybe use old ones)

• Is it worth it? On of the questions for the study group is how much improvement we might expect.

Page 16: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Upgrade Cost EstimateTUNERNew ferrite cores 28 $500 $14,000New copper disks 28 $300 $8,400End caps 2 $300 $600Center hub casting 1 $5,000 $5,000Center conductor cones 2 $1,500 $3,000Internal bus package 1 $5,000 $5,000External bus package 1 $5,000 $5,000Stem 1 $1,500 $1,500Machine Shop per Tuner 1 $5,000 $5,000Misc. 1 $5,000 $5,000Total per tuner cost $52,500

CAVITYNew ceramic windows 2 $10,000 $20,000New blocking capacitor 1 $13,750 $13,750New B+ choke 1 $2,500 $2,500New beam tube 1 $1,500 $1,500New mu tube 1 $1,000 $1,000New end plate assemblies 2 $1,000 $2,000New outer shell 1 $15,000 $15,000New inner conductor 1 $10,000 $10,000New gap electrodes 4 $500 $2,000New tuner 3 $52,500 $157,500Machine Shop per Cavity 1 $23,810 $23,810Misc 1 $10,000 $10,000

Total per cavity cost $259,060

Total for 21 cavities 21 $5,440,249.92Labor Cost Estimate is shown below

LABOR (in man-years) Estimate for Cavity & Tuner OnlyMechanical Engineer 1 $100,000 $100,000RF Engineer 1.5 $100,000 $150,000Drafting 1 $100,000 $100,000Technician 3 $100,000 $300,000

Total labor cost $650,000

Series Tube Modulator 20 90,000 1,800,000.00

6 Kwatt Solid State Wideband driver 20 100,000 2,000,000.00

200 Kwatt Power Amplifier 20 80,000 1,600,000.00 -

Installation 18 5,000 90,000.00

Total Excluding FNAL Labor 10,930,249.92

Summary:

• ~$260K per cavity, of which $160K goes for the three tuners.

• A roughly equal amount for the power supply chain.

• About 20 cavities.

-> $11M total

Page 17: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

RF Upgrade: Questions to Answer

• Accuracy of the Cost Estimate?• Status:

– First prototype– Vacuum prototype– Design

• Reasonable timeline.• Ways to save money:

– Use old tuners?– Use existing power supplies?

• Ways in which universities can help:– Political pressure– Money– Fabrication

Page 18: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

ORBUMP Project

• The current ORBUMP magnets can ramp at 7.5 Hz, with a substantial temperature rise.

• Need to go to 12 to support MiniBooNE and NuMI.• New design underway, but needs much more

attention.• Can new design incorporate injection improvements??

Page 19: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Simulation/Studies

• Any major improvement in the Booster will very likely involve at least some hardware improvements (in 30 years, every knob has been tuned).

• Any proposed hardware improvement will have to be supported by simulations and measurements.

• In a perfect world, we would be able to model the entire acceleration cycle of the Booster, and reproduce losses.

• We are probably years away from that.• We need to focus our efforts:

– Obtain the best lattice we can – including measurements!!– Do limited modeling studies to try to identify what are likely important factors in

instabilities:• Alignment??• Nonlinearities??• Aperiodicities??• Etc.

• There should be a much closer relationship between simulations and measurements.

Page 20: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Some General Comments

• The Proton Source CANNOT achieve its goals parasitically.

• The pressure from the collider program is not going to go away, so we have to come up with a plan to live together.

• We need, at the very least:– A commitment to a certain amount of dedicated study time

(few hours a week).– A commitment to priority on a console (preferably #2).

Page 21: Getting the Booster to 2010 Eric Prebys December 20, 2002 Outine Longevity Issues Non-radiation related Radiation related Personnel Performance Issues

Conclusions

• We are at or near the present limit of the Booster output.

• This is a factor of up to ten away from what is needed.• Current plans might realistically increase things by a

factor of two or three, tops.• Getting further will be hard!!!


Top Related